Challenges in partnering on major research platforms and facilities William L. Miller, Ph.D. AAAS Science and Technology Policy Fellow National Science Foundation Used with permission
Challenges in partnering on major research platforms and facilities
William L. Miller, Ph.D.AAAS Science and Technology Policy Fellow
National Science Foundation
Used with permission
PMC2010: Partnering challenges on large projects 2W. Miller
Scope
• High cost and complexity of major projects have drive partnering between U.S. agencies and with international entities.
How do partner processes and practices align? (Start with agencies)
What are the challenges and best practices for partnering?
PMC2010: Partnering challenges on large projects 3W. Miller
Science platforms and facilities: a highly varied class…
PMC2010: Partnering challenges on large projects 4W. Miller
Big science projects engage many stakeholders…
Large ScienceInfrastructure
ScienceEnterprise
TechnologyEnterprise
NationalPriorities
InteragencyPartnerships
InternationalCooperation
lots of interest in process, performance and outcomes…
PMC2010: Partnering challenges on large projects 5W. Miller
Comparison of project practices at DOE, NASA and NSF
Organizations and portfolios studied:
DOE Office of Science “Science User Facilities”
NASA Science Missions Directorate (SMD)“Robotic Science Missions”
NSF Science & Engineering Directorates, OPP“Large Facilities” (MREFCs)
W. Miller, PRECONSTRUCTION PLANNING FOR LARGE SCIENCE INFRASTRUCTURE PROJECTS: A comparative analysis of practices and challenges at DOE, NASA and NSF, November 3, 2009
• Reviewed key agency guidelines, external reports & analyses…
• “Looked under the hood”: ~45 stakeholder interviews; site visits; direct observations…
PMC2010: Partnering challenges on large projects 6W. Miller
Comparative Approach
• Framework for agency comparison along many dimensionsOrganizational structures
Development processes
Oversight and decision/approval
Funding and acquisition
etc….
• Identify partnering issues along these and other dimensions…
PMC2010: Partnering challenges on large projects 7W. Miller
Comparative anatomy of agency science structures
FPD Federal Project DirectorOECM Office of Engineering and Construction MgmtOPA Office of Project AssessmentSRB Standing Review Board
LFO Large Facilities OfficeNSB National Science BoardS&E Science and engineering
Provides policyProvides independent review
$33.8B
$4.8B $4.5B
$17.8B
$2.0B
$6.5B
$5.3B
Budgets: FY 2009 plans (no ARRA), from FY2010 Requests
“Project assurance” bodies
DOESecretary
Program Offices
Laboratories
Projects
OPA
Programs
Centers
Projects
Science MissionsDirectorate
NSFDirector
Programs
Awardees
Projects
Directorates& Offices
NASAAdministrator
ChiefEngineer
NSB
SRBs PanelsDivisions
Divisions
UnderSec
Divisions
42 U.S.C.§1873b(“shall not operate
laboratories”)
Adm
inis
trat
ion
Prog
ram
sPr
ojec
ts
FPDs
Ofc of Science
ManagementSupport Office
OECM
Budget, Finance& Award Mgmt
LFO
PMC2010: Partnering challenges on large projects 8W. Miller
Development process framework look at elements
Earlyacquisitions
Early operations
ProjectCloseout
TerminateFacility
Development
Conceptualization& Prioritization Construction DOperations
Begin majorInvestment
Conceptual
Preconstruction Planning*Preliminary
Finaldesign
Ongoing community input, horizon planning, reprioritization, and portfolio adjustment
*Also called definition, formulation, front-end planning…
• Plan Management/governance plans, WBS assemble project team• Design Goals, requirements iterative design bring to readiness• Invest R&D, necessary technologies bring to readiness• Estimate Effort, cost, schedule, reserves, risks refine to believability• Govern Progress oversight and decision-making
PMC2010: Partnering challenges on large projects 9W. MillerW.Miller - Big Projects & Sponsor Processes 9ProjSci Oct 22, 2009
ImplementationFormulation
ConceptStudies
Prelim Design & Tech Completion
Final Design & Fabrication*
Assembly, Integ & Test,
LaunchOperationsConcept &
Tech Devel
Pre-Phase A Phase A Phase B Phase C Phase D Phase E
KDP-A KDP-B KDP-C KDP-D KDP-ENASA-SMD Ref: NASA NPR 7120.5D
Development processes: alignment and terminology
MCR MDRSRR
PDR CDR SIR
ORR
FRRLRR PLAR
CERR
CDR Critical Design ReviewCERR Critical Events Readiness ReviewFRR Flight Readiness ReviewLRR Launch Readiness ReviewMCR Mission Concept ReviewMDR Mission Definition Review
ORR Operational Readiness ReviewPDR Preliminary Design ReviewPLAR Post-Launch Assessment ReviewSDR System Definition ReviewSIR System Integration ReviewSRR System Requirements Review
*elongated to visually align NASA, NSF & DOE equivalent events. Sequences on this chart do not represent typical or relative phase durations.
