1 Demand-Side Management Bruce Folsom, Regulatory Compliance Manager before the DSM Subcommittee of the Interim Energy Committee August 23, 2006
36

Why Avista Does DSM

Feb 04, 2016

Download

Documents

hisoki

Demand-Side Management Bruce Folsom, Regulatory Compliance Manager before the DSM Subcommittee of the Interim Energy Committee August 23, 2006. Fulfilling Avista’s least-cost resource acquisition obligation Customer Service Customers expect Avista to be their “energy experts” - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Why Avista Does DSM

1

Demand-Side Management

Bruce Folsom, Regulatory Compliance Manager

before theDSM Subcommittee of theInterim Energy Committee

August 23, 2006

Page 2: Why Avista Does DSM

2

Why Avista Does DSM

• Fulfilling Avista’s least-cost resource acquisition obligation

• Customer Service

– Customers expect Avista to be their “energy experts”

• Community Service

– Helps meet needs of the limited income community

• Economic Development

– Cost-effective DSM improves the competitiveness of existing customers in national and world-wide markets

Page 3: Why Avista Does DSM

3

How Avista Does DSM:Northwest Electric DSM Basics

• Electric DSM history:

– The Regional Review of the 1990’s established a non-binding recommendation for a 3% public purposes charge for, among other things, electric-efficiency funding

– Deregulation and the prospects for vertical disintegration led to the “stranded rate base” issue in the early ’90s

– Northwest utilities substantially reduced DSM funding

– Washington Water Power initiated a “non-bypassable public purposes charge,” the first in the country, to continue DSM by:

• Establishing funding for DSM that was not subject to the utility capital budgeting process

• Ensuring timely cost-recovery for DSM investments without incurring the risks of stranding rate base

Page 4: Why Avista Does DSM

4

How Avista Does DSM:Natural Gas DSM Basics

• Natural Gas DSM

– Prior to 2002 natural gas DSM was difficult to “sell”

• Natural Gas DSM typically:

– Used in passive end-uses (space and water heating)

– Was inexpensive

– Has fewer efficient technology alternatives

– Doesn’t incur the same environmental concerns as electric

• MUCH of this has changed since 2002

– Future natural gas DSM planning does not have a rich historical precedence as found on the electric side

• Own-price and cross-price elasticity issues currently being analyzed

Page 5: Why Avista Does DSM

5

How Avista Does DSM:Regulatory & Political History

• The tariff rider approach is favorable in that:

– Provides a significant funding mechanism for DSM to meet customer need

– It shields DSM infrastructure from fluctuating capital budgets

• And unfavorable in that:

– Utilities aren’t permitted to earn on what would otherwise be a very secure investment

• This approach has been widely copied throughout the country

• There is no significant internal or external demand for revising this successful approach to DSM funding

Page 6: Why Avista Does DSM

6

How Avista Does DSM:Regulatory & Political History

• Avista has used the “non-bypassable public purposes” tariff rider funding since 1995

– A tariff surcharge on

• All retail electric customers

• All non-transport gas customers

– Excludes transport schedules 146 and 148

– Surcharges tariffed as Schedule 91 (electric) and Schedule 191 (natural gas)

– Tariff rider levels have changed several times since this time, generally ranging from

• 1.00% to 1.95% electric

• 0.00% to 0.96% natural gas

Page 7: Why Avista Does DSM

7

External Energy Efficiency (“Triple-E”) Board

• Successful stakeholder participation• Non-binding external oversight board

– A sounding board and communication vehicle– The board can convene their own meetings and make board

recommendations to regulators• Two traditional meetings per year• Quarterly newsletter established 2005• “Triple-E Reports”

– Primary tool for communicating cost-effectiveness, measurement & evaluation (M&E), resource acquisition, disclosure

– Used as a basis for DSM regulatory and informational requests– Summarizes selected managerial accounting and analysis findings

