Top Banner
New Developments in Heavy Haul in South Africa Heavy Haul Rail Africa 2014 March 2014 W C Kuys: Project Director, TFR
43

Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

Jan 21, 2015

Download

Business

Willem Kuys, Project Director at TFR delivered the presentation at the 2014 Heavy Haul Rail Africa Conference.

The Heavy Haul Rail Africa Conference 2014 covers all the relevant issues including government and resource sector perspectives on future developments in heavy haul rail infrastructure, opportunities to source relevant funding, regulatory progress, challenges in planning and construction, rolling stock requirements, maintenance and capacity enhancement.

For more information about the event, please visit: http://www.railconferences.com/hhrafricaconference
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

New Developments in Heavy Haul in South Africa

Heavy Haul Rail Africa 2014

March 2014

W C Kuys: Project Director, TFR

Page 2: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

2

Presentation Outline

1 Introduction

2 Heavy Haul in South Africa: Context

3 The Richards Bay Coal Export line

4 The Sishen – Saldanha Iron Ore Export line

5 Challenge: Apply HH Technology on GF Lines

6 Practical Application of HH Technology in GF

7 Processes to be developed

8 Future Capacity Expansions

9 Heavy Haul: Concluding Remarks

Page 3: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

3

Introduction

o  Coal and Ore Lines heavy haul operations

o  Lessons and technology developments

o  Application of some heavy haul principles on GF

o  Building blocks to support GF higher tonnages

o  Concluding remarks

Page 4: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

4

Presentation Outline

1 Introduction

2 Heavy Haul in South Africa: Context

3 The Richards Bay Coal Export line

4 The Sishen – Saldanha Iron Ore Export line

5 Challenge: Apply HH Technology on GF Lines

6 Practical Application of HH Technology in GF

7 Processes to be developed

8 Future Capacity Expansions

9 Heavy Haul: Concluding Remarks

Page 5: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

5

Transnet Freight Rail Network

Sishen

Saldanha

Cape Town

East London

Port Elizabeth

Hotazel

Durban

Musina

Kimberley

Lephalale Polokwane

De Aar

Richards Bay

Johannesburg

Ngqura

Core Freight Lines

Branch lines

Not active

Picked up Lines

Heavy Haul Coal Export Line

Ermelo

30t/axle 26t/axle

Heavy Haul Iron Ore Export Line

1067mm Gauge

2ND Longest Heavy Haul line in the world @ 861 km

7% of route kilometre

588 km from Mpumalanga Coalfields

Page 6: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

6

o  60% of present Volumes generated from coal and iron ore exports

o  Renewed effort to regain revenue and volumes.

o  Emphasis on General freight growth that is critical for viability. Grow to 50% of total volumes

Heavy Haul Iron Ore line

Heavy Haul Coal line

General Freight

Transnet Freight Rail: Market Demand Strategy (Mt)

Page 7: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

7

Presentation Outline

1 Introduction

2 Heavy Haul in South Africa: Context

3 The Richards Bay Coal Export line o Profile

o Operating Philosophy

o Technology

o Technologies embedded

o Future Challenges/Strategy

4 The Sishen – Saldanha Iron Ore Export line

5 Challenge: Apply HH Technology on GF Lines

6 Practical Application of HH Technology in GF

7 Processes to be developed

Page 8: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

The Coal Line: Profile Distance +/- 580km from Blackhill to Richards Bay

Topography o Descends from 1700 meters altitude to sea level

o Undulating topography and high rainfall

Axle loads 26 t/axle on heavy haul and some feeder lines

Ruling Gradient 1:100 North of Ermelo 1:160 for loaded trains South of Ermelo on one of the two tracks, and 1:66 for empties

Traction 3kV DC: North of Ermelo 25kV AC: South of Ermelo

Civil 137 bridges, 37 tunnels Overvaal tunnel = 4 km (single)

# of lines Double, 3rd line on some feeder sections

Authorisation Colour light signalling with CTC

Locomotives o 7E/11E on AC, 10E on DC sections o 110 new AC/DC 19E in commissioning

Wagons CCL gondola: max payload of 84 tons

Gross tons per train 22 000 tons at 2,2km in length

Volumes in 2012/13 63 mt export coal, 11 mt general freight

Capacity 74 mt export coal; 14 mt general freight

Competitiveness Most affordable global coal transporter

Page 9: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

9

Coal line: Complexity of Operations o  Operating Philosophy

  100 wagon trains on the feeder line ; train sets combined at Ermelo as 200 wagon trains to RBCT

