WHATCOM COUNTY WATER RESOURCES PUBLIC WORKS DEPARTMENT 322 N. Commercial Street, Suite 210 Bellingham, WA 98225 FRANK M. ABART Telephone: (360) 676-6692 Director FAX: (360) 738-4561 www.whatcomcounty.us MEMORANDUM TO: The Honorable Jack Louws, Whatcom County Executive, and Honorable Members of the Whatcom County Council THROUGH: Frank M. Abart, Director FROM: Gary S. Stoyka, Natural Resources Manager DATE: February 10, 2014 RE: February 2014 Council Surface Water Work Session Please refer to the proposed agenda below for the next Surface Water Work Session. Supporting documents will be distributed at or before the meeting. AGENDA Date: Tuesday, February 18, 2014 Time: 10:30 a.m. to 12:00 p.m. Place: Civic Center Garden Level Conference Room Time Topic Council Action Requested Background Information Attached 10:30 AM – 11:00 AM BBWARM Funding Request for Birch Point Flooding Study Discussion None 11:00 AM – 12:00 PM Syre Farm Bank Stabilization Alternatives Analysis Discussion River Bank Stabilization Alternatives Assessment Report If you have questions, please feel free to call me at (360) 676-6876, extension 50618. cc: Frank Abart Mike McFarlane Remy McConnell Joe Rutan Jeff Hegedus Josh Fleischmann Kirk Christensen Roland Middleton Sue Blake Paula Cooper John Thompson Karen Frakes Dana Brown-Davis Lonni Cummings George Boggs John Wolpers Kraig Olason Martha Blakely Jennifer Paulson Atina Casas Mike Donahue Erika Douglas Jill Nixon Cathy Craver Mark Personius
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
WHATCOM COUNTY WATER RESOURCES PUBLIC WORKS DEPARTMENT 322 N. Commercial Street, Suite 210 Bellingham, WA 98225 FRANK M. ABART Telephone: (360) 676-6692 Director FAX: (360) 738-4561 www.whatcomcounty.us
MEMORANDUM
TO: The Honorable Jack Louws, Whatcom County Executive, and Honorable Members of the Whatcom County Council
THROUGH: Frank M. Abart, Director FROM: Gary S. Stoyka, Natural Resources Manager DATE: February 10, 2014
RE: February 2014 Council Surface Water Work Session Please refer to the proposed agenda below for the next Surface Water Work Session. Supporting documents will be distributed at or before the meeting.
AGENDA
Date: Tuesday, February 18, 2014
Time: 10:30 a.m. to 12:00 p.m.
Place: Civic Center Garden Level Conference Room
Time Topic Council Action
Requested Background Information
Attached
10:30 AM – 11:00 AM
BBWARM Funding Request for Birch Point Flooding Study
Discussion
None
11:00 AM – 12:00 PM
Syre Farm Bank Stabilization Alternatives Analysis
Discussion
River Bank Stabilization Alternatives Assessment Report
If you have questions, please feel free to call me at (360) 676-6876, extension 50618.
cc: Frank Abart Mike McFarlane Remy McConnell
Joe Rutan Jeff Hegedus Josh Fleischmann Kirk Christensen Roland Middleton Sue Blake
Paula Cooper John Thompson Karen Frakes Dana Brown-Davis Lonni Cummings George Boggs
John Wolpers Kraig Olason Martha Blakely Jennifer Paulson Atina Casas
Mike Donahue Erika Douglas Jill Nixon Cathy Craver Mark Personius
RIVER BANK STABILIZATION ALTERNATIVES
ASSESSMENT
SYRE FARM
Prepared for Whatcom County Flood Control Zone
District
Prepared by Herrera Environmental Consultants, Inc.
Note: Some pages in this document have been purposely skipped or blank pages inserted so that this document will copy correctly when duplexed.
RIVER BANK STABILIZATION ALTERNATIVES
ASSESSMENT
SYRE FARM
Prepared for
Whatcom County Flood Control Zone District
322 N. Commercial Street, Suite 120
Bellingham, Washington 98225
Prepared by
Herrera Environmental Consultants, Inc.