Page 8: Why Avista Does DSM

8

Our Tariffs and Programs• Programs regulated under Schedules 90 (electric) and 190 (gas)

– Electric incentives increased in early ’05 (ID) and mid ’05 (WA)

• Incentives based upon– Customer simple payback– First-year kWh’s or therms– Tiered incentive structure

• Addresses “free-ridership” issues with regulators• Increases incentive $ per kWh / therm results• Subject to 50% and 30% cap

– Commercial / Industrial applications• “Site-Specific” programs subject to Dual Fuel Incentive

Calculation– An “anything qualifies” program

• Prescriptive programs conform with tariff based on prototypical application

– Reduces administrative cost (used for routine, homogenous measures)

Page 9: Why Avista Does DSM

9

Electric DSM Incentive Tiers

$-

$0.02

$0.04

$0.06

$0.08

$0.10

$0.12

$0.14

$0.16

0 20 40 60 80 100 120 140 160 180 200

$ per first-year kWh

Mon

ths

Sim

ple

Payb

ack

El-Eff

Fuel-Eff

Page 10: Why Avista Does DSM

10

Gas DSM Incentive Tiers

0

0.5

1

1.5

2

2.5

3

3.5

4

0 20 40 60 80 100 120 140 160 180 200

$ per first-year therm

Mon

ths

sim

ple

payb

ack

Gas-Eff

New Tech

Page 11: Why Avista Does DSM

11

DSM Role in Resource Planning – Electric

• Electric Integrated Resource Planning (IRP) process– Regulated process– Mandatory IRP every two years– Followed by Request For Proposals (RFP)– Typically six to twelve month process– For DSM

• Cumulatively DSM aggregates to a moderate-sized resource (approximately 80 aMW on-line net of degradation)

• Requires comprehensive assessment of cost-effectiveness of potential utility programs, characterization of risk and other characteristics, etc.

• Ultimately leading to a DSM supply curve thus identifying the DSM goal for the foreseeable future

– To be modified two years later in the next IRP

Page 12: Why Avista Does DSM

12

DSM Role in Resource Planning – Electric

• Request For Proposals process

• Two previous DSM experiences

– Early 1990s process resulted in one short-listed project

– 2000 All-Resource RFP

• Rec’d 8 proposals, 3 short-listed and negotiated, 2 selected

• WAGA and Quantum Engineering

• Focus no specified market segments and jurisdictions

• 2002-2004 identification, 2005 completion

– 38 mills levelized cost to be paid over ten year period

• 2005 identification, 2006 completion

– 25 cents front-loaded cost (approx 38 mills levelized)

• Acquisition:

– WAGA (2 + 1 aMW); Quantum (1 + 1 aMW)

Page 13: Why Avista Does DSM

13

DSM Role in Resource Planning – Electric

• 2005 / 2006 RFPs

– In addition to Avista’s standard DSM programs

– Power Supply Department is fielding a renewable (predominantly wind) RFP

– Current DSM direction is to pursue a series of targeted RFP’s plus a general solicitation for cost-effective DSM resources

Page 14: Why Avista Does DSM

14

Demand Response

• Demand Response

– Interruptible, curtailable, TOU, real-time pricing options

– Past evaluation of opportunities failed to clear the Cost-Effectiveness hurdle

• Technology advancements, growing TOU differentials and price spikes

Need to continuously evaluate potential and be prepared to respond

Page 15: Why Avista Does DSM

15

Summary of Cost-Effectiveness Tests

• Cost-effectiveness is the cornerstone of DSM acquisition• The 1987 California Standard Practice Tests:

– Total Resource Cost (TRC)• Comparison of avoided cost and non-energy benefits vs. customer

and non-incentive utility cost– Utility Cost Test (UCT)

• Comparison of avoided cost vs. total utility cost (incentives and non-incentives)

