What we plan to do next BIM and Government Soft Landings: achieving better operational outcomes What Now for the Performance Gap? Reid Cunningham @CunninghamReid Strategic Development Director, BAM FM
Jun 08, 2015
What we plan to do next
BIM and Government Soft Landings: achieving better operational outcomes
What Now for the Performance Gap?
Reid Cunningham
@CunninghamReid
Strategic Development Director, BAM FM
BAM FM Context
• Royal BAM and BAM UK Group
• £44m facilities management
• 60% turnover in PFI– Public sector heath, education, law & order, public sector accommodation– Long term (25 to 30 years)– Performance / Availability– Fixed price
• 40% turnover in maintenance– Commercial sector– Static & mobile engineers/technicians
Traditional Construction Process, Knowledge and Data Transfer
Design
OperationConstruction
Soft Landings, Whole Life Cost Enabled by Collaboration, Knowledge and Transfer – (The Vision)
Design
OperationConstruction
Collaboration and Application of BIM
UK FM Context
Project Robin
Phase 1 Populate CAFM with BIM Data
Phase 2 Populate CAFM with BIM data for UCL Academy Camden
Operate Live 3D BIM using 360 Field
Operational synchronization between BIM and CAFM
Project Robin – Operational Phase2BIM360 Field – Navigation by end users
• Room or Asset listing to model or model to Room or Asset listing
• Navigational Views and hiding of Objects or separated ModelsProvides full facility to get to the equipment data for FM purposes
• ALL information available as required to FM Engineers
Project Robin – Faster First Fix
New Job received by technician via tablet
Report of Heating Issue in room 501
Technician visits room to perform checks.User has the ability to view services within room
Technician has the ability to view plant and interrogate operatingmanuals including elements of commissioning data
Project Robin – Faster First Fix
Project Robin Faster PPM
Technician receives job card via FSI GO. This includes Asset ID and Uniclass Code.
The Asset ID enables the technicianto search for asset within BIM 360Field.
Project Robin Faster PPM
Technician has the ability to interrogate O&M ‘s including elements of commissioning information, fault codes and supplier maintenance manuals
QR codes have been implemented to provide those without access to BIM 360 Field / FSI GO with access similar information.