Key Decision Point (KDP) approvalsKDP-C Approve Implementation
CDR PDR FDR Ops
NSB Approved
Preliminary Design Final Design Construction OperationsHorizon planning and
Conceptual Design
Readiness
NSFRef: NSF 0738CDR Conceptual Design ReviewFDR Final Design ReviewPDR Preliminary Design ReviewOps Operations Review
ApprovalsPost-CDR Approve advance to ReadinessPost-PDR Approve submission to Nat. Science Board (NSB)Post-FDR Congress appropriates MREFC fundsPost-Ops Approve Operations start
IPR** CDR EIRPDR
FDRIPR/EIR**
ORR/RA
**CD-0 IPR and CD-3 EIR for >$750M projects
CDR Conceptual Design ReviewEIR External Independent Review (OECM)FDR Final Design ReviewIPR Independent Project Review (SC)ORR Operations Readiness ReviewPDR Preliminary Design ReviewRA Readiness Assessment
Critical Decision (CD) approvalsCD-0 Approve mission needCD-1 Approve Alternatives selection & cost rangeCD-2 Approve Performance baselineCD-3 Approve Construction startCD-4 Approve Operations start
DOE-SCRef: DOE O 413.3A
Execution
Pre-conceptualPlanning
Trans/CloseoutOperations
ConceptualDesign
CD-0 CD-1 CD-2 CD-4CD-3
Initiation Definition
PreliminaryDesign Final Design Construction
Decision
WLM Rev2.05052009
Review
PMC2010: Partnering challenges on large projects 10W. Miller
Oversight: two modes of assessment
Conception PreconstructionPlanning Construction DOperations
Initiate Ready Finished
Review &Approve
Qualitativeassessment
(Reviews at major milestones)
Quantitative Tracking
-0.60
-0.40
-0.20
0.00
0.20
0.40
CV
SV
• EVM required by OMB for major projects
• Industry standards• Encourages baselining• Fuller assessment of
outcomes
PMC2010: Partnering challenges on large projects 11W. Miller
Review-based oversight and decision/approval
Independent Review
Internal decisionsupport
Sign Off(e.g. Implement Project)
NASAPDR
by Standing Review Board
Program Mgmt Council
• Program Manager• Center Mgmt Council• Technical Authority• Project Manager
KDP-CDecision Authority (DA)
(AA for Cat 1, otherwise MDAA)Approve Implementation
(Enter Phase C – Final Design & Fab)
NSFPDR
by Review PanelNSF Director
MREFC* Panel• CFO, DDLFP• Directorate/Division• Program Officer
NSB Approvalfor inclusion in a future
budget in MREFC* construction account
DOEPDR
by OPA“Lehman Review”
(also: EIR by OECM)
Energy Systems Acquisition Advisory Board (ESAAB)
• OPA briefs AE, calls ESAAB• Federal Project Director
CD-2Acquisition Exec (AE)
(DepSec, US Sci, SC Dir/AD)Approve Performance Baseline
(Enter Final Design Stage)
* Major Research Equipment and Facilities Construction
PMC2010: Partnering challenges on large projects 12W. Miller
Baseline establishment – with focus on cost
“Baseline”(what you were promised)
“Outcome”(what you got)
During construction, projects performance assessed relative tobaseline…
CostCost
DOE • “Bottom-up" Independent Cost Estimate (ICE) or Independent Cost Review as part of External Independent Review for CD-2.
