Top Banner
WESTRIDGE MARINE TERMINAL MARINE TRAFFIC TECHNICAL REPORT WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT APPLICATION TO VANCOUVER FRASER PORT AUTHORITY Trans Mountain Pipeline ULC Kinder Morgan Canada Inc. Suite 2700, 300 – 5 Avenue S.W. Calgary, Alberta T2P 5J2 Ph: 403-514-6400 May 2017
209

WESTRIDGE MARINE TERMINAL UPGRADE AND ...

May 08, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

W E S T R I D G E M A R I N E T E R M I N A L M A R I N E T R A F F I CT E C H N I C A L R E P O R T

WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT APPLICATION TO VANCOUVERFRASER PORT AUTHORITY

Trans Mountain Pipeline ULC Kinder Morgan Canada Inc. Suite 2700, 300 – 5 Avenue S.W. Calgary, Alberta T2P 5J2 Ph: 403-514-6400

May 2017

Page 2: WESTRIDGE MARINE TERMINAL UPGRADE AND ...
Page 3: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

PR0420171202CGY ES-1

Executive Summary The Trans Mountain Expansion Project (Project) will include construction and subsequent operation of three new berths at the existing Westridge Marine Terminal (WMT or the Terminal) in Burnaby, British Columbia (BC). Each new berth will be capable of handling Aframax class vessels. The Project has undergone review by the National Energy Board, as well as having been reviewed by a Technical Review Process of Marine Terminal Systems and Transshipment Sites (TERMPOL) Review Committee led by Transport Canada. The purpose of this Marine Traffic Technical Report is to specifically address the following 11 Vancouver Fraser Port Authority (VFPA) information requests for the Westridge Marine Terminal Upgrade and Expansion Project component of the Project and Environmental Review Application Submission Requirements:

1. Confirmation of the design vessel range (maximum and minimum size of vessels that can be berthed and loaded) and anticipated traffic levels; anchorage strategy; bunkering program (whether this is permitted at the terminal); and any other operational criteria

2. Confirmation of the approaches that vessels will take to each berth and the departure from each berth, based on simulations or advice from the Pacific Pilotage Authority (PPA) and British Columbia Coast Pilots (BCCP)

3. A description of any plans for notification or broadcast of information regarding the transit or operations of the vessels associated with the Project

4. Mooring plan for design vessels at maximum and minimum size

5. A copy of berthing simulation including approaches to the proposed marine terminal and plans for docking and undocking

6. A statement on whether the PPA will require a training program for pilots

7. Description of the updated Vessel Acceptance Criteria for the Terminal

8. Passing Vessel Analysis for largest vessels passing the facility with largest design vessels at the proposed berth at different tidal current conditions

9. Confirmation that the Passing Vessel Analysis already completed will still accurately reflect outcomes considering any engineering changes that have occurred since its completion

10. Analysis of tug requirements to be conducted: report on any special requirements because of severe weather or currents at the Terminal location

11. Description of all anticipated marine traffic that will be associated with construction

The WMT will be designed to handle a range of vessels, from barges to Aframax tankers. While most of the tankers are expected to be Aframax class vessels (80,000 to 120,000 dead weight tonnage [DWT]), Panamax class tankers (60,000 to 80,000 DWT) and barges may also be nominated to load from the WMT.

Based on the expected maximum throughput at the dock, it is expected that the typical number of tanker loadings during Project operations will be up to 34 partly loaded Aframax vessels per month, which is an increase from the current total of approximately 5 tankers per month. Shippers may also opt to use Panamax vessels.

Near southern Indian Arm, located just north of the Terminal and east of Second Narrows in Central Harbour, the VFPA has provided four anchorages, at least three of which are suitable for Aframax-size vessels. Although most anchorages within the VFPA’s jurisdiction are suitable to accommodate vessels

Page 4: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

ES-2 PR0420171202CGY

EXECUTIVE SUMMARY

of Aframax size, Trans Mountain Pipeline ULC (Trans Mountain) expects that WMT tankers will not normally frequent those anchorages that are not in the immediate vicinity of the WMT.

Trans Mountain has determined that, during Project operations, incoming vessels will normally not proceed to anchorage, even if an anchorage location is available. Subject to a berth being available and conditions being acceptable, the vessels will be directed to berth immediately upon their arrival to Central Harbour. Should a berth not be immediately needed to load an incoming vessel, a completed vessel may be held back at the berth until the applicable tide is available for it to directly transit safely through Second Narrows. This means that there will be times during which there are vessel docked at all three berths, but only one or two vessels might be actually undertaking cargo transfer.

Trans Mountain carried out a mooring analysis as part the submission to the Transport Canada TERMPOL Process and has updated it based upon the final dock design (see Appendix B). A typical tanker uses 14 to 16 mooring lines to secure the vessel to the berth, and the analysis has confirmed that number of lines to be sufficient for all conditions. A more up-to-date assessment of mooring layout for different sizes of vessels is presented in the Drawings Technical Report (TR-1).

A desktop simulation study was conducted by LANTEC Marine Inc. to identify any design issues that would unnecessarily complicate the conduct of vessel maneuvers during berthing and unberthing at the new dock system. No concerns were identified during fast-time simulations carried out in the areas surrounding the Terminal. After construction is started, Trans Mountain will conduct real-time berthing simulations around the Terminal that will be led by BCCP and developed in consultation with the VFPA and the PPA. These simulations will be used to confirm vessel berthing parameters, such as minimum safe speeds, navigability of tankers, and operational requirements for tugs.

The results of a Passing Vessel Analysis (see Appendix C) conducted for Trans Mountain indicate that the minimum distance between traffic within the proposed channel and a moored vessel at Berth 3 of the proposed expanded terminal is approximately 190 metres (m). Peak to peak motions of all vessels at the berth were minimal and well within recommended envelopes of the World Association for Waterborne Transport Infrastructure. All lines and fenders maintained loading safety factors well below the suggested Oil Companies International Marine Forum criteria for moored tankers at berth.

The current dock extends 75 m into Burrard Inlet, and the new dock is anticipated to extend approximately 250 m into Burrard Inlet; as such, the maximum marine footprint of construction activities may be approximately 350 m into Burrard Inlet. Trans Mountain expects that most of the marine facilities construction will be conducted from the water, using marine derricks and various other construction-related equipment. These may extend up to about 100 m beyond the footprint of the expanded dock, for which the Project will seek a working space from the VFPA. It is not anticipated that construction-related vessels (which will display appropriate lights and shapes in accordance with ColRegs) and marine equipment will obstruct passage of other vessels in Burrard Inlet, given the size of the inlet passage at the Terminal site. In the unlikely event that there is any potential short-term obstruction of the waterway during construction that might affect safe navigation of other vessels, this would be coordinated in advance through the VFPA Harbour Master and Canadian Coast Guard. In consultation with the VFPA, a detailed communications plan will be developed for the construction phase that will include the establishment of clear communication links using established modern means (including feedback and complaints hotlines). Regular updates will be posted to the Trans Mountain website for information of stakeholders and the public.

Page 5: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

PR0420171202CGY I

Contents Section Page

Executive Summary ..........................................................................................................................ES-1

Acronyms and Abbreviations ............................................................................................................. iii

1 Introduction ....................................................................................................................... 1-1

2 Size of Vessels and Tanker Loading ...................................................................................... 2-1 2.1 Berth and Anchorage Strategy ......................................................................................... 2-2 2.2 Bunkering of Vessels ........................................................................................................ 2-2

3 Approaches to the Expanded Dock ...................................................................................... 3-1 3.1 Notification and Broadcasting ......................................................................................... 3-1 3.2 Dock Mooring Plan ............................................................................................................ 3-2 3.3 Berthing Simulation ......................................................................................................... 3-3 3.4 Pilot Training and Familiarization .................................................................................... 3-3 3.5 Vessel Acceptance Criteria ............................................................................................... 3-4 3.6 Passing Vessel Analysis .................................................................................................... 3-4 3.7 Analysis of Tug Requirements .......................................................................................... 3-4 3.8 Anticipated Construction-related Marine Traffic ............................................................ 3-5 3.9 Westridge Marine Terminal Construction Safety Boom .................................................. 3-7

4 References .......................................................................................................................... 4-1

Appendixes

A

B

C

D

Letters of Support

Mooring and Berthing Analysis

Passing Ship Analysis

Navigation and Safety Plan

Tables

2-1 Typical Crude Oil Vessel Parameters ............................................................................................ 2-1 3-1 Peak Mooring Line Loads – Oil Companies International Marine Forum Criteria ........................ 3-2 3-2 VFPA Tug and Bollard Pull Requirements ..................................................................................... 3-5

Figures

1-1 VFPA Jurisdiction Showing Location of the Westridge Marine Terminal within Burrard Inlet ..... 1-2 2-1 Westridge Marine Terminal in relation to other Bulk Terminals in Burrard Inlet ........................ 2-2

Page 6: WESTRIDGE MARINE TERMINAL UPGRADE AND ...
Page 7: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

PR0420171202CGY III

Acronyms and Abbreviations BC British Columbia

bbl barrel(s)

BCCP British Columbia Coast Pilots

CCG Canadian Coast Guard

DNV Det Norske Veritas

DWT deadweight tonnage

ID identification

LOA length overall

LOA+B length overall plus beam

m metre(s)

MBL minimum allowable breaking load

MCTS Marine Communications and Traffic Services

MRA Movement Restricted Area

NEB National Energy Board

NNSP Navigation and Navigation Safety Plan

NOTSHIP Notices to Shipping

OCIMF Oil Companies International Marine Forum

PPA Pacific Pilotage Authority

Seaport Seaport Group

TERMPOL Technical Review Process of Marine Terminal Systems and Transshipment Sites

Trans Mountain Trans Mountain Pipeline ULC

TRC TERMPOL Review Committee

TMEP/the Project Trans Mountain Expansion Project

VFPA Vancouver Fraser Port Authority

VHF very high frequency (marine radio)

VTS Vessel Traffic Services

WMT Westridge Marine Terminal

Page 8: WESTRIDGE MARINE TERMINAL UPGRADE AND ...
Page 9: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

SECTION 1

PR0420171202CGY 1-1

Introduction The Trans Mountain Expansion Project (TMEP or the Project) will include construction and subsequent operation of three new berths at the existing Westridge Marine Terminal (WMT or the Terminal) in Burnaby, British Columbia (BC), to accommodate increased throughput from the expanded pipeline capacity. Each new berth will be capable of handling Aframax class vessels. Figure 1-1 shows the location of the Terminal in the Burrard Inlet.

The marine transportation aspects of the Project have been fully described in the submission to the Transport Canada Technical Review Process of Marine Terminal Systems and Transshipment Sites (TERMPOL) (TERMPOL Review Committee [TRC], 2014), which has been reviewed by the TRC, including representatives of the Vancouver Fraser Port Authority (VFPA), and was submitted to the National Energy Board (NEB) in November 2014 (NEB Filing Identification [ID] A64923).

The purpose of this Marine Traffic Technical Report is to specifically address the following 11 VFPA information requests for the Marine Traffic Study component of the Project and Environmental Review Application Submission Requirements:

1. Confirmation of the design vessel range (maximum and minimum size of vessels that can be berthedand loaded) and anticipated traffic levels; anticipated anchorage patterns and utilization periods;bunkering program (whether this is permitted at the terminal); and any other operational criteria

2. Confirmation of the approaches that vessels will take to each berth and the departure from eachberth, based on simulations or advice from the Pacific Pilotage Authority (PPA) and British ColumbiaCoast Pilots (BCCP)

3. A description of any plans for notification or broadcast of information regarding the transit oroperations of the vessels associated with the Project

4. Mooring plan for design vessels at maximum and minimum size

5. A copy of berthing simulation, including approaches to the proposed marine terminal and plans fordocking and undocking

6. A statement on whether the PPA will require a training program for pilots

7. Description of the updated Vessel Acceptance Criteria for the Terminal

8. Passing Vessel Analysis for largest vessels passing the facility with largest design vessels at theproposed berth at different tidal current conditions

9. Confirmation that the Passing Vessel Analysis already completed will still accurately reflectoutcomes considering any engineering changes that have occurred since its completion

10. Analysis of tug requirements to be conducted: report on any special requirements because of severeweather or currents at the Terminal location

11. Description of all anticipated marine traffic that will be associated with construction

As such, this report has been structured to address each requirement.

Appendix A provides two letters of support for the Project.

Page 10: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

SECTION 1 – INTRODUCTION

1-2 PR0420171202CGY

Figure 1-1. VFPA Jurisdiction Showing Location of the Westridge Marine Terminal within Burrard Inlet Source: VFPA, 2017a

Westridge

Page 11: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

SECTION 2

PR0420171202CGY 2-1

Size of Vessels and Tanker Loading Trans Mountain Pipeline ULC (Trans Mountain) does not own or operate tankers or barges. Shippers on the Trans Mountain pipeline system will source barges and tankers from the international fleet and nominate to offtake cargo oil from the WMT.

The WMT will be designed to handle a range of vessels, from barges to Aframax tankers. Most tankers are expected to be Aframax class vessels (80,000 to 120,000 deadweight tonnage [DWT]); however, Panamax class tankers (60,000 to 80,000 DWT) and barges may also be nominated to load from the WMT.

Parameters of typical size vessels are provided in Table 2-1.

Table 2-1. Typical Crude Oil Vessel Parameters

Parameter Drakes Bay Oil Barge Handymax Vessel Panamax Vessel Aframax Vessel

Vessel Length overall (m) 115.8 190.0 232.0 250.0

Vessel beam (m) 23.2 32.2 32.2 44.0

Vessel draft (m) 7.9 11.0 14.0 15.5

Design deadweight (DWT; tonnes)

17,300 50,000 75,000 120,000

Maximum vessel capacity (bbl) 100,000 300,000 495,000 815,000

Average Project cargo size (bbl) 100,000 300,000 485,000 585,000

Average Project cargo size (m3) 15,900 47,700 77,100 93,000

Average Project Vessel Draft (m) 7.9 11.0 12.5a 12.5a

Source: TERMPOL Section 3.10, NEB Filing ID A3S4T3 a Draft limited by the VFPA Movement Restricted Area (MRA) rules to 13.5 m.

Notes:

bbl = barrel(s) m = metre(s) m3 = cubic metre(s)

It is expected that the typical number of tanker loadings during Project operations will be up to 34 partly loaded Aframax vessels per month, based upon the expected maximum throughput at the dock. Based upon historical records, on average, the WMT handles approximately 5 tankers per month. Barge traffic is not forecast to change.

East of Second Narrows, there are seven bulk terminals including WMT, namely: Canexus Chemicals; Ioco Refinery; Kinder Morgan Westridge; Pacific Coast Terminals; Suncor; Shellburn; and Stanovan (Figure 2-1). In addition to the planned expansion of the WMT, several bulk terminals in Burrard Inlet have planned or have already undergone expansion

Page 12: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

SECTION 2 – SIZE OF VESSELS AND TANKER LOADING

2-2 PR0420171202CGY

Figure 2-1. Westridge Marine Terminal in relation to other Bulk Terminals in Burrard Inlet Source: TERMPOL 3.2, NEB Filing ID A3S4R8

2.1 Berth and Anchorage Strategy Trans Mountain will continue to follow the rules and guidance in effect in scheduling vessels to WMT. In addition, under normal circumstances, vessels destined to Westridge will not place undue strain on anchorages in the Port of Vancouver. Utilization of anchorages is expected to remain low under Trans Mountain’s strategy of active management of the berths, as follows: subject to a berth being available (i.e., it is not required for another vessel on the schedule), arriving or completed vessels may await cargo readiness or departure tide, respectively, while remaining alongside a berth. This will also contribute towards making more efficient use of available pilots and tugs in the port related to Trans Mountain traffic.

2.2 Bunkering of Vessels The international tanker trade requires a tanker to submit a notice of readiness to WMT to indicate the vessel’s readiness in all respects, including having a sufficient bunker on board, to complete the voyage for which it has been engaged. Time under the charter party begins to count from the time the notice of readiness is accepted.

Trans Mountain’s core business and expertise is in pipeline transportation and tanker loading. Trans Mountain does not currently provide bunker fuel service to tankers calling at the WMT and does not desire to enter the bunker fuel business in the future. Currently, only a small percentage of tankers calling at the WMT bunker in the Port of Vancouver, because tanker operators have the choice to purchase bunker fuel at many ports and will choose the most economical port, when practical, to improve overall voyage returns. Trans Mountain considered the possibility of providing bunker fuel service at the WMT; however, Trans Mountain did not include a bunkering facility in the scope of the proposed expansion primarily for the following reasons:

• It is expected that arriving tankers will, in most cases, be carrying sufficient fuel for the voyage fromthe WMT before they arrive at the berth.

• The tanker operator and/or agent will arrange to obtain bunker fuel from one of several localsuppliers, if indeed a tanker requires such fuel. Bunkering is typically carried out from a barge whilethe tanker is at anchor.

• Physical space is very limited at the WMT, and Trans Mountain’s goal is to limit the footprint of thefacility to the greatest extent practical.

However, Trans Mountain has considered that occasionally a tanker operator may wish to obtain bunker fuel from a barge while at the WMT. Whereas Trans Mountain does not exercise operational control

Page 13: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

SECTION 2 – SIZE OF VESSELS AND TANKER LOADING

PR0420171202CGY 2-3

over calling tankers, Trans Mountain will consider allowing this practice in the future dock complex, upon request, on a case-by-case basis. Subject to acceptance by the VFPA of the WMT bunkering vessels while alongside, procedures will be developed before the commencement of the expanded operations at the WMT, to verify that any approved bunkering activities will be carried out within the safety boom and in accordance with international best practices for safety and environmental protection. In all cases, bunkering operations will be carried out according to the latest edition of the International Safety Guide for Oil Tankers and Terminals and the additional information provided in the VFPA’s Port Information Guide (VFPA, 2017b).

The master of every vessel engaged in bunkering operations will communicate with the VFPA’s Operation Center and will e-mail a copy of the bunkering checklist to [email protected] after bunkering is completed.

Page 14: WESTRIDGE MARINE TERMINAL UPGRADE AND ...
Page 15: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

PR0420171202CGY 3-1

SECTION 3

Approaches to the Expanded Dock The WMT will consist of three Aframax capable berths. Vessels may make fast to their allocated berths in accordance with mooring best practices for which engineering assessments have been carried out. The WMT is approached from the west, and berthing maneuvers for Berths #1 and #2 must also be executed from the west (whereas Berth #3 berthing maneuvers can be executed from both the west and the east). All berths can accommodate vessels port or starboard side alongside, at the pilot’s discretion, based upon maneuvering safety. However, it is expected that pilots typically will dock the vessels with bow to the west to avoid having to turn the vessel around after it has been loaded.

The TRC has reviewed the proposed berth layout and does not have any concerns (TERMPOL Review Process Report on the TMEP [NEB Filing ID A64923]).

The TRC noted in the TERMPOL Report that the “existing Canadian marine laws and regulations, including international frameworks, complemented by the enhanced safety measures Trans Mountain has in place or is committed to implementing and the recommendations contained within this report will provide for safer shipping in support of the proposed Project” (TERMPOL Review Process Report on the TMEP [NEB Filing ID A64923]).

3.1 Notification and Broadcasting Marine Communications and Traffic Services (MCTS) is a program within the Canadian Coast Guard (CCG), which communicates with vessels transiting given waterways through Vessel Traffic Services (VTS). The role of MCTS is to provide initial response to ships in distress situations, to reduce the possibility of ships being involved in collisions, groundings, and strikings; and to be a cornerstone in the marine information collection and dissemination infrastructure (CCG, 2016).

The CCG issues Notices to Shipping (NOTSHIP) to inform mariners about hazards to navigation and to share other important information. Verbal NOTSHIP alerts are broadcast by radio by MCTS, and written NOTSHIP alerts are issued when the hazard location is beyond broadcast range or when the information remains in effect for an extended period.

MCTS can communicate with, and monitor the movement of, vessels in the VFPA’s jurisdiction. Vessels receiving instructions from MCTS relating to the movement or operation of vessels, works, or services in the waters of the Port of Vancouver are to assume that these are measures required by the authority and that they relate to safety or environmental protection. Periodic notices requiring action by vessels within port waters will be broadcast by MCTS as NOTSHIP or on the continuous marine broadcast.

All vessels transiting the port with very high frequency (VHF) radio capability, and not just those radios required by the MCTS and VTS Zone Regulations, should monitor the VHF channel used for MCTS communications in the respective area. The Vancouver Harbour limits MCTS uses to VHF Channel 12 for communications.

Page 16: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

SECTION 3 – APPROACHES TO THE EXPANDED DOCK

3-2 PR0420171202CGY

3.2 Dock Mooring Plan There are three different classifications of mooring lines that are relative to the ship’s orientation:

1. Breast lines: generally perpendicular to the ship, restraining the vessel from moving away from theberth

2. Spring lines: generally parallel with the ship, restraining the vessel from moving along the berth(i.e., fore and aft)

3. Head and stern lines: typically, 45 degrees to the ship, which assist in keeping the vessel alongsideand in position

Modern terminals rely more on the breast and spring lines to restrain the vessel, since these are more efficient at directly restricting the vessel in those directions. The head and stern lines are deployed for redundancy by the vessel master and improve safety. The mooring structures layout incorporates these line configurations in the design.

Mooring analysis was carried out and presented in the TERMPOL studies (TERMPOL 3.13, Appendix A [NEB Filing ID A3S4V0]) and updated based on the final design. A typical tanker uses 14 to 16 mooring lines to secure the vessel to the berth, and the analysis has confirmed that to be sufficient for all conditions. A more up-to-date assessment of mooring layout for different sizes of vessels has been presented, together with other drawings being submitted as part of this permitting application (refer to Drawings Technical Report, TR-1).

Table 3-1 presents a summary of peak mooring line tensions for all Oil Companies International Marine Forum (OCIMF) environmental criteria examined. Loads are presented as a percentage of their minimum allowable breaking load (MBL). OCIMF recommends that the peak line tension is not to exceed 55 percent of the respective tanker’s MBL. According to the mooring analysis report, the Aframax tanker generally results in the largest mooring line loads; however, no vessel exceeds OCIMF recommendations for safe mooring.

Table 3-1. Peak Mooring Line Loads – Oil Companies International Marine Forum Criteria Mooring Line Aframax (%) Handymax (%) 650 Barge (%) Oil Barge (%)

1 25 39 18 27

2 25 41 18 12

3 31 35 30 12

4 29 38 31 12

5 38 24 30 25

6 37 24 29 28

7 34 43 30 --

8 34 53 30 --

9 28 40 -- --

10 28 40 -- --

11 38 28 -- --

12 38 28 -- --

13 35 -- -- --

14 34 -- -- --

15 29 -- -- --

Page 17: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

SECTION 3 – APPROACHES TO THE EXPANDED DOCK

PR0420171202CGY 3-3

Table 3-1. Peak Mooring Line Loads – Oil Companies International Marine Forum Criteria Mooring Line Aframax (%) Handymax (%) 650 Barge (%) Oil Barge (%)

16 29 -- -- --

Source: TERMPOL 3.13, Appendix A (NEB Filing ID A3S4V0) Note: -- = not applicable

3.3 Berthing Simulation After the selection of a preferred design for the new WMT facility, which was filed with the NEB, a desktop navigation simulation study was conducted by LANTEC Marine Inc. to identify any design issues that might complicate the conduct of vessel maneuvers to and from the berths of the new dock system. No concerns were identified during such simulation exercises that were carried out in the areas surrounding the Terminal.

The proposed berth design has several features that are assessed as facilitating the ship maneuvering process. In all cases, the main berthing faces are unobstructed, and they allow an approach from an axis of at least 45 degrees, which provides flexibility and safety when maneuvering the vessel and working the tugs. In addition, the mooring pads and catwalks are recessed approximately 35 m from the plane of the main berthing face. This provides good clearance for the tugs, if needed, to work on the inboard side of the ship prior to connecting or after slipping mooring lines. More detail is available in the Summary Report of Maneuvering Assessment Westridge Terminals Vancouver Expansion Supplementary Report – July 2014 Modifications (NEB Filing ID A4A7R0).

It is important to note that the goal of this analysis was not to determine the ideal or best methodology for conducting approach and departure maneuvers from the proposed terminal. As such, Trans Mountain will conduct real-time simulations around the Terminal, led by the BCCP and in consultation with the VFPA and the PPA. These exercises will be used to confirm various berthing parameters (such as minimum safe speeds and operational requirements for tugs). Such real-time simulation exercises will be planned in cooperation with the VFPA, PPA, and BCCP, and they are expected to be conducted after construction is started.

3.4 Pilot Training and Familiarization The TMEP marine hazard identification process identified pilot availability and familiarization as important to the Project (TERMPOL Study 3.15, NEB Filing IDs A3S5F4, A3S5F6, and A3S5F8). The PPA has confirmed that there will be a sufficient number of licensed unrestricted pilots to provide necessary pilotage service to project tankers (NEB Filing ID A4A8T7).

Trans Mountain is aware that the highly trained pilots of the BCCP safely operate and guide vessels at a high rate of success. The PPA, which licenses all pilots operating on the BC Coast, places a high priority on refresher programs and continuous improvement of pilotage techniques, spending between $500,000 and $1,000,000 annually on training. Pilots have been trained in BC, Eastern Canada, the United States, and Europe. Recently, the PPA has installed its own navigation simulator using world-leading Kongsberg technology to further facilitate pilot training.

Trans Mountain expects that real-time simulation (Section 3.2) will be used by the PPA, the BCCP, and the VFPA to inform and run a familiarization program for pilots and tug masters in docking and undocking vessels at the expanded WMT dock system. Trans Mountain expects that initially the familiarization program will be developed and simulator databases updated by the end of 2017. The actual extent and timeframe for pilots to undergo the program would be determined by early 2018. In

Page 18: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

3-4 PR0420171202CGY

SECTION 3 – APPROACHES TO THE EXPANDED DOCK

any case, pilot familiarization would be completed at least 3 months prior to the expanded Westridge dock system becoming operational.

3.5 Vessel Acceptance Criteria As the terminal operator, Trans Mountain has authority to vet and to grant or deny permission for tankers to berth, which is a tool to compel tankers to comply with Trans Mountain’s tanker acceptance process and terminal regulations.

Under Trans Mountain’s robust Tanker Acceptance Standard (National Energy Board [NEB] Filing ID A3W9J8), all vessels nominated to transfer cargo at the WMT must undergo a review to assess that the vessel will not pose any undue hazard or risk to the Terminal, other vessels, or the public. Unacceptable vessels or those not meeting the criteria are denied berthing rights. For added safety, Trans Mountain allocates a Loading Master to every vessel at the WMT and pre-deploys an oil spill boom whenever oil is being transferred to or from a vessel at the WMT. These industry-leading practices will continue to be applied (with necessary updates to account for the Project enhancements).

The Tanker Acceptance Standard will be updated in accordance with the NEB conditions prior to commencing operations. The basic requirements are not expected to change from its current version; rather, they will be enhanced in accordance with improvements through the project.

3.6 Passing Vessel Analysis During review of the Project under the TERMPOL Review Process, the VFPA requested that an independent party complete a Passing Vessel Analysis on behalf of Trans Mountain. The VFPA requested the analysis to take into account the proposed berth layout and to determine the safety parameters for all maneuvering situations that may result east of Second Narrows.

Trans Mountain provided the results of the Passing Vessel Analysis to the VFPA (Appendix C and NEB Filing ID A4A7Q9). The study results indicate that the minimum distance between traffic within the proposed channel and a moored vessel at Berth 3 of the proposed expanded terminal is approximately 190 m. Peak-to-peak motions of all vessels at the berth were minimal and well within recommended envelopes of the World Association for Waterborne Transport Infrastructure. All lines and fenders maintained loading safety factors well below the suggested OCIMF criteria for moored tankers at berth.

According to the TERMPOL Report, the VFPA intends to use the results of the Passing Vessel Analysis provided by Trans Mountain to inform redesign of the channel in the eastern section of the Burrard Inlet between Second Narrows and Port Moody, as well as the location of the anchorages east of Second Narrows.

Trans Mountain confirms that the Passing Vessel Analysis already completed accurately reflects outcomes considering the engineering changes that have occurred since its completion.

3.7 Analysis of Tug Requirements Tugs can provide a variety of services (ranging from escorting, tethering, and assisting in berthing to unberthing, safety and security, spill contingency, and firefighting). For the purposes of this study, only those tug services required to assist tankers calling WMT to navigate through Vancouver Harbour are considered.

Requirements for tug escorts in Vancouver Harbour are defined in the Port Information Guide (VFPA, 2017b). Vessel calling WMT are required to navigate the Second Narrows MRA and must already comply with VFPA standards for tug requirements, which have been reproduced in Table 3-2, summarizing the configuration of the tug package and the bollard pull requirements for such vessels. For those vessels

Page 19: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

SECTION 3 – APPROACHES TO THE EXPANDED DOCK

PR0420171202CGY 3-5

arriving directly to berth at WMT the same tugs will assist during berthing. Similarly, those tugs assisting a vessel to depart from the berth will also provide the necessary assistance through the Second Narrows as well. However, in case there is a requirement of an intervening period of anchoring of the vessel, separate tugs will be called to fulfill the service requirements.