  Loaded coal trains are run separately from general freight trains

o  Richards Bay is developing as a mega bulk port

o  Coal line is becoming a multi-product bulk export line   Coal export and general freight

‘systems’ evident

  General freight potential in excess of 30mt

o  Shifting of coal sources to Waterberg and Botswana   Longer haul distance

  Longer trains north of Ermelo

  Interim sourcing over GF lines

Ermelo

General Freight Source Areas

Rustenburg

Lephalale

Richards Bay Coal

Source Areas

Steelpoort

Soutpansberg

Phalaborwa

Extension of the ‘pipe’ from 600km to 1200km Increase in length of haul warrants review of longer trains

Page 10: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

10

Coal line: Major Technologies Embedded

o  Increases capacity: Higher speeds & improved braking

o  Improves train handling - related derailments and train breaks

o  Improves turnaround time

o  Increase Safety margins

o WDP being deployed

o Utilised on AD & DC powered sections or run

through

o Reduces cycle times in change over yards

o  Improved energy efficiency of 18%

o Regen capability

o  Increase reliability and availability of the

locomotive fleet – AC traction motors

o  Freeing up of class 7E and 10E locomotive

fleet to address the GFB growth requirement

ECP/WDP

BEN

EFIT

S

New 19 AC/DC

Locomotives

Page 11: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

11

The 19E AC/DC Locomotive

Page 12: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

12

Coal Export line: Future Challenges/Strategy

Page 13: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

13

Presentation Outline

1 Introduction

2 Heavy Haul in South Africa: Context

3 The Richards Bay Coal Export line

4 The Sishen – Saldanha Iron Ore Export line

o Profile

o Operating Philosophy

o Technologies Embedded

o Future Strategy

5 Challenge: Apply HH Technology on GF Lines

6 Practical Application of HH Technology in GF

7 Processes to be developed

8 Future Capacity Expansions

Page 14: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

14

Iron Ore Line: Profile

Distance 861 km

Topography Semi-desert, descending to the coast from 1 295 m above sea level at the Sishen mines.

Axle loads Operated at 30 t/axle

Ruling Gradient 1:250 loaded trains 1:100 empty trains

Traction 50kV AC

Civil Olifantsrivier Bridge

# of lines Single line with crossing loops at 40km intervals

Train Authorisation SIMS-S colour light signalling

Locomotives o Class 9E and 34 Class Diesels o Class 15 E locomotives being commissioned

Wagons CR type: max payload of 100 tons

Gross tons per train 41 000 tons @ 4km train length

Volumes in 2010/11 55 mt export iron ore, 1 mt general freight

Capacity 60 mt infrastructure capacity

Competitiveness Longest heavy haul production trains in the world

Page 15: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

15

Iron Ore Line: Operating Philosophy

To Saldanha Steel

KUMBA/ASSMANG/BURK/Small loaders Loading Stations

Port Terminals Tippler, Stacking/

Reclaiming

Port Terminals Reclaiming & Ship Loading

SALKOR Compiling/De-compiling trains, Shunting, NTG, Wagon & Locomotive maintenance

Rail operations Train operations, Crews, Traffic Control, Per way, Communication, Signalling, Power supply, Infrastructure- and Rolling Stock maintenance Haul distance of 860 km

Beeshoek

New Kolomela

link ERTS

Khumani

National Ports Authority Berth capacity, Berths,

Marine services

Halfweg – Re- manning of trains Crew book off

342 wagon RDP Trains – total mass 41 000 tons 114 wagon rakes – total mass 13 667 tons