NASA • Project’s bottom-up Life-Cycle Cost Estimate (LCCE).
• ICE prepared and owned by the Standing Review Board (SRB), (generally parametric, using same definitions as LCCE)
Project must reconcile ICE with LCCE at Preliminary Design Review.
NSF • Bottom-up cost estimate in proposal.
• NSF may acquire an independent top-down estimate for comparison.
Cost estimation toward the baseline:
PMC2010: Partnering challenges on large projects 13W. Miller
Funding
MO&DAProgram Funds, project line-itemMission Operations and Data Analysis
ExecutionPre-conceptual
PlanningTrans/Closeout
OperationsConceptual
Design
CD-0 CD-1 CD-2 CD-4CD-3
Initiation DefinitionPreliminary
Design Final Design Construction
NSB ApprovedPreliminary
Design Final Design Construction OperationsHorizon planning and Conceptual Design
Readiness
R&RAProgram Funds (Research & Related Activity, R&RA) MREFCMajor Research Equipment and Facilities Construction
ConceptStudies
Prelim Design & Tech Completion
Final Design & Fabrication*
Assembly, Integ & Test,
LaunchOperationsConcept &
Tech Devel
Pre-Phase A Phase A Phase B Phase C Phase D Phase E
KDP-A KDP-B KDP-C KDP-D KDP-E
Formulation Implementation
Requires separate appropriation
Program Ops FundsLIC Prelim Engr & Design (PED)Program Funds
Two modes for intramural projects: Line Item Construction (LIC) orMajor Item of Equipment (MIE, no major construction)
Major Item of Equipment (MIE) LIC Construction
NASA-SMD
NSF
DOE-SC
• Separate funds support research (Research and Analysis, R&A)
• Same funds support research (Research & Related Activities, R&RA)
• Separate funds support research
PMC2010: Partnering challenges on large projects 14W. Miller
Scope
How do partner processes and practices align? (Start with agencies)
What are the challenges and best practices for partnering? Try to “systematize”
Sources: • Interviews with ~45 stakeholders for study• “Lessons learned” and other reports
PMC2010: Partnering challenges on large projects 15W. Miller
Some recent cases of major partnered projects
NASA DOE NSF International
Ulysses ▲ ESA
Cassini ▲ ESA, ASI
Tropical Rainfall Measuring Mission (TRMM) ▲ Japan/JAXA
Global Precipitation Measurement (GPM) ▲ Japan/JAXA
Fermi (operating) ▲ ▲
LHC (operating) ▲ ▲ CERN members
International Ocean Drilling Program (IODP) ▲ Japan/Mext
Atacama Large Millimeter Array ▲ Europe, Japan, Asia
PMC2010: Partnering challenges on large projects 16W. Miller
Examples of interagency Joint Oversight Groups (JOG)
• DOE-NASA: FERMI, Joint Dark Energy Mission
• NSF-DOE: U.S. Large Hadron Collider (LHC), Deep Underground Science and Engineering Laboratory (DUSEL, in planning)
PMC2010: Partnering challenges on large projects 17W. Miller
-Source: R. Staffin, 14Feb2006, FY06 presentation to HEPAP, www.er.doe.gov/hep/files/pdfs/HEPAPFeb142005Staffin.pdf
Partnering Levels of impedance (mis)matches
Strategicvaluation
Technicaldomains
Managementpractices
Capabilities& Practices
Better planning could involve assessment of COMPLEMENTARITY across capabilities, practices, lessons learned, etc…)
PMC2010: Partnering challenges on large projects 18W. Miller
Challenges: Strategic Management Technical
• Valuation. How highly does each partner prioritize the project – and how much is it willing to spend based on that priority? What does it expect as an outcome (science, jobs, prestige) and when? Where does it fit in the partner's national plan?
• Goals and roles. Are the overall goals and specific objectives shared? Does each partner want a leadership or participatory role? How committed are the commitments?
• Approval and allocation. Which hoops does each partner have to jump through to obtain funding and approval? What are the pressures? What is the funding source and cycle? How long does prioritization and approval typically take?