Table 3-2. VFPA Tug and Bollard Pull Requirements

Number of Tugs Bollard Pull (tonnes)

LOA/LOA +B Draught Bow Stern At Bow At Stern Total

LOA less than 200m and beam less than 35m

<8 m 1 1 20 30 50

>8 m <10 m 1 1 30 40 70

>10 m 1 1 30 50 80

LOA 200m – 229.9m and beam less than 35m

<8 m 1 1 30 50 80

>8 m <10 m 1 1 or 2 60 65 125

>10 m <12 m 1 or 2 1 or 2 60 80 140

>12 m 1 or 2 2 60 110 170

LOA 230m – 250m and beam less than 45m

<10 m 1 or 2 1 or 2 60 65 125

>10 m <12 m 1 or 2 1 or 2 60 80 140

>12 m 1 or 2 2 60 110 170

Source: VFPA, 2017b

Notes:

LOA = length overall LOA+B = length overall plus beam

Trans Mountain has been in close dialogue with tug operators in the Port of Vancouver to confirm each operator’s ability to provide the necessary tug support in future. Between the two operators, Seaspan and SAAM Smit, there are currently nine tugs each with over 60 tonnes bollard pull capacity working in the port. Both operators intend to support TMEP with tugs and, for this purpose, would be willing to obtain additional vessels as indicated by their letters of support (which are appended to the end of this report in Appendix A).

3.8 Anticipated Construction-related Marine Traffic Trans Mountain expects that a major portion of the marine facilities will be constructed from the water using marine derricks and other construction-related equipment, which may extend up to about 100 m beyond the footprint of the expanded dock. The current dock extends 75 m into Burrard Inlet, and the new dock is anticipated to extend approximately 250 m into Burrard Inlet; as such, the maximum marine footprint of construction activities may be approximately 350 m into Burrard Inlet.

It is anticipated that barges will be used to transport construction materials related to the WMT expansion. As such, during the construction phase, there will be numerous barge deliveries to the WMT site towed by tugs; other tugs, barges, vessels, and booms related to expansion of the docks will be around the new dock area as it is being built.

It is not anticipated that construction-related vessels and marine equipment will obstruct or impede the passage of other vessels in Burrard Inlet, given the size of the inlet passage at the Terminal site. These vessels will display appropriate lights and shapes in accordance with ColRegs. In the unlikely event that

Page 20: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

3-6 PR0420171202CGY

SECTION 3 – APPROACHES TO THE EXPANDED DOCK

there is any potential short-term obstruction of the waterway during construction that would affect safe navigation of other vessels, this would be coordinated in advance through the VFPA Harbour Master and the CCG. Waterway users are notified of such activities through the CCG’s Weekly Notice to Mariners.

Increased activity at the terminal during construction may factor into certain users changing their movement patterns away from areas around the Terminal, or may result in minor delays for certain users. Should it be deemed necessary, launches will be employed by the Project to guide and direct other vessels, and such vessels will display the appropriate signals and make appropriate broadcasts by VHF radio to ensure that approaching and passing traffic is kept suitably informed (and cautioned) of the works under progress. In consultation with VFPA, a detailed communications plan will be developed for the construction phase that will include the establishment of clear communication links using established modern means, which will include feedback and complaints hotlines. Regular updates will be posted to the Trans Mountain website for information of stakeholders and the public. Please see the In-Water Excavation Technical Report (TR-6) for further detail on equipment to be used during in-water excavation.

Certain construction-related vessels and marine equipment such as pile driving rigs operating within the construction zone will utilize appropriate anchoring systems that will consist of several anchors deployed to the seafloor and extending beyond the designated construction zone. The anchors and cable will not interfere with surface navigation and will be clear of the general vessel traffic in the area and will also not impact the designated anchorage locations. Due to the bathymetry of the inlet with deep water down the center where the anchors would typically be placed, the catenary of the anchor cables would generally lay on the seafloor except when from time to time these are tightened up to reposition the construction vessel. A preliminary layout, including profile drawings, of the anchoring systems are being developed and can be provided if required as part of the technical review.

NEB Condition #48 requires development of a Navigation and Navigation Safety Plan (NNSP). The condition requires a list of navigable waterways affected by the Project and requires mitigation measures to address navigation and navigation safety. The navigable waterway that interacts with the WMT is Burrard Inlet.

The NNSP does not apply to potential navigation effects of moving tankers; however, it does apply to the presence of the expanded marine terminal during Project construction and operations. The NNSP document can be found through the NEB weblink: https://apps.neb-one.gc.ca/REGDOCS/Item/View/3241376 (see also Appendix D).

The NNSP has listed several planned mitigation measures that have been (and will be) conducted during the construction of the WMT, as follows:

• Dock design and siting has been developed so that it will not impede boat traffic. Trans Mountainhas committed that they will:

− Continue to work with the VFPA on permitting and design requirements.

− Seek input on strategies to communicate construction schedule and work areas to residents and others.

− Notify marine commercial and recreational operators of hazards associated with construction, and place warning signs offshore and onshore near construction activities.

− Facilitate barges for heavy equipment access being placed in appropriate areas.

− Operate Project vessels at low speeds.

− Provide detailed design information to the CCG to evaluate the need for additional navigational aids.

Page 21: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

SECTION 3 – APPROACHES TO THE EXPANDED DOCK

PR0420171202CGY 3-7

− Share the NNSP for the WMT area with marine waterway users and implement it after engaging with appropriate authorities and stakeholders.

Trans Mountain also advised participants at the event that, during construction of the WMT, the following will occur:

• The VFPA will be requested to implement the proposed passing ship channel described in the TMEPsubmission to the NEB.

• The working zone for WMT construction will be demarcated by navigation buoys and other means inconsultation with the CCG and the VFPA.

• On-water safety vessels will provide guidance and assistance, as necessary.

Furthermore, Trans Mountain will regularly communicate with and update all marine waterway users (including boaters, commercial fishers, and Aboriginal groups) on construction activities in the construction area through a variety of methods, including the following:

• Meetings or workshops with key user groups

• Neighbourhood resident mail-outs

• Local advertising and public service announcements

• On-water and onshore signage

• Website postings, e-mail notifications, and social media

• Access to e-mail and phone-line contacts

3.9 Westridge Marine Terminal Construction Safety Boom Plans are in hand to install a floating marine safety boom around the entire Westridge working zone during construction. The marine construction safety boom, a key element of the NNSP, will be designed to ensure the safety of commercial and recreational users of the local marine area, and the safety of workers working within a clearly demarcated working zone. The overall Westridge area working zone is expected to encompass waters covering the future Westridge water lot area plus an additional temporary working space. It will be fitted with several access points or gates to accommodate the passage of construction vessels and vessels coming to and from the existing Westridge dock. The existing terminal will remain in operation for the majority of the construction period.

The marine construction safety boom will consist of floats and suitable vertical panels and its layout will be configured according to the construction operations and schedule. It will be highly visible during the day and the structure will be equipped with reflective placards on both the inside and outside so the marine safety boom remains visible between the buoys. At night, in accordance with general Canadian Coast Guard requirements, the boom will be marked by navigation lights (flashing yellow one nautical mile range) on all offshore corners. Additional lights will be mounted on the ship gate buoys. Radar reflectors will be installed strategically to assist approaching traffic identify the boom on radar during night time and periods of reduced visibility.

This boom will be moored using suitable anchors to withstand typical and worst case environmental conditions found in this area. Although the anchors securing the boom will be deployed to the seafloor and might extend outside the area enclosed by the boom, the anchors will not pose any concern for surface navigation.

The marine safety boom will be staged at a nearby yard in the Burrard Inlet. From here it will be assembled and launched. The NNSP in Appendix D includes a figure of the safety boom.

Page 22: WESTRIDGE MARINE TERMINAL UPGRADE AND ...
Page 23: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

SECTION 4

PR0420171202CGY 4-1

References Canadian Coast Guard (CCG). 2016. Marine Communications and Traffic Services MCTS. Accessed May 2016. http://www.ccg-gcc.gc.ca/Marine-Communications/Home.

Fisheries and Oceans Canada (DFO). 2012. Pacific Region Integrated Fisheries Management Plan: Surf Smelt - April 1, 2012 to December 31, 2014. Accessed May 2016. http://www.dfo-mpo.gc.ca/Library/343255.pdf.

Fisheries and Oceans Canada (DFO). 2013. Permitted Fishing Within Rockfish Conservation Areas. Accessed May 2016. http://www.pac.dfo-mpo.gc.ca/fm-gp/maps-cartes/rca-acs/permitted-permis-eng.html.

TERMPOL Review Committee (TRC). 2014. TERMPOL Review Process Report for the Trans Mountain Expansion Project. 68 pp.

Vancouver Fraser Port Authority (VFPA). 2017a. Home. Accessed April 2017. http://www.portvancouver.com/.

Vancouver Fraser Port Authority (VFPA). 2017b. Port Information Guide. Accessed April 2017. http://www.portvancouver.com/wp-content/uploads/2015/03/Port-Information-Guide-12-Port-of-Vancouver-August-2016-amended.pdf

Page 24: WESTRIDGE MARINE TERMINAL UPGRADE AND ...
Page 25: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Appendix A Letters of Support

Page 26: WESTRIDGE MARINE TERMINAL UPGRADE AND ...
Page 29: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Appendix B Mooring and Berthing Analysis

Page 30: WESTRIDGE MARINE TERMINAL UPGRADE AND ...
Page 31: WESTRIDGE MARINE TERMINAL UPGRADE AND ...
Page 32: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal – Berthing & Mooring Analysis Final Report PRODUCED FOR TRANS MOUNTAIN PIPELINE LP APRIL 27, 2017

Page 33: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page i

Document Verification Client Trans Mountain Pipeline LP Project name TMEP Westridge Marine Terminal Document title Westridge Marine Terminal - Berthing & Mooring Analysis Document subtitle TMP Report 01-13283-TW-WT00-MD-RPT-0002 RB Status Final Report Date April 27, 2017 Project number 9665 File reference 2017.04.06.REP.WMT Final Mooring Analysis

Revision Description Issued by Date Checked A Draft Final Report - Issued for Review AJ April 5, 2017 TR/RDB B Final Report - Issued for Review AJ April 6, 2017 TR/RDB 0 Final Report – Issued for Design/Use AJ April 27, 2017 TR/RDB

Produced by: Moffatt & Nichol, Vancouver Suite 301 - 777 West Broadway Vancouver BC V5Z 4J7 Canada T +1 604-707-9004 www.moffattnichol.com

Page 34: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page ii

Table of Contents Document Verification .................................................................................................................................................. i

Disclaimer .................................................................................................................................................................... vi

Executive Summary ..................................................................................................................................................... 1

1. Introduction ....................................................................................................................................................... 4 1.1. Scope .................................................................................................................................................................. 4 1.2. Purpose .............................................................................................................................................................. 4 1.3. Site Layout .......................................................................................................................................................... 4 2. Design Basis ..................................................................................................................................................... 6 2.1. Design Vessel Characteristics ............................................................................................................................ 6 2.2. General Arrangement of Marine Facilities .......................................................................................................... 9 2.2.1. Parallel Midbody Analysis ................................................................................................................................... 9 2.2.1. Breasting Dolphin Locations ............................................................................................................................. 10 2.2.2. Mooring Dolphins .............................................................................................................................................. 14 2.3. Metocean Criteria ............................................................................................................................................. 15 2.3.1. OCIMF Criteria .................................................................................................................................................. 15 2.3.2. Water Depth ...................................................................................................................................................... 15 2.3.3. Water Levels ..................................................................................................................................................... 15 2.3.4. Winds ................................................................................................................................................................ 17 2.3.5. Current .............................................................................................................................................................. 19 2.3.6. Waves ............................................................................................................................................................... 20 2.3.7. Tsunami ............................................................................................................................................................ 21 2.3.8. Selected Metocean Criteria............................................................................................................................... 21

3. Berthing Analysis ........................................................................................................................................... 23 3.1. Berthing Energy Requirements ......................................................................................................................... 23 3.2. Berthing Velocity ............................................................................................................................................... 23 3.3. Eccentricity Factor ............................................................................................................................................ 24 3.4. Added Mass Factor ........................................................................................................................................... 24 3.5. Berthing Configuration and Fender Softness Factor ......................................................................................... 24 3.6. Abnormal Berthing Energy Factor ..................................................................................................................... 24 3.7. Berthing Loads .................................................................................................................................................. 24 3.8. Fender Selection ............................................................................................................................................... 27 4. Mooring Point Loads ...................................................................................................................................... 29 4.1. MOTEMS .......................................................................................................................................................... 29 4.2. PIANC WG 153 ................................................................................................................................................. 29 4.3. British Standard (European Union) ................................................................................................................... 30 4.4. Determining Largest Mooring Line .................................................................................................................... 31 4.5. Method Selection .............................................................................................................................................. 32 5. Mooring Analysis Methodology ..................................................................................................................... 33 5.1. Static Mooring Model Software – OPTIMOOR ................................................................................................. 33 5.2. Dynamic Mooring Model Software – aNyMoor.................................................................................................. 33

Page 35: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page iii

5.3. Limiting Mooring Criteria ................................................................................................................................... 33 5.3.1. Mooring Line Tension Limits ............................................................................................................................. 33 5.3.2. Fender Loads .................................................................................................................................................... 34 5.3.3. Motions ............................................................................................................................................................. 34 5.4. Mooring Line Arrangements.............................................................................................................................. 34 5.4.1. Aframax Tanker ................................................................................................................................................ 34 5.4.2. Panamax Tanker .............................................................................................................................................. 37 5.4.3. Handymax Tanker ............................................................................................................................................ 39 5.4.4. Handysize Tanker ............................................................................................................................................. 40 5.4.5. Jet Fuel Barge .................................................................................................................................................. 41 5.4.6. Oil Barge ........................................................................................................................................................... 42

6. Static Mooring Analysis Results ................................................................................................................... 43 6.1. Aframax Tanker ................................................................................................................................................ 43 6.2. Panamax Tanker .............................................................................................................................................. 48 6.3. Handymax Tanker ............................................................................................................................................ 51 6.4. Jet Fuel Barge .................................................................................................................................................. 54 6.5. Jet Fuel Barge .................................................................................................................................................. 56 6.6. Oil Barge ........................................................................................................................................................... 57 7. Dynamic Mooring Analysis Results .............................................................................................................. 58 7.1. Mooring Analysis Summary .............................................................................................................................. 58 7.1.1. Tsunami Mooring Analysis Results ................................................................................................................... 58

8. Conclusions .................................................................................................................................................... 64

9. References ...................................................................................................................................................... 65

List of Figures Figure 1-1: Artist Rendering of the Proposed Westridge Terminal Expansion ........................................................... 5 Figure 2-1: KM TMEP Marine Facilities Arrangement ................................................................................................ 9 Figure 2-2: Side Profile – Parallel Midbody Curve on Panamax Tanker ................................................................... 10 Figure 2-3: Recommended Dolphin Spacing (OCIMF MEG-3) ................................................................................. 11 Figure 2-4: General Arrangement of Berths 1&2 (all dimensions in meters) ............................................................ 12 Figure 2-5: General Arrangement of Berth 3 (all dimensions in meters) .................................................................. 12 Figure 2-6: General Arrangement of Loading Platforms (Top: Berth 2; Bottom: Berth 3) ......................................... 13 Figure 2-7: General Arrangement of Tanker Manifolds (OCIMF - 1991) .................................................................. 14 Figure 2-8: Breasting Dolphin elevation .................................................................................................................... 14 Figure 2-9: Water Level Exceedance Curve at Station 7735 Vancouver .................................................................. 17 Figure 2-10: Annual wind rose developed from measurements at the Site ............................................................ 18 Figure 2-11: Peak Ebb (Depth-Averaged) Currents ............................................................................................... 20 Figure 3-1: Generalized Performance Curve of Trelleborg Super Cone Fender ...................................................... 27 Figure 3-2: Photograph of Example Fender Panel with 100 mt capacity Fender Posts............................................ 28 Figure 5-1: Mooring Line Arrangement – Aframax Tanker ....................................................................................... 35 Figure 5-2: Extreme Low Water Mooring Line Arrangement – Aframax Tanker ....................................................... 36

Page 36: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page iv

Figure 5-3: Mooring Line Arrangements – Panamax Tanker .................................................................................... 37 Figure 5-4: Extreme Low WaTer Mooring Line Arrangements – Panamax Tanker .................................................. 38 Figure 5-5: Mooring Line Arrangements – Handymax Tanker .................................................................................. 39 Figure 5-6: Mooring Line Arrangements – Handysize Tanker .................................................................................. 40 Figure 5-7: Mooring Line Arrangements – Jet Fuel Barge ........................................................................................ 41 Figure 5-8: Mooring Line Arrangements – Oil Barge ................................................................................................ 42

List of Tables Table 2-1: Basis of Design Vessels ........................................................................................................................... 6 Table 2-2: Design Vessel Characteristics .................................................................................................................. 7 Table 2-3: Parallel Midbody Confidence Intervals ................................................................................................... 10 Table 2-4: Characteristic Tidal Datums in the Site Vicinity ...................................................................................... 16 Table 2-5: Extreme Wind Speeds at Westridge Terminal........................................................................................ 19 Table 2-6: Peak Depth-Averaged Current from Hydrodynamic Model .................................................................... 20 Table 2-7: Metocean criteria for mooring analyses ................................................................................................. 22 Table 3-1: Berthing Analysis Summary ................................................................................................................... 26 Table 4-1: BS6349: 1-2 “Table H” ........................................................................................................................... 31 Table 4-2: Aframax Confidence Banding ................................................................................................................. 31 Table 4-3: Panamax Confidence Banding ............................................................................................................... 31 Table 6-1: Peak Mooring Loads – Aframax Tanker at Ballast Draft ........................................................................ 44 Table 6-2: Peak Mooring Loads – Aframax Tanker at Loaded Draft ....................................................................... 45 Table 6-3: Peak Mooring Loads – Aframax Tanker at Ballast Draft – Extreme Low Water ..................................... 46 Table 6-4: Peak Mooring Loads – Aframax Tanker at Loaded Draft – Extreme Low Water .................................... 47 Table 6-5: Peak Mooring Loads – Panamax Tanker at Ballast Draft ....................................................................... 48 Table 6-6: Peak Mooring Loads – Panamax Tanker at Loaded Draft ..................................................................... 49 Table 6-7: Peak Mooring Loads – Panamax Tanker at Ballast Draft – Extreme Low Water ................................... 50 Table 6-8: Peak Mooring Loads – Panamax Tanker at Loaded Draft – Extreme Low Water .................................. 51 Table 6-9: Peak Mooring Loads – Handymax Tanker at Ballast Draft ..................................................................... 52 Table 6-10: Peak Mooring Loads – Handymax Tanker at Loaded Draft ............................................................... 53 Table 6-11: Peak Mooring Loads – Handymax Tanker at Ballast Draft ................................................................ 54 Table 6-12: Peak Mooring Loads – Handymax Tanker at Loaded Draft ............................................................... 55 Table 6-13: Peak Mooring Loads – Jet Fuel Barge at Ballast Draft ...................................................................... 56 Table 6-14: Peak Mooring Loads – Jet Fuel Barge at Loaded Draft ..................................................................... 56 Table 6-15: Peak Mooring Loads – Oil Barge at Ballast Draft............................................................................... 57 Table 6-16: Peak Mooring Loads – Oil Barge at Loaded Draft ............................................................................. 57 Table 7-1: Peak Dynamic Mooring Loads – Aframax .............................................................................................. 59 Table 7-2: Peak Mooring Motions – Aframax .......................................................................................................... 59 Table 7-3: Peak Dynamic Mooring Loads – Panamax ............................................................................................ 60 Table 7-4: Peak Mooring Motions – Panamax ........................................................................................................ 60 Table 7-5: Peak Dynamic Mooring Loads – Handymax .......................................................................................... 61 Table 7-6: Peak Mooring Motions – Handymax ...................................................................................................... 61 Table 7-7: Peak Dynamic Mooring Loads – Handysize ........................................................................................... 62

Page 37: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page v

Table 7-8: Peak Mooring Motions – Handysize ....................................................................................................... 62 Table 7-9: Peak Dynamic Mooring Loads – Jet Fuel Barge .................................................................................... 63 Table 7-10: Peak Mooring Motions – Jet Fuel Barge ............................................................................................ 63

Page 38: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page vi

Disclaimer Moffatt & Nichol devoted effort consistent with (i) the level of diligence ordinarily exercised by competent professionals practicing in the area under the same or similar circumstances, and (ii) the time and budget available for its work, to ensure that the data contained in this report is accurate as of the date of its preparation. This study is based on estimates, assumptions and other information developed by Moffatt & Nichol from its independent research effort, general knowledge of the industry, and information provided by and consultations with the client and the client's representatives. No responsibility is assumed for inaccuracies in reporting by the Client, the Client's agents and representatives, or any third-party data source used in preparing or presenting this study. Moffatt & Nichol assumes no duty to update the information contained herein unless it is separately retained to do so pursuant to a written agreement signed by Moffatt & Nichol and the Client.

Moffatt & Nichol’s findings represent its professional judgment. Neither Moffatt & Nichol nor its respective affiliates, makes any warranty, expressed or implied, with respect to any information or methods disclosed in this document. Any recipient of this document other than the Client, by their acceptance or use of this document, releases Moffatt & Nichol and its affiliates from any liability for direct, indirect, consequential or special loss or damage whether arising in contract, warranty (express or implied), tort or otherwise, and irrespective of fault, negligence and strict liability.

This report may not to be used in conjunction with any public or private offering of securities, debt, equity, or other similar purpose where it may be relied upon to any degree by any person other than the Client. This study may not be used for purposes other than those for which it was prepared or for which prior written consent has been obtained from Moffatt & Nichol.

Possession of this study does not carry with it the right of publication or the right to use the name of "Moffatt & Nichol" in any manner without the prior written consent of Moffatt & Nichol. No party may abstract, excerpt or summarise this report without the prior written consent of Moffatt & Nichol. Moffatt & Nichol has served solely in the capacity of consultant and has not rendered any expert opinions in connection with the subject matter hereof. Any changes made to the study, or any use of the study not specifically identified in the agreement between the Client and Moffatt & Nichol or otherwise expressly approved in writing by Moffatt & Nichol, shall be at the sole risk of the party making such changes or adopting such use.

This document was prepared solely for the use by the Client. No party may rely on this report except the Client or a party so authorised by Moffatt & Nichol in writing (including, without limitation, in the form of a reliance letter). Any party who is entitled to rely on this document may do so only on the document in its entirety and not on any excerpt or summary. Entitlement to rely upon this document is conditioned upon the entitled party accepting full responsibility and not holding Moffatt & Nichol liable in any way for any impacts on the forecasts or the earnings from the project resulting from changes in "external" factors such as changes in government policy, in the pricing of commodities and materials, price levels generally, competitive alternatives to the project, the behaviour of consumers or competitors and changes in the owners’ policies affecting the operation of their projects.

This document may include “forward-looking statements”. These statements relate to Moffatt & Nichol’s expectations, beliefs, intentions or strategies regarding the future. These statements may be identified by the use of words like “anticipate,” “believe,” “estimate,” “expect,” “intend,” “may,” “plan,” “project,” “will,” “should,” “seek,” and similar expressions. The forward-looking statements reflect Moffatt & Nichol’s views and assumptions with respect to future events as of the date of this study and are subject to future economic conditions, and other risks and uncertainties. Actual and future results and trends could differ materially from those set forth in such statements due to various factors, including, without limitation, those discussed in this study. These factors are beyond Moffatt & Nichol’s ability to control or predict. Accordingly, Moffatt & Nichol makes no warranty or representation that any of the projected values or results contained in this study will actually be achieved.

This study is qualified in its entirety by, and should be considered in light of, these limitations, conditions and considerations.

Page 39: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 1

Executive Summary As part of the Trans Mountain Expansion Project, Trans Mountain Pipeline (TMP) intends to expand its existing Westridge Marine Terminal in Burnaby, British Columbia. The expansion includes the construction of three new jetty berths, as shown in the figure below, which are capable of accepting vessels ranging from barges to Aframax tankers. Berth 1 shall accommodate vessels carrying jet fuel, crude and other oil that range from inland barges to Aframax tankers. Berth 2 and 3 shall accommodate vessels carrying only crude oils that range from inland barges to Aframax tankers.

ARTIST RENDERING OF THE PROPOSED WESTRIDGE TERMINAL EXPANSION

Moffatt & Nichol (M&N) has been retained by TMP to perform the detailed engineering design of the terminal’s marine facilities. In this report, M&N presents the mooring analyses conducted for the design range of vessels to evaluate the loads on the mooring elements (mooring lines, mooring hooks, and fenders) and the vessel motions as a result of environmental forcing imposed by winds, currents, and waves, with the objective of presenting mooring arrangements and limiting environmental criteria that satisfy industry standards for safe operations.

Berth 1

Berth 2

Berth 3

Page 40: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 2

Berthing Energy

Berthing energies were calculated using methods developed by the World Association for Waterborne Transportation Infrastructure (PIANC) for the design of fender systems. Berthing energies were calculated at both loaded and ballast draft for the design range of tankers and barges.

The largest displacement, Aframax tanker, at loaded draft develops a berthing energy demand of 275 mt-m. For the mooring and tsunami analyses presented in this report, a representative Trelleborg SCN 2000 F 1.0 CV was modeled, with an available reaction of 256 mt and energy absorption of 306 mt-m.

Static Mooring Analysis

Static mooring analyses were conducted using OPTIMOOR software for the Oil Companies International Marine Forum (OCIMF) recommended environmental conditions, which include an omni-directional 60 knot wind concomitant with a range of current velocities and directions. Analyses were conducted for the design range of tanker and barges.

Ballast draft conditions were examined at Extreme Highest High Water including 0.5 m of sea level rise of +3.0 m [Geodetic Datum (GD)], which results in the largest windage areas and highest (least efficient) mooring line angles. Loaded draft conditions were examined at Lower Low Water Large Tide (LLW-LT) of -3.0m (GD), which result in the smallest depth to draft ratio and which magnifies the effects of current on the increased wetted area. The OCIMF winds are representative of a 500-year wind conditions and currents exceed the criteria anticipated at the project site as a result of metocean data analysis and numerical modeling conducted by M&N and presented in the 2014 Metocean Study Report.

Safe mooring criteria for all analyses include:

• Limiting line tensions to 55% of minimum breaking load (MBL) for steel wire lines and 50% for synthetic lines; Note that typically MBL of any fitted synthetic lines is higher to compensate for the reduced limiting line tensions applicable to synthetic mooring ropes.

• Limiting winch brake holding capacity to 60% of minimum breaking load (MBL) • Limiting fender reactions to the rated capacity of the selected fender (256 mt); • Limiting surge and sway motions to ±3.0 meters, per PIANC guidelines for operational conditions.

All safe mooring criteria are satisfied for all OCIMF recommended environmental conditions for all tankers and barges examined, including all water level and draft conditions. For the Aframax and Panamax tankers, an extreme low water mooring arrangement has been developed, as tankers at LLW-LT may have interference issues with the optimal arrangement of spring lines with the fender system of the interior breasting dolphins.

Dynamic Mooring Analyses

Dynamic mooring analyses were conducted using the aNyMooR-TERMSIM software, a time -domain six degree of freedom mooring analysis software. Analyses were carried out for operational metocean conditions which are defined as an omnidirectional 40 knot wind speed, including a gust spectrum. The most conservative mooring conditions of the static mooring analyses are utilized for the dynamic

Page 41: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 3

mooring analyses, implying only ballast draft conditions are examined, as successful results at ballast draft predicate successful results at loaded draft. The same safe mooring criteria as applied for the static mooring analyses are utilized for dynamic analyses with the addition of reporting vessel motion referenced to the cargo manifold.

Results of the dynamic mooring analyses for the operational metocean conditions are successful for line tensions, fender reactions and vessel motions.

Tsunami Analysis

M&N conducted a tsunami assessment of the Westridge Terminal as part of the Trans Mountain Expansion Project, which evaluated the impact of landslide-generated tsunami in the Indian Arm and Burrard Inlet using a MIKE 21, two-dimensional hydrodynamic model. Time series of depth-averaged current velocities at the berths for each modeled landslide are available from this study. The highest depth-averaged currents were applied to the Aframax tanker to assess feasibility of sustaining a tsunami event combined with a 25-year wind of 36.8 knots (2-minute duration) wind. Tsunami analyses are considered only for the loaded Aframax tanker, on the predication that successful results for the largest design vessel will be successful for tankers with less wetted area for tsunami forces to act. Tsunami forces were also applied independently of the 25-year wind condition, to ensure that no motions are damped out as a result of applied wind force.