2200 Sixth Avenue, Suite 1100
Seattle, Washington 98121
Telephone: 206/441-9080
August 26, 2013
i
jr 13-05649-000 syre farm river bank stabilization alternatives assessment
Citation: USDA, Aerial (2011); Whatcom County, GPS (2013);WCAR, Parcel (2006)
0 250 500125ft
Coordinates: NAD 1983 Washington State Plane North FIPS 4601 Feet
Legend
Existing log jam
") 2013 GPS bank lineLog revetment
! PileExisting revetmentParcel
August 2013
River Bank Stabilization Alternatives Assessment—Syre Farm 9
reduced with the log revetment alternative through the use of pilings to hold the logs in place, and because the potential scour depth would be less due to increased hydraulic roughness (and reduced flow velocities as a result of that roughness). The log revetment would tie into the existing rock revetments upstream and downstream.
As with the rock revetment alternative, this design includes laying back a portion of the existing downstream revetment to a flatter slope to reduce the potential for deflection of flows towards the left bank. It may be feasible to reduce the length of the log revetment and the extent of the tie-in with existing revetments with further design development and evaluation. However, for this planning level alternatives analysis, a reduced log revetment length was not addressed in detail. Figure 3 shows the approximate extents of the following, numbered accordingly on the figure: 1) a log revetment that would stabilize the downstream end of the eroding bank, 2) a log revetment that would cover the entire length of the eroding bank, and 3) the area at the downstream end of the new log revetment where the existing revetment and the bank above it should be modified to tie in the new log revetment.
Unlike the rock revetment alternative, a log revetment may be considered “self-mitigating” with respect to environmental impacts because it can be designed to enhance aquatic habitat. This reduces some of the uncertainty with regard to the permitting process and overall project cost relative to the rock revetment alternative.
2.2.4. Engineered Logjams The engineered logjam (ELJ) alternative (Figure 4) consists of constructing four flow-deflecting logjams on the right-bank gravel bar upstream of the eroding bank and one logjam on the left bank at the inlet to the existing high flow overflow channel. The ELJs would be approximately 70 to 90 feet wide and consist of driven timber piles (driven well below scour depth) with large log pieces layered from below the channel bed elevation to at or near the flood water elevations within the reach. The intent of these logjams would be to create hydraulic roughness that reduces flow velocities, absorb erosive energy during large floods, and direct flow away from the eroding right bank and toward the entrance of the existing left-bank overflow channel. The ELJs could encourage deposition of cobbles and gravel on the downstream (leeward) side of each structure with the potential for vegetated islands/bars to develop over the long term in front of the bank, providing greater erosion protection as they evolve. This alternative would also include grading and enhancement of the existing high flow overflow channel to improve hydraulic conveyance at both low and high flows and to enhance side channel functions. Woody habitat structures would be constructed within the overflow channel to improve habitat complexity.
ELJs have successfully been used for this purpose in many locations throughout western Washington, including in the Nooksack River. However, since the ELJs would not tie into the existing revetments upstream and downstream of the eroding bank, there would remain potential for the river to periodically erode portions of the bank between ELJs. If designed appropriately, the ELJs would prevent this from being a significant ongoing problem and could effectively protect Syre Farm from worsening loss of land. Similar to the log revetment alternative, ELJs could be considered self-mitigating in regards to environmental permitting process and requirements.
August 2013
10 River Bank Stabilization Alternatives Assessment—Syre Farm
2.2.5. Preliminary Cost Estimates for Action Alternatives
Planning-level cost estimates for design, permitting, and construction of each of the rock
revetment, log revetment, and ELJ alternatives are presented in Appendix A and summarized
in Table 1. These estimates are based in part on experience with other river projects in
Whatcom County and elsewhere in western Washington, professional judgment, and general
assessment of habitat mitigation requirements as applicable. These estimates are intended to
inform comparison of the alternatives and provide an understanding of the overall magnitude
of the cost of implementing a long-term, reliable bank protection solution at Syre Farm, and
should be considered subject to change as more design information becomes available and
regulatory agencies react to any proposed action.
Table 1. Summary of Action Alternative Planning-Level Cost Estimates.