System 1: Mines System 2: Rail System 3: Stockpile System 4: Ship-loading

1 2

4 3

Page 16: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

16

Iron Ore Line: Technologies Embedded

o  DP (RDP) Longest operational trains in the world   RDP – Quickly implementation on new routes

o  DP with mixed locomotive fleet   9E electric locomotives

  Old Class 34 diesel locomotives

  New 15E electric locomotives

  New Class 43 diesel locomotives

  Complex: Non homogeneous tractive effort

o  Train dynamics   Long train over various grades

  Complements: Technical team AND Train Drivers

Page 17: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

Train over various grades

17

0  

1  

2  

3  

4  

5  

6  

7  

8  

9  

1   6   11   16   21   26   31   36   41   46   51   56   61   66   71  

Gradient  

Gradient  

Page 18: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

18

Iron Ore Line: Technologies Embedded

o  DP (RDP) Longest operational trains in the world   RDP – Quickly implementation on new routes

o  DP with mixed locomotive fleet   9E electric locomotives

  Old Class 34 diesel locomotives

  New 15E electric locomotives

  New Class 43 diesel locomotives

  Complex: Non homogeneous tractive effort

o  Train dynamics   Long train over various grades

  Complements: Technical team AND Train Drivers

o  Energy efficient locomotives   Power Factor close to 1 - 18 % energy saving

  Regen capability of locomotives – 20% to 30% of trip power returned to grid

o  AC traction motors   Maintenance

  Adhesion

  Minimal overheating at low speeds

o  Supporting infrastructure

Page 19: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

19

Iron Ore Line: Supporting Infrastructure

Wayside Monitoring o  VIS Vehicle Identification System o  Hot Box Detector o  Dragging Equipment Detectors o  Wheel Impact Monitoring System o  Wheel profile monitoring system o  Skew bogie detector o  BAM- Bearing Acoustic Measuring System for wheels

o  WILMA - Wayside Intelligent Long-stress Management system. o  UBRD – Ultrasonic Brocken Rail Detector system

Signalling

o  Electronic interlocking

o  Saldanha CTC via microwave communication/fibre

Telecommunications Telecommunication system is being upgraded to TCS-R and GSM train communication Constrained by SKA (Square Kilometer Array radio telescope)

Page 20: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

20

342 Wagon RDP Train

End of train @ 4 kilometres

Page 21: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

21

Iron Ore Line: Future Strategy

o  Upgrading of capacity on the Ore line is crucial

for:

  the development of the mineral rich Northern

Cape

  Retaining a competitive export channel

  Supporting sustainable development of

emerging and junior miners

o  Expansion Challenges for Ore Line   Electric Traction Power   Incremental infrastructure steps high   GF Traffic

o  Expansion of the corridor to 82mt of iron ore

being investigated   Third tippler in Saldanha Port

  Additional infrastructure capacity – GF Trains

  Present Port capacity 58 mtpa – Major expansion required

Sishen

Saldanha

Page 22: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

22

Salkor Office block

Ore Yard

General freight yard

Work-shops

Port of Saldanha Ship Loader

Saldanha: Infrastructure

Page 23: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

23

Presentation Outline

1 Introduction

2 Heavy Haul in South Africa: Context

3 The Richards Bay Coal Export line

4 The Sishen – Saldanha Iron Ore Export line

5 Challenge: Apply HH Technology on GF Lines

6 Practical Application of HH Technology in GF

7 Processes to be developed

8 Future Capacity Expansions

9 Heavy Haul: Concluding Remarks

Page 24: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

24

Challenge: Apply HH Technology on GF

o  Options to increase rail capacity are:   Increase train speeds

  Increase axle loads of wagons

  Increase the train lengths

  Additional crossing loops to run more trains at shorter intervals

  Clever signalling to increase slot utilisation

o  Longer trains the most attractive in the short term   Long hauls

  Set-up time

  Terminals and yards

  Incremental roll-out

  Short hauls

Page 25: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

25

Challenge: Apply HH Technology on GF

o  Distributed Power   Long trains – Joining short trains

  One crew

  RDP and ECP/WDP - Both technologies operational in TFR

o  Modern locomotives opens new opportunities   Energy savings – Efficient and regen

  Maintenance & reliability – Better scheduled railway

  Better adhesion – Creep over steep hills

  Locomotives must work hard!

o  Simulations   Operations

  Yards

  Look into the future

  Assume a scheduled railway

Page 26: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

26

Operational Slot Design

o  Empiric rule: Practical train plan only 66% of maximum slots o  34% for Catch-up/Recovery and

Infrastructure maintenance

o  Recovery implies bunching:   Power peaks   Terminal block-out

  Less maintenance time

Slots

Page 27: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

27

Operational Slot Design

o  Empiric rule: Practical train plan only 66% of maximum slots o  34% for Catch-up/Recovery and

