Keeping our Promises Whitelee Windfarm Infrastructure Contract 90.5 km of access roads 59 km floating on deep peat Access Road Construction
14

Whitelee Windfarm Infrastructure Contract Access Road ...

Jan 15, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

90.5 km of access roads

59 km floating on deep peat

Access Road Construction

Page 2: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

Wham Brae Culvert Construction

Page 3: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

Floating Road Construction near Ardochrig

Page 4: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

Crane Hardstanding Construction in Fluid

Peat

T39 – Array 7

Page 5: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

T39 – Array 7

T21 – Array 7

Turbine Base Excavation in Fluid Peat

Page 6: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

140 turbine bases

199,000 cu. m. engineered fill

50,000 cu. m. concrete

On site batching plant

Turbine Base Construction

Page 7: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

Turbine Installation Operations

T39 – Array 7

Page 8: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

Tower Sections

Page 9: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

Nacelle Installation

Page 10: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

Lifting the Blades

Page 11: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

Ardochrig Substation

Lochgoin Control Building

986 km Cables HV/LV/SCADA

140 Transformers

Switchgear

Electrical Infrastructure

Page 12: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

Lochgoin Reservoir – February 2009

Page 13: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

Ardochrig Substation & Array 12 – February 2009

Page 14: Whitelee Windfarm Infrastructure Contract Access Road ...

Keeping our Promises

Whitelee Windfarm – Infrastructure Contract

Completed turbines between Dunwan Dam & Lochgoin Reservoir - June 2009