Alternative Estimated Cost
Rock Revetment w/ Mitigation $2,200,000
Log Revetment $2,100,000
Engineered Logjams $1,700,000
For each of the rock revetment and log revetment alternatives, further design refinement
may allow the assumed revetment length to be shortened or otherwise modified to reduce
the construction cost. However, any new revetment configuration that does not tie into
existing infrastructure would need to be keyed into the bank sufficiently to protect
the leading edge from being flanked where flow engages the revetment. A revetment
configuration that does not tie into existing infrastructure would reduce the reliability of the
design in return for cost savings.
")
")")
")")")")")
")")")
")")")
")
")
")
")
")
")
")
")
")
")
")
")
")
")
")")
")
")")
")")")
")")")
")")")")")
")")
")")") ") ")") ")")")
Syre FarmHouse
Existing rockrevetment
Existing rockrevetment
UV9
High flowoverflow channel
Existing sidechannel
Log structuresin the aerialare no longeron the site
Citation: USDA, Aerial (2011); Whatcom County, GPS (2013);WCAR, Parcel (2006)
0 400 800200ft
Coordinates: NAD 1983 Washington State Plane North FIPS 4601 Feet
LegendApproximate left bank
") 2013 GPS bank line
Existing revetmentHistoric channel occupation
Darker color indicates more frequentoccupation of low flow channel
August 2013
River Bank Stabilization Alternatives Assessment—Syre Farm 19
Table 5. Nooksack River Channel Migration Characteristics Near Syre Farm, 1859-2013.
Map or Photo Year
Time Since
Prior Map or Photo
(yrs)
Direction of Approaching
River
Syre Farm Citron Trust Property State Route 9 Perpendicular Main Channel
Approach
Channel Type: Main (M) or
Secondary (S) or None (X)
Distance from Pre-2005 Bank
(ft)
Channel Type: Main (M) or
Secondary (S) or None (X)
Distance from 2013 Left Bank
(ft)
Closest Approach of
Left Bank (ft)
Direction to Closest
Approach
Eastward Migration Distance
Intercept Distance From Upstream End of Syre Farm Bank Erosion
(ft)
1859 SE M 0 X - 780 SW - -
1885 26 SE X 540 M 60 1,670 S - -
1906 21 E, SE, S S 70 M 100 1,000 SSW - -
1933 27 E, ESE S 110 M 370 560 WSW - -
1938 5 E, SE S -370 a M 360 410 SW - -
1950 12 ESE, SE M -120 a S 380 660 SW - -
1955 5 SE, SSE M 0 S 340 780 SW - -
1967 12 SE M 0 S 320 780 SW - -
1976 9 ESE S 0 S 280 780 SW - -
1980 4 E S 0 M 290 780 SW - -
1986 6 ESE S 0 M 280 780 SW - -
1995 9 SE, ESE M 0 S 0 780 SW - -
1998 3 SE M 0 S 0 780 SW - -
2002 4 SSW M 0 S 0 780 SW 0 c -390
2006 4 SSW M -70 S* 0 780 SW 150 -150
2010 4 SSW M -180 S 0 780 SW 340 0
2011 1 SSW M -180 b S 0 780 SW 420 80
2013 2 SSW M -270 S 0 660 S 770 640
a Downstream of current (2013) eroding bank b No lateral expansion of eroded area, but 130 feet downstream extension of eroding bank c Reference bank position (2002)
August 2013
20 River Bank Stabilization Alternatives Assessment—Syre Farm
Photo showing the eroding right bank, the wooded area in the background, and the farm road and planted field to the right.
August 2013
River Bank Stabilization Alternatives Assessment—Syre Farm 21
Photo showing the right bank aggrading bar upstream of the eroding bank at Syre Farm, with the vegetated left bank floodplain to the left.
August 2013
22 River Bank Stabilization Alternatives Assessment—Syre Farm
Photo showing the left bank overflow channel entrance on the opposite side of the main channel from Syre Farm.
August 2013
River Bank Stabilization Alternatives Assessment—Syre Farm 23
Photo showing right bank materials at the downstream end of the eroding bank, with fine soil material above the more permeable coarse channel bed material below, also showing overhanging bank condition.