Results indicate that safe mooring criteria are not exceeded for the tsunami condition, with or without the addition of a 25-year wind.

Page 42: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 4

1. Introduction

1.1. Scope

As part of the Trans Mountain Expansion Project (TMEP), Trans Mountain Pipeline (TMP) intends to expand its existing Westridge Marine Terminal in Burnaby, British Columbia. The expansion includes the construction of three new jetty berths which are capable of accepting vessels ranging from barges to Aframax tankers. TMP has engaged Moffatt & Nichol (M&N) to perform the detailed engineering design of the terminal’s marine facilities, which includes:

• Crude oil loading jetties equipped to load crude tankers ranging in size from 17,000 DWT oil barges to 127,000 DWT Aframax tankers;

• Berthing and mooring structures for the tankers, complete with quick release mooring hooks and an automated mooring line load monitoring system;

• Access trestle, intermediate platforms and other structures providing access and support for pipelines and utilities from shore to the jetties;

• Utility berth to accommodate support tugs and spill response vessels; and,

• Bulkhead wall fill structure along existing shoreline

1.2. Purpose

This document describes the static and dynamic mooring analyses conducted for the range of design vessels in order to: 1) evaluate the loads on the mooring elements (mooring lines, mooring hooks, and fenders) and the vessel motions expected to occur due to conservative, yet plausible environmental conditions and; 2) make recommendations on the mooring arrangement and limiting environmental criteria to safely carry out operations according to industry standards.

1.3. Site Layout

Figure 1-1 shows an artist’s rendering of the proposed Westridge Terminal. The three new berths are numbered from west to east, with berths 1 and 2 in a back to back configuration, sharing three (3) outboard mooring dolphins fore and aft. Berth 3 represents the western most berth of the proposed expansion plan and has a mooring arrangement identical to that of Berth 2.

Page 43: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 5

FIGURE 1-1: ARTIST RENDERING OF THE PROPOSED WESTRIDGE TERMINAL EXPANSION

Berth 1

Berth 2

Berth 3

Page 44: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 6

2. Design Basis The following are the design basis assumptions for the mooring analyses.

2.1. Design Vessel Characteristics Table 2-1 presents a summary of the vessel types, classes, and anticipated cargo types which need to be accommodated by the marine facilities.

TABLE 2-1: BASIS OF DESIGN VESSELS

Vessel Class DWT Range Cargo Type

Aframax 80,000 - 120,000 Oil

Panamax 60,000 - 80,000 Oil

Handymax 40,000 - 50,000 Oil

Handysize < 40,000 Jet Fuel

Jet Fuel Barge 15,000 - 30,000

Jet Fuel

Oil Barge Oil

Table 2-2 presents a detailed summary of vessel characteristics for the design basis tankers and barges to be used for mooring analyses. These vessels are representative of the design range of tankers and barges. Where applicable, corrected deadweight and displacements are provided for the terminal’s draft limit of 13.5 m.

Although the limiting water depth at the terminal is 18 m (Chart Datum), the draft limit of 13.5 m is currently imposed by the Port of Vancouver at Second Narrows through which vessels calling at the Westridge Terminal must navigate. As such, the mooring and berthing analyses conducted basis fully laden drafts of the design vessels are considered to be conservative.

Page 45: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 7

TABLE 2-2: DESIGN VESSEL CHARACTERISTICS

Vessel Oil Barge Crowley 650-6 Handysize Handymax Panamax Aframax

Cargo Type Oil Barge Jet Fuel Jet Fuel Jet Fuel / Oil Oil Oil

Berth 1,2,3 1 1 1,2,3 2&3 2&3

Deadweight Tonnage, DWT

Loaded Draft 15,242 27,456 16,775 50,000 70,297 117,654

Limited 13.5 m N/A N/A N/A N/A 66,036 97,799

Length Overall, LOA (m) 115.82 179 144.05 183.2 228 250

Length Between Perpendiculars, LBP (m) N/A 177.7 134 174 219 239

Beam (m) 23.16 22.56 23.3 32.2 32.23 44

Depth (m) 9.54 12.19 12.4 18.8 20.9 21

Draft Loaded (m) 7.82 9.24 8.7 11.9 13.82* 15.10*

Ballast (m) 1.65 4.95 6.21 7.18 9.9 7.13

Displacement

Loaded (mt) 17,583 33,558 21,977 54,915 84,204 136,337

Limited 13.5 m N/A N/A N/A N/A 82,060 120,276

Ballast (mt) 3,014 17,083 16,061 30,912 46,612 59,900

Side Windage Loaded (m2) 379 739 1,055 1,778 2,423 2,177

Ballast (m2) 1,011 1,485 1,390 2,595 3,177 4,169

Frontal Windage

Loaded (m2) 182 661 320 723 709 800

Ballast (m2) 325 756 378 875 776 1,152

Bow to Center Manifold (m) 61.29 89.6 74.81 91.6 113.72 124.2

Q88 Bow to Center Manifold (m) 61.8 - 69 91.88 112.78 125.79

Parallel Midbody Forward of Manifold (m) 34.4 89.02 34 42.84 65.79 69.68

Parallel Midbody Aft of Manifold (m) 34.4 89.02 38 39.76 57.59 48.44

Mooring Line Type Dyneema Dyneema PP/PE Euroflex Steel-Wire Steel-Wire

Mooring Line Minimum Breaking Load (mt) 74 82 38 62 79 83

Page 46: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 8

Vessel Oil Barge Crowley 650-6 Handysize Handymax Panamax Aframax

Mooring Tail Type N/A N/A N/A Nylon Nylon Polyester

Mooring Tail Length (m) N/A N/A N/A 11 11 11

Tail Minimum Breaking Load (mt) N/A N/A N/A 80 120 116

*Denotes that Design Draft Values Exceed Existing Terminal Draft Limit of 13.5 m

Page 47: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 9

2.2. General Arrangement of Marine Facilities The layout of the three marine berths (Figure 2-1) considers the following criteria: • Berth 1 is required to accommodate:

All vessels carrying jet fuel All vessels carrying oil up to Aframax tankers as design maximum

• Berths 2 and 3 will have the same general arrangement and are required to accommodate: All vessels carrying oil up to Aframax tankers as design maximum

Each berth will consist of a pile supported loading platform, four (4) breasting dolphins, and six (6) mooring dolphins whose function are to accommodate safe mooring and berthing of the design range of tankers and barges. Each Berth arrangement is identical in terms of number and placement of mooring structures. Berths 1 and 2 will share concrete caps for mooring dolphins.

FIGURE 2-1: KM TMEP MARINE FACILITIES ARRANGEMENT

Industry guidelines provided by the Oil Companies International Marine Forum (OCIMF) and the World Association for Waterborne Transport Infrastructure (PIANC) were utilized for optimal placement of mooring and berthing structures.

2.2.1. Parallel Midbody Analysis To determine the appropriate number and placement of breasting dolphins, a parallel mid-body analysis was conducted for the design range of tankers and barges.

The parallel mid-body is defined as the flat section of a vessel’s hull which can make parallel contact with the fender system. To determine optimal fender location, the distance of the parallel midbody is measured at the waterline at ballast draft, where the dimensions are least. Figure 2-2 presents the side profile of a representative Panamax tanker indicating the midbody curve, and how the dimensions are calculated at ballast draft. As the fender and fender panel are located above the waterline,

MD1

MD2

MD3

BD1

BD5

C1

C2

BD2

BD6

MD4

MD5

MD6

C13

C3

BD7

BD4

BD8

TP1

TR1

TP2

TR2

TP3

TR3

TP8

TR8

TP9

TR9

TR7TP7

TR6TP6

TP5

TP4

TS1

TS2

TS6

MD7

MD8

MD9

MD10

MD11

MD12

C19

C20

C27

C28

C21

BD9BD10

BD11BD12

LP1-2

C14

C15

C4

C5

C22

C23

LP3

UF1UF2

FP1

C6C7

C16C17

TS5

C18

C8

TS4

TS3

C9

C11

JP2

JP1

TP10

TR10

TP11

TR11

TP12

TR12

TS8

TS7

TS0

C24C25

C26

C10

C12

Page 48: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 10

additional contact with the vessels parallel midbody is anticipated to be made over and above the dimensions provided at ballast draft.

FIGURE 2-2: SIDE PROFILE – PARALLEL MIDBODY CURVE ON PANAMAX TANKER1

The INTERTANKO (Q88) database was polled for the design range of tankers and barges to determine parallel midbody dimensions for as many vessels as possible. The result is approximately 3,200 vessels which have reported information for the design range of vessels. Confidence intervals were determined and presented in Table 2-3 and utilized to help determine breasting dolphin locations.

TABLE 2-3: PARALLEL MIDBODY CONFIDENCE INTERVALS Confidence Level 5% 25% 50% 75% 95%

Barge PBL FWD (Ballast) 31.4 42.3 50.5 56.7 65.8 PBL AFT (Ballast) 29.3 40.9 48.0 64.0 89.0

Handysize PBL FWD (Ballast) 23.5 31.9 40.0 45.0 56.5 PBL AFT (Ballast) 24.0 32.2 40.0 47.1 53.9

Handymax PBL FWD (Ballast) 33.1 38.6 43.0 44.5 50.6 PBL AFT (Ballast) 29.0 36.0 39.9 46.4 53.2

Panamax PBL FWD (Ballast) 46.2 62.1 67.1 69.1 70.9 PBL AFT (Ballast) 42.9 52.0 57.5 61.2 70.3

Aframax PBL FWD (Ballast) 50.7 59.1 61.8 67.2 73.0 PBL AFT (Ballast) 41.5 45.9 49.7 53.0 62.8

2.2.1. Breasting Dolphin Locations The functions of the breasting dolphins are to absorb the energy of the berthing vessels, resist breasting forces of a moored vessel, and to provide a foundation for the quick release mooring hooks which accommodate the vessels spring lines. 1 Diagram is for illustrative purposes only – not necessarily to scale

Page 49: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 11

Each breasting dolphin will support an independent fender system, which will consist of a frontal frame against which the vessels make contact and, behind the frame, a flexible energy-absorbing rubber element to provide a cushion between the vessel and the dolphin. Fender selection is presented in Section 3.8.

Additionally, the Oil Companies International Marine Forum (OCIMF) Mooring Equipment Guidelines 3rd Edition recommends limiting vessel overhang to 1/3rd length overall (LOA) with respect to the outboard fenders. Meaning that no more than 1/3rd of the vessel’s overall length should extend past the last point of contact with the fender system. Overhang in excess of 1/3rd may potentially result in higher mooring line loads due to the increased moment arm pivot about the breasting dolphin. OCIMF finds that fender spacing on the order of 0.25-0.4 LOA is acceptable for berths considering a range of vessel lengths and types, as presented in Figure 2-3.

FIGURE 2-3: RECOMMENDED DOLPHIN SPACING (OCIMF MEG-3)

Figure 2-4 and Figure 2-5 present the general arrangement of berths 1-3 with dolphin dimensioning presented in meters. Figure 2-6 presents the arrangement of the loading platform for Berths 1 and 2. The layout of marine loading arms (MLA) is the same for Berth 3 as it is for Berth 2. The layout of the vapor line is to comply with tanker manifold configurations as specified by the OCIMF Recommendations for Oil Tanker Manifolds and Associated Equipment, as presented in Figure 2-7.

Breasting dolphin spacing accommodates the design range of tankers parallel midbody, with the exception of approximately 3% of tankers whose midbody does not make contact at ballast draft. These vessels are the lower 5% confidence intervals for the Handysize vessels. However, values reported by INTERTANKO are at ballast draft, at the waterline, and may in fact contact the fender system.

Figure 2-8 presents the breasting dolphin orientation, indicating the concrete cap to be +5.3 m Geodetic Datum (GD).

Page 50: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 12

FIGURE 2-4: GENERAL ARRANGEMENT OF BERTHS 1&2 (ALL DIMENSIONS IN METERS)

FIGURE 2-5: GENERAL ARRANGEMENT OF BERTH 3 (ALL DIMENSIONS IN METERS)

Page 51: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 13

FIGURE 2-6: GENERAL ARRANGEMENT OF LOADING PLATFORMS (TOP: BERTH 2; BOTTOM: BERTH 1)

Page 52: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 14

FIGURE 2-7: GENERAL ARRANGEMENT OF TANKER MANIFOLDS (OCIMF - 1991)

FIGURE 2-8: BREASTING DOLPHIN ELEVATION

2.2.2. Mooring Dolphins The function of the mooring dolphins is to secure the vessels fore and aft mooring lines. All mooring dolphins have a deck elevation of +5.3 m GD and are equipped with quick release mooring hook (QRH) assemblies with remote release, load sensing and an electric reversing capstan. Mooring dolphin (MD) 6, which is shared by Berths 1 and 2, as well as MD 12, located on Berth 3, are equipped

Page 53: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 15

with quadruple QRHs. All remaining mooring dolphins are equipped with triple QRHs; all quick release hooks have a safe working load rating of 100 mt (each hook).

The number and placement of mooring dolphins is designed to accommodate the full design range of tankers and barges. As presented in Figure 2-3, OCIMF recommends that breasting lines remain as perpendicular as possible to increase efficiency for resisting loads which act to push the vessel off the berth.

When accommodating a large range of tankers and barges, whose characteristics can vary significantly, it may not be possible to have OCIMF recommended horizontal line angles which are 15 or less under all loading conditions; however, mooring arrangements still satisfy OCIMF maximum line tension and operating metocean criteria. The results of the mooring analyses, presented in this report, properly assess the functionality of the mooring structures placement.

2.3. Metocean Criteria Two series of meteorological and oceanographic (metocean) criteria were utilized for the mooring analyses. First, criteria recommended by OCIMF Mooring Equipment Guidelines, 3rd edition were applied statically. These criteria serve to validate a vessels’ mooring equipment established for worldwide trade. Secondly, dynamic, time-varying environmental conditions which are representative of operational conditions at the project location are applied. These dynamic criteria provide insight to vessel response under operational conditions.

2.3.1. OCIMF Criteria OCIMF states that for tankers above 16,000 DWT, intended for worldwide trade, the mooring system should be capable of withstanding the following environmental conditions:

60 knots constant wind from any direction simultaneously with either: • 3-knot current at 0 deg or 180 deg; • 2-knot current at 10 deg or 170 deg; and, • 0.75 knots current from the direction of maximum beam current loading.

Wind velocity is the velocity measured at the standard datum height of 10 m above ground and is representative of a 30 second average mean velocity. Current direction is direction traveling to and relative to the bow of the vessel.

2.3.2. Water Depth According to a hydrographic survey conducted by Golder Associates in 2014, water depths over the footprint of the proposed expansion range from 18 to 21 m with respect to Chart Datum (CD). For mooring analyses purposes, the water depth at all three berths is assumed to be 18 m (CD).

2.3.3. Water Levels Water levels at the project site are dominated by a semi-diurnal mixed tide, characterized by two unequal high and low waters in a day. Table 2-4 provides tidal datums at multiple sites in the vicinity

Page 54: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 16

of the Westridge Terminal from the Canadian Hydrographic Survey (CHS). An additional 0.5 m above the high tide line is included in the analysis of water levels to account for future sea level rise.

TABLE 2-4: CHARACTERISTIC TIDAL DATUMS IN THE SITE VICINITY

Datum Vancouver Tide Table

Vancouver CHS Chart

#3494 Port Moody Tide Table

Deep Cove CHS Chart

#3494

EHHW (m, CD) 5.60 - - - HHWLT (m, CD) 5.00 5.00 5.12 5.10 HHWMT (m, CD) 4.40 4.40 4.46 4.40

MWL (m, CD) 3.10 3.10 3.08 3.10 Chart Datum (m, CD) 0.00 0.00 0.00 1.00

LLWMT (m, CD) 1.10 1.10 1.07 1.10 LLWLT (m, CD) -0.10 0.00 -0.10 0.20 ELLW (m, CD) -0.30 - - -

EHHW: Extreme Highest High Water HHWLT: Higher High Water Large Tide HHWMT: Higher High Water Mean Tide MWL: Mean Water Level CD: the plane of Lowest Normal Tides to which charts and water levels are referred LLWMT: Lower Low Water Mean Tide LLWLT: Lower Low Water Large Tide ELLW: Extreme Lowest Low Water For the Vancouver Harbour area, Geodetic Datum is 3.1 m above CD (see BC Ministry of Env., 1995)

In addition, Figure 2-9 presents the water level exceedance curve corresponding to the water levels measured at Station 7735 Vancouver, BC. The record extends from November 1909 to February, 2017 with a sample of one hour.

Page 55: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 17

FIGURE 2-9: WATER LEVEL EXCEEDANCE CURVE AT STATION 7735 VANCOUVER

2.3.4. Winds Winds at the terminal were measured from February 8, 2013 to February 28, 2014. As shown in the annual wind rose in Figure 2-10, winds primarily blow from the NE at speeds lower than 10 knots, followed by winds from the W of similar range. During the winter, winds from the NE prevail and are associated with outflows from the Indian Arm. During the summer, winds from the W increase in frequency and magnitude, and are associated with onshore sea breezes. The highest wind speed recorded during the period of measurements was 17.2 m/s (33.4 knots).

Page 56: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 18

FIGURE 2-10: ANNUAL WIND ROSE DEVELOPED FROM MEASUREMENTS AT THE SITE

Page 57: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 19

Extreme wind speeds cannot be accurately predicted with one year of measurements. In the site vicinity, the Vancouver International Airport has the longest hourly record of measured wind speeds. The record extends from 1953 to present (March 2017).

Comparison of wind speeds for the overlapping period indicates that extreme winds at the site are approximately 25% lower than at the Vancouver International Airport. Thus, extreme wind speeds calculated from the historical record at the airport were reduced by 25% as a means to estimate extremes at the site. The resulting extremes are shown in Table 2-5. These values are slightly different than those presented in the Metocean Study Report (M&N, 2014a) because more years have been included in the present analysis.

TABLE 2-5: EXTREME WIND SPEEDS AT WESTRIDGE TERMINAL

Return Period (years)

Wind Speed (2-min, 10 m height), knots

5% non-Exceedance Best Fit 95% non-Exceedance

1 25.5 26.3 27.0 2 28.6 29.4 30.1 5 30.9 32.0 33.2 10 32.2 34.1 35.9 25 34.0 36.8 39.5 50 35.3 38.8 42.3

100 36.6 40.8 45.1 200 37.8 42.8 47.9 500 39.5 45.5 51.5

The 60-knot, 30-second wind speed outlined in the OCIMF guidelines corresponds to a 2-minute wind speed of 52.9 knots. According to Table 2-5, this wind speed has a return period beyond 500 years; therefore, use of this wind speed for static analysis of the mooring system is conservative.

For dynamic mooring analyses, a 40 knot omni-directional wind speed is applied, as a typical limiting wind speed for vessels to remain at berth, disconnected from loading equipment. This corresponds approximately to the 100-year wind speed of 40.8 knots. In the event safe mooring criteria are exceeded, maximum allowable wind speeds are reduced.

2.3.5. Current Measurements of current velocities at the site were made using an Acoustic Doppler Current Profiler (ADCP) for a 2-month period in April and May of 2013. The maximum current speed recorded along the water column was 0.64 m/s (1.2 knots) and the maximum depth-averaged current was 0.47 m/s (0.9 knots).

Page 58: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 20

Depth-averaged currents at each berth were estimated from a 2-dimensional Mike 21 hydrodynamic model of Burrard Inlet. The Metocean Study Report (M&N, 2014a) describes in detail the model development and the results at the site.

Figure 2-11 presents the peak ebb currents as a result of the largest predicated tidal variation; Table 2-6 presents a summary of peak currents and directions. The OCIMF currents of 3 and 2 knots are conservative in comparison to the measured and model-predicted currents.

FIGURE 2-11: PEAK EBB (DEPTH-AVERAGED) CURRENTS

TABLE 2-6: PEAK DEPTH-AVERAGED CURRENT FROM HYDRODYNAMIC MODEL

Location

Ebb Flood

Current Speed Direction Current Speed Direction

m/s knot (°N) m/s knot (°N) Berth 3 0.51 1.0 277.0 0.40 0.77 80.9 Berth 2 0.46 0.89 268.2 0.39 0.75 71.7 Berth 1 0.45 0.87 269.8 0.38 0.73 67.4

Utility Dock 0.54 1.05 278.7 0.45 0.87 74.0

2.3.6. Waves Burrard Inlet is well sheltered from the long period waves characteristic of the Pacific Ocean. Waves at the site are generated by the local winds blowing over the limited fetch. M&N developed a Mike 21 wave model to assess wind-generated waves (M&N, 2014a). A number of wind speeds were evaluated, ranging from the 10th percentile to the estimated 100-year return period. The wind directions that were evaluated were the NE (35 °N) and W (270 °N) which provide the longest fetch.

Page 59: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 21

The 100-year wave will be used for dynamic mooring analyses. The model results show that winds blowing from the NE generate a greater wave height compared to westerly winds. The parameters of the 100-year wave are: significant wave height, Hs = 0.6 m; peak wave period, Tp = 2.6 s, and mean wave direction, MWD = 35 °N.

2.3.7. Tsunami M&N conducted a tsunami assessment of the Westridge Terminal as part of the TMEP (M&N, 2015). The study evaluated the impact of several hypothetical landslide-generated tsunamis in the Indian Arm and Burrard Inlet using a MIKE 21, two-dimensional hydrodynamic model. Time series of depth-averaged current velocities at the berths for each modeled landslide are available from this study. The highest depth-averaged current at the berths from all the tsunami scenarios was 1.86 knots, which is less than the 3-knot current considered in Section 2.3.1.

2.3.8. Selected Metocean Criteria Static and dynamic mooring analyses will be conducted to determine the suitability of the mooring system. The metocean criteria that will be used for each analysis is presented in Table 2-7. The peak wave period of the wave used in the dynamic analysis was increased from 2.6 sec to 3.0 sec as this is the minimum peak wave period accepted by the program.

Page 60: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 22

TABLE 2-7: METOCEAN CRITERIA FOR MOORING ANALYSES

Parameter Static Analysis Dynamic Analysis

Depth 18 m (CD) 18 m (CD)

Water Level

Vancouver Tides: 1) 6.1 m (CD) (HHWLT + SLR) 2) -0.1 m (CD) (LLWLT)

Vancouver Tides: 1) 6.1 m (CD) (HHWLT + SLR) 2) -0.1 m (CD) (LLWLT)

Winds

OCIMF Criteria: • Speed: 60 knot (30-sec duration) • Direction: Full compass

Analysis of Local Winds: • Speed: 40 knot (2-min duration) • Direction: Full compass • 100-year return period

Currents

OCIMF Criteria: 1) 3-knot at 0°or 180° 2) 2-knot at 10° or 170° 3) 0.75 knots from the direction of

maximum beam current loading

Mike 21 Model Results: • Speed: 1.0 knot • Direction: Parallel to berth (ebb and

flood)

Waves NA

Mike 21 Model Results: • Sign. wave height, Hs = 0.6 m • Peak wave period, Tp = 3.0 s • Mean wave dir., MWD = 35 °N • 100-year return period

Tsunami NA

Mike 21 Model Results: • Maximum calculated currents

corresponding to Landslide 1 • Concurrent 25-year wind (36.8

knots)

Page 61: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 23

3. Berthing Analysis This section of the report presents the berthing analysis and selection of fenders. All three berths will be capable of handling Aframax class tankers as well as barges. The berthing structure layouts are similar with four breasting dolphins. This implies that the dominant berthing impact load and selected fender for one berth, determines the design condition for all three berths.

Vessels berthing and unberthing will be tug-assisted. A fast-time simulation performed by LANTEC Marine Incorporated determined that each berth has adequate space for assist tugs to work effectively and adequate maneuvering space for the ship itself.

3.1. Berthing Energy Requirements The primary function of the fender is to absorb the berthing energy from the berthing vessel. Fender design method starts with estimating berthing energy for some appropriate design cases and selecting fender types. The method outlined in the World Association for Waterborne Transport Infrastructure (PIANC) Guidelines for the design of Fender Systems: 2002 (PIANC, 2002) is widely used and has been applied for this analysis. A brief description of the method is given.

Berthing impact kinetic energy is:

absmeDb CCCCMVE 221

= (1)

E = berthing impact energy (N-m) Vb = berthing velocity normal to berth (m/s) MD = vessel mass, displacement tonnage (tonnes) Ce = eccentricity coefficient Cm = added mass coefficient Cs = softness coefficient Cc = berth configuration coefficient Cab = abnormal impact coefficient or factor of safety

The appropriate factors to be used in the kinetic energy method have been selected as per PIANC guidelines and fender manufacturer design aids.

3.2. Berthing Velocity The berthing velocity is assumed to be 0.15 m/s for tankers and 0.25 m/s for barges. This is determined using the design approach velocities as recommended by Brolsma et.al. in 1977 shown in Figure 4.2.1 in PIANC (2002). As shown in the figure, the design berthing velocity is a function of navigation conditions and size of vessel. For the project site, the berthing velocities of vessels are based on tug-assisted berthing, easy berthing conditions in exposed water (category c). A vessel docking information system will provide real-time data on vessel approach speed, distance off, and angles of approach to assist vessel pilots in maintaining appropriate docking speeds.

Page 62: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 24

3.3. Eccentricity Factor The eccentricity factor (CE) is used in the berthing energy calculation to allow for dissipating energy as the vessel rotates about an off-centre impact point. The eccentricity factor CE has been calculated using the following formula as recommended by PIANC:

22

222 cosRK

RKCE+

∗+=

ϕ (2)

Where: • CE = Eccentricity factor • K = Vessel radius of gyration (m) • R = Distance from point of contact to vessel’s center of mass (m) • φ = Angle between the velocity vector and the line between the point of contact and the

center of mass

3.4. Added Mass Factor The virtual mass factor CM accounts for the effective increase in the overall mass of the ship attributed to the entrained body of water carried along with the ship as it moves sideways. The calculation of the virtual mass factor has been performed using the Shigera Ueda and Vasco Costa methods, as recommended by PIANC (2002), with the most conservative result used for berthing energy calculation.

BDCM

∗+=

21 (3)

Where: • CM = Virtual mass factor • D = Vessel draught (m) • B = Vessel beam (m)

3.5. Berthing Configuration and Fender Softness Factor The softness factor, CS, which allows for the energy absorbed by the elastic deformation of the ship’s hull, and the berth configuration factor, Cc, which allows for the cushioning effect of the water trapped between the vessel and berth, have been determined as per the recommended values by PIANC as 1.0.

3.6. Abnormal Berthing Energy Factor Abnormal berthing energy factor or factor of safety is recommended by PIANC to account for human error, malfunctions, exceptional weather conditions or combination of these factors. In this analysis a factor of 1.25 is assumed for tankers and 1.75 for barges per PIANC (2002) Table 4.2.5.

3.7. Berthing Loads The three berths will be capable of accommodating fully laden Aframax vessels. Since this is an export facility the majority of the vessels will be ballasted while berthing, however the fenders need to have

Page 63: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 25

the capacity to accommodate both laden and ballasted vessels in the rare event that a laden vessel needs to return to the berth.

The berthing energy is calculated from Equation (1). Table 3-1 shows the berthing energies of the different design vessels. The berthing analysis shows that the berthing impact from a laden Aframax vessel governs the fender selection and design. Assuming that the breasting dolphin structure is exceptionally rigid absorbing no energy, the required energy absorption capacity of the fender is 2,700 kN-m.

Page 64: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 26

TABLE 3-1: BERTHING ANALYSIS SUMMARY

Vessels Cargo Oil Oil/Jet Fuel Jet Fuel Oil Oil Oil Vessel Class Oil Barge ATB Barge Handysize Handymax Panamax Aframax DWT 13,005 27,456 16,775 50,000 70,297 11,7654 LOA m 116.0 206.0 144.1 183.2 228.0 249.9 LBP m 116.0 177.7 134.0 174.0 219.0 239.0 B m 23.2 22.6 23.3 32.2 32.2 44.0 Berthing Energy- Fully Laden D m 7.8 9.25 8.7 11.9 13.82 15.1 M mt 15,697 33,558 21,977 54,915 84,204 136,337 Vb m/s 0.25 0.25 0.25 0.15 0.15 0.15 Alpha degrees 15.0 15.0 15.0 6.0 6.0 6.0 Cb 0.9 0.9 0.9 0.9 0.9 0.9 Cm 1.7 1.8 1.7 1.7 1.9 1.7 Ce 0.5 0.5 0.5 0.5 0.8 0.8 Cs 1.0 1.0 1.0 1.0 1.0 1.0 Cc 1.0 1.0 1.0 1.0 1.0 1.0 Cab 1.75 1.75 1.50 1.25 1.25 1.25 Ev kNm 433 1,036 639 579 1,334 1,963 Evab kNm 758 1,813 958 724 1,667 2,454 Edesign kNm 834 1,994 1,054 796 1,834 2,700 Berthing Energy – Ballasted D m 1.6 4.95 6.21 7.18 9.9 7.13 M mt 2,690 17,083 16,061 30,912 46,612 59,900 Vb m/s 0.25 0.25 0.25 0.15 0.15 0.15 Alpha degrees 15.0 15.0 15.0 6.0 6.0 6.0 Cb 0.9 0.9 0.9 0.9 0.9 0.9 Cm 1.1 1.4 1.5 1.4 1.6 1.3 Ce 0.5 0.5 0.5 0.5 0.8 0.8 Cs 1.0 1.0 1.0 1.0 1.0 1.0 Cc 1.0 1.0 1.0 1.0 1.0 1.0 Cab 1.8 1.8 1.5 1.3 1.3 1.3 Ev kNm 51 417 410 271 642 677 Evab kNm 88 730 614 339 802 847 LOA Length Overall Cm Added Mass Coefficient LBP Length Between Parallels Ce Eccentricity Coefficient B Beam Cs Softness Factor D Draught Cc Berth Configuration Factor M Displacement Cab Abnormal Berthing Factor Vb Berthing velocity Ev Normal Berthing Energy Alpha Angle of Approach Evab Abnormal Berthing Energy Cb Block Coefficient Edesign Design Energy includes manufacturer tolerance,

angular, velocity, and temperature factors

Page 65: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 27

3.8. Fender Selection All breasting dolphins, for all three berths, are equipped with a single fender and fender panel. Trelleborg marine super cone fenders 2000 F1.0 CV are selected for the purposes of mooring analyses. The fender element has a rated reaction of 2,511 kN (256 mt) and an energy absorption of 3,000 kN-m (306 mt-m). Therefore, it is adequate for the range of design berthing energies presented in Table 3-1.