– Participant Cost Test• Comparison of bill reduction and non-energy benefits vs. customer

cost– Non-Participant (AKA Rate Impact Measure, or RIM) Test

• Measure of rate impact upon the non-participant customer (DSM will almost never pass the RIM test)

– Societal Test• TRC test with the addition of quantifiable externality reduction as a

program benefit

Page 16: Why Avista Does DSM

16

Cost-Effectiveness Tests Used by Avista

• Primarily TRC and UCT-based– Difference is

• TRC includes customer cost, UCT does not• TRC excludes utility incentives, UCT includes them• TRC includes non-energy benefits, UCT does not• TRC < UCT since customer cost > incentive

• Cost-Effectiveness Issues– Quantification of non-energy benefits

• We apply a conservative standard– Timeliness of avoided cost streams– Reviewed by entire Triple-E plus other external parties on a regular basis

Page 17: Why Avista Does DSM

17

2002-2005 DSM Business Plan

• Objectives

– Recover $12.4 million negative balance from 2001 Western Energy Crisis

– Recovery without revision to rider

– Recovery while meeting resource acquisition guidelines

• Plan

– Established “ordered priorities”

• Meet customer obligations

• Field a cost-effective portfolio

• Recover the negative balance in a timely fashion

– Target lost opportunities and low-cost / no-cost market niches

– Aggressively apply cost-containment strategies

– Hit zero in aggregate by the close of 2005

Page 18: Why Avista Does DSM

18

2002-2005 DSM Business Plan

• Results– Made modifications (reductions) to tariff riders

• Down in ID electric, sunsetted increase in WA gas

– Also received non-tariff rider funding

• Oil rebate over-refund and tax credits, hydro facility sale

– Successfully implemented cost-containment strategies

– Reached balance in August 2005

Page 19: Why Avista Does DSM

19

2002-2005 DSM Business Plan• Four individual tariff riders

• Hit zero in August ‘05

Actual and Projected Rider Balances

$(10,000,000)

$(8,000,000)

$(6,000,000)

$(4,000,000)

$(2,000,000)

$-

$2,000,000

$4,000,000

WA Electric

WA E projected

ID Electric

ID E projected

WA Gas

WA G projected

ID Gas

ID G projected

Page 20: Why Avista Does DSM

20

2002-2005 DSM Business Plan• Management of aggregate vs. individual tariff rider levels

Balance Expressed in # of Months of Revenue

(30.0)

(27.0)

(24.0)

(21.0)

(18.0)

(15.0)

(12.0)

(9.0)

(6.0)

(3.0)

-

3.0

6.0

9.0

WA electric WA gas ID electric ID gas WA total ID total Electric total Gas total Overall total

Rider Jurisdiction Fuel Aggregate

Page 21: Why Avista Does DSM

21

2002-2005 DSM Business Plan• Substantially exceeded our overall mmbtu goal

Combined Gas and Electric DSM Acquisition

-

100,000

200,000

300,000

400,000

500,000

600,000

700,000

0 10 20 30 40 50 60 70 80 90

Month

mm

btu Actual mmbtu

mmbtu goal

1999 2000

2001

2002

2003

2004 2005 2006

Page 22: Why Avista Does DSM

22

2002-2005 DSM Business Plan• Exceeded tariffed gas goal

Gas DSM Acquisition

0

200,000

400,000

600,000

800,000

1,000,000

1,200,000

1,400,000

1,600,000

0 10 20 30 40 50 60 70 80 90

Month

Th

erm

s

Actual therms

Therm goal

2001

2002

2003

2004

2005

2006

Page 23: Why Avista Does DSM

23

2002-2005 DSM Business Plan

Electric DSM Acquisition

0.00

5.00

10.00

15.00

20.00

25.00

0 10 20 30 40 50 60 70 80 90

Months

aM

W

Actual aMW

aMW goal

W regional

NPCC

20041999

2000

2001

20022003

20052006

Page 24: Why Avista Does DSM

24

2006 DSM Business Plan

• Oriented around “stewardship”