August 2013
24 River Bank Stabilization Alternatives Assessment—Syre Farm
3.3. Geomorphic Response to Alternatives
3.3.1. No Action
With no stabilization of the right bank at Syre Farm, it can be expected that the bank will
continue to erode and retreat, and that the point of greatest retreat will continue to migrate
downstream. The rate of retreat is likely to slow over the next few years, because as the
left bank continues to erode and the right bank cobble bar upstream continues to aggrade
the meander and related locus of erosion will continue to shift west, eventually shifting
beyond the Syre Farm or avulsing through the left bank floodplain, where the main channel
was located as recently as 1986. Unless the main channel shifts, it is likely that the rock
revetment downstream of the currently-eroding bank will continue to unravel episodically
during flood events, potentially allowing the river to cut into the forested area behind
the revetment, as it did early in the 20th century. The time frame for these potential
developments could be accelerated with large channel-changing flood events or slowed if
future flooding is benign. The potential for large scale flooding similar to what occurred in
the mid-1990s, that delivers large volumes of sediment and debris, makes predictions of
channel migration on a yearly and subreach scale uncertain.
The recent bank erosion at Syre Farm has raised concerns that State Route 9 (SR 9) could be
threatened. Figure 6 shows the distance from the current location of SR 9 to the right bank
of the Nooksack River between 1859 and 2013. For most of that period, the distance has been
constant due to the Syre Farm revetment. In the first few years after the revetment failed,
that continued to be the case. The landward and downstream progression of erosion since
2011 has caused the distance between the river and SR 9 to shrink by approximately 120 feet,
from approximately 780 feet to 660 feet, but bank erosion is propagating in a direction that
will take it further away from SR 9, and the upstream end of the failing bank has stabilized.
It is therefore unlikely that SR 9 is in any short-term danger of being attacked by the river.
It should be noted, however, that the area downstream of the currently eroding bank is at
moderate risk from channel migration, and that realignment of the river upstream of Syre
Farm could change the rate and direction of bank erosion in this vulnerable bank area. A
threat to SR 9 could arise if the river breaches the revetment and erodes the forest that lies
between the revetment and the corner of SR 9 where it turns north at the entrance to Syre
Farm.
3.3.2. Rock Revetment
Rock revetments act as hard, hydraulically smooth banks and can often attract the mainstem
low flow of rivers as a result, further exacerbating an erosion problem as the channel ―hugs‖
the revetment and erodes unprotected bank areas downstream. Tying into the existing
revetment would reduce the potential for downstream erosion to occur, but in general
construction of a rock revetment on the right bank at Syre Farm would encourage the
mainstem to ―occupy‖ the right bank more frequently than it would if the bank was allowed
to erode or if a more roughened bank revetment design was constructed (see the log
revetment discussion below). More frequent occupation of the right side of the floodplain
would correspond to less frequent occupation of the left side of the floodplain, potentially
August 2013
River Bank Stabilization Alternatives Assessment—Syre Farm 25
allowing the development of more mature vegetation there. If that occurs, overflow channels
in the left bank floodplain could fill in with sediment trapped by the vegetation, thereby
encouraging the river to occupy the right bank even more.
Figure 6. Distance from SR 9 to Left Bank of Nooksack River at Syre Farm.
3.3.3. Log Revetment
Because the log revetment alternative would be designed to be hydraulically rough, this
alternative would be less likely to entrain the mainstem channel along its length than a rock
revetment would. This would result in a similar probability of the mainstem flow reoccupying
the left bank channel migration zone as described above for the ―no action‖ alternative. Both
rock and log revetments would prevent the channel from migrating further into the Syre Farm
property, and so both of these alternatives would keep the channel generally within the
bounds of its historical migration corridor.
3.3.4. Engineered Logjams
Construction of engineered logjams on the right bank bar upstream of Syre Farm would
accelerate the process of channel migration away from the eroding right bank and encourage
more frequent occupation of mainstem flow within the left bank historic channel migration
zone. This alternative would not, however, do anything to increase slope stability at the
eroded bank along Syre Farm. The ELJs would encourage sediment deposition directly
downstream of them, which would further reinforce the deflection of flow and energy away
from the right bank and create the potential for a forested floodplain or forested island/side
channel mosaic to develop between the ELJs and the Syre Farm property.