The super cone fenders supersede the previously proposed Trelleborg marine cone fenders MCN 2000 G1.2 per the project memorandum to TMP “Berthing Analysis and Fender Selection” (M&N, 2014b).

Figure 3-1 presents the generic super cone fender performance curve.

FIGURE 3-1: GENERALIZED PERFORMANCE CURVE OF TRELLEBORG SUPER CONE FENDER

Each fender system consists of one cone fender centered at elevation +0.85 m (GD). To accommodate barges at varying elevations of water level, it is recommended the fender panel be incorporated with mooring posts which flank the fender panel. For mooring analyses, it is assumed that mooring posts on each side of the fender panel are available with a load rating up to 100 mt.

Figure 3-2 present examples of the recommended fender panel with flanking mooring posts.

Page 66: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 28

FIGURE 3-2: PHOTOGRAPH OF EXAMPLE FENDER PANEL WITH 100 MT CAPACITY FENDER POSTS

Page 67: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 29

4. Mooring Point Loads There are a number of publications which provide discretion, instruction, recommendations, and in some instances, requirements, with regards to the design of a mooring point tied to a jetty or wharf structure. This section summarizes the various available calculation methods and presents the method utilized for final design of mooring and breasting dolphins and sizing quick release hook (QRH) capacity.

4.1. MOTEMS The Marine Oil Terminal Engineering and Maintenance Standards (MOTEMS) were initiated by the Marine Facilities Division (MFD) as a result of the California State Lands Commission (CSLC) which provide specifications and qualifications for marine oil terminals along California’s coast. Although the statutory regulations identified in MOTEMS are enforceable only in California, MOTEMS is commonly used as an industry guidance document for terminals outside of California, and is included as a reference in WMT Design Basis Memorandum.

MOTEMS specifies that a mooring hook must be able to withstand the minimum breaking load (MBL) of the strongest anticipated mooring line, with a Safety Factor of 1.2. The following formula is utilized for multiple hook units:

Fd = 1.2 (MBL) x [1 + 0.75 (n-1)] (4)

Where:

n = Number of hooks on the assembly

MBL = Minimum Breaking Load

Fd = Design lateral load for the tie-down into the wharf

4.2. PIANC WG 153 The World Association for Waterborne Transport Infrastructure (PIANC) provides a publication titled “Recommendations for the Design and Assessment of Marine Oil and Petrochemical Terminals”, which is the report of an international Working Group convened by the Maritime Navigation Commission. The report provides information and recommendations, however states: “conformity is not obligatory and engineering judgement should be used in its application, especially in special circumstances.”

PIANC WG 153 states that for structural design practice, the combined hook assembly load on the mooring structure (FZA) can be calculated as:

FZA = SWL [1.0 + 0.6 x (n-1)] (5)

Page 68: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 30

Where:

FZA = Design load for hook anchorage and supporting structure

SWL = Safe Working Load of the hook assembly, based on highest anticipated MBL of the design range of vessels.

n = Number of hooks in the assembly

For the case of n = 1, a factor of 1.18 is recommended

The load formula above is based on a failure sequence as follows: • Ships winch brakes are set so that the holding capacity, beyond which it renders, equals 0.6 x the

rated capacity of the ships mooring lines; • The rated capacity of the mooring line is its minimum breaking load; • The factor of 0.6 x MBL is based on the OCIMF recommendation for winch rated brake holding

load; • In the event of accidental overload of the mooring system, winches will render before exceeding

the SWL of any individual hook; • For the case of n = 1, the hook should be designed to sustain a load of 1.18 times the hook SWL,

because the mooring fittings are designed for a safety margin against a yield of 1.18 per Oil Companies International Marine Forum (OCIMF) Mooring Equipment Guidelines.

4.3. British Standard (European Union) The British Standard BS 6349 1-2 provides guidance on the planning, design, construction and maintenance of maritime structures and which are in line with Eurocodes, which are European standards for specifying structural design within the European Union. Eurocodes are mandatory for the specification of European public works which recently replaced national building codes. Eurocodes, however, are not implicitly required on private sector projects.

Table 4-2 presents guidance provided by British Standard for the design of mooring points.

Page 69: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 31

TABLE 4-1: BS6349: 1-2 “TABLE H”

Number of Mooring Hooks per Mooring Point (N)

Total Accidental Mooring Point Load as Multiple of the Factored Rated Hook SWL (or factored rated MBL of vessel's mooring line, where appropriate)

Scenario for Derivation of Total Mooring Point Load from Mooring Line MBL

2 1.8 x 1.18 = 2.1 1 x 0.8 +1 x MBL = line on one mooring hook at MBL and the other at ship's winch design brake holding load

3 2.4 x 1.18 = 2.8 3 x 0.8 x MBL = lines on each hook at ship's winch design brake holding load

4 3.0 x 1.18 = 3.5

3 x 0.8 x MBL + 1 x 0.6 x MBL = 3 x MBL lines on each hook at ship's winch design brake holding load, one line at ship's winch brake setting

4.4. Determining Largest Mooring Line To determine the appropriate minimum breaking load which services all methods of mooring point calculation, INTERTANKO (Q88) registry was queried for information regarding mooring line minimum breaking load for any/ all vessels which were labelled, “Aframax”, and “Panamax”. It is assumed that barges and smaller vessels will have lesser mooring line capacity.

Table 4-2 and Table 4-3 present confidence banding for mooring line strength for the Aframax and Panamax tankers, respectively. The largest MBL at the 95% confidence banding and is 93 metric tons.

Therefore, a QRH with a minimum capacity of 100 metric tons will satisfy the design range of tankers and barges.

TABLE 4-2: AFRAMAX CONFIDENCE BANDING

Confidence Level 5% 25% 50% 75% 95% Cubic Capacity 98% 112,092 117,926 120,330 126,526 128,011 Ropes Forecastle (BS) 0.00 0.00 0.00 69.00 87.00 Wires Forecastle (BS) 64.00 74.00 81.00 85.00 93.00

TABLE 4-3: PANAMAX CONFIDENCE BANDING

Confidence Level 5% 25% 50% 75% 95% Cubic Capacity 98% 37,426 79,649 83,613 84,314 86,652 Ropes Forecastle (BS) 0.00 0.00 63.00 72.00 87.00 Wires Forecastle (BS) 0.00 57.00 67.00 76.00 93.00

Page 70: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 32

4.5. Method Selection Table 4-1 presents a comparison summary of mooring point loads for a representative quadruple quick release hook. The PIANC recommended formulae are utilized for structural design, with the underlying design premise that each successive element of the mooring system from the ship’s winch to the shore mooring structure should be designed to be progressively stronger. In the event of overload, this is intended to result in an inherent “fail safe” design where the mooring line would render out before the mooring line parts, before the mooring hook fails, and before the stability of the whole mooring structure is compromised. The PIANC load formula is based on a failure sequence which follows: • Ships winch brakes are set so that the holding capacity, beyond which it renders, equals 60% of

the rated capacity of the ships mooring lines; • The rated capacity of the mooring line is its minimum breaking load; • The factor of 0.6 x MBL is based on the OCIMF recommendation for winch rated brake holding

load. • In the event of accidental overload of the mooring system, winches will render before exceeding

the SWL of any individual hook;

Page 71: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 33

5. Mooring Analysis Methodology All mooring analyses are performed at the following conditions: • Ballast Draft at Extreme Highest High Water and Sea Level Rise: +3.0 m GD: This criterion

ensures vertical line angles are the largest and least efficient; additionally, the ballast draft of the vessel has the largest windage area for the wind force to be imposed.

• Loaded Draft at Lower Low Water (Large Tide): -3.0 m GD: This criterion ensures the least amount of underkeel clearance which amplifies current force acting on the loaded draft vessel.

5.1. Static Mooring Model Software – OPTIMOOR All OCIMF recommended criteria for mooring analyses are carried out using the static mooring program OPTIMOOR v.5.6.1, developed by Tension Technology International.

OPTIMOOR is a static mooring analysis program used widely in both industrial marine and naval mooring analyses. The program allows users to input vessel particulars, pier descriptions, and mooring arrangements. The environmental conditions can be applied at various speeds from any direction. The resultant wind force on the vessel is provided by the program and distributed to the mooring lines. The lines are modeled with the elasticity of actual mooring line.

5.2. Dynamic Mooring Model Software – aNyMoor All operational metocean criteria for mooring analyses are carried out using the dynamic program aNyMoor-Termsim, developed by the Maritime Research Institute Netherlands (MARIN). The program is a time domain mooring software used to simulate the dynamic characteristics of mooring systems undergoing environmental forcing. The calculation methods are derived from the evolution of TERMSIM II (developed by MARIN), which was developed and verified through extensive model testing and is well accepted for industry use.

All metocean conditions examined use a simulation time of 3 hours (10,800 seconds) per wind direction that varied by 15 degree increments and include the API gusting spectrum. The program will not establish second order drift forces for waves whose peak period is less than three (3) seconds; therefore, all waves listed in Table 2-7 will have an increased peak wave period of at least three seconds.

5.3. Limiting Mooring Criteria The following are criteria which establish industry guidelines for safe mooring conditions.

5.3.1. Mooring Line Tension Limits The allowable safe working load (SWL) in the mooring lines was set at 55% of the minimum breaking load (MBL) per recommendations provided by OCIMF for steel wire mooring lines.

For synthetic mooring lines, OCIMF recommends a safe working load equal to 50% of the MBL.

Page 72: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 34

5.3.2. Fender Loads The allowable working load in the fenders was the rated reaction at design performance for the representative fender design which is 256 mt.

5.3.3. Motions PIANC “Criteria for Movements of Moored Ships in Harbours” recommends ±3.0m (peak to peak) for surge and ±3.0 m (zero to peak) for sway. Values recommended by PIANC guidelines are conservative given the capabilities of modern marine loading arms, however serve as the primary limit for operational criteria.

5.4. Mooring Line Arrangements Figure 5-1 through Figure 5-8 present the mooring line arrangements for the design range of vessels at Berth 1. All vessels at Berth 1 shall be moored starboard side to, while all vessels at Berths 2 & 3 shall be moored portside to. In all mooring scenarios, the preferred method of mooring allows the bow of the vessel to be pointed towards the channel to allow for emergency departure; and allows the stern of the vessel to maximize use of the quadruple quick release mooring hooks. As the layout of the mooring and breasting dolphins are symmetrical for vessels moored starboard side-to at Berth 1 and port-side-to at Berth 2; mooring analyses are conducted for vessels positioned at Berth 1, and are considered representative for all berths.

5.4.1. Aframax Tanker Figure 5-1 presents the conventional mooring arrangement for the Aframax tanker; which deploys sixteen (16) mooring lines, and contacts all four (4) breasting dolphins. Due to the placement of onboard mooring winches, four (4) stern mooring lines are required to be sent to the aft-most mooring dolphin, equipped with the quadruple QRH.

Figure 5-2 presents the mooring line arrangement for the Aframax tanker at Lower Low Water-Large Tide (LLWLT). During extreme low water conditions, the tankers deck level, where winch mounted mooring lines are deployed, will be below the elevation of the QRH located on the interior breasting dolphins. As presented in Section 2.3.3, the LLWLT condition is exceeded only 1% of the time. Conditions where the tankers deck is lower than the top of dolphin is exceeded approximately 9% of the time. As a result, at low water, it may not be feasible to deploy the two aft spring lines (ML-9 and ML-10 as presented in Figure 5-1). Therefore an alternate mooring arrangement is provided, and the Aframax tanker is able to deploy fourteen (14) mooring lines, and contacts all four (4) breasting dolphins.

Page 73: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 35

FIGURE 5-1: MOORING LINE ARRANGEMENT – AFRAMAX TANKER

Page 74: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 36

FIGURE 5-2: EXTREME LOW WATER MOORING LINE ARRANGEMENT – AFRAMAX TANKER

Page 75: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 37

5.4.2. Panamax Tanker Figure 5-3 presents the conventional mooring arrangement for the Panamax tanker; which deploys twelve (12) mooring lines, and contacts all four (4) breasting dolphins.

Figure 5-4 presents the mooring line arrangement for the Panamax tanker at LLWLT (-3.0 GD). During extreme low water conditions, the tankers deck level, where winch mounted mooring lines are deployed, will be below the elevation of the QRH located on the interior breasting dolphins. As a result, the spring lines, both forward and aft of the marine loading arm, must be attached to the quick release hooks located on the outer breasting dolphins. This placement of spring lines is not as efficient as the layout presented in Figure 5-3, however, allows spring lines to be deployed and maintain the use of all available winch mounted mooring lines. Conditions where the tankers deck is lower than the top of dolphin is exceeded approximately 5% of the time.

FIGURE 5-3: MOORING LINE ARRANGEMENTS – PANAMAX TANKER

Page 76: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 38

FIGURE 5-4: EXTREME LOW WATER MOORING LINE ARRANGEMENTS – PANAMAX TANKER

Page 77: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 39

5.4.3. Handymax Tanker Figure 5-5 presents the mooring arrangement for the Handymax tanker; which deploys twelve (12) mooring lines, and contacts all four (4) breasting dolphins. Due to the location of the winch-deployed mooring lines, the spring lines are sent to the interior breasting dolphins, and do not interfere with outer breasting dolphins at any water level.

FIGURE 5-5: MOORING LINE ARRANGEMENTS – HANDYMAX TANKER

Page 78: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 40

5.4.4. Handysize Tanker Figure 5-6 presents the mooring arrangement for the Handysize tanker; which deploys twelve (12) mooring lines, and contacts the two inner breasting dolphins. Spring lines are deployed to the outer breasting dolphins, and do not require an alternate mooring line arrangement for extreme low water conditions. The handysize tanker is positioned only at Berth 1 with its central manifold spotted at the jet fuel marine loading arm.

FIGURE 5-6: MOORING LINE ARRANGEMENTS – HANDYSIZE TANKER

Page 79: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 41

5.4.5. Jet Fuel Barge Figure 5-7 presents the mooring arrangement for ocean-going Articulated Tug Barge (ATB) servicing jet fuel; which deploys eight (8) mooring lines, and contacts all four (4) breasting dolphins. Spring lines are deployed to the outer breasting dolphins, and do not require an alternate mooring line arrangement for extreme low water conditions. The ocean going barge is positioned only at Berth 1 with its central manifold spotted at the jet fuel marine loading arm.

FIGURE 5-7: MOORING LINE ARRANGEMENTS – JET FUEL BARGE

Page 80: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 42

5.4.6. Oil Barge Figure 5-8 presents the mooring arrangement for the oil barge which deploys eight (8) mooring lines, and contacts three breasting dolphins at ballast draft; contact is made with the two forward most breasting dolphins, and with the inner breasting dolphin aft of the marine loading arms. At loaded draft, the barge makes contact with all four (4) breasting dolphin fenders.

Spring lines are deployed from bitts located onboard the barge, but are not deployed from winches, and therefore have no pretension. The spring lines are attached to the mooring posts on the outsides of the fender panels, as presented in Figure 3-2. The ocean going barge is positioned with its central manifold spotted across from the crude marine loading arm, as connecting the vapor recovery arm is not anticipated with small barges.

FIGURE 5-8: MOORING LINE ARRANGEMENTS – OIL BARGE

Page 81: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 43

6. Static Mooring Analysis Results Results from static mooring analyses are included for all examined design range vessels in this section. Results are presented in tabular format reporting the peak mooring line tension as a percent of the minimum allowable load. For mooring lines, peak line load is a percentage of its minimum breaking load (MBL) which can vary by vessel. Peak fender reactions are reported in kips, and should not exceed the combined fender and pile rated reaction of 256 mt. Peak loads are indicative of all environmental conditions and directions applied to the moored vessel. All tables indicate varied current directions, and include applied wind speed of 60 knots.

6.1. Aframax Tanker Table 6-1 and Table 6-2 present a summary of peak mooring line and fender loads using the mooring arrangement presented in Figure 5-1 for the ballast and loaded draft conditions, respectively. For both draft conditions, peak mooring line load is 40% of the minimum breaking load (MBL) and occurs at ballast draft. No mooring line loads exceed the OCIMF recommended criteria of 55% MBL for wire lines. No fender reactions exceed their rated capacity.

Table 6-3 and Table 6-4 present a summary of peak mooring line and fender loads for the extreme low water mooring arrangement, as presented in Figure 5-2. Peak mooring load is 50% MBL, which does not exceed the OCIMF recommended criteria of 55% MBL.

Page 82: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 44

TABLE 6-1: PEAK MOORING LOADS – AFRAMAX TANKER AT BALLAST DRAFT (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 26% 25% 27% 25% 25% 25% 27% ML-2 26% 25% 27% 25% 25% 25% 27% ML-3 30% 30% 30% 30% 29% 29% 32% ML-4 31% 31% 31% 30% 30% 30% 32% ML-5 22% 23% 21% 22% 21% 21% 23% ML-6 23% 24% 22% 23% 21% 22% 24% ML-7 14% 16% 12% 15% 13% 14% 14% ML-8 14% 17% 12% 15% 13% 14% 14% ML-9 24% 20% 27% 22% 25% 24% 23% ML-10 24% 20% 27% 22% 25% 24% 24% ML-11 39% 38% 40%1 37% 39% 37% 40% ML-12 38% 37% 39% 36% 38% 37% 40% ML-13 28% 29% 27% 28% 27% 27% 29% ML-14 28% 29% 27% 28% 28% 27% 29% ML-15 29% 30% 29% 29% 29% 28% 30% ML-16 29% 30% 29% 29% 29% 28% 30% BD-1 30% 31% 30% 31% 32% 32% 30% BD-2 29% 29% 29% 30% 30% 30% 29% BD-3 32% 33% 32% 34% 32% 34% 31% BD-4 36% 36% 36% 38% 36% 37% 35%

1Shaded cell(s) indicates peak load for this condition

Page 83: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 45

TABLE 6-2: PEAK MOORING LOADS – AFRAMAX TANKER AT LOADED DRAFT (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 11% 9% 12% 13% 7% 10% 14% ML-2 11% 9% 13% 14% 7% 10% 14% ML-3 8% 8% 8% 12% 4% 7% 15% ML-4 8% 8% 8% 12% 4% 7% 16% ML-5 10% 12% 8% 14% 6% 9% 12% ML-6 10% 12% 8% 14% 6% 9% 12% ML-7 11% 14% 9% 13% 10% 11% 11% ML-8 11% 14% 9% 13% 10% 11% 11% ML-9 19% 15% 23% 16% 20% 18% 19% ML-10 18% 14% 23% 16% 20% 18% 19% ML-11 16% 14% 17% 6% 16% 10% 24% ML-12 16% 14% 17% 6% 15% 10% 24% ML-13 14% 16% 12% 9% 15% 11% 20% ML-14 14% 16% 13% 8% 15% 11% 20% ML-15 14% 16% 13% 8% 15% 11% 20% ML-16 14% 16% 13% 8% 15% 11% 20% BD-1 13% 13% 13% 11% 25% 18% 7% BD-2 13% 14% 13% 15% 23% 19% 8% BD-3 18% 18% 18% 30% 21% 24% 13% BD-4 20% 20% 21% 35%2 21% 26% 14%

2 The figure of 35% for BD-4 is the highest value in the table, but this is a reference to fender reaction force as a percent of rated reaction force, not an indication of mooring force.

Page 84: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 46

TABLE 6-3: PEAK MOORING LOADS – AFRAMAX TANKER AT BALLAST DRAFT – EXTREME LOW WATER (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 30% 28% 33% 29% 31% 29% 31% ML-2 30% 29% 34% 29% 32% 30% 31% ML-3 31% 31% 31% 30% 30% 30% 32% ML-4 33% 32% 33% 32% 31% 31% 34% ML-5 17% 19% 16% 18% 16% 17% 18% ML-6 18% 20% 17% 19% 17% 18% 19% ML-7 13% 16% 11% 15% 12% 13% 13% ML-8 13% 16% 11% 15% 12% 13% 13% ML-9 48% 46% 50% 45% 49% 46% 50% ML-10 48% 45% 50% 45% 48% 46% 50% ML-11 26% 28% 25% 26% 25% 25% 27% ML-12 26% 28% 25% 26% 26% 26% 27% ML-13 28% 30% 27% 28% 28% 27% 29% ML-14 28% 30% 27% 28% 28% 28% 29% BD-1 32% 31% 33% 31% 34% 33% 30% BD-2 29% 29% 30% 29% 30% 30% 28% BD-3 32% 32% 32% 33% 32% 33% 31% BD-4 36% 36% 35% 38% 36% 37% 35%

Page 85: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 47

TABLE 6-4: PEAK MOORING LOADS – AFRAMAX TANKER AT LOADED DRAFT – EXTREME LOW WATER (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 21% 13% 28% 24% 18% 21% 20% ML-2 22% 14% 29% 25% 19% 22% 21% ML-3 8% 8% 8% 12% 4% 7% 16% ML-4 9% 9% 9% 12% 4% 7% 17% ML-5 9% 12% 7% 14% 5% 9% 10% ML-6 9% 11% 7% 13% 5% 9% 10% ML-7 10% 14% 7% 13% 9% 10% 10% ML-8 10% 14% 7% 13% 9% 10% 10% ML-9 25% 18% 33% 17% 30% 25% 32% ML-10 26% 18% 34% 17% 31% 25% 32% ML-11 13% 15% 11% 8% 14% 10% 18% ML-12 13% 15% 11% 8% 14% 10% 18% ML-13 14% 16% 12% 8% 14% 10% 19% ML-14 14% 16% 12% 8% 14% 10% 20% BD-1 13% 13% 15% 11% 27% 18% 7% BD-2 13% 13% 14% 15% 24% 18% 8% BD-3 18% 18% 17% 30% 20% 23% 12% BD-4 20% 20% 20% 35% 20% 26% 14%

Page 86: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 48

6.2. Panamax Tanker Table 6-5 and Table 6-6 present a summary of peak mooring line and fender loads using the mooring arrangement presented in Figure 5-3 for the ballast and loaded draft conditions, respectively. For both draft conditions, peak mooring line load is 46% of the minimum breaking load (MBL) and occurs at ballast draft. No mooring line loads exceed the OCIMF recommended criteria of 55% MBL for wire lines. No fender reactions exceed their rated capacity.

Table 6-7 and Table 6-8 present a summary of peak mooring line and fender loads for the extreme low water mooring arrangement, as presented in Figure 5-4. Peak mooring load is 46% MBL, which does not exceed the OCIMF recommended criteria of 55% MBL for steel wire lines.

TABLE 6-5: PEAK MOORING LOADS – PANAMAX TANKER AT BALLAST DRAFT (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 18% 16% 19% 17% 11% 12% 24% ML-2 18% 16% 19% 17% 12% 13% 23% ML-3 20% 21% 19% 18% 10% 13% 28% ML-4 20% 21% 20% 18% 9% 13% 28% ML-5 19% 26% 15% 22% 18% 19% 20% ML-6 19% 26% 15% 22% 18% 19% 20% ML-7 18% 14% 23% 17% 20% 18% 18% ML-8 18% 14% 23% 17% 19% 18% 18% ML-9 23% 22% 24% 11% 21% 17% 30% ML-10 23% 22% 24% 11% 21% 17% 29% ML-11 30% 32% 28% 16% 28% 23% 38% ML-12 30% 32% 28% 15% 28% 23% 38% BD-1 16% 16% 15% 13% 24% 19% 12% BD-2 16% 16% 16% 16% 23% 20% 13% BD-3 21% 21% 22% 30% 23% 25% 17% BD-4 25% 24% 25% 36% 24% 29% 20%

Page 87: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 49

TABLE 6-6: PEAK MOORING LOADS – PANAMAX TANKER AT LOADED DRAFT (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 32% 30% 33% 30% 29% 29% 34% ML-2 30% 28% 32% 29% 28% 28% 32% ML-3 36% 37% 36% 36% 33% 33% 39% ML-4 37% 37% 36% 36% 33% 34% 40% ML-5 21% 27% 18% 24% 19% 21% 22% ML-6 21% 27% 18% 24% 19% 21% 23% ML-7 20% 16% 25% 19% 23% 20% 20% ML-8 20% 16% 25% 19% 23% 20% 20% ML-9 35% 34% 36% 31% 35% 33% 38% ML-10 34% 33% 35% 30% 34% 32% 37% ML-11 44% 46% 42% 41% 42% 41% 46% ML-12 44% 46% 42% 41% 42% 41% 46% BD-1 25% 26% 25% 25% 27% 27% 24% BD-2 24% 24% 24% 24% 26% 25% 23% BD-3 28% 28% 29% 30% 29% 30% 27% BD-4 32% 32% 33% 35% 32% 34% 31%

Page 88: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 50

TABLE 6-7: PEAK MOORING LOADS – PANAMAX TANKER AT BALLAST DRAFT – EXTREME LOW WATER (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 27% 24% 29% 26% 26% 25% 29% ML-2 26% 22% 28% 24% 25% 24% 27% ML-3 32% 34% 31% 32% 29% 30% 35% ML-4 32% 33% 31% 32% 29% 30% 35% ML-5 28% 38% 24% 32% 24% 28% 29% ML-6 27% 33% 24% 29% 24% 25% 29% ML-7 22% 17% 26% 19% 24% 22% 22% ML-8 24% 19% 29% 21% 27% 24% 24% ML-9 29% 26% 31% 25% 29% 27% 31% ML-10 28% 25% 30% 24% 28% 26% 30% ML-11 42% 46% 40% 40% 41% 40% 45% ML-12 42% 46% 40% 40% 40% 40% 45% BD-1 26% 27% 26% 25% 28% 27% 25% BD-2 25% 25% 25% 25% 27% 26% 23% BD-3 29% 29% 29% 31% 29% 30% 27% BD-4 32% 34% 33% 36% 32% 34% 31%

Page 89: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 51

TABLE 6-8: PEAK MOORING LOADS – PANAMAX TANKER AT LOADED DRAFT – EXTREME LOW WATER (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 24% 17% 31% 25% 23% 24% 25% ML-2 28% 20% 37% 28% 28% 28% 28% ML-3 37% 46% 24% 46% 30% 37% 37% ML-4 24% 31% 21% 29% 18% 22% 33% ML-5 6% 6% 6% 6% 6% 6% 6% ML-6 6% 6% 6% 6% 6% 6% 6% ML-7 6% 6% 6% 6% 6% 6% 6% ML-8 6% 6% 6% 6% 6% 6% 6% ML-9 27% 19% 35% 21% 31% 27% 28% ML-10 29% 20% 37% 22% 32% 28% 29% ML-11 40% 46% 32% 39% 40% 37% 46% ML-12 39% 46% 32% 36% 38% 35% 46% BD-1 16% 15% 17% 13% 25% 19% 12% BD-2 16% 15% 17% 15% 23% 20% 12% BD-3 24% 28% 21% 35% 23% 28% 19% BD-4 29% 34% 25% 44% 27% 34% 25%

6.3. Handymax Tanker Table 6-9 and Table 6-10 present a summary of peak mooring line and fender loads using the mooring arrangement presented in Figure 5-5 for the ballast and loaded draft conditions, respectively. For both draft conditions, peak mooring line load is 50% of the minimum breaking load (MBL) and occurs at ballast draft. Mooring loads for the aft breast lines approach, but do not exceed the 50% MBL recommendation provided by OCIMF for synthetic lines.