– Achieve the maximum benefit for our customers’ tariff rider funding

– Add new programs

– Annually revise tariff rider to recover carryover balance and recover budgeted expenditures in the following calendar year

Page 25: Why Avista Does DSM

25

2006 DSM Business Plan• Additional programs under evaluation

– Non-residential• Rooftop HVAC• Steam trap maintenance• Whole-building commissioning• Boiler tune-ups• Pre-rinse sprayers• Burner-tip maintenance• Prescriptive premium-efficiency motors• Computer controls (Verdiem-type)• LEED assistance• Prescriptive LED traffic lights• Dairy heat exchangers• Greenhouse curtains

Page 26: Why Avista Does DSM

26

2006 DSM Business Plan

• Residential programs

– Gas back-up heat pumps

– Programmable thermostats

• Planned “Sunsetted” programs

– Programs with a specified end-date

– Oftentimes seasonal windows of opportunity

– Addresses procrastination issue

Page 27: Why Avista Does DSM

27

.

2006 DSM Budget

60%

7%

9%

10%

14% C/I incentives

Residentialincentives

Limited incomeincentives

Non-incentive, non-labor

Labor

Page 28: Why Avista Does DSM

28

.

2006 Electric Budget

63%

4%

8%

12%

13% C/I incentives

Residentialincentives

Limited incomeincentives

Non-incentive, non-labor

Labor

Page 29: Why Avista Does DSM

29

.

2006 Gas DSM Budget

47%

23%

13%

1%

16% C/I incentives

Residentialincentives

Limited incomeincentives

Non-incentive, non-labor

Labor

Page 30: Why Avista Does DSM

30

Total DSM Composition

83%

17%

Electric

Gas

Page 31: Why Avista Does DSM

31

Commercial / Industrial DSM• Everything qualifies

• Site-Specific vs. Prescriptive

– Performance contract policy

• RFP contracts

– Quantum Engineering and WAGA

– 2002-2004 / 2005 plus 2005 / 2006 contracts

• Operations

– Engineers / Technicians

– Contracting process (including scheduling)

– Coordination / program development

Page 32: Why Avista Does DSM

32

Residential DSM

• Prescriptive-based (i.e., “standard offer” based on rebate)

– Covering gas and electric opportunities

– Has and is continuing to change as new programs are ramped-up

– Rebate processing operation focus

• Geographic Saturation program

Page 33: Why Avista Does DSM

33

Limited Income DSM

• High profile• Currently conducted through six agencies under annual

contract– One WA & ID, four WA electric-only, one WA gas

only• Recent funding enhancements

– Added $350k total funding in ID– Added $200k to existing funding in WA plus flexibility

• Operational revisions– Scheduled periodic in-person visits with CAP agencies

Page 34: Why Avista Does DSM

34

BPA Conservation & Renewables Discount • BPA’s 2001-2006 approach for DSM

– A ½ mill discount on firm sales• Our 90 aMW of residential exchange $2.0 million in five

years– To be expended in accordance with BPA program guidelines– Incremental language– Regional Technical Forum– Avista’s use

• 2001 CFLs• Conservation Voltage Reduction• Limited income

– Reporting and audit requirements• 2006-2011 program

– Generally similar

Page 35: Why Avista Does DSM

35

Regional DSMNorthwest Energy Efficiency Alliance (NEEA)

• Regional market transformation orientation

• Electric-only

• Funded by BPA, all significant generating publics, all regional IOUs

• 1997-1999, 2000-2004 and 2005-2009 contracts

• Current funding $20 million / year

– Subject to NEEA board approval of expenditures

– Avista slightly under 4% of funding

• Delivering 10 mill resource

• Avista represented on the board

• Future … regional coordination, gas market transformation ?

Page 36: Why Avista Does DSM

36

Recommendations

• Energy Codes• Appliance Codes• Updated tax credits• State LIHEAP