August 2013
River Bank Stabilization Alternatives Assessment—Syre Farm 27
4. DISCUSSION
The eroding bank at Syre Farm is located in a dynamic reach of the Nooksack River with a
record of frequent channel switching from one side of the floodplain to the other. Although
the historical record suggests that the Syre Farm property should be at a relatively low risk
due to channel migration, recent changes in the direction from which the river approaches
the farm changed its vulnerability. The recent loss of revetment and subsequent bank retreat
at Syre Farm clearly indicate that the revetment was inadequate to prevent bank erosion with
the current channel alignment. While it is likely that the main force of the river will not be
directed at the Syre Farm bank for more than another 2 or 3 years as the locus of flow energy
migrates downstream on the right bank, prevention of further erosion at Syre Farm in the
meantime will require some action. Of the four alternatives analyzed in this report (see
Table 6), the ELJ alternative would have the least likelihood of triggering permitting and
mitigation complications, but is less likely to arrest bank erosion in the short term and would
mainly serve to accelerate the pace of leftward channel migration upstream of Syre Farm.
The rock revetment alternative would be likely to arrest bank erosion, but it has a high
likelihood of triggering mitigation and permitting complications. To predictably arrest bank
erosion at Syre Farm, the log revetment alternative is recommended for its combination of a
high likelihood of success in stopping bank erosion coupled with a medium to low likelihood of
triggering complicated permitting and mitigation requirements.
Table 6. Bank Stabilization Alternatives Summary.
Alternative
Likelihood of Arresting Right Bank
Erosion Construction Cost
Likelihood of Requiring Habitat Mitigation and a Complicated
Permitting Process
No Action Low None None
Rock Revetment High High High
Log Revetment High High Medium/Low
ELJs Medium High Low
August 2013
River Bank Stabilization Alternatives Assessment—Syre Farm 29
5. REFERENCES
Catchments and Creeks Pty, Ltd. 2010. Watercourse erosion – part 1: Erosion types and their
Project: Syre FarmProject #: 13‐05649‐000Client: Whatcom County Public WorksCompleted By: CECompleted Date: 7/31/2013Checked by: GK, ME, JBChecked Date: 8/20/2013
Item Description Qty Unit Unit Cost Total Cost Notes and Assumptions
Mobilization 1 LS 97,900.00$ 97,900$ Assume 10% of project costsClearing and Grubbing 1.0 AC 5,000.00$ 5,000$ Includes moderate clearing and
grubbing of trees, shrubs and grass along access and side channels
ELJ construction 5 EA 88,250.00$ 441,250$ Excavation 1,500 CY 10.00$ 15,000$ Key Logs 50 EA 600.00$ 30,000$ assume 10 key logs every 30ftracking logs 150 EA 75.00$ 11,250$ assume 10 racking logs every 30ftTimber Pilings 20 EA 1,200.00$ 24,000$ assume one every 10ftAssembly of Structure 1 EA 8,000.00$ 8,000$ Side Channel Enhancement 2 EA 217,777.78$ 435,556$ starter channel and inlet excavation 7,222 CY 8.00$ 57,778$ Assumes 1300ft of starter
channel/inet excavation and can waste spoils on site.
Side channel habitat log structures 26 EA 5,000.00$ 130,000$ Assumes one every 100ft of channel
side channel planting and land scaping 1 LS 30,000.00$ 30,000$ This cost for floodplain and ELJ, starter channel planting restoration
Erosion/Water Pollution Control (TESC) 1 LS 97,100.00$ 97,100$ Assume 10% of Div 2-6 construction subtotal not incl. mobilization. Engineer's estimate based on
Construction Subtotal 1,076,806$ A&E (+15%) 161,520.83$ Contingency (+30%) 323,042$ Subtotal (with +30% Contingency) 1,561,000$ Tax (8.5%) 132,685$ Total (with +30% Contingency and Tax) 2012 Dollars 1,694,000$
Planning Level Cost EstimateDEFLECTOR ELJ
Project: Syre FarmProject #: 13‐05649‐000Client: Whatcom County Public WorksCompleted By: CECompleted Date: 7/31/2013Checked by: GK, ME, JBChecked Date: 8/20/2013
Item Description Qty Unit Unit Cost Total Cost Notes and Assumptions
Mobilization 1 LS 121,400.00$ 121,400$ Assume 10% of project costsClearing and Grubbing 0.5 AC 5,000.00$ 2,500$ Includes moderate clearing and
grubbing of trees, shrubs and grass along downstream end of study area
Excavation for Log Revetment 10,000 CY 12.00$ 120,000$ conservative unit cost to account for potential requirement to haul and dispose of spoils and inwater wet excavation required below low water level. Quantity less than rock revetment to acount for log roughness moving scour away from toe so less depth/excavation required. Assumes layback existing bank and excavate for toe.