Page 90: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 52

TABLE 6-9: PEAK MOORING LOADS – HANDYMAX TANKER AT BALLAST DRAFT (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 25% 24% 26% 24% 25% 24% 26% ML-2 25% 24% 26% 24% 25% 24% 26% ML-3 37% 37% 37% 36% 35% 35% 39% ML-4 39% 39% 39% 38% 37% 37% 41% ML-5 24% 28% 21% 26% 22% 24% 24% ML-6 23% 27% 21% 25% 22% 23% 23% ML-7 31% 27% 34% 29% 33% 31% 31% ML-8 31% 27% 35% 29% 33% 31% 31% ML-9 48% 49% 48% 46% 48% 46% 50% ML-10 50% 50% 50% 47% 49% 48% 50% ML-11 29% 30% 27% 28% 28% 28% 30% ML-12 29% 31% 28% 29% 28% 28% 30% BD-1 22% 22% 22% 22% 23% 23% 21% BD-2 21% 21% 21% 21% 21% 21% 20% BD-3 25% 25% 25% 26% 25% 26% 24% BD-4 29% 30% 29% 31% 29% 30% 29%

Page 91: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 53

TABLE 6-10: PEAK MOORING LOADS – HANDYMAX TANKER AT LOADED DRAFT (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 16% 15% 18% 15% 16% 16% 19% ML-2 16% 15% 18% 16% 17% 16% 19% ML-3 20% 20% 20% 19% 13% 15% 25% ML-4 21% 21% 22% 20% 14% 16% 27% ML-5 21% 25% 17% 23% 19% 21% 21% ML-6 21% 25% 17% 23% 19% 21% 21% ML-7 26% 21% 31% 23% 28% 26% 26% ML-8 26% 21% 31% 23% 28% 25% 26% ML-9 30% 31% 29% 18% 27% 23% 36% ML-10 30% 31% 30% 18% 28% 24% 37% ML-11 20% 22% 18% 16% 19% 18% 23% ML-12 20% 23% 19% 16% 19% 18% 23% BD-1 16% 15% 16% 13% 20% 17% 14% BD-2 15% 15% 15% 14% 18% 17% 13% BD-3 18% 19% 18% 23% 19% 21% 16% BD-4 21% 22% 21% 29% 21% 23% 19%

Page 92: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 54

6.4. Jet Fuel Barge Table 6-9 and Table 6-10 present a summary of peak mooring line and fender loads using the mooring arrangement presented in Figure 5-7 for the ballast and loaded draft conditions, respectively. For both draft conditions, peak mooring line load is 50% of the minimum breaking load (MBL) and occurs at ballast draft. Mooring loads for the aft breast lines approach, but do not exceed the 50% MBL recommendation provided by OCIMF for synthetic lines.

TABLE 6-11: PEAK MOORING LOADS – HANDYMAX TANKER AT BALLAST DRAFT (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 25% 24% 26% 24% 25% 24% 26% ML-2 25% 24% 26% 24% 25% 24% 26% ML-3 37% 37% 37% 36% 35% 35% 39% ML-4 39% 39% 39% 38% 37% 37% 41% ML-5 24% 28% 21% 26% 22% 24% 24% ML-6 23% 27% 21% 25% 22% 23% 23% ML-7 31% 27% 34% 29% 33% 31% 31% ML-8 31% 27% 35% 29% 33% 31% 31% ML-9 48% 49% 48% 46% 48% 46% 50% ML-10 50% 50% 50% 47% 49% 48% 50% ML-11 29% 30% 27% 28% 28% 28% 30% ML-12 29% 31% 28% 29% 28% 28% 30% BD-1 22% 22% 22% 22% 23% 23% 21% BD-2 21% 21% 21% 21% 21% 21% 20% BD-3 25% 25% 25% 26% 25% 26% 24% BD-4 29% 30% 29% 31% 29% 30% 29%

Page 93: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 55

TABLE 6-12: PEAK MOORING LOADS – HANDYMAX TANKER AT LOADED DRAFT (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 16% 15% 18% 15% 16% 16% 19% ML-2 16% 15% 18% 16% 17% 16% 19% ML-3 20% 20% 20% 19% 13% 15% 25% ML-4 21% 21% 22% 20% 14% 16% 27% ML-5 21% 25% 17% 23% 19% 21% 21% ML-6 21% 25% 17% 23% 19% 21% 21% ML-7 26% 21% 31% 23% 28% 26% 26% ML-8 26% 21% 31% 23% 28% 25% 26% ML-9 30% 31% 29% 18% 27% 23% 36% ML-10 30% 31% 30% 18% 28% 24% 37% ML-11 20% 22% 18% 16% 19% 18% 23% ML-12 20% 23% 19% 16% 19% 18% 23% BD-1 16% 15% 16% 13% 20% 17% 14% BD-2 15% 15% 15% 14% 18% 17% 13% BD-3 18% 19% 18% 23% 19% 21% 16% BD-4 21% 22% 21% 29% 21% 23% 19%

Page 94: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 56

6.5. Jet Fuel Barge Table 6-13 and Table 6-14 present a summary of peak mooring line and fender loads using the mooring arrangement presented in Figure 5-7 for the ballast and loaded draft conditions, respectively. For both draft conditions, peak mooring line load is 31% of the minimum breaking load (MBL) and occurs at ballast draft. All mooring lines and fenders are within their safe working loads.

TABLE 6-13: PEAK MOORING LOADS – JET FUEL BARGE AT BALLAST DRAFT (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 18% 16% 18% 17% 17% 13% 19% ML-2 17% 16% 17% 16% 16% 13% 18% ML-3 24% 27% 22% 25% 23% 6% 24% ML-4 24% 27% 22% 26% 23% 6% 24% ML-5 20% 17% 22% 18% 21% 18% 20% ML-6 19% 17% 21% 18% 20% 18% 19% ML-7 30% 30% 29% 28% 29% 4% 31% ML-8 29% 29% 28% 27% 28% 5% 30% BD-1 7% 7% 7% 7% 8% 4% 7% BD-2 8% 8% 8% 8% 9% 4% 8% BD-3 13% 13% 13% 13% 13% 5% 13% BD-4 15% 15% 15% 16% 15% 6% 14%

TABLE 6-14: PEAK MOORING LOADS – JET FUEL BARGE AT LOADED DRAFT (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 13% 11% 15% 13% 13% 13% 13% ML-2 13% 11% 15% 13% 13% 13% 13% ML-3 23% 27% 19% 26% 21% 23% 23% ML-4 23% 28% 19% 26% 21% 23% 23% ML-5 18% 14% 22% 15% 20% 18% 18% ML-6 18% 14% 21% 15% 20% 18% 18% ML-7 15% 17% 15% 9% 15% 12% 20% ML-8 15% 16% 14% 9% 15% 11% 19% BD-1 5% 5% 5% 4% 8% 6% 4% BD-2 4% 5% 4% 4% 7% 6% 3% BD-3 7% 7% 8% 11% 8% 9% 6% BD-4 9% 9% 9% 13% 9% 11% 7%

Page 95: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 57

6.6. Oil Barge Table 6-15 and Table 6-16 present a summary of peak mooring line and fender loads using the mooring arrangement presented in Figure 5-8 for the ballast and loaded draft conditions, respectively. For both draft conditions, peak mooring line load is 29% of the minimum breaking load (MBL) and occurs at ballast draft. All mooring lines and fenders are within their safe working loads.

TABLE 6-15: PEAK MOORING LOADS – OIL BARGE AT BALLAST DRAFT (60 KNOTS WIND)

Mooring Line (ML)

No Current

3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off

ML-1 20% 20% 20% 20% 20% 20% 21% ML-2 20% 20% 21% 20% 20% 20% 21% ML-3 19% 20% 19% 19% 18% 19% 19% ML-4 19% 20% 19% 19% 19% 19% 20% ML-5 12% 14% 10% 12% 12% 12% 12% ML-6 11% 10% 13% 11% 12% 11% 12% ML-7 10% 12% 9% 11% 10% 10% 10% ML-8 26% 23% 29% 25% 26% 26% 26% BD-1 8% 8% 9% 8% 9% 9% 8% BD-2 8% 8% 8% 8% 8% 8% 8% BD-3 12% 13% 12% 12% 12% 12% 12%

BD-4 No Contact

No Contact

No Contact

No Contact

No Contact

No Contact

No Contact

TABLE 6-16: PEAK MOORING LOADS – OIL BARGE AT LOADED DRAFT (60 KNOTS WIND)

Mooring Line (ML)

No Current 3 knots 2 knots 0.75 knots

0° 180° 10° 170° Beam On Beam Off ML-1 9% 8% 9% 7% 9% 8% 12% ML-2 9% 8% 10% 8% 9% 8% 12% ML-3 8% 9% 7% 8% 7% 8% 10% ML-4 8% 9% 7% 8% 7% 8% 10% ML-5 2% 4% 0% 2% 1% 2% 5% ML-6 1% 0% 2% 1% 2% 1% 1% ML-7 2% 4% 0% 2% 1% 2% 4% ML-8 7% 3% 12% 7% 9% 8% 12% BD-1 4% 4% 5% 7% 5% 6% 3% BD-2 4% 4% 4% 6% 5% 5% 3% BD-3 3% 3% 3% 3% 5% 4% 2% BD-4 3% 3% 2% 2% 5% 4% 2%

Page 96: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 58

7. Dynamic Mooring Analysis Results Dynamic mooring analyses were conducted using the arrangements obtained from the static analysis. Ballast draft and high water were assumed for the simulations, as this combination was observed to provide the most conservative conditions from the static mooring analysis. The environmental conditions used in the simulations are those presented in Table 2-7, which in summary are: 100-year wind of 40 knots (2-min gust duration), ebb and flood current of 1.0 knot (parallel to berth), and 100-year wave from the NE (34 °N) with Hs = 0.6 m and Tp = 3.0 sec.

The oil barge’s small overall length does not provide reasonable Froude scaling for hydrodynamic input to the dynamic mooring analysis program, and is therefore excluded from dynamic analysis. As the project area is dominated primarily by winds, the OCIMF criteria considered in the static analysis, which correspond to a 500-year wind condition, are sufficient for confirming the feasibility of the oil barge to be moored at the marine facilities.

Additionally, a time series of maximum tsunami currents, as described in Section 2.3.7, concomitant with the 25-year wind of 36.8 knots (2-minute duration) were carried out for the Aframax tanker. Tsunami analyses are considered only for the Aframax tanker, on the predication that successful results for the largest design vessel will be successful for tankers with less wetted area for tsunami forces to act. Tsunami forces are also applied independently of the 25-year wind condition, to ensure that no motions are damped out as a result of applied wind force.

7.1. Mooring Analysis Summary All results for dynamic analyses, including peak mooring line loads, fender reactions, and vessel motions, are presented in Table 7-1 through Table 7-10 for all design vessels examined. Results are presented for the 40 knot wind condition (100-year wind) and indicate that safe mooring criteria for mooring lines, fender loads and vessel motions is not exceeded.

7.1.1. Tsunami Mooring Analysis Results As noted in Section 2.3.7, M&N conducted a tsunami assessment of the Westridge Terminal as part of the TMEP (M&N, 2015). The study evaluated the impact of several hypothetical landslide-generated tsunamis in the Indian Arm and Burrard Inlet using a MIKE 21, two-dimensional hydrodynamic model. Time series of depth-averaged current velocities at the berths for each modeled landslide were produced. The highest depth-averaged current at the berths from all the tsunami scenarios was 1.86 knots. M&N performed a dynamic mooring analysis using the worst case current time series to evaluate the effect of a hypothetical tsunami on a moored vessel.

As presented in Table 7-1 and Table 7-2, the Aframax tanker is able to maintain safe mooring criteria for the applied tsunami forces. For many mooring lines, peak loads do not exceed the pretension set in the mooring lines, indicating the Aframax tanker is able to sustain the applied tsunami forces.

Page 97: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 59

TABLE 7-1: PEAK DYNAMIC MOORING LOADS – AFRAMAX (BALLAST DRAFT AT HIGH WATER)

Element 40 knot Wind, 100-yr Wave,

1 knot Ebb Current

40 knot Wind, 100-yr Wave,

1 knot Flood Current 25-Year Wind with Tsunami Currents

ML-1 27% 30% 10% ML-2 27% 30% 10% ML-3 28% 32% 9% ML-4 29% 32% 9% ML-5 20% 21% 7% ML-6 21% 21% 7% ML-7 12% 10% 7% ML-8 12% 10% 7% ML-9 20% 20% 11% ML-10 20% 20% 11% ML-11 34% 38% 11% ML-12 33% 38% 11% ML-13 25% 25% 9% ML-14 25% 25% 9% ML-15 26% 27% 9% ML-16 26% 27% 9% FD-1 25% 29% 12% FD-2 24% 26% 11% FD-3 25% 25% 11% FD-4 27% 27% 12%

* Minimum breaking load = 83 mt; Allowable MBL = 55%; Peak fender reaction = 256 mt

TABLE 7-2: PEAK MOORING MOTIONS – AFRAMAX (BALLAST DRAFT AT HIGH WATER)

Peak Motion 40 knot Wind, 100-yr Wave,

1 knot Ebb Current

40 knot Wind, 100-yr Wave,

1 knot Flood Current 25-Year Wind with Tsunami Current

Surge FWD [m] 0.25 0.24 0.11 Surge AFT [m] -0.09 -0.12 -0.01 Sway OFF-Berth [m] 0.15 0.14 0.08 Sway On-Berth [m] -0.6 -0.52 -0.04 Heave [+ deg] 0 0 -0.02 Heave [- deg] -0.08 -0.07 -0.03 Roll [ + deg] 0.2 0.18 0.07 Roll [- deg] -0.01 -0.01 0.06 Yaw [+ deg] 0 0 0 Yaw [- deg] -0.01 -0.01 0

Page 98: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 60

TABLE 7-3: PEAK DYNAMIC MOORING LOADS – PANAMAX (BALLAST DRAFT AT HIGH WATER)

Element 40 knot Wind, 100-yr Wave,

1 knot Ebb Current

40 knot Wind, 100-yr Wave,

1 knot Flood Current ML-1 35% 33% ML-2 31% 30% ML-3 44% 38% ML-4 43% 38% ML-5 18% 19% ML-6 18% 19% ML-7 14% 13% ML-8 14% 13% ML-9 35% 39% ML-10 34% 38% ML-11 50% 51% ML-12 51% 52% FD-1 47% 48% FD-2 34% 42% FD-3 35% 31% FD-4 42% 39%

* Minimum breaking load = 79 mt; Allowable MBL = 55%; Peak fender reaction = 256 mt

TABLE 7-4: PEAK MOORING MOTIONS – PANAMAX (BALLAST DRAFT AT HIGH WATER)

Peak Motion 40 knot Wind, 100-yr Wave,

1 knot Ebb Current

40 knot Wind, 100-yr Wave,

1 knot Flood Current Surge FWD [m] 0.43 0.38 Surge AFT [m] -0.64 -0.71 Sway OFF-Berth [m] 0.19 0.22 Sway On-Berth [m] -1.12 -1.13 Heave [+ deg] 0 0.01 Heave [- deg] -0.07 -0.07 Roll [ + deg] 0.23 0.25 Roll [- deg] -0.02 -0.04 Yaw [+ deg] 0 0 Yaw [- deg] -0.01 -0.01

Page 99: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 61

TABLE 7-5: PEAK DYNAMIC MOORING LOADS – HANDYMAX (BALLAST DRAFT AT HIGH WATER)

Element 40 knot Wind, 100-yr Wave,

1 knot Ebb Current

40 knot Wind, 100-yr Wave,

1 knot Flood Current ML-1 22% 22% ML-2 22% 22% ML-3 33% 35% ML-4 35% 37% ML-5 15% 16% ML-6 15% 16% ML-7 17% 17% ML-8 17% 17% ML-9 41% 42% ML-10 43% 44% ML-11 22% 23% ML-12 23% 23% FD-1 56% 60% FD-2 42% 50% FD-3 43% 35% FD-4 50% 42%

* Minimum breaking load = 62 mt; Allowable MBL = 50%; Peak fender reaction = 256 mt

TABLE 7-6: PEAK MOORING MOTIONS – HANDYMAX (BALLAST DRAFT AT HIGH WATER)

Peak Motion 40 knot Wind, 100-yr Wave,

1 knot Ebb Current

40 knot Wind, 100-yr Wave,

1 knot Flood Current Surge FWD [m] 1.07 1.09 Surge AFT [m] -0.9 -0.85 Sway OFF-Berth [m] -2.14 -2.29 Sway On-Berth [m] 0.24 0.26 Heave [+ deg] 0.02 0.03 Heave [- deg] -0.13 -0.14 Roll [ + deg] 0.46 0.48 Roll [- deg] -0.1 -0.14 Yaw [+ deg] 0 0 Yaw [- deg] -0.01 -0.01

Page 100: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 62

TABLE 7-7: PEAK DYNAMIC MOORING LOADS – HANDYSIZE (BALLAST DRAFT AT HIGH WATER)

Element 40 knot Wind, 100-yr Wave,

1 knot Ebb Current

40 knot Wind, 100-yr Wave,

1 knot Flood Current ML-1 19% 19% ML-2 19% 18% ML-3 29% 29% ML-4 28% 28% ML-5 32% 31% ML-6 33% 32% ML-7 18% 17% ML-8 17% 16% ML-9 33% 37% ML-10 32% 36% ML-11 19% 21% ML-12 20% 22% FD-1 - - FD-2 33% 48% FD-3 46% 39% FD-4 - -

* Minimum breaking load = 38 mt; Allowable MBL = 50%; Peak fender reaction = 256 mt

TABLE 7-8: PEAK MOORING MOTIONS – HANDYSIZE (BALLAST DRAFT AT HIGH WATER)

Peak Motion 40 knot Wind, 100-yr Wave,

1 knot Ebb Current

40 knot Wind, 100-yr Wave,

1 knot Flood Current Surge FWD [m] 0.29 0.23 Surge AFT [m] -0.47 -0.48 Sway OFF-Berth [m] 0.15 0.15 Sway On-Berth [m] -1.78 -1.59 Heave [+ deg] 0.01 0.02 Heave [- deg] -0.09 -0.09 Roll [ + deg] 0.43 0.44 Roll [- deg] -0.08 -0.11 Yaw [+ deg] 0.01 0.01 Yaw [- deg] -0.01 -0.01

Page 101: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 63

TABLE 7-9: PEAK DYNAMIC MOORING LOADS – JET FUEL BARGE (BALLAST DRAFT AT HIGH WATER)

Element 40 knot Wind, 100-yr Wave,

1 knot Ebb Current

40 knot Wind, 100-yr Wave,

1 knot Flood Current ML-1 28% 30% ML-2 25% 27% ML-3 18% 22% ML-4 19% 24% ML-5 14% 13% ML-6 14% 13% ML-7 24% 26% ML-8 23% 25% FD-1 11% 14% FD-2 11% 12% FD-3 12% 11% FD-4 14% 13%

* Minimum breaking load = 82 mt; Allowable MBL = 50%; Peak fender reaction = 256 mt

TABLE 7-10: PEAK MOORING MOTIONS – JET FUEL BARGE (BALLAST DRAFT AT HIGH WATER)

Peak Motion 40 knot Wind, 100-yr Wave,

1 knot Ebb Current

40 knot Wind, 100-yr Wave,

1 knot Flood Current Surge FWD [m] 0.08 0.07 Surge AFT [m] -0.09 -0.08 Sway OFF-Berth [m] 0.07 0.07 Sway On-Berth [m] -0.25 -0.33 Heave [+ deg] 0 -0.01 Heave [- deg] -0.05 -0.06 Roll [ + deg] 0.23 0.26 Roll [- deg] -0.01 0.01 Yaw [+ deg] 0.01 0.01 Yaw [- deg] -0.01 -0.01

Page 102: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 64

8. Conclusions Extensive mooring and berthing analyses have been conducted for the design range of tankers and barges.

• Static mooring analyses conducted using OPTIMOOR and OCIMF environmental conditions result in safe mooring criteria satisfied for line tensions and fender reactions for all vessels, all draft and water level conditions.

• Dynamic mooring analyses conducted for a 100-yr conditions yield successful results for safe mooring criteria.

• Tsunami forces were applied to the Aframax tanker with successful results.

Page 103: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 65

9. References Moffatt & Nichol (M&N). (2014a). “WMT Metocean Study Report.” Trans Mountain Expansion Project, Westridge Marine Terminal. Prepared for Trans Mountain Pipeline LP. TMP Report No. 01-13283-TW-WT00-MD-RPT-0004 RA.

Moffatt & Nichol (M&N). (2014b). “WMT Berthing Analysis and Fender Selection.” Trans Mountain Expansion Project, Westridge Marine Terminal. Prepared for Trans Mountain Pipeline LP.

Moffatt & Nichol (M&N). (2015). “WMT Tsunami Assessment.” Trans Mountain Expansion Project, Westridge Marine Terminal. Prepared for Trans Mountain Pipeline LP. TMP Report No. 01-13283-TW-WT00-MFN-RPT-0008.

Moffatt & Nichol (M&N). (2017). “WMT Design Basis Memorandum” Trans Mountain Expansion Project, Westridge Marine Terminal. Prepared for Trans Mountain Pipeline LP. TMP Report No. 01-13283-TW-WT00-MFN-RPT-0002.

OCIMF (Oil Companies International Marine Forum): “Mooring Equipment Guidelines”, 3rd Edition, 2008.

OCIMF (Oil Companies International Marine Forum): “Recommendations for Oil Tanker Manifold and Associated Equipment, Fourth Edition, 1991.

PIANC: “Guidelines for the Design of Fenders Systems: 2002”, MarCom Report of WG33, 2002.

PIANC: “Criteria for Movements of Moored Vessels”, MarCom Report of WG24 1995.

PIANC: “Recommendations for the Design and Assessment of Marine Oil and Petrochemical Terminals”, MarCom report of WG153, 2016

California State Lands Commission (SLC), “Marine Oil Terminals Engineering and Maintenance Standards (MOTEMS). Chapter 31F, California Code of Regulations, Title 24, Part 2 (2010)

Page 104: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Westridge Marine Terminal - Berthing & Mooring Analysis | Trans Mountain Pipeline LP Revision 0 | April 27, 2017

Creative People, Practical Solutions.® Page 66

Moffatt & Nichol, Vancouver Suite 301 - 777 West Broadway

Vancouver BC V5Z 4J7 Canada

T +1 604-707-9004

www.moffattnichol.com

Page 105: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Appendix C Passing Ship Analysis

Page 106: WESTRIDGE MARINE TERMINAL UPGRADE AND ...
Page 107: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Prepared by: 

WESTRIDGE MARINE TERMINAL VANCOUVER, BC 

PASSING SHIP ANALYSIS 

Prepared for: 

Page 108: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

WESTRIDGE MARINE TERMINAL VANCOUVER, BC 

PASSING SHIP ANALYSIS 

M&N Project No. 7773‐01 

Revision  Description  Issued Date  Author  Reviewed  Approved 

C  Final  August 25, 2014  DRD  EDS  RDB 

B  Draft  May 09, 2014  DRD  EDS  RDB 

A  Interim Draft  April 30, 2014  DRD  EDS  RDB 

Page 109: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  3

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

TABLE OF CONTENTS 

1. INTRODUCTION ......................................................................................................................... 6 

1.1  Scope of work ...................................................................................................................... 6 

2. PROJECT BACKGROUND ............................................................................................................ 8 

2.1  Site Location ........................................................................................................................ 8 2.2  Site Bathymetry ................................................................................................................. 11 2.3  Proposed Facility design .................................................................................................... 11 2.4  Design Vessels ................................................................................................................... 12 2.5  Existing traffic .................................................................................................................... 13 2.6  Proposed Vessel Traffic Corridor ....................................................................................... 15 

3. PASSING VESSEL ANALYSIS ..................................................................................................... 17 

3.1  ROPES ................................................................................................................................ 19 3.1.1  Passing Vessel Simulated Scenarios ........................................................................... 19 3.1.2  Results ........................................................................................................................ 20 

3.2  Termsim ............................................................................................................................. 29 3.2.1  Environmental Parameters ........................................................................................ 31 3.2.2  Berth Geometries and Model Setup .......................................................................... 31 3.2.3  Mooring Evaluation Criteria ...................................................................................... 32 3.2.4  Results ........................................................................................................................ 32 

4. CONCLUSIONS AND RECOMMENDATIONS ............................................................................. 45 

5. REFERENCES ............................................................................................................................ 46 

LIST OF FIGURES 

Figure 1‐1:  PMV Proposed Channel and Anchorage Realignment ........................................... 7 

Figure 2‐1:  Site Plan Overview .................................................................................................. 8 

Figure 2‐2:  All Vessel Traffic in the Westridge Area.................................................................. 9 

Figure 2‐3:  General Arrangement Plan for the Proposed Westridge Facilities ...................... 10 

Figure 2‐4:  Site Bathymetry .................................................................................................... 11 

Figure 2‐5:  Recent  Vessel  Traffic  (LOA  >  150m  SOG  >=  6  kts)    around  the Westridge 

Facilities ................................................................................................................ 14 

Figure 2‐6:  Vessel  Speed  Over  Ground  around  the  Westridge  Facilities  (Limited  to 

Channel Traffic) ..................................................................................................... 15 

Figure 2‐7:  PMV’s Proposed Traffic Channel Alignment near Westridge Terminal ................ 16 

Page 110: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  4

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

Figure 3‐1:  Typical representation of a passing vessel scenario ............................................. 17 

Figure 3‐2:  Non‐dimensional results for a passing vessel scenario (Wang, 1975) ................. 18 

Figure 3‐3:  Snapshot  of  the  ROPES model  developed  for moored  Aframax  tankers  at 

Berth 3 ................................................................................................................... 20 

Figure 3‐4:  Modeled Surge Forces on the Panamax Tanker at Berth 1 .................................. 21 

Figure 3‐5:  Modeled Sway Forces on the Panamax Tanker at Berth 1 ................................... 21 

Figure 3‐6:  Modeled Heave Forces on the Panamax Tanker at Berth 1 ................................. 22 

Figure 3‐7:  Modeled Roll Forces on the Panamax Tanker at Berth 1 ..................................... 22 

Figure 3‐8:  Modeled Pitch Forces on the Panamax Tanker at Berth 1 ................................... 23 

Figure 3‐9:  Modeled Yaw Forces on the Panamax Tanker at Berth 1 .................................... 23 

Figure 3‐10:  Modeled Surge Forces on the Aframax Tanker at Berth 2 ................................... 24 

Figure 3‐11:  Modeled Sway Forces on the Aframax Tanker at Berth 2 .................................... 24 

Figure 3‐12:  Modeled Heave Forces on the Aframax Tanker at Berth 2 .................................. 25 

Figure 3‐13:  Modeled Roll Forces on the Aframax Tanker at Berth 2 ...................................... 25 

Figure 3‐14:  Modeled Pitch Forces on the Aframax Tanker at Berth 2 .................................... 26 

Figure 3‐15:  Modeled Yaw Forces on the Aframax Tanker at Berth 2 ...................................... 26 

Figure 3‐16:  Modeled Surge Forces on the Aframax Tanker at Berth 3 ................................... 27 

Figure 3‐17:  Modeled Sway Forces on the Aframax Tanker at Berth 3 .................................... 27 

Figure 3‐18:  Modeled Heave Forces on the Aframax Tanker at Berth 3 .................................. 28 

Figure 3‐19:  Modeled Roll Forces on the Aframax Tanker at Berth 3 ...................................... 28 

Figure 3‐20:  Modeled Pitch Forces on the Aframax Tanker at Berth 3 .................................... 29 

Figure 3‐21:  Modeled Yaw Forces on the Aframax Tanker at Berth 3 ...................................... 29 

Figure 3‐22:  Panamax Mooring Arrangement at Berth 1 ......................................................... 31 

Figure 3‐23:  Aframax Mooring Arrangement at Berths 2 and 3 ............................................... 32 

LIST OF TABLES 

Table 2‐1:  Moored Vessel Characteristics ............................................................................. 12 

Table 2‐2:  Passing Vessel Characteristics ............................................................................... 13 

Table 3‐1:  Simulated Passing Vessel Scenarios ...................................................................... 20 

Table 3‐2:  Mooring  Line  and  Hook  Loads  for  Panamax  Bulker  at  Berth  1 with  10  kt 

Passing Vessel Speed ............................................................................................ 33 

Table 3‐3:  Bollard Loads for Panamax Bulker at Berth 1 with 10 kt Passing Vessel Speed ... 34 

Table 3‐4:  Fender Loads for Panamax Bulker at Berth 1 with 10 kt Passing Vessel Speed ... 34 

Table 3‐5:  Panamax Bulker Motions at Berth 1 with 10 kt Passing Vessel Speed ................. 34 

Page 111: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  5

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

Table 3‐6:  Mooring  Line  and  Hook  Loads  for  Panamax  Bulker  at  Berth  1 with  11  kt 

Passing Vessel Speed ............................................................................................ 35 

Table 3‐7:  Bollard Loads for Panamax Bulker at Berth 1 with 11 kt Passing Vessel Speed ... 35 

Table 3‐8:  Fender Loads for Panamax Bulker at Berth 1 with 11 kt Passing Vessel Speed ... 35 

Table 3‐9:  Panamax Bulker Motions at Berth 1 with 11 kt Passing Vessel Speed ................. 36 

Table 3‐10:  Mooring  Line  and  Hook  Loads  for  Aframax  Bulker  at  Berth  2  with  10  kt 

Passing Vessel Speed ............................................................................................ 37 

Table 3‐11:  Bollard Loads for Aframax Bulker at Berth 2 with 10 kt Passing Vessel Speed .... 37 

Table 3‐12:  Fender Loads for Aframax Bulker at Berth 2 with 10 kt Passing Vessel Speed .... 38 

Table 3‐13:  Aframax Bulker Motions at Berth 2 with 10 kt Passing Vessel Speed .................. 38 

Table 3‐14:  Mooring  Line  and  Hook  Loads  for  Aframax  Bulker  at  Berth  2  with  11  kt 

Passing Vessel Speed ............................................................................................ 39 

Table 3‐15:  Bollard Loads for Aframax Bulker at Berth 2 with 11 kt Passing Vessel Speed .... 39 

Table 3‐16:  Fender Loads for Aframax Bulker at Berth 2 with 11 kt Passing Vessel Speed .... 40 

Table 3‐17:  Aframax Bulker Motions at Berth 2 with 11 kt Passing Vessel Speed .................. 40 

Table 3‐18:  Mooring  Line  and  Hook  Loads  for  Aframax  Bulker  at  Berth  3  with  10  kt 

Passing Vessel Speed ............................................................................................ 41 

Table 3‐19:  Bollard Loads for Aframax Bulker at Berth 3 with 10 kt Passing Vessel Speed .... 41 

Table 3‐20:  Fender Loads for Aframax Bulker at Berth 3 with 10 kt Passing Vessel Speed .... 42 

Table 3‐21:  Aframax Bulker Motions at Berth 3 with 10 kt Passing Vessel Speed .................. 42 

Table 3‐22:  Mooring  Line  and  Hook  Loads  for  Aframax  Bulker  at  Berth  3  with  11  kt 

Passing Vessel Speed ............................................................................................ 43 

Table 3‐23:  Bollard Loads for Aframax Bulker at Berth 3 with 11 kt Passing Vessel Speed .... 43 

Table 3‐24:  Fender Loads for Aframax Bulker at Berth 3 with 11 kt Passing Vessel Speed .... 44 

Table 3‐25:  Aframax Bulker Motions at Berth 3 with 11 kt Passing Vessel Speed .................. 44 

Page 112: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  6

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

1. INTRODUCTION 

Kinder Morgan Canada  (KMC)  is currently considering expansion of marine  facilities at 

their Westridge Terminal in Burnaby which includes the construction of new moorings capable 

of accepting 3  tanker vessels which may  range  from 17,000 DWT barges  to Aframax  tankers. 