PMC2010: Partnering challenges on large projects 19W. Miller
Challenges: Strategic Management Technical
• Role of project management. Is project management valued? Are managers well chosen, given sufficient authority? Who do they report to?
• Project definition and baselining. How are requirements, risks and baseline elements defined, documented and managed? Change control? How much emphasis placed on system I&T and operations planning?
• Budgeting. Can be large differences in costing – e.g. labor cost inclusion in project budgets. Can funds be used early, carried-over? Contribution approach (in kind, etc.)? How are contingency and reserve handled?
• Oversight. Partners may not perform reviews with the same rigor or frequency. Identified problems may be addressed with less urgency. What systems do partners use for tracking and quantifying performance?
• Cultural differences. Sense of urgency to obtain desired outcome? Consequences of (and solutions adopted for) cost overruns, late development, poor performance, outright failure?
PMC2010: Partnering challenges on large projects 20W. Miller
Challenges: Strategic Management Technical
• Complementarity. Synergies among partners in technical know-how relative to requirements of the project? Is at least one partner strong in each area? What are the gaps?
• Design process. What approaches are employed by each partner? How are software and IT systems developed?
• Systems engineering. To what degree is systems engineering valued by each partner? Is each partner familiar with establishing interfaces? With I&T planning?
• HR. How do partners obtain their skill contributions – via contractors, in-house staff, exchanges of personnel from member academic institutions…? Workforce stablity?
PMC2010: Partnering challenges on large projects 21W. Miller
Synchronizing “On-ramps”: when does a project start?
DOE • Projects identified in a SC 20-year prioritized facility plan1
• Establish “mission need”, feasibility at CD-0 Definition phase
NASA • Strategic and Science Plans2 based on Decadal Surveys, roadmaps.
Two flavors:• Strategic missions are internally initiated (KDP-A) and managed• “PI-led” missions are competed in Phase A selected Phase B
NSF • Peer-reviewed unsolicited proposals, workshops, studies, etc.• Evolved concepts may be brought to development
“Mission-driven” – projects determined via strategically-defined goals and priorities
1. Facilities for the Future of Science, A twenty year outlook, DOE/SC-0078, Dec 2003; and Four Years Later: an Interim Report on Facilities for the Future…, Aug 2007. 2. NASA Strategic Plan, 2006; and NASA Science Plan 2007–2016
“Community-driven” – projects “bubble up” from the scientific disciplines
ConceptualizationConceptual Preliminary Final
Preconstruction Planning
?
PMC2010: Partnering challenges on large projects 22W. Miller
Reported best practices – responses to challenges• Early engagement. Agree on clear goals, timeframe, and effective
membership rules and governance structure. Having a dominant partner may work best…
• Communication. Identify the appropriate interfaces at all levels. Maintain open, frequent and honest communication.
• Complementarity. Learn partner enterprises and realities. Identify technical domains required and respective partner(s) capabilities.
• Strong project management. Devise clear process for project management and oversight. Aim for integrated a single project management team, in place before funding begins and with effective budget authority (not just a coordinator).
• Budgeting. Aim to adopt standard costing and budgeting techniques.
PMC2010: Partnering challenges on large projects 23W. Miller
AcronymsCD Critical Decision (DOE)
CDR Conceptual Design Review (DOE, NSF)Critical Design Review (NASA)
DDLFP Deputy Director for Large Facility Projects, head of LFO (NSF)
EIR External Independent Review (DOE OECM)
IPAO Independent Program Assessment & Oversight Office (NASA)
KDP Key Decision Point (NASA)
LFO Large Facilities Office (NSF)
MO&DA Mission Operations and Data Analysis funding account (NASA)
MREFC Major Research Equipment and Facilities Construction funding account (NSF)
NAR Non-Advocate Review (PDR, NASA)
OECM Office of Engineering and Construction Management (DOE)
OPA Office of Program Assessment (DOE/SC)
PED Preliminary Engineering and Design funding account (DOE)
PDR Preliminary Design Review
PNAR Preliminary Non-Advocate Review (MDR, NASA)
R&RA Research and Related Activities funding account (NSF)
R&A Research and Analysis funding account (NASA)
SC Office of Science (DOE)
SRB Standing Review Board (NASA)
SMD Science Missions Directorate (NASA)