Revetment Rock 5,000.00 CY 59.50$ 297,500$ assume $35/ton and 1.7tons/CY. Assume 1300ft long, 40ft slope length with top 5ft (10ft slope length) as coir and 50% less rock than rock revetment to acount for log volume and reduced quantity needed for toe rock). Same geometry assumed as Rock Rev.
Key Logs 650 EA 600.00$ 390,000$ assume 10 key logs every 30ftracking logs 433 EA 75.00$ 32,500$ assume 10 racking logs every 30ftTimber Pilings 130 EA 1,200.00$ 156,000$ assume one every 10ftCoir Wrap with plantings above OHW flow elevation
6,500 SF 15.00$ 97,500$ Assume top 5ft of revetment is coir wrap lifts with plantings.
planting and land scaping 1 LS 30,000.00$ 30,000$ assumes coir lift plantings cost included in related item. This cost for floodplain planting restoration
Erosion/Water Pollution Control (TESC) 1 LS 87,700.00$ 87,700$ Assume 8% of Div 2-6 construction subtotal not incl. mobilization. Estimate. Reduced from rock
Construction Subtotal 1,335,100$ A&E (+15%) 200,265$ Contingency (+30%) 400,530$ Subtotal (with +30% Contingency) 1,936,000$ Tax (8.5%) 164,560$ Total (with +30% Contingency and Tax) 2012 Dollars
2,101,000$
Planning Level Cost EstimateLOG REVETMENT
Project: Syre FarmProject #: 13‐05649‐000Client: Whatcom County Public WorksCompleted By: CECompleted Date: 7/31/2013Checked by: GK, ME, JBChecked Date: 8/20/2013
Item Description Qty Unit Unit Cost Total Cost Notes and Assumptions
Mobilization 1 LS 131,900.00$ 131,900$ Assume 10% of project costsClearing and Grubbing 0.5 AC 5,000.00$ 2,500$ Includes moderate clearing and
grubbing of trees, shrubs and grass along downstream end of study area
Excavation for Rock Revetment 17,000 CY 12.00$ 204,000$ conservative cost to account for potential requirement to haul and dispose of spoils and inwater wet excavation required below low water level.
Revetment Rock 10,000.00 CY 59.50$ 595,000$ assume $35/ton and 1.7tons/CY. Assume 1300ft long, 40ft slope length with top 5ft (10ft slope length) as coir, 2:1 slope, 5ft thick including rock filterl layer and assumes salvaged existing rock volume equals launch toe.
Coir Wrap with plantings above OHW flow elevation
6,500 SF 15.00$ 97,500$ Assume top 5ft of revetment is coir wrap lifts with plantings.
habitat Mitigation 1 LS 300,000$ Estimate.planting and land scaping 1 LS 30,000.00$ 30,000$ assumes coir lift plantings cost
included in related item. This cost for floodplain planting restoration
Erosion/Water Pollution Control (TESC) 1 LS 89,900.00$ 89,900$ Assume 10% of Div 2-6 construction subtotal not incl. mobilization. Engineer's estimate based on
Construction Subtotal 1,450,800$ A&E (+12%) 174,096$ Contingency (+30%) 435,240$ Subtotal (with +30% Contingency) 2,060,000$ Tax (8.5%) 175,100$ Total (with +30% Contingency and Tax) 2012 Dollars 2,235,000$