The  geographic  location  of  these  facilities  provides  about  190 meters  of  clearance  between 

tankers moored at Westridge and the proposed channel realignment scheme within Port Metro 

Vancouver (PMV).  KMC has engaged Moffatt and Nichol to investigate passing vessel effects on 

moored ships at the proposed Westridge Terminal expansion. 

1.1 SCOPE OF WORK 

The objective of this study is to determine the loads imparted by passing vessels under 

the proposed channel alignment on selected tankers berthed at the new Westridge facilities. In 

a meeting held on April 7 with KMC and PMV, specific scenarios were laid out for this analysis: 

Panamax and Aframax tankers were to be used as the moored vessels 

The  considered passing vessel would be based on  the  largest  vessel en  route  to Port 

Moody with dimensions similar to the dry bulk carrier Shi Dai 20 

The closest passing distance between berth 3 and the proposed channel realignment is 

approximately 190 meters (Figure 1‐1) 

A transiting speed of 10 knots would be assumed for the passing vessel. 

The analysis of the passing vessel effects on the moored vessels would be carried out in 

two steps: first, the forces  imparted on the moored vessel by the passing ship are calculated, 

and then these forces are  input  into a time‐domain mooring simulation model that computes 

the moored vessel  response with  the associated mooring  line  loads,  fender  loads, and vessel 

motions. 

 

Page 113: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  7

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

 

 

 

Figure 1‐1:  PMV Proposed Channel and Anchorage Realignment 

 

Page 114: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  8

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

2. PROJECT BACKGROUND

2.1 SITE LOCATION 

The Westridge terminal is situated along the southern shore of Burrard Inlet within the 

port of Vancouver roughly 5 kilometers east of the Second Narrows Bridge and adjacent to the 

southern entrance to the Indian Arm (Figure 2‐1).  

Figure 2‐1:  Site Plan Overview 

Vessel traffic in the immediate vicinity is typically limited to shallow draft vessels; deep 

draft vessel activity in the area is predominantly traffic calling at bulk terminals east of the site 

or at the anchorages just northwest of Westridge (Figure 2‐2). 

Page 115: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  9

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

Figure 2‐2:  All Vessel Traffic in the Westridge Area 

A general arrangement of the proposed facility is shown in Figure 2‐3. The exact layout 

of  the  terminal  is  still  evolving  as  the  engineering  process  continues,  so  the  final  layout  is 

expected to be somewhat different than  is depicted here, but any potential changes  in  layout 

are not expected to have a material effect on this study.   

Page 116: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  10

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

 

Figure 2‐3:  General Arrangement Plan for the Proposed Westridge Facilities 

 

Page 117: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  11

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

2.2 SITE BATHYMETRY 

Bathymetry used  in  the  analysis was  taken  from  survey data delivered  to M&N  from 

Golder Associates on March 27, 2014. All three proposed berth locations are in naturally deep 

water with 20 meters or more of depth. Bathymetric  slope  from  the berths  to  the proposed 

channel realignment  is very mild with grades close to 30:1 (H:V). Bathymetric slopes closer to 

the shoreline are typically 8:1 until reaching the surface.  

 

Figure 2‐4:  Site Bathymetry 

2.3 PROPOSED FACILITY DESIGN 

Proposed  expansion  plans  at  the  Westridge  facilities  call  for  3  new  berths  to  be 

constructed in naturally deep water. The berths are numbered from west to east, with Berths 1 

and  2  in  a  back‐to‐back  configuration.    Each  berth has  three mooring dolphins  forward  and 

three aft.   The forward mooring dolphins for Berths 1 and 2 are combined structures whereas 

for  the aft mooring dolphins  they are  separate  structures  to accommodate  the  roadway and 

piperack that passes between them.  

Page 118: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  12

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

Berth 3  represents  the westernmost berth of  the proposed expansion plan and has a 

mooring arrangement similar to that of Berth 2.  

All berths moor vessels at a heading of 288 degrees true. 

2.4 DESIGN VESSELS 

The tanker vessels used for this analysis were based on characteristics and dimensions 

documented  in M&N’s mooring and berthing analysis submitted  in November of 2012.   PMV 

identified which  vessel  classifications  should  be  used  for  the  passing  vessel. M&N  selected 

representative  vessels  from  those  classes  and  obtained  their  principal  characteristics  from 

published  ship databases  such  as Clarkson’s Register.    Table  2‐1 presents  a  summary of  the 

moored design vessel characteristics used. Passing vessel effects on deep draft, loaded ships is 

greater than on ballasted ships due to reduced underkeel clearance and greater submerged hull 

areas. Therefore, only loaded condition tankers were evaluated in this preliminary report. 

Table 2‐1:  Moored Vessel Characteristics 

Vessel  Panamax  Aframax 

Name Torm Ottowa 

Nevisky Prospect 

DWT  70,297  117,654 

LOA (m)  228.0  250.00 

LBP (m)  219.0  239.00 

Beam (m)  32.23  44.00 

Draft  Loaded (m)  13.82  15.10 

Displacement  Loaded (mt)  84,204  136,337 

Side Windage  Loaded (m2)  1,378  2,177 

Frontal Windage  Loaded (m2)  448  800 

Mooring Line Type  Steel‐Wire  Steel‐Wire 

Mooring Line MBL (mt)  79  83 

Mooring Tail Type  Nylon  Polyester 

Mooring Tail Length (m)/ MBL (mt) 11m/ 120mt 

11m/ 116mt 

 

Vessel characteristics for the passing vessel were taken from the presentation given by 

PMV during the April 7 meeting with KMC and M&N. Table 2‐2 provides the modeled passing 

vessel characteristics. 

Page 119: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  13

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

Table 2‐2:  Passing Vessel Characteristics 

Vessel  Bulk Carrier

Name  Shi Dai 20 

Gross Registered Tonnage 64,654 

Deadweight (mt)  115,664 

LOA (m)  254.0 

Beam (m)  43 

Draft (m)  13.5 

Transit Speed (kts)  10 

2.5 EXISTING TRAFFIC 

Historical AIS ship movement data was accessed to  identify the current traffic patterns 

and  existing  beam  to  beam  clearances  of  navigation  traffic  from  the  proposed  Westridge 

berths.  Figure  2‐5  displays  recent  vessel  traffic  around  the  proposed Westridge  facilities  for 

ships with a  length overall greater than 150 meters and a speed over ground greater than or 

equal  to  6  knots. With  the  exception  of  vessels  passing  immediately  over  the  new  facility 

locations,  the current  traffic  separation  scheme keeps  inbound  traffic more  than 220 meters 

away  from  the berth 3;  therefore  the proposed 190 meter  traffic  separation  scheme used  in 

this analysis is considered conservative. Vessel speed over ground is displayed in Figure 2‐6. 

Page 120: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  14

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

 

Figure 2‐5:  Recent Vessel Traffic (LOA > 150m SOG >= 6 kts)  around the Westridge Facilities 

   

Page 121: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  15

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

Figure 2‐6:  Vessel Speed Over Ground around the Westridge Facilities (Limited to Channel Traffic) 

2.6 PROPOSED VESSEL TRAFFIC CORRIDOR 

Port  Metro  Vancouver  has  reviewed  the  proposed  Westridge  Marine  Terminal 

expansion  and  proposes  defining  a  corridor  within  the  Central  Harbour  for  ship  traffic  to 

increase  the  separation  distances  and  safety  for  large  vessels  passing  the  terminal.    The 

proposed  traffic  corridor  is  shown  in  Figure  2‐7.    The minimum  distance  between  inbound 

traffic within the corridor and a moored vessel at Berth 3 of the proposed Westridge facilities is 

about  190 meters  (Figure  2‐7).      The  proposed  corridor will  require  adjusting  some  of  the 

existing designated anchorages in the area.  The proposed corridor and anchorage locations are 

considered draft  locations for the purpose of doing this analysis, subject to finalized design to 

be carried out by PMV at a later date. 

Page 122: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  16

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

 

Figure 2‐7:  PMV’s Proposed Traffic Channel Alignment near Westridge Terminal  

Page 123: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  17

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

3. PASSING VESSEL ANALYSIS 

When transiting ships pass at high speed and/or in close proximity to a moored vessel, 

the moored  vessel  can experience  transient dynamic mooring  forces  that  can  cause  adverse 

ship movements  and  broken mooring  lines.  The  forces  imparted  to  the moored  vessel  are 

dependent on the distance to the passing vessel, the speed of the passing vessel, the underkeel 

clearance of both vessels,  the displacement of  the  two vessels, hull geometry,  channel bank 

geometry, and channel cross section. A representation of a passing vessel scenario  is given  in 

Figure 3‐1 below. 

 

Figure 3‐1:  Typical representation of a passing vessel scenario 

The primary loads imposed by the passing ship are longitudinal and lateral forces as well 

as  a  moment  on  the  moored  vessel,  although  forces  are  developed  in  all  six  degrees  of 

freedom.  Idealized  forces based on a deep, open‐water passing scenario are shown  in Figure 

3‐2 and demonstrate  that a  relatively  large, but  transient  load  is experienced by  the moored 

vessel. A surge  force pulls the moored vessel aft then pushes  forward as the vessel  in transit 

passes while a suction force pulls the moored vessel away from the berth as the passing vessel 

is adjacent  to  the moored vessel. The  curves  in Figure 3‐2  represent non‐dimensional  forces 

experienced  at  unconfined  deepwater  conditions.  For  shallow  water  and  confined‐channel 

conditions,  more  detailed  methods  are  required.  The  method  of  passing  vessel  forces 

calculation  used  in  this  report  is  based  on  the  ROPES  numerical model which  is  based  on 

computational methods developed by Pinkster Marine Hydrodynamics. 

Page 124: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  18

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

Figure 3‐2:  Non‐dimensional results for a passing vessel scenario (Wang, 1975) 

To  fully  examine  practical  problems,  however,  it  is  necessary  to  conduct  a  dynamic 

analysis that simulates the dynamic response of a moored vessel to the imposed hydrodynamic 

forces. The hydrodynamic  forces are normally  computed assuming  the moored  vessel hull  is 

rigid. In reality, the moored ship is relatively free to move somewhat in response to the passing 

ship  forces  and  will  be  restrained  by  mooring  lines  and  fenders.  The  moored  vessel  may 

experience loads less than, equal to, or larger than the imposed passing ship forces depending 

on  all  the  factors  that  dictate  dynamic  response  (i.e.  ship mass,  system  damping, mooring 

stiffness, etc.). Given  the propensity  for vessels  to  respond dynamically  in most  cases where 

passing problems have been experienced, M&N has found that dynamic analysis  is  imperative 

for practical applications, rather than static analysis.  

The  effects  of  the  passing  ship  forces were  examined  using  the  TERMSIM  computer 

program  which  is  a  six  degree‐of‐freedom,  time‐domain  model  for  mooring  dynamics 

developed by  the Maritime Research  Institute of  the Netherlands  (MARIN). The six degree of 

freedom hydrodynamic characteristics of the ship used in the computer model are based on a 

series  of  tanker  physical model  tests.  The model  simulates  the  vessel  response  to  incident 

waves, winds, and currents including damping and shallow water effects. The wind coefficients 

are based on Oil Companies International Marine Forum (OCIMF) recommendations. The forces 

generated by the passing vessel model may be directly applied on the moored vessel. TERMSIM 

computes the at‐berth motions in all six degrees of freedom as well as the loads in the mooring 

lines and fenders. The program includes a database of the non‐linear load‐extension/deflection 

curves for typical mooring  line and fender types. The user may also define the  load‐deflection 

curves manually. The output of  the  simulation  is  time  trace  signals of  all motions  and  loads 

calculated in the mooring system. 

Page 125: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  19

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

3.1 ROPES 

The ROPES 3‐d diffraction model accounts for the classical suction forces which are a result 

of the interaction of the passing ship's draw down wave system with the port geometry. The model 

uses  a  potential  flow  calculation  to  compute  the  pressure  fields  and  induced  forces  due  to  the 

passing ship. The model separately calculates the diffraction effects of channel and basin geometry 

to  compute  long‐period  disturbances  in  the  channel.  The  effects  of  the  potential  flow  and 

diffraction effects are then superposed to compute the total velocities, pressures, and fluid forces 

on  the  moored  vessel.  The  model  has  been  validated  against  scale  and  prototype  scale 

measurements by the ROPES Joint Industry Project. 

3.1.1 Passing Vessel Simulated Scenarios 

Passing  vessels  forces were  assessed  for  the moored design  vessels  identified  above. 

The largest forces will be generated by large ships with low under‐keel clearance; therefore, all 

ships were assumed at maximum draft. The analysis assumed that the passing ship travels at 10 

knots along the proposed navigational channel realignment.  

Bathymetric  setup  of  the models mimicked  the  description  provided  in  Section  2.2 

above:  a  side  slope of 8:1 was  created  from  the water  surface down  to  an elevation of  ‐20 

meters; a second slope of 30:1 was modeled from ‐20 meters to ‐30 meters. Bathymetry north 

of  the  transiting vessel was not modeled as  local depths were deep enough and bathymetric 

slopes to the north were far enough away not to affect  loads generated on either the passing 

ship or moored tankers. 

Page 126: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  20

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

 

Figure 3‐3:  Snapshot of the ROPES model developed for moored Aframax tankers at Berth 3 

In order to capture the effects of a stemming current on the passing vessel forces, the 

transiting vessel speed was increased to 11 knots to increase the apparent hydrodynamic speed 

of a passing vessel and generate forces related to such an event on the moored vessel. 

Simulated scenarios are summarized in table Table 3‐1 below. 

Table 3‐1:  Simulated Passing Vessel Scenarios 

Run Number  Berth Number  Moored Ship  Passing Distance  Passing Speed 

1  1  Panamax  440 m  10 kts 

2  1  Panamax  440 m  11 kts 

3  2  Aframax  320 m  10 kts 

4  2  Aframax  320 m  11 kts 

5  3  Aframax  190 m  10 kts 

6  3  Aframax  190 m  11 kts 

 

3.1.2 Results 

The loads generated in the passing ship simulations are presented below for each berth. 

Page 127: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  21

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

BERTH 1 

 

Figure 3‐4:  Modeled Surge Forces on the Panamax Tanker at Berth 1 

 

Figure 3‐5:  Modeled Sway Forces on the Panamax Tanker at Berth 1 

0 50 100 150 200 250 300 350 400−40

−30

−20

−10

0

10

20

30

40

Sur

ge F

orce

, kN

Sumulation Time, seconds

10 kts11 kts

0 50 100 150 200 250 300 350 400−100

−50

0

50

Sw

ay F

orce

, kN

Sumulation Time, seconds

10 kts11 kts

Page 128: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  22

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

Figure 3‐6:  Modeled Heave Forces on the Panamax Tanker at Berth 1 

Figure 3‐7:  Modeled Roll Forces on the Panamax Tanker at Berth 1 

0 50 100 150 200 250 300 350 400−1000

−500

0

500

1000

1500

2000

Hea

ve F

orce

, kN

Sumulation Time, seconds

10 kts11 kts

0 50 100 150 200 250 300 350 400−150

−100

−50

0

50

100

Rol

l For

ce, k

N−

m

Sumulation Time, seconds

10 kts11 kts

Page 129: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  23

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

 

Figure 3‐8:  Modeled Pitch Forces on the Panamax Tanker at Berth 1 

 

 

Figure 3‐9:  Modeled Yaw Forces on the Panamax Tanker at Berth 1 

 

0 50 100 150 200 250 300 350 400−1.5

−1

−0.5

0

0.5

1x 10

4

Pitc

h F

orce

, kN

−m

Sumulation Time, seconds

10 kts11 kts

0 50 100 150 200 250 300 350 400−2000

−1500

−1000

−500

0

500

1000

Yaw

For

ce, k

N−

m

Sumulation Time, seconds

10 kts11 kts

Page 130: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  24

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

BERTH 2 

 

Figure 3‐10:  Modeled Surge Forces on the Aframax Tanker at Berth 2 

 

 

Figure 3‐11:  Modeled Sway Forces on the Aframax Tanker at Berth 2 

 

   

0 50 100 150 200 250 300 350 400−150

−100

−50

0

50

100

150S

urge

For

ce, k

N

Sumulation Time, seconds

10 kts11 kts

0 50 100 150 200 250 300 350 400−400

−300

−200

−100

0

100

200

Sw

ay F

orce

, kN

Sumulation Time, seconds

10 kts11 kts

Page 131: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  25

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

 

Figure 3‐12:  Modeled Heave Forces on the Aframax Tanker at Berth 2 

 

 

Figure 3‐13:  Modeled Roll Forces on the Aframax Tanker at Berth 2 

0 50 100 150 200 250 300 350 400−2000

−1000

0

1000

2000

3000

Hea

ve F

orce

, kN

Sumulation Time, seconds

10 kts11 kts

0 50 100 150 200 250 300 350 400−400

−200

0

200

400

600

800

1000

Rol

l For

ce, k

N−

m

Sumulation Time, seconds

10 kts11 kts

Page 132: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  26

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

 

Figure 3‐14:  Modeled Pitch Forces on the Aframax Tanker at Berth 2 

 

 

Figure 3‐15:  Modeled Yaw Forces on the Aframax Tanker at Berth 2 

 

0 50 100 150 200 250 300 350 400−4

−2

0

2

4x 10

4

Pitc

h F

orce

, kN

−m

Sumulation Time, seconds

10 kts11 kts

0 50 100 150 200 250 300 350 400−1

−0.5

0

0.5

1x 10

4

Yaw

For

ce, k

N−

m

Sumulation Time, seconds

10 kts11 kts

Page 133: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  27

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

BERTH 3 

Figure 3‐16:  Modeled Surge Forces on the Aframax Tanker at Berth 3 

Figure 3‐17:  Modeled Sway Forces on the Aframax Tanker at Berth 3 

0 50 100 150 200 250 300 350 400−400

−200

0

200

400S

urge

For

ce, k

N

Sumulation Time, seconds

10 kts11 kts

0 50 100 150 200 250 300 350 400−1500

−1000

−500

0

500

Sw

ay F

orce

, kN

Sumulation Time, seconds

10 kts11 kts

Page 134: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  28

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

 

Figure 3‐18:  Modeled Heave Forces on the Aframax Tanker at Berth 3 

 

 

Figure 3‐19:  Modeled Roll Forces on the Aframax Tanker at Berth 3 

 

   

0 50 100 150 200 250 300 350 400−6000

−4000

−2000

0

2000

4000

Hea

ve F

orce

, kN

Sumulation Time, seconds

10 kts11 kts

0 50 100 150 200 250 300 350 400−2000

−1000

0

1000

2000

3000

Rol

l For

ce, k

N−

m

Sumulation Time, seconds

10 kts11 kts

Page 135: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  29

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

 

Figure 3‐20:  Modeled Pitch Forces on the Aframax Tanker at Berth 3 

 

 

Figure 3‐21:  Modeled Yaw Forces on the Aframax Tanker at Berth 3 

 

3.2 TERMSIM 

The analysis of the mooring forces was computed using the mooring model TERMSIM.  

TERMSIM  is  a  time domain program, developed by Maritime Research  Institute Netherlands 

(MARIN), and  is used to analyze the behavior of a moored vessel subject to wind, waves, and 

0 50 100 150 200 250 300 350 400−1

−0.5

0

0.5

1

1.5x 10

5

Pitc

h F

orce

, kN

−m

Sumulation Time, seconds

10 kts11 kts

0 50 100 150 200 250 300 350 400−4

−2

0

2

4x 10

4

Yaw

For

ce, k

N−

m

Sumulation Time, seconds

10 kts11 kts

Page 136: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  30

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

current.    The mooring  system may  be  a  Single  Point Mooring  (SPM),  a Multi Buoy Mooring 

(MBM) or a  Jetty  terminal, as  in  the case of  the proposed Westridge  facilities.   The program 

simulates  the mooring  loads and  vessel motions when  the  system  is exposed  to operational 

environmental conditions. 

Vessel: The vessel is a generic tanker/bulker of regular dimensions.  The hydrodynamic 

data  for  the  vessel  is  based  on  the  scale model  tests  of  tanker‐shaped  hulls  conducted  at 

MARIN.   Based on the main particulars of the bulker (e.g.  length, breadth, draft, water depth, 

and displacement), a selection from the database is made and scaled to match the design vessel 

and site conditions.  A user‐defined vessel can also be input in the program. 

Environment:  The  environmental  conditions may  include  steady  currents,  steady  or 

irregular wind  fields, and/or swell and  long crested  irregular waves  from arbitrary directions.  

Several  spectral  formulations  for  the wind, waves  and  swell  are  available.    The  program  is 

capable of simulating vessels  in both shallow and deep water. Environmental conditions were 

kept as static inputs to evaluate the effects of the passing vessel. 

Databases:  Several databases are delivered with the program. 

‐Mooring elements:  The mooring  element  database  contains  particulars  of  common 

offshore chains, steel wires, synthetic ropes and fenders.  For synthetic ropes, load‐elongation 

characteristics are included.  The load‐compression curves for various fender types are included 

in the database.  User‐defined characteristics of lines and fenders may also be used. 

‐OCIMF wind and current coefficients:  This  database  contains  non‐dimensional 

wind  and  current  force/moment  coefficients  for  calculation  of  wind  and  current  loads  on 

tanker‐shaped vessels (valid for bulkers). 

‐OCIMF  diffraction  data:  The  new OCIMF  diffraction  database  contains  the  results  of 

diffraction analyses for several vessel configurations. 

‐Hydrodynamic reaction coefficients:  This  database  contains  non‐dimensional 

coefficients for use in the formulation of hydrodynamic reaction forces. 

Output: The output of each simulation consists of a binary file containing all samples of 

the calculated signals.  The signals include vessel motions, loads in the mooring legs and other 

measures of mooring system behavior. In addition, an output file is produced summarizing the 

maximum,  minimum,  and  mean  forces  and  motions,  as  well  as  factors  of  safety.    A 

comprehensive data processing package  is delivered with the program to view, plot and print 

the results. 

Page 137: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  31

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

3.2.1 Environmental Parameters 

The following environmental conditions were utilized in the mooring model: 

Wind:  Static winds were  run  at  every  15°  at  25  knots. No wind  scenarios were  also conducted  to  evaluate  if wind  forces  on  the  tankers  damp  out  loads  induced  by  the passing vessel.  

Current: A one knot current was applied to those simulations in which the passing vessel forces were simulated for a transit during a stemming tide. This current was applied 10° off  of  the  starboard  quarter  of  the  vessels,  in  agreement with  hydrodynamic model results developed for previous studies related to the new facility design. 

3.2.2 Berth Geometries and Model Setup 

All  mooring  models  were  set  up  to  be  identical  to  Optimoor  mooring  analyses 

developed  in 2012. For reference, figures used to represent the mooring arrangements  in the 

2012 report are reproduced below. 

 

Figure 3‐22:  Panamax Mooring Arrangement at Berth 1 

 

 

Page 138: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  32

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

Figure 3‐23:  Aframax Mooring Arrangement at Berths 2 and 3 

3.2.3 Mooring Evaluation Criteria 

MOORING LINE TENSION LIMITS 

Per  recommendations  provided  by OCIMF,  the  allowable  safe working  load  (SWL)  in 

mooring lines is set at 55% of the minimum breaking load (MBL) for the steel wire lines found 

on tankers. Though each vessel deploys lines with 11 meter synthetic tails, the loading the steel 

lines will control the allowable safe working load limits. 

FENDERS 

Fenders were selected for the proposed facility based on requirements set by a berthing 

energy  study conducted  in 2012. Trelleborg Supercone Fenders SCN2000  (E1.0  rubber grade) 

were  selected  with  a  rated  energy  capacity  of  305  t‐m  and  a  rated  reaction  of  295  mt. 

Acceptable  fender  loadings  are  those  at  or  below  the  rate  reaction  of  the  fender  at  design 

performance (2894 kN). 

MOTIONS 

PIANC guidelines set envelopes for tanker motions at berth based on loading arm travel 

restrictions; these criteria allow for 3 meters of peak to peak motion  in surge and 3 meters of 

zero to peak motion in sway for oil tankers. 

3.2.4 Results 

The  following  sections  present  the  results  of  the  dynamic mooring  analyses  for  each 

modeled  berth  location.  Tables  are  developed  in  an  effort  to  evaluate  the  loading  in  the 

mooring lines (and hooks), bollards, fenders, and examine the induced vessel motions. 

Directions presented below are referenced to true North. Mooring  lines are numbered 

sequentially from the bow to the stern. Bollard  load components are as follows: X‐directional 

loading is parallel with the fender line, Y‐directional loading is perpendicular to the fender line, 

and  Z‐directional  loading  is  along  the  vertical  axis  of  the  bollard.  Values  presented  for  the 

magnitudes of vessel motions  represent  the envelope of motions during  simulations;  i.e.  the 

amplitude between the maximum and minimum excursions of the vessel COG over the entire 

simulation. 