Infrastructure maintenance

o  Recovery implies bunching:   Power peaks   Terminal block-out

  Less maintenance time

Slots

o  Integrate the following requirements:

  Balanced operations

  Operational efficiency – Old unreliable equipment

  Infrastructure Maintenance – Accommodate special requirements

  Character of line – Long single line/Double line

  Capacity level of line – Construction requirements before capacity

increase

o  Do not steal slots! Deny maintenance justifiable time on track

Operational

Designs

Page 28: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

28

Presentation Outline

1 Introduction

2 Heavy Haul in South Africa: Context

3 The Richards Bay Coal Export line

4 The Sishen – Saldanha Iron Ore Export line

5 Challenge: Apply HH Technology on GF Lines

6 Practical Application of HH Technology in GF

o Manganese Corridor

o Waterberg Corridor

7 Processes to be developed

8 Future Capacity Expansions

9 Heavy Haul: Concluding Remarks

Page 29: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

29

Development of the Manganese Corridor

o  Manganese presently being exported from the Northern Cape to Port Elizabeth with 104 wagon GF trains at 20 ton per axle

o  This corridor is being developed using heavy haul principles to:

  Expand capacity to 16mtpa

  Retain the exports in the Eastern Cape with economic benefits for Ngqura

harbor and the Coega IDZ

  The manganese channel investment allows TFR to:

  Diversify overall network investment;

  Densify this critical GF corridor, and

  The flexibility to utilise rolling stock elsewhere in commodity downturns

Page 30: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

8  

4  x  104  (1:80)  

22  19  16  

4  x  183  (1:80)  

4  x  246  (1:100)  

4  x  200  (1:80)  

4  x  216  (1:100)  

Million  tons  per  annum  

Op=

ons  Develop

men

t  

20  ta

l  26  ta

l  

Manganese Corridor: Volume Ramp-up Strategy

•  Optimal (overall system cost) short term ramp-up in line with demand is 16Mtpa with logical capacity

breakpoints at 8 and 16Mtpa

•  Significant capital cost increase beyond 19Mtpa due to Eskom upgrade

•  Concurrent conversion of corridor to 26t/axle through sustaining capex will allow future operation of

integrated heavy haul system

Train  configura>on  Development  path  

Page 31: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

Manganese Corridor: Systems Solution

Mamathwane  Compila>on  Yard  

Coega  Compila>on  Yard  

100  wagons  

100  wagons  

200  wagon

 trains  

Operating Philosophy

•  16Mtpa solution based on heavy

haul principles (long trains and

operations)

•  200 wagon + 9 dual voltage loco

RDP trains between compilation

yards

•  100 wagon unit train distribution

to mines and tippler yard with

diesel locos

•  Main line & distribution operated

by TFR

•  4 x 200 wagon trains / day, 350

days/annum

Page 32: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

32

Development of the Waterberg Corridor

o  Augment coal for the Witbank basin   Eskom coal requirements for power stations

  Domestic coal

  Export coal

o  Long Term: New heavy haul line Lephalale-Thabazimbi-Ermelo   Long new line, 558km

  All or nothing

o  Interim: Develop existing line to 25mtpa   Schedule & Costs

Page 33: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

33

Development of the Waterberg Corridor

o  Augment coal for the Witbank basin

o  Long Term: New heavy haul line Lephalale-Thabazimbi-Ermelo

o  Interim: Develop existing line to 25mtpa

o  Thinking:   Long DP trains on existing GF line – 200 wagons

  Incremental development – 3 short trains, 3 long trains, 6 long trains

  Technologies   DP – ECP/WDP (Mixed locomotives, later all electric)

  AC/DC locomotives – Run through AC/DC sections

  DP train know how

  Challenges

  Traction Power

  Gradients

  Compiling and splitting of 200 wagon trains

o  Processes to develop

Lephalale (Ellisras)

Atlanta

Matlabas

Thabazimbi

Pendoring Pyramid Pyramid South

Ogies

Witbank Greenview

Vaalwater

Springs Welgedag

Trichardt

Modimolle (Nylstroom) Naboomspruit

Rustenburg

Polokwane

Roossenekal

Belfast Boshoek

Steelpoort

Groenbult

Blackhill

Gaborone

Wonderfontein

Hamelfontein ERMELO

Bela-Bela (Warmbaths)

