What we plan to do next BIM and Government Soft Landings: achieving better operational outcomes What Now for the Performance Gap? Reid Cunningham @CunninghamReid Strategic Development Director, BAM FM
12

What Now For The Performance Gap? By Reid Cunningham (BAM FM)

Jun 08, 2015

Download

Design

Reid Cunningham's of BAM FM Ecobuild 2014 presentation discussing what's now for the performance gap?
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: What Now For The Performance Gap? By Reid Cunningham (BAM FM)

What we plan to do next

BIM and Government Soft Landings: achieving better operational outcomes

What Now for the Performance Gap?

Reid Cunningham

@CunninghamReid

Strategic Development Director, BAM FM

Page 2: What Now For The Performance Gap? By Reid Cunningham (BAM FM)

BAM FM Context

• Royal BAM and BAM UK Group

• £44m facilities management 

• 60% turnover in PFI– Public sector heath, education, law & order, public sector accommodation– Long term (25 to 30 years)– Performance / Availability– Fixed price

• 40% turnover in maintenance– Commercial sector– Static & mobile engineers/technicians

Page 3: What Now For The Performance Gap? By Reid Cunningham (BAM FM)

Traditional Construction Process, Knowledge and Data Transfer

Design

OperationConstruction

Page 4: What Now For The Performance Gap? By Reid Cunningham (BAM FM)

Soft Landings, Whole Life Cost Enabled by Collaboration, Knowledge and Transfer – (The Vision)

Design

OperationConstruction

Page 5: What Now For The Performance Gap? By Reid Cunningham (BAM FM)

Collaboration and Application of BIM

Page 6: What Now For The Performance Gap? By Reid Cunningham (BAM FM)

UK FM Context

Page 7: What Now For The Performance Gap? By Reid Cunningham (BAM FM)

Project Robin

Phase 1 Populate CAFM with BIM Data

Phase 2 Populate CAFM with BIM data for UCL Academy Camden

Operate Live 3D BIM using 360 Field

Operational synchronization between BIM and CAFM

Page 8: What Now For The Performance Gap? By Reid Cunningham (BAM FM)

Project Robin – Operational Phase2BIM360 Field – Navigation by end users

• Room or Asset listing to model or model to Room or Asset listing

• Navigational Views and hiding of Objects or separated ModelsProvides full facility to get to the equipment data for FM purposes

• ALL information available as required to FM Engineers

Page 9: What Now For The Performance Gap? By Reid Cunningham (BAM FM)

Project Robin – Faster First Fix

New Job received by technician via tablet

Report of Heating Issue in room 501

Page 10: What Now For The Performance Gap? By Reid Cunningham (BAM FM)

Technician visits room to perform checks.User has the ability to view  services within room

Technician has the ability to view plant and interrogate operatingmanuals including elements of commissioning data

Project Robin – Faster First Fix

Page 11: What Now For The Performance Gap? By Reid Cunningham (BAM FM)

Project Robin Faster PPM

Technician receives job card via FSI GO. This includes Asset ID and Uniclass Code.

The Asset ID enables the technicianto search for asset within BIM 360Field. 

Page 12: What Now For The Performance Gap? By Reid Cunningham (BAM FM)

Project Robin Faster PPM

Technician has the ability to interrogate O&M ‘s including elements of commissioning information, fault codes and supplier maintenance manuals

QR codes have been implemented to provide those without access to BIM 360 Field / FSI GO with access similar information.