Page 139: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  33

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

BERTH 1: 10 KT PASSING SHIP 

Table 3‐2:  Mooring Line and Hook Loads for Panamax Bulker at Berth 1 with 10 kt Passing Vessel Speed  

Mooring Line 

Max Load, kN 

%MBL  Wind Speed, m/s / Direction, deg Current Speed, m/s, Direction, deg 

1  103  14.20%  12.9/80.0  0.0/120.0 

2  103  14.20%  12.9/95.0  0.0/120.0 

3  103  14.20%  12.9/80.0  0.0/120.0 

4  103  14.20%  12.9/80.0  0.0/120.0 

5  107  14.70%  12.9/140.0  0.0/120.0 

6  107  14.80%  12.9/110.0  0.0/120.0 

7  247  34.10%  12.9/290.0  0.0/120.0 

8  247  34.00%  12.9/290.0  0.0/120.0 

9  104  14.30%  12.9/200.0  0.0/120.0 

10  104  14.30%  12.9/170.0  0.0/120.0 

11  101  13.90%  12.9/200.0  0.0/120.0 

12  101  13.90%  12.9/215.0  0.0/120.0 

Page 140: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  34

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

Table 3‐3:  Bollard Loads for Panamax Bulker at Berth 1 with 10 kt Passing Vessel Speed 

Bollard Max 

Load, kN 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

X‐Component, 

kN 

Y‐Component, 

kN 

Z‐Component, 

kN 

1  209  12.9/80.0  0.0/120.0 24  204  34 

2  208  12.9/80.0  0.0/120.0 117  169  32 

3  225  12.9/110.0 0.0/120.0 206  56  68 

4  516  12.9/290.0 0.0/120.0 ‐479  120  148 

5  211  12.9/170.0 0.0/120.0 104  179  40 

6  204  12.9/200.0 0.0/120.0 160  123  26 

 

 

Table 3‐4:  Fender Loads for Panamax Bulker at Berth 1 with 10 kt Passing Vessel Speed 

Fender Max 

Load, kN%Rated 

Rx 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

1  389  13.40%  12.9/155.0 0.0/120.0

2  349  12.10%  12.9/ 5.0  0.0/120.0

3  325  11.20%  12.9/50.0  0.0/120.0

4  321  11.10%  12.9/50.0  0.0/120.0

 

Table 3‐5:  Panamax Bulker Motions at Berth 1 with 10 kt Passing Vessel Speed 

Motion Magnitude, 

m/deg 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

Surge  0.67  12.9/290.0 0.0/120.0

Sway  0.056  12.9/20.0  0.0/120.0

Heave  0.013  12.9/95.0  0.0/120.0

Roll  0.289  12.9/20.0  0.0/120.0

Pitch  0.004  12.9/245.0 0.0/120.0

 

BERTH 1: 11 KT PASSING SHIP 

 

Page 141: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  35

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

Table 3‐6:  Mooring Line and Hook Loads for Panamax Bulker at Berth 1 with 11 kt Passing Vessel Speed 

Mooring Line 

Max Load, kN

%MBL 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

1  103  14.20%  12.9/80.0  0.5/120.0

2  103  14.20%  12.9/65.0  0.5/120.0

3  103  14.20%  12.9/95.0  0.5/120.0

4  103  14.20%  12.9/95.0  0.5/120.0

5  107  14.70%  12.9/125.0 0.5/120.0

6  107  14.80%  12.9/95.0  0.5/120.0

7  257  35.40%  12.9/275.0 0.5/120.0

8  256  35.30%  12.9/275.0 0.5/120.0

9  104  14.30%  12.9/200.0 0.5/120.0

10  104  14.30%  12.9/185.0 0.5/120.0

11  101  13.90%  12.9/200.0 0.5/120.0

12  101  13.90%  12.9/170.0 0.5/120.0

 

Table 3‐7:  Bollard Loads for Panamax Bulker at Berth 1 with 11 kt Passing Vessel Speed 

Bollard Max 

Load, kN 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

X‐Component, 

kN 

Y‐Component, 

kN 

Z‐Component, 

kN 

1  209  12.9/65.0  0.5/120.0 24  204  34 

2  208  12.9/95.0  0.5/120.0 117  169  32 

3  225  12.9/95.0  0.5/120.0 206  56  68 

4  535  12.9/275.0 0.5/120.0 ‐497  125  153 

5  211  12.9/185.0 0.5/120.0 104  179  40 

6  204  12.9/170.0 0.5/120.0 160  123  26 

 

Table 3‐8:  Fender Loads for Panamax Bulker at Berth 1 with 11 kt Passing Vessel Speed 

Fender Max 

Load, kN%Rated 

Rx 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

1  426  14.70%  12.9/155.0 0.5/120.0

2  346  12.00%  12.9/ 5.0  0.5/120.0

3  217  7.50%  12.9/50.0  0.5/120.0

4  180  6.20%  12.9/50.0  0.5/120.0

Page 142: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  36

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

 

Table 3‐9:  Panamax Bulker Motions at Berth 1 with 11 kt Passing Vessel Speed 

Motion Magnitude, 

m/deg 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

Surge  0.689  12.9/275.0 0.5/120.0

Sway  0.048  12.9/20.0  0.5/120.0

Heave  0.038  12.9/200.0 0.5/120.0

Roll  0.249  12.9/35.0  0.5/120.0

Pitch  0.005  12.9/200.0 0.5/120.0

 

Page 143: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  37

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

BERTH 2: 10 KT PASSING SHIP 

Table 3‐10:  Mooring Line and Hook Loads for Aframax Bulker at Berth 2 with 10 kt Passing Vessel Speed 

Mooring Line 

Max Load, kN

%MBL 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

1  127  13.90%  12.9/290.0 0.0/120.0

2  128  14.00%  12.9/290.0 0.0/120.0

3  102  11.10%  12.9/185.0 0.0/120.0

4  103  11.20%  12.9/170.0 0.0/120.0

5  102  11.10%  12.9/185.0 0.0/120.0

6  102  11.10%  12.9/170.0 0.0/120.0

7  103  11.20%  12.9/185.0 0.0/120.0

8  177  19.30%  12.9/290.0 0.0/120.0

9  103  11.20%  12.9/80.0  0.0/120.0

10  103  11.20%  12.9/65.0  0.0/120.0

11  102  11.10%  12.9/80.0  0.0/120.0

12  102  11.10%  12.9/50.0  0.0/120.0

13  101  11.00%  12.9/80.0  0.0/120.0

14  101  11.00%  12.9/65.0  0.0/120.0

 

Table 3‐11:  Bollard Loads for Aframax Bulker at Berth 2 with 10 kt Passing Vessel Speed 

Bollard Max 

Load, kN 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

X‐Component, 

kN 

Y‐Component, 

kN 

Z‐Component, 

kN 

1  256  12.9/290.0 0.0/120.0 ‐128  ‐221  22 

2  206  12.9/170.0 0.0/120.0 ‐16  ‐204  24 

3  205  12.9/170.0 0.0/120.0 90  ‐183  24 

4  207  12.9/185.0 0.0/120.0 202  ‐39  28 

5  362  12.9/290.0 0.0/120.0 ‐337  ‐108  78 

6  207  12.9/65.0  0.0/120.0 58  ‐197  29 

7  407  12.9/50.0  0.0/120.0 236  ‐330  38 

 

Page 144: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  38

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

Table 3‐12:  Fender Loads for Aframax Bulker at Berth 2 with 10 kt Passing Vessel Speed 

Fender Max 

Load, kN%Rated 

Rx 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

1  504  17.40%  12.9/80.0  0.0/120.0

2  495  17.10%  12.9/215.0 0.0/120.0

3  545  18.80%  12.9/170.0 0.0/120.0

4  566  19.50%  12.9/170.0 0.0/120.0

 

Table 3‐13:  Aframax Bulker Motions at Berth 2 with 10 kt Passing Vessel Speed 

Motion Magnitude, 

m/deg 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

Surge  0.418  12.9/290.0 0.0/120.0

Sway  0.084  12.9/200.0 0.0/120.0

Heave  0.021  12.9/335.0 0.0/120.0

Roll  0.127  12.9/200.0 0.0/120.0

Pitch  0.01  12.9/305.0 0.0/120.0

 

Page 145: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  39

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

BERTH 2: 11 KT PASSING SHIP 

 

Table 3‐14:  Mooring Line and Hook Loads for Aframax Bulker at Berth 2 with 11 kt Passing Vessel Speed 

Mooring Line 

Max Load, kN

%MBL 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

1  129  14.00%  12.9/290.0 0.5/120.0

2  129  14.10%  12.9/290.0 0.5/120.0

3  103  11.30%  12.9/155.0 0.5/120.0

4  106  11.50%  12.9/155.0 0.5/120.0

5  102  11.10%  12.9/170.0 0.5/120.0

6  102  11.10%  12.9/170.0 0.5/120.0

7  103  11.20%  12.9/170.0 0.5/120.0

8  168  18.30%  12.9/290.0 0.5/120.0

9  103  11.20%  12.9/65.0  0.5/120.0

10  103  11.20%  12.9/80.0  0.5/120.0

11  102  11.10%  12.9/65.0  0.5/120.0

12  102  11.10%  12.9/80.0  0.5/120.0

13  101  11.00%  12.9/65.0  0.5/120.0

14  101  11.00%  12.9/80.0  0.5/120.0

 

Table 3‐15:  Bollard Loads for Aframax Bulker at Berth 2 with 11 kt Passing Vessel Speed 

Bollard Max 

Load, kN 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

X‐Component, 

kN 

Y‐Component, 

kN 

Z‐Component, 

kN 

1  259  12.9/290.0 0.5/120.0 ‐129  ‐224  22 

2  211  12.9/155.0 0.5/120.0 ‐16  ‐208  24 

3  205  12.9/170.0 0.5/120.0 90  ‐183  24 

4  207  12.9/170.0 0.5/120.0 202  ‐39  28 

5  344  12.9/290.0 0.5/120.0 ‐320  ‐103  74 

6  207  12.9/65.0  0.5/120.0 58  ‐197  29 

7  407  12.9/65.0  0.5/120.0 236  ‐330  38 

 

Page 146: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  40

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

Table 3‐16:  Fender Loads for Aframax Bulker at Berth 2 with 11 kt Passing Vessel Speed 

Fender Max 

Load, kN%Rated 

Rx 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

1  478  16.50%  12.9/80.0  0.5/120.0

2  507  17.50%  12.9/215.0 0.5/120.0

3  647  22.40%  12.9/170.0 0.5/120.0

4  698  24.10%  12.9/170.0 0.5/120.0

Table 3‐17:  Aframax Bulker Motions at Berth 2 with 11 kt Passing Vessel Speed 

Motion Magnitude, 

m/deg 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

Surge  0.386  12.9/290.0 0.5/120.0

Sway  0.091  12.9/200.0 0.5/120.0

Heave  0.045  12.9/110.0 0.5/120.0

Roll  0.136  12.9/200.0 0.5/120.0

Pitch  0.012  12.9/335.0 0.5/120.0

Page 147: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  41

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

BERTH 3: 10 KT PASSING SHIP 

 

Table 3‐18:  Mooring Line and Hook Loads for Aframax Bulker at Berth 3 with 10 kt Passing Vessel Speed 

Mooring Line 

Max Load, kN

%MBL 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

1  151  16.40%  12.9/320.0 0.0/120.0

2  153  16.70%  12.9/320.0 0.0/120.0

3  113  12.30%  12.9/155.0 0.0/120.0

4  114  12.40%  12.9/155.0 0.0/120.0

5  108  11.80%  12.9/125.0 0.0/120.0

6  108  11.80%  12.9/125.0 0.0/120.0

7  109  11.90%  12.9/80.0  0.0/120.0

8  317  34.60%  12.9/320.0 0.0/120.0

9  104  11.30%  12.9/65.0  0.0/120.0

10  104  11.30%  12.9/65.0  0.0/120.0

11  104  11.30%  12.9/80.0  0.0/120.0

12  103  11.30%  12.9/80.0  0.0/120.0

13  103  11.20%  12.9/80.0  0.0/120.0

14  103  11.20%  12.9/80.0  0.0/120.0

 

Table 3‐19:  Bollard Loads for Aframax Bulker at Berth 3 with 10 kt Passing Vessel Speed 

Bollard Max 

Load, kN 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

X‐Component, 

kN 

Y‐Component, 

kN 

Z‐Component, 

kN 

1  305  12.9/320.0 0.0/120.0 ‐152  ‐263  26 

2  228  12.9/155.0 0.0/120.0 ‐17  ‐225  26 

3  218  12.9/125.0 0.0/120.0 96  ‐194  26 

4  220  12.9/80.0  0.0/120.0 215  ‐41  30 

5  650  12.9/320.0 0.0/120.0 ‐604  ‐194  140 

6  209  12.9/65.0  0.0/120.0 59  ‐199  30 

7  414  12.9/80.0  0.0/120.0 240  ‐336  39 

 

Page 148: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  42

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

Table 3‐20:  Fender Loads for Aframax Bulker at Berth 3 with 10 kt Passing Vessel Speed 

Fender Max 

Load, kN%Rated 

Rx 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

1  514  17.80%  12.9/ 5.0  0.0/120.0

2  501  17.30%  12.9/215.0 0.0/120.0

3  572  19.80%  12.9/170.0 0.0/120.0

4  601  20.80%  12.9/170.0 0.0/120.0

 

Table 3‐21:  Aframax Bulker Motions at Berth 3 with 10 kt Passing Vessel Speed 

Motion Magnitude, 

m/deg 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

Surge  0.827  12.9/320.0 0.0/120.0

Sway  0.086  12.9/200.0 0.0/120.0

Heave  0.045  12.9/185.0 0.0/120.0

Roll  0.13  12.9/200.0 0.0/120.0

Pitch  0.028  12.9/185.0 0.0/120.0

 

Page 149: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  43

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

BERTH 3: 10 KT PASSING SHIP 

Table 3‐22:  Mooring Line and Hook Loads for Aframax Bulker at Berth 3 with 11 kt Passing Vessel Speed 

Mooring Line 

Max Load, kN

%MBL 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

1  167  18.20%  12.9/350.0 0.5/120.0

2  170  18.50%  12.9/350.0 0.5/120.0

3  130  14.10%  12.9/140.0 0.5/120.0

4  129  14.10%  12.9/140.0 0.5/120.0

5  131  14.20%  12.9/20.0  0.5/120.0

6  131  14.20%  12.9/ 5.0  0.5/120.0

7  126  13.80%  12.9/95.0  0.5/120.0

8  342  37.20%  12.9/350.0 0.5/120.0

9  103  11.20%  12.9/65.0  0.5/120.0

10  103  11.20%  12.9/50.0  0.5/120.0

11  103  11.20%  12.9/65.0  0.5/120.0

12  102  11.10%  12.9/65.0  0.5/120.0

13  101  11.00%  12.9/65.0  0.5/120.0

14  101  11.00%  12.9/80.0  0.5/120.0

 

Table 3‐23:  Bollard Loads for Aframax Bulker at Berth 3 with 11 kt Passing Vessel Speed 

Bollard Max 

Load, kN 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

X‐Component, 

kN 

Y‐Component, 

kN 

Z‐Component, 

kN 

1  338  12.9/350.0 0.5/120.0 ‐168  ‐292  29 

2  261  12.9/140.0 0.5/120.0 ‐20  ‐258  30 

3  263  12.9/ 5.0  0.5/120.0 116  ‐234  31 

4  255  12.9/95.0  0.5/120.0 248  ‐47  35 

5  700  12.9/350.0 0.5/120.0 ‐651  ‐209  150 

6  207  12.9/50.0  0.5/120.0 58  ‐197  29 

7  409  12.9/65.0  0.5/120.0 237  ‐331  38 

 

Page 150: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  44

 

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014 

Table 3‐24:  Fender Loads for Aframax Bulker at Berth 3 with 11 kt Passing Vessel Speed 

Fender Max 

Load, kN%Rated 

Rx 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

1  643  22.20%  12.9/ 5.0  0.5/120.0

2  526  18.20%  12.9/260.0 0.5/120.0

3  674  23.30%  12.9/170.0 0.5/120.0

4  732  25.30%  12.9/170.0 0.5/120.0

 

Table 3‐25:  Aframax Bulker Motions at Berth 3 with 11 kt Passing Vessel Speed 

Motion Magnitude, 

m/deg 

Wind Speed, m/s / 

Direction, deg 

Current Speed, m/s, 

Direction, deg 

Surge  0.949  12.9/ 5.0  0.5/120.0

Sway  0.123  12.9/ 5.0  0.5/120.0

Heave  0.072  12.9/185.0 0.5/120.0

Roll  0.138  12.9/200.0 0.5/120.0

Pitch  0.034  12.9/200.0 0.5/120.0

Page 151: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  45

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

4. CONCLUSIONS AND RECOMMENDATIONS

Passing  vessel  analysis  at  the  three  proposed  berths  revealed  that  the  proposed

realigned channel provides ample clearance between transiting and moored vessels. Peak surge 

forces  induced on  the  loaded Aframax  tanker at berth 3 were about 400 kN  (40 mt)  for  the 

transiting bulker making 10 knots against a 1 knot  stemming current. Coupling  these passing 

vessel  forces  with  static  winds  and  currents  did  not  overstrain  the  planned  mooring 

arrangements  and  their  related  equipment.  The  largest  line  loadings were  observed  in  the 

shortest forward spring lines when they were resisting the initial surge forward induced by the 

passing vessel.  

Peak  to Peak motions of all vessels at  the berth were minimal and well within PIANC 

recommended envelopes. All  lines  and  fenders maintained  loading  safety  factors well below 

the suggested OCIMF criteria for moored tankers at berth.  

The study also serves  to  illustrate  the sensitivity of passing vessel  forces  to  the vessel 

speeds; calculated  loads were about 30% higher for the 11 knot simulations than those of the 

10  knot.  Potential  flow  theory  demonstrates  that  changes  in  the  modeled  ships’  draft, 

displacement, passing distance, and observed speed will greatly affect the observed forces on 

both vessels. Bathymetric effects also greatly contribute to these effects, but the bathymetry is 

deep  and mildly  sloping  around  the Westridge  facility  so  as  to  provide  ample  under  keel 

clearance and minimal amplification to passing vessel forces. 

Moffatt and Nichol does not think it is warranted to repeat this analysis for transits at a 

higher speed, as it seems unlikely that deep draft vessels would exceed 10 kts at engine settings 

comfortable for harbour transit. Should vessels  larger than those considered  in the report call 

at facilities east of Westridge, it would be prudent to verify that these ships will not strain the 

proposed tanker moorings beyond acceptable limits.  

While  the  layout  of  the  proposed  new  Westridge  Marine  Terminal  is  still  being 

optimized, it should not be necessary to repeat this analysis for the final layout, provided that 

the  final  configuration  is  no  closer  to  the  vessel  corridor  than  190m.  Similarly,  should  PMV 

decide to realign the channel adjacent to the Westridge facilities so as to bring inbound traffic 

closer  to  the  tanker  berths,  reanalysis  of  the  passing  vessel  effects  at  that  time would  be 

warranted.  

Page 152: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Passing Ship Analysis  46

Trans Mountain Pipeline LP – Westridge Marine Terminal August 25, 2014

5. REFERENCES

Kriebel, D., 2005  “Mooring  Loads due  to Parallel Passing  Ships,” Technical Report TR‐

6056‐OCN, Naval Facilities Engineering Service Center. 

Muga, B. and Fang, S., 1975 “Passing Ship Effects – From Theory and Experiment,” OTC 

16719, Offshore Technology Conference, ASCE.  

OCIMF, 2008, “Mooring Equipment Guidelines, 3rd Edition,” London, United Kingdom. 

PIANC, 1995  ‘Criteria for Movements of Moored Ships  in Harbours ‐ a Practical Guide,’ 

Supplement to Bulletin nr. 88, PTC2 report of WG 24, October. 

Seelig, W., 2001, “Passing Ship Effects on Moored Ships,” Technical Memorandum TM‐

6027‐OCN, Facilities Engineering Service Center. 

Wang,  S.,  1975,  “Dynamic  Effects  of  Ship  Passage  on  Moored  Vessels,”  Journal  of 

Waterway, Port, Coastal and Ocean Engineering, Harbour and Coastal Division, ASCE. 

Page 153: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Appendix D Navigation and Safety Plan

Page 154: WESTRIDGE MARINE TERMINAL UPGRADE AND ...
Page 155: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

t

NAVIGATION AND NAVIGATION SAFETY PLAN

FOR THE TRANS MOUNTAIN PIPELINE ULC

TRANS MOUNTAIN EXPANSION PROJECT NEB CONDITION 48

April 2017 REV 1

01-13283-GG-0000-CHE-RPT-0010 R1

Prepared for:

Trans Mountain Pipeline ULC Kinder Morgan Canada Inc. Suite 2700, 300 – 5th Avenue S.W. Calgary, Alberta T2P 5J2 Ph: 403-514-6400

Page 156: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Expansion Project

Guide to the Environmental Plans

Environmental Plans

Volume 1 – Temporary Construction Lands and Infrastructure Environmental Protection Plan Volume 2 – Pipeline Environmental Protection Plan Volume 3 – Facilities Environmental Protection Plan Volume 4 – Westridge Marine Terminal Environmental Protection Plan Volume 5 – Reactivation Environmental Protection Plan Volume 6 – Environmental Management Plans Volume 7 – Resource-Specific Mitigation Tables Volume 8 – Environmental Alignment Sheets Volume 9 – Burnaby Mountain Tunneling Environmental Protection Plan Volume 10 – Power Lines Environmental Protection Plans

This plan forms part of Volume 6 and is located:

Volume 6 – Environmental Management Plans

Section 1 – Organizational Structure Section 2 – Socio–Economic Management Section 3 – Contaminated Sites and Waste Management Section 4 – Geological and Groundwater Management Section 5 – Vegetation Management Section 6 – Wildlife Management Plans Section 7 – Wetland Management Section 8 – Aquatic Resource Management Section 9 – Reclamation Plans Section 10 – Facilities Management Plans Section 11 – Burnaby Mountain Tunneling Management

Page 157: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page i

Page i

TABLE OF CONCORDANCE NEB Condition 48 is applicable to the following legal instruments: OC-064 (CPCN), AO-003-OC-2 (OC2), XO-T260-007-2016 (Temp), XO-T260-008-2016 (Pump 1) and XO-T260-009-2016 (Pump 2). Table 1 describes how this Plan addresses the Condition requirements applicable to Project activities.

TABLE 1

LEGAL INSTRUMENT CONCORDANCE WITH NEB CONDITION 48: NAVIGATION AND NAVIGATION SAFETY PLAN

NEB Condition 48 OC-064 (CPCN)

AO-003-OC-2 (OC2)

XO-T260-007-2016 (Temp)

XO-T260-008-2016 (Pump1)

XO-T260-009-2016 (Pump2)

Trans Mountain must file with the NEB, for approval, at least 4 months prior to commencing construction, a Navigation and Navigation Safety Plan that includes: a) an updated list of navigable waterways to be crossed by or affected by the Project (including power lines, marine

terminal, temporary or permanent bridge crossings, or other ancillary works that are physically or operationally connected to the Project);

Appendix A of this Plan

Appendix A of this Plan

Appendix A of this Plan

Appendix A of this Plan

Appendix A of this Plan

b) an updated listing of effects of the Project on navigation and navigation safety for each of the identified waterways identified in a);

Section 3.2 and Appendix A of this Plan

Section 3.2 and Appendix A of this Plan

Section 3.2 and Appendix A of this Plan

Section 3.2 and Appendix A of this Plan

Section 3.2 and Appendix A of this Plan

c) proposed mitigation measures to address Project effects on navigation and navigation safety for each of the identified waterways, including adherence to codes and standards (such as the Canadian Standards Association); and

Section 4.0 and Appendix A of this Plan

Section 4.0 and Appendix A of this Plan

Section 4.0 and Appendix A of this Plan

Section 4.0 and Appendix A of this Plan

Section 4.0 and Appendix A of this Plan

d) a summary of its consultations with Appropriate Government Authorities, potentially affected Aboriginal groups and waterway users, regarding their navigational use of each of the identified waterways. In its summary, Trans Mountain must:

-- -- -- -- --

i) describe the Appropriate Government Authorities, potentially affected Aboriginal groups, and commercial and recreational waterway users consulted;

Section 2.0; Appendix B, C and D of this Plan

Section 2.0; Appendix B, C and D of this Plan

Section 2.0; Appendix B, C and D of this Plan

Section 2.0; Appendix B, C and D of this Plan

Section 2.0; Appendix B, C and D of this Plan

ii) describe how Trans Mountain identified those consulted; and Section 2.0; Appendix B, C and D of this Plan

Section 2.0; Appendix B, C and D of this Plan

Section 2.0; Appendix B, C and D of this Plan

Section 2.0; Appendix B, C and D of this Plan

Section 2.0; Appendix B, C and D of this Plan

iii) provide a description and justification for how Trans Mountain has incorporated the results of its consultation, including any recommendations from those consulted, into the plan.

Section 2.0, Appendix B of this Plan

Section 2.0, Appendix B of this Plan

Section 2.0, Appendix B of this Plan

Section 2.0, Appendix B of this Plan

Section 2.0, Appendix B of this Plan

Page 158: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page ii

EXECUTIVE SUMMARY The Navigation and Navigation Safety Plan (the Plan) was prepared to meet National Energy Board (NEB) Condition 48 for the Trans Mountain Expansion Project (TMEP or the Project).

The NEB defines navigable waters as “any body of water capable, in its natural state, of being navigated by floating vessels of any description for the purpose of transportation, recreation or commerce, and may also be a human-made feature such as a canal or reservoir”.

Trans Mountain Pipeline ULC (Trans Mountain) understands NEB Condition 48 to refer to those aspects of the Project that are within the NEB’s jurisdiction as outlined in the Condition. This includes the pipeline, power lines, marine terminal, temporary or permanent bridge crossings, or other ancillary works that are physically or operationally connected with the Project. From a marine perspective, this includes the construction and site operation of the Westridge Marine Terminal in Burrard Inlet. It does not cover the movement of Project-related marine vessels (i.e., oil tankers, tugs) using the shipping lanes in Burrard Inlet, Georgia Strait, Haro Strait, and Juan de Fuca Strait in approach to, or upon departure from, the Westridge Marine Terminal. Jurisdiction over shipping safety in marine waterways remains with Transport Canada.

The Plan provides an updated list of navigable and potentially navigable waterways (including watercourses and wetlands) that may be affected by the Project and a review of assessment outcomes and mitigation measures to address Project effects on navigation and navigation safety for each identified navigable waterway (Appendix A). The Plan also summarizes concerns related to navigation and navigation safety raised through Trans Mountain’s stakeholder and Aboriginal engagement to-date Appendix B) and how the Project has addressed them and considered them in the Plan.

Construction of the Project could potentially affect 50 watercourse crossings that are considered navigable, 145 watercourse crossings that are considered potentially navigable and 9 navigable wetlands. Aquatics and wetlands field work has determined that construction and operations of the pump stations, temporary facilities, tanks, and non-marine terminal work will not be located in, on, over, under, through or across a navigable waterway.

The potential residual effects of Project construction on navigation and navigation safety were identified in the TMEP NEB Facilities Application (Application) (Section 7.2.6 of Volume 5B for pipeline, power lines, temporary or permanent bridge crossings and other ancillary works) and include:

• impediments to watercourse users on navigable watercourses during construction or site-specific maintenance activities; and

• the safety of watercourse users on navigable watercourses may be affected in the event the user enters the construction zone.

The potential residual effects associated with the Westridge Marine Terminal (as discussed in Section 7.6.6 of Volume 5B of the Application) include:

• disruption to a navigable water (Burrard Inlet) during construction and operations; and

• concern for the safety of marine users due to changing movement patterns.

Since the filing of the Application in 2013, no new or additional interactions have been identified between the Project and navigation and navigation safety.

Page 159: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page iii

TABLE OF CONTENTS

Page TABLE OF CONCORDANCE ........................................................................................................................ i EXECUTIVE SUMMARY ............................................................................................................................... ii 1.0 INTRODUCTION .............................................................................................................................. 1

1.1 Project Description .............................................................................................................. 1 1.2 Links to Other Trans Mountain Plans .................................................................................. 2 1.3 Commitments Management ................................................................................................ 3 1.4 Navigability – Context and Approach .................................................................................. 3

2.0 CONSULTATION AND ENGAGEMENT .......................................................................................... 6 3.0 NAVIGABLE WATERWAYS ............................................................................................................ 7

3.1 Project Interactions ............................................................................................................. 7 3.2 Potential Residual Effects ................................................................................................... 8

4.0 MITIGATION MEASURES ............................................................................................................. 10 5.0 SUMMARY ..................................................................................................................................... 13 6.0 REFERENCES ............................................................................................................................... 14

LIST OF APPENDICES

Appendix A Navigable and Potentially Navigable Waterways Crossed by the Project ....................... A-1 Appendix B Consultation and Engagement ......................................................................................... B-1 Appendix C Record of Stakeholder Notifications of Draft Plan .......................................................... C-1 Appendix D Aboriginal Groups Engaged on the Navigation and Navigation Safety Plan .................. D-1 Appendix E Westridge Marine Construction Safety Boom .................................................................. E-1 Appendix F Marine Public Outreach Plan (Draft) ................................................................................ F-1

LIST OF TABLES Table 1 Legal Instrument Concordance with NEB Condition 48: Navigation and

Navigation Safety Plan ......................................................................................................... i Table 2 Trans Mountain Plans Linked to Navigation and Navigation Safety ................................... 3 Table 3 Potential Residual Effects of Project on Navigation and Navigation Safety ....................... 8 Table 4 Mitigation Measures Related to Navigation and Navigation Safety .................................. 10 Table A-1 Navigable and Potentially Navigable Watercourses Crossed by the Pipeline

Construction Right-of-Way ............................................................................................... A-2 Table A-2 Navigable and Potentially Navigable Watercourses Crossed by Power Lines ..............A-12 Table A-3 Navigable and Potentially Navigable Watercourses Crossed by the Marine

Terminal .........................................................................................................................A-12 Table A-4 Navigable Wetlands Crossed by the Pipeline Construction Right-of-Way ....................A-13 Table A-5 Navigable and Potentially Navigable Watercourses Crossed by Reactivation

Activity ............................................................................................................................A-14 Table A-6 Navigable and Potentially Navigable Watercourses Crossed by Contingency

Routes ............................................................................................................................A-15 Table A-7 Navigable and Potentially Navigable Watercourses Crossed by New

Temporary or Permanent Bridge Crossings ..................................................................A-15

Page 160: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page iv

TABLE OF CONTENTS CONT'D

Page

Table B-1 New Interests, Issues, Concerns from Public Consultation Related to Navigation and Navigation Safety Plan (July 2015 to January 2017) .............................. B-2

Table B-2 Summary of Issues and Concerns Related to Navigation and Navigation Safety (May 2012 To June 2015) ..................................................................................... B-3

Table B-3 Summary of Appropriate Government Authority and Waterway User Consultation Feedback Relevant to Navigation and Navigation Safety Plan (July 2015 To February 2017) .......................................................................................... B-4

Table B-4 Summary of Aboriginal Concerns Regarding Navigation and Navigation Safety ............................................................................................................................... B-5

Table C-1 Record of Notification ...................................................................................................... C-1

Page 161: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 1

1.0 INTRODUCTION The Navigation and Navigation Safety Plan (the Plan) was prepared to meet National Energy Board (NEB) Condition 48 for the Trans Mountain Expansion Project (TMEP or the Project). The draft Plan was submitted to Appropriate Government Authorities, potentially affected Aboriginal groups, and commercial and recreational waterway users on September 16, 2016 for a review and feedback period, which concluded on December 16, 2016. No feedback specific to this Plan was received during this period.