BOTSWANA RSA Maha

lapye

Page 34: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

34

Presentation Outline

1 Introduction

2 Heavy Haul in South Africa: Context

3 The Richards Bay Coal Export line

4 The Sishen – Saldanha Iron Ore Export line

5 Challenge: Apply HH Technology on GF Lines

6 Practical Application of HH Technology in GF

7 Processes to be developed

8 Future Capacity Expansions

9 Heavy Haul: Concluding Remarks

Page 35: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

35

Processes to be Development for long GF DP trains

o  Longer trains on existing GF infrastructure is the future to successfully enhance volumes at reasonable costs.

o  Long trains work well over long haul distances

  The set-up time to compile and decompile long DP trains

  Dual voltage electric locomotives increases haul distances.

  Diesel powered trains

  Mixed traction (Dual voltage locomotives combination with diesel locomotives)

o  The OHTE power supply a constraint with all electric powered long heavy DP trains

o  The key lever in running long trains is the DP technology. DP trains the platform to

launch long trains in GF

o  Five supporting sub-processes to be develop and refine to enhance the efficiency of

long DP trains

Page 36: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

36

Five Processes to Develop

1.  On the Fly AC/DC changeover points

  The On the Fly AC/DC changeover points to be tested soon.

  The AC/DC technology on 19E locomotives will then also be tested thoroughly.

2.  Compiling and Decompiling DP trains

  Presently DP trains are compiled and decompiled in a yards

  Develop processes to couple/split DP train outside yards on a single loop

  Reduce setup time and yard infrastructure

3.  Brake Test Requirements

  Reducing the brake test time of coupling and splitting DP trains to less than 10 minutes.

  Do not compromise safety

4.  Crawling of trains over steep inclines

  Negotiate trains over inclines at less than the balancing speed of the locomotives.

  Especially possible with locomotives fitted with AC traction motors with higher adhesion levels

5.  Telemeters for DP Trains

  Telemeters required for all trains

  Develop a telemeter that is attached on the last wagon, but not fitted on the buffer.

  Join and split DP trains without removing the telemeter.

Page 37: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

37

Presentation Outline

1 Introduction

2 Heavy Haul in South Africa: Context

3 The Richards Bay Coal Export line

4 The Sishen – Saldanha Iron Ore Export line

5 Challenge: Apply HH Technology on GF Lines

6 Practical Application of HH Technology in GF

7 Processes to be developed

8 Future Capacity Expansions

9 Heavy Haul: Concluding Remarks

Page 38: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

Saldanha

Cape Town

East London

Durban

Richards Bay

De Aar

Ngqura

Botswana

Zimbabwe

Namibia

Maputo

Swaziland

Mozambique

Future Developments

• Due to the interfaces and dependencies, work packages need to be progressed within a holistic Coal Strategy.

Coal Backbone

Swazi link

Techobanine

23

4

1

SA-Botswana link

1 2 3 4

Central Basin Waterberg Fields Botswana South Fields Soutpansberg/ Limpopo

Lephalale

Ermelo

List Projects Waterberg Upgrade existing line

New heavy haul

Manganese

Ore Line 82mtpa

Maputo link Coal 81/91mtpa

Page 39: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

39

Presentation Outline

1 Introduction

2 Heavy Haul in South Africa: Context

3 The Richards Bay Coal Export line

4 The Sishen – Saldanha Iron Ore Export line

5 Challenge: Apply HH Technology on GF Lines

6 Practical Application of HH Technology in GF

7 Processes to be developed

8 Future Capacity Expansions

9 Heavy Haul: Concluding Remarks

Page 40: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

40

Concluding Remarks

o  Heavy Haul operations provides a commercial, competitive advantage in economies with vast mineral resources

o  Heavy haul operations in South Africa are at the cutting edge of technology on a 1067mm gauge rail system

o  The heavy haul technologies and heavy haul principles can be implemented in GF to:

  Enhance MDS volumes

  Develop GF corridors in semi-heavy haul operations

o  Five processes must be further developed for the flexible implementation of long trains on GF lines

o  Operational staff to be developed to operate these sophisticated system

Page 41: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

Thank You

Page 42: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

42

Page 43: Willem Kuys, TFR - New Developments in Heavy Haul in South Africa

43

Ore line: 1:250

Mn: 1:80