Since the September 2016 release of the draft Plan, engineering design has continued to progress and there have been changes that are described in detail in TMEP Fall 2016 Project Updates (www.transmountain.com/environmental-plans). All of the changes have been reviewed, and the relevant Project design updates have been incorporated into this Plan. It is anticipated route refinement will continue to occur as engineering design progresses. Subsequent changes will be reviewed in consideration of impacts to this Plan.

The Plan provides an updated list of navigable and potentially navigable waterways (watercourses and wetlands) that may be affected by the Project (Appendix A). As stated in NEB Condition 48, this includes consideration of the pipeline construction right-of-way, power lines, marine terminal, temporary or permanent bridge crossings, or other ancillary works that are physically or operationally connected with the Project. The Plan also provides review of assessment outcomes and mitigation measures to address Project effects on navigation and navigation safety for each identified navigable waterway (Section 4.0). In addition, the Plan summarizes issues or concerns related to navigation and navigation safety raised through Trans Mountain’s stakeholder and Aboriginal engagement to-date (Section 2.0 and Appendix B) and how the Project has addressed them and considered them in the Plan.

1.1 Project Description

Trans Mountain Pipeline ULC (Trans Mountain) filed its Facilities Application (the Application) with the NEB in December 2013. In developing its Application, Trans Mountain commenced a program of extensive discussions with landowners, engagement with Aboriginal groups and consultation with affected stakeholders. This program was intended to gather input from these groups into the Application and supporting Environmental and Socio-Economic Assessment (ESA), and to continue to assist Trans Mountain in the design and execution of the Project. Trans Mountain is also working with Appropriate Government Authorities to carry out the necessary reviews, studies and assessments required for the Project.

For ease of description, the following terms are used:

Kilometre Post (KP): describes distances measured along the centreline of the pipeline1.

Project Footprint: includes the area directly disturbed by surveying, construction, clean-up and operation of the pipeline, as well as associated physical works and activities (including the temporary construction lands and infrastructure, the pipeline, reactivation, facilities, the Westridge Marine Terminal and access roads). For clarity, specific components of the Project Footprint are further described by Trans Mountain below.

• Temporary construction lands and infrastructure refers to preparatory works to be undertaken prior to Project construction and includes temporary camps, stockpile sites, equipment staging areas and borrow pits located on land that has been previously disturbed, as well as access roads within the first 10 km of each designated construction spread. For ease of assessing Project interactions, these access roads within the first 10 km of each construction spread will not be considered under

1 Kilometre Posts (KPs) are calibrated to a number of fixed values derived from the original Trans Mountain Pipeline (TMPL) Mile Posts (MPs) in 1978 and do not necessarily represent actual chainage (measurement) along the pipeline. This is the result of integrating more accurate In-Line Inspection (ILI) data without forcing adjustments to KP values along TMPL. As the Trans Mountain Expansion Project (TMEP) is required to tie into the existing pipeline these fixed TMPL KP values also force a calibration of TMEP KPs. Therefore the actual lengths of pipeline cannot be calculated accurately by simply differencing two KP values.

Page 162: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 2

temporary construction lands and infrastructure, but instead are considered as part of the overall access road network. Temporary construction and infrastructure initiated prior to pipeline construction does not include the clearing of forested vegetation.

• Pipeline construction footprint refers to the total area used to construct the pipeline and includes the right-of-way and temporary workspace.

• Reactivation of currently deactivated pipeline segments include: engineering assessment under Section 45 of the National Energy Board Onshore Pipeline Regulations (NEB OPR); and associated construction activities. Currently known disturbance activities and associated access (as of July 2016), were assessed to determine the Project interactions. For ease of assessing Project interactions, these access roads were considered as part of the overall access road network.

• Facilities refer to pump stations, terminals (Edmonton, Sumas and Burnaby), and associated infrastructure (i.e., traps), most of which are located on land that has been previously disturbed. Westridge Marine Terminal has infrastructure located on land and in the marine environment, and is included in the Facilities component of the Project.

• Access roads include new temporary and permanent roads and existing roads that may require upgrades or improvements. For ease of assessing Project interactions, this includes the access roads to be developed as part of temporary construction lands and infrastructure, as well as those accesses associated with reactivation.

• Power lines include the two new power lines required to supply power to Project pump stations from the provincial electrical grid: a) approximately 23.5 km line required at Kingsvale pump station, and b) approximately 1.4 km line required at the proposed new Black Pines pump station.

Contingency Alternate Routes: refer to three alternate pipeline route segments that have been identified and assessed for use if construction on the preferred route is not feasible. These are not included in the Project Footprint defined above since they are considered contingency alternates.

• Raft River, in BC (KP 713.1 to 714.4), is an alternate open cut contingency alignment. The preferred primary crossing method, a horizontal directional drill (HDD), does not support an open cut contingency crossing method at the same location.

• Pembina River, in Alberta (KP 133.0 to 134.7), is an alternate open cut contingency alignment. Similar to Raft River, the preferred primary crossing method (HDD) does not support an open cut contingency crossing method at the same location.

• Westridge Delivery Lines (WDL KP 0.0 to 3.4) is an alternate contingency alignment for a trenched installation around the Burnaby Conservation Area in BC. The preferred pipeline corridor requires tunnel construction and does not support a trenched contingency option; therefore, an alternate trenched contingency alignment has been identified.

Variances: as part of the Project Footprint update that occurred in December 2016, a number of route revisions located outside of the Project corridor were identified. Trans Mountain is in the process of seeking approval from the NEB in 2017 for these route realignments.

1.2 Links to Other Trans Mountain Plans

Information from other plans prepared for the Project that are related to navigable waterways has been considered in this Plan. This includes other NEB Conditions as well as Environmental Protection Plans (EPPs). The links between this Plan and other Trans Mountain plans are provided in Table 2.

Page 163: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 3

TABLE 2

TRANS MOUNTAIN PLANS LINKED TO NAVIGATION AND NAVIGATION SAFETY

Environmental Plan Description of the Environmental Plan Linkages to this Plan Pipeline EPP (Volume 2 of the Environmental Plans)

The Pipeline EPP contains Trans Mountain’s environmental procedures and mitigation measures to be implemented during construction of the pipeline to avoid, reduce or mitigate potential adverse environmental effects. The EPP serves as reference information for construction and inspection personnel to support decision-making and to provide direction to more detailed information (i.e., resource-specific mitigation, management and contingency plans).

The Pipeline EPP includes general construction measures applicable to navigable waterways crossed by the Project. Additional pre-construction and construction measures applicable to watercourse crossings are included.

Westridge Marine Terminal EPP (Volume 4 of the Environmental Plans)

The Westridge Marine Terminal EPP contains Trans Mountain’s environmental procedures and mitigation measures to be implemented during construction of the marine terminal to avoid, reduce or mitigate potential adverse environmental effects.

The Westridge Marine Terminal EPP includes general construction measures applicable to navigation in Burrard Inlet.

Watercourse Crossing Inventory (NEB Condition 43)

The Watercourse Crossing Inventory provides an updated inventory of all watercourses to be crossed by the Project, including details for each crossing on (but not limited to) the location of the crossing; the primary and contingency crossing methods; planned construction timing; the provincial instream work window.

Determination of navigability for each watercourse was made during the field studies related to NEB Condition 43, and data from NEB Condition 43 is the basis for navigable watercourses named in this Plan for NEB Condition 48.

Wetland Survey and Mitigation Plan (Volume 6 of the Environmental Plans) (NEB Condition 41)

The Wetland Survey and Mitigation Plan provides an overview of wetlands encountered by the Project, recommended mitigation measures and crossing methods to be implemented during construction, and reclamation measures to be implemented during construction and operations.

Determination of navigability for each wetland was made during the field studies related to NEB Condition 41, and data from NEB Condition 41 is the basis for navigable wetlands named in this Plan for NEB Condition 48.

Light Emissions Management Plan for the Westridge Marine Terminal (NEB Condition 82)

The Light Emissions Management Plan for the Westridge Marine Terminal will present a summary of the results of an area lighting study, including how potential impacts on surrounding communities and safety and operational requirements were considered. It will describe any additional mitigation and best practice measures considered for the terminal lighting design and how the proposed design and operation will minimize the impacts from light on land-based residents and marine users.

For marine users, such mitigation may also support the reduction of navigation and navigation safety effects in Burrard Inlet related to the presence of the expanded marine terminal.

Traffic Access and Control Management Plan (NEB Condition 73)

The Traffic Access and Control Management Plan (TACMP) outlines, amongst other things, the Project’s traffic management strategy, anticipated traffic volumes and associated risks, and includes construction access management maps.

TACMP identifies planned routes for access to construction and construction use areas, which is information used in determining if any temporary or permanent bridge structures are required.

1.3 Commitments Management

Trans Mountain made a number of commitments regarding the Project during the OH-001-2014 proceedings and engagement activities up to May 2016. Commitments were made to improve and optimize planning and mitigation measures. As Trans Mountain has consolidated its commitments into a Commitments Tracking Table in order to make it easier for interested parties to access and reference this information, the table of commitments in each plan has been removed.

The Commitments Tracking Table was filed with the NEB and will be available on Trans Mountain’s web site at www.transmountain.com. Trans Mountain continues to monitor and track compliance with its commitments and will update, post to its website and file with the NEB updated versions of the Commitments Tracking Table according to the timeframes outlined in NEB Condition 6. Commitments with specific relevance to this Plan have been considered and addressed.

1.4 Navigability – Context and Approach

Since July 2013, the NEB has been the “one window” federal regulator for NEB-regulated pipeline and power line projects that cross navigable waters. Previously, this had been the responsibility of Transport Canada. Transport Canada and the NEB have entered into a Memorandum of Understanding to provide guidance as to when a project is regulated by the NEB or Transport Canada. Navigation Protection Act review is not required as it is covered under the NEB approval.

Page 164: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 4

The NEB Filing Manual indicates navigation and navigation safety is a consideration when a project includes activities to be conducted or components to be located in, on, over, under, through or across a navigable waterway when the water is flowing (i.e., not seasonally dry or frozen) (NEB 2015a).

Navigable waters in the context of the NEB follow Transport Canada’s longstanding definition of navigable waters, and include “any body of water capable, in its natural state, of being navigated by floating vessels of any description for the purpose of transportation, recreation or commerce, and may also be a human-made feature such as a canal or reservoir” (NEB 2015b).

The criteria for the definition of navigability were established for the purposes of the Project by the Aquatics Specialists (lead by GeoMarine Environmental Consultants Ltd.). The navigability criteria outlined in the Minor Works and Waters Ministerial Order (Navigable Waters Protection Act [NWPA]) (Government of Canada 2009) and the Minor Waters User Guide (Transport Canada 2010) were used as the basis for determining whether each watercourse crossed by the Project could be classed as a minor navigable water and, therefore, unlikely to be navigable. In addition to the Minor Works criteria, a supplemental benchmark based on industry experience was also used to further expand classification of presumably non-navigable watercourses.

Wetlands, in some circumstances, fall within this definition as they have characteristics that allow floating vessels to traverse across them (i.e., deeper, more permanent water channels through the wetland). Specific types of wetlands that would fall under this designation include deep emergent marshes, open water ponds and non-woody fens, which have open water channels throughout, or any wetlands associated with a classified watercourse.

Results from field and other investigations (conducted by Aquatics and Wetlands Resource Specialists since 2012) were used to screen watercourses and wetlands against the following criteria to determine if each waterway could be defined as a minor navigable water (i.e., non-navigable). Class 1 or Class 2 non-navigable waters meet the conditions in either Section 11(2) or 11(3), respectively, of the Minor Navigable Waters of the Minor Works and Waters (NWPA) Ministerial Order (Government of Canada 2009). In addition to Class 1 and Class 2 non-navigable waters, a third class (Class 3) was added to include minor watercourses up to 5 m wide. Experience has also shown that watercourses from 3 to 5 m wide, and with one or more of the criteria used to categorize Class 2 non-navigable waters, are also likely to be deemed “non-navigable”. Only the Burrard Inlet where Westridge Marine Terminal is located and the Fraser River are currently navigated by a full range of vessels, including large ocean-going vessels.

The classes of non-navigable minor waters for the Project are defined as follows:

Class 1: Watercourses that have one of the following:

• an average width measured at the high water level that is less than 1.2 m; or

• an average depth measured at the high water level that is less than 0.3 m.

Class 2: Watercourses that have an average width measured at the high water level that is greater than 1.2 m and less than 3 m and at least one of the following:

• an average depth at the high water level that is greater than 0.3 m but not more than 0.6 m;

• a slope measured at high water level that is greater than 4%;

• a sinuosity ratio that is greater than 2; or

• more than two natural obstacles with at least one upstream and another downstream from the crossing.

Class 3: Watercourses that have an average width measured at the high water level that is greater than 3 m but less than 5 m and at least one of the criteria of a Class 2 minor navigable water (above).

Page 165: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 5

Watercourses which did not meet the criteria of any of these three classifications were assumed to be navigable for recreational, commercial or traditional purposes.

In some instances, watercourses did not meet the criteria for non-navigable and yet were not clearly navigable (e.g., typically subject to seasonal flows). Such watercourses have been identified as ‘potentially navigable’.

Additional criteria were developed to help with identifying any potentially navigable wetlands. Criteria used included:

• classification of wetland (i.e., deep marsh, open water pond, non-woody fen or any wetland associated with classified watercourses);

• permanency of water (i.e., semi-permanent or permanent); and

• presence of semi-permanent or permanent open water channels within the wetland (e.g., within non-woody fens).

The Plan also considers the 2014 Order Amending the Minor Works and Waters (NWPA) Order (Government of Canada 2014).

Page 166: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 6

2.0 CONSULTATION AND ENGAGEMENT Consultation and engagement activities related to navigation and navigation safety were completed between May 2012 and January 2017 with Appropriate Government Authorities, potentially affected Aboriginal groups and waterway users. Opportunities to discuss navigation and navigation safety, and identify issues or concerns were provided to public stakeholders through the Trans Mountain website, workshops, meetings and ongoing engagement activities during the reporting period. Appendix B includes a comprehensive record of these engagement activities, stakeholder feedback and Trans Mountain responses.

The draft Plan was released on September 16, 2016 for review and feedback. Feedback was requested by December 16, 2016. No feedback specific to the draft Plan was received during the feedback period.

Engineering design changes were issued in the TMEP Fall 2016 Project Update document (www.transmountain.com/environmental-plans) along with a request for feedback. All of the design updates have been reviewed, and the Project design updates that are relevant have been incorporated into this Plan.

Page 167: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 7

3.0 NAVIGABLE WATERWAYS Construction of the Project could potentially affect 50 watercourse crossings that are considered navigable, 145 watercourse crossings that are considered potentially navigable, and 9 navigable wetlands, as outlined in Appendix A.

Trans Mountain understands NEB Condition 48 to refer to those aspects of the Project that are within the NEB’s jurisdiction. From a marine perspective, this includes the construction and site operation of the Westridge Marine Terminal in Burrard Inlet. It does not cover the movement of Project-related marine vessels (i.e., oil tankers, tugs) using the shipping lanes in Burrard Inlet, Georgia Strait, Haro Strait, and Juan de Fuca Strait in approach to, or upon departure from, the Westridge Marine Terminal. Jurisdiction over shipping safety in marine waterways remains with Transport Canada.

3.1 Project Interactions

Information on the specific components of the Project Footprint as defined in Section 1.1 (temporary construction lands and infrastructure, pipeline construction footprint, reactivation, facilities, access roads, power lines, contingency alternate routes) is provided below.

Temporary Construction Lands and Infrastructure Temporary construction lands and infrastructure (which includes temporary camps, stockpile sites, equipment staging areas and borrow pits, and works on access roads within the first 10 km of each designated construction spread) will not be located in, on, over, under, through or across a navigable waterway. As such, temporary construction lands and infrastructure activity will not interact with navigation and navigation safety.

Pipeline Construction Footprint In places, the pipeline construction footprint (i.e., specifically the pipeline right-of-way) will be located in, on, over, under, through and/or across navigable waterways. As such, the pipeline construction footprint will interact with navigation and navigation safety. Refer to Appendix A, Table A-1 (watercourses) and Table A-4 (wetlands).

Access Roads Some proposed new temporary or permanent bridge structures associated with the road access network are anticipated to be located in, on, over and/or across navigable watercourses. Approximately 18 potentially navigable or navigable watercourses have been identified as needing new temporary structures (i.e., clear span bridge), some of which may result in an interaction with navigation and navigation safety depending on conditions at the time of construction. Refer to Appendix A, Table A-7.

There are no navigable wetlands crossed by proposed temporary access roads.

Reactivation Some known reactivation activities are anticipated to occur in, on, over, under, through and/or across some watercourses that are considered navigable or potentially navigable, and thus, may interact with navigation and navigation safety. Refer to Appendix A, Table A-5.

Reactivation activities will not be located in, on, over, under, through or across a navigable wetland.

Facilities Aquatics and wetlands field work has determined that construction and operations of the pump stations, temporary facilities, terminals (Edmonton, Sumas and Burnaby, and associated infrastructure) will not be located in, on, over, under, through or across a navigable waterway. As such, these aspects of the Project will not interact with navigation and navigation safety.

The construction and operations of the Westridge Marine Terminal will be located, in part, on a navigable waterway (Burrard Inlet). As such, the Westridge Marine Terminal will interact with navigation and navigation safety. Refer to Appendix A, Table A-3.

Page 168: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 8

Power Lines Power lines will cross over a navigable watercourse (North Thompson River), and thus, may interact with navigation and navigation safety. Refer to Appendix A, Table A-2.

No navigable wetlands will be crossed by power lines.

Contingency Alternate Routes The alternate contingency alignments for the crossing of the Raft River and Pembina River will interact with navigation and navigation safety, as these rivers are navigable. Refer to Appendix A, Table A-6.

The alternate contingency alignment for the Westridge Delivery Lines is not located in, on, over, under, through or across a navigable watercourse, and thus, it will not interact with navigation and navigation safety.

There are no navigable wetlands along any of the contingency alternate routes.

3.2 Potential Residual Effects

The potential residual effects of Project construction on navigation and navigation safety were identified in the Application (Sections 7.2.6 and 7.6.6 of Volume 5B), and are summarized in Table 3. Since the filing of the Application in 2013, no new or additional potential residual effects on navigation and navigation safety have been identified.

TABLE 3

POTENTIAL RESIDUAL EFFECTS OF PROJECT ON NAVIGATION AND NAVIGATION SAFETY

Potential Residual Effect Effect Characterization Pipeline, Power Line, Reactivation, Contingency Routes, Bridge Crossings 1. Impediments to watercourse users on navigable watercourses during

construction or site-specific maintenance activities. Short-term in duration, periodic in frequency, reversible in the short-term, low in magnitude.

2. The safety of watercourse users on navigable watercourses may be affected in the event the user enters the construction zone.

Immediate in duration, accidental in frequency, reversible in the short-term, low to high in magnitude.

Westridge Marine Terminal 3. Disruption to a navigable water (Burrard Inlet) during construction and

operations. Construction: Short-term in duration, isolated in frequency, reversible in the short-term, low-to-medium in magnitude. Operations: Long-term in duration, isolated to periodic in frequency, reversible in the long-term, low in magnitude.

4. Concern for safety of marine users due to changing movement patterns. Immediate in duration, accidental in frequency, reversible in the short-term, low-to-high in magnitude.

The degree of potential effect depends on the method of construction, the season of construction and the state of the watercourse (frozen or unfrozen). Watercourse crossings that occur during winter will have a reduced effect on navigation and navigation safety, as some types of uses may be reduced during winter and in some areas, no navigation use will occur during the winter due to frozen conditions. Impediments to watercourse users on navigable watercourses may occur during construction and site-specific maintenance. Watercourse users vary depending on the watercourses and location of each crossing. In general, activities on watercourses crossed by the Project include commercial and non-commercial rafting, kayaking, fishing, boating, tubing, as well as traditional cultural activities. The navigability of some watercourses along the Project may be affected if open water conditions occur during a trenched crossing or installation of a temporary vehicle crossing as part of construction or site-specific maintenance activities (e.g., integrity dig).

Construction through watercourses will utilize a number of appropriate pipeline watercourse crossing methods selected in consideration of the size, environmental sensitivities of each watercourse and the season/timeframe of the construction period of each particular crossing. Pipe installations at watercourse crossings can be classified as either wet (trenched) or dry (trenched with water flow control or trenchless) crossings. With a wet crossing (e.g., open cut), the trench can be excavated through flowing water, if

Page 169: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 9

present. With a dry crossing, excavation of the trench normally occurs through the streambed once the water flow has been isolated, either by a dam and pump-around mechanism, or by using a flume over the excavated trench. Trenchless crossings (e.g., bore or HDD) techniques could also be used for watercourse crossings, where feasible.

The navigability of watercourses will generally not be affected during the operations phase since the pipeline will be buried under watercourses and the usage of new permanent vehicle crossings is not anticipated. However, impediments to navigation may occur during the operations phase if site-specific maintenance activities occur during open water conditions.

For the purposes of this Plan, each navigable and potentially navigable waterway is identified, and potential effects are described as outlined below.

• Tables A-1 outlines which potential residual effects from Table 3 are applicable to each navigable watercourse crossed by the mainline construction right-of-way.

• Table A-2 outlines which potential residual effects are applicable to navigable watercourses crossed by power lines.

• Table A-3 outlines which potential residual effects are applicable to the navigable watercourse affected by Westridge Marine Terminal.

• Table A-4 outlines which potential residual effects are applicable to each navigable wetland crossed by the mainline construction right-of-way.

• Table A-5 outlines which potential residual effects are applicable to each navigable watercourse crossed by reactivation activity.

• Table A-6 notes which potential residual effects are pertinent to navigable watercourses affected by contingency alternate routes.

• Table A-7 notes which potential residual effects may be pertinent to navigable watercourses affected by temporary or permanent bridge crossings, if potentially navigable watercourses are deemed navigable at the time of construction.

Page 170: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 10

4.0 MITIGATION MEASURES Trans Mountain has developed numerous mitigation measures to address potential Project effects on navigation and navigation safety. Measures were identified in the ESA (Volume 5B of the Application) and through commitments to various parties throughout the NEB process. Table 4 identifies the measures Trans Mountain has committed in order to mitigate potential effects of the Project on navigation and navigation safety. Some mitigation language has been revised since the Application to reflect input from various parties; mitigation outlined in Table 4 reflects that in the most recent EPPs and Socio-Economic Management Plan (SEMP) (Volumes 2, 4 and 6 of the Environmental Plans). Table 4 does not include general communication measures that Trans Mountain will undertake to communicate Project details to regulatory authorities, municipal tourism offices, waterway user groups, and other relevant organizations so they may share details of construction activity with waterway users. Such communication measures will be outlined in the construction phase Communication and Notification Program. Mitigation also considers the 2014 Order Amending the Minor Works and Waters (NWPA) Order (Government of Canada 2014). Additional mitigation may emerge through the issuance of approvals, licenses and permits necessary for construction.

TABLE 4

MITIGATION MEASURES RELATED TO NAVIGATION AND NAVIGATION SAFETY

Activity/Concern Mitigation Measures Terrestrial (Pipeline, Power Line, Access Roads, Reactivation) Vehicle Crossing Selection a) Install temporary vehicle crossings in a manner that protects the bed and banks of watercourses from erosion, maintains

flow, does not disrupt fish passage and does not interfere with or impede navigation on navigable watercourses [Section 14.0 of Pipeline EPP].

b) If it is necessary to consider changes or modifications of vehicle crossing methods on a site-specific basis, the decision-making process will include the Contractor, the Construction Manager, Project Engineer, an Environmental Inspector, an Aquatic Resource Specialist and the management of change process [Section 14.0 of Pipeline EPP]. Criteria to be considered when making a vehicle/equipment crossing structure decision will include protection of the riparian vegetation and fisheries values associated with the crossing, navigability, the time of year and duration the crossing is required for, as well as applicable legislation and guides [Section 14.0 Pipeline EPP].

Water Crossings - General c) Limit instream construction to the shortest duration practical given the characteristics of the watercourse and the construction season [Section 14.0 Pipeline EPP].

Open Cut Crossings d) Ensure streamflow, if present at the time of construction, is maintained at all times when trenching through a watercourse [Section 14.0 Pipeline EPP].

e) Return the bed and banks of each crossing as close as practical to their pre-construction contours. Watercourses are not to be realigned or straightened, nor have their hydraulic characteristics changed [Section 14.0 Pipeline EPP].

f) If the contours of the bed of a navigable waterway are disturbed by placement, construction or removal of works, ensure that contours are restored to their natural state on completion of construction or placement of the works.

Erosion Control g) Stabilize disturbed shoreline to prevent erosion [Section 2.10 SEMP]. h) Monitor equipment/vehicle crossings to ensure that erosion control measures are adequate and streamflow is not

disrupted [Section 14.0 Pipeline EPP]. Facilitate Ongoing Navigation i) Keep channel clear upon completion of construction [Section 2.10 SEMP].

j) Ensure that vessels can navigate safely through or around the work site, or if navigation is interrupted by any activity related to construction of placement, that suitable means, such as portage, exist to allow vessels to resume navigation on the side of the work site.

Notification of Interested Parties - Waterway Users

k) Notify recreational boaters of the hazards associated with instream construction in accordance with NEB guidelines or approval conditions for navigable waters. Place warning signs (e.g., “Construction Ahead” and “Travaux de construction”) up and downstream of all the navigable crossings. The signs are to be legible at a distance recommended by the conditions of necessary permit approvals granted by the NEB. Maintain signage and other warning systems in place until navigational hazards are removed [Section 5.0 Pipeline EPP].

l) Install construction notification signs at road crossings, navigable watercourse crossings and rail crossings, as needed [Section 2.6 SEMP].

m) Work sites on navigable waterways are to be marked, from dusk to dawn and during periods of restricted visibility, with yellow flashing lights that are: (i) located on the end of the works that is farthest from the nearest bank or shore if the works are not more than 3 m in length; (ii) located on each end of the works, if the works are more than 3 m in length, but not more than 20 m in length; (iii) located on each end of the works and at any other location on the works so that the lights are spaced not more than 20 m apart if the works are more than 20 m in length, but not more than 30 m in length; or (iv) located on each end of the works and at any other location on the works so that the lights are spaced not more than 30 m apart, if the works are more than 30 m in length.

Page 171: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 11

TABLE 4 Cont'd

Activity/Concern Mitigation Measures Notification of Interested Parties - Waterway Users (cont’d)

n) Work sites in or through a navigable waterway are to be marked with cautionary buoys that are lighted from dusk to dawn and during periods of reduced visibility and are: (i) located at the end of the works that is farthest from the nearest bank or shore, if the works are not more than 3 m in length; (ii) located at each end of the works, if the works are more than 3 m in length, but not more than 20 m in length; (iii) located at each end of the works and at any other location alongside the works so that the buoys are spaced not more than 20 m apart, if the works are more than 20 m in length, but not more than 30 m in length; or (iv) located at each end of the works and at any other location alongside the works so that the buoys are spaced not more than 30 m apart, if the works are more than 30 m in length.

Marine (Westridge Marine Terminal) Notification of Interested Parties – Municipal Authorities

o) Notify the City of Burnaby of the anticipated construction schedule as per the agreed upon schedule [Section 5.0 Westridge Marine Terminal EPP].

Notification of Interested Parties - Marine Operators

p) Notify marine commercial and recreational operators of the hazards associated with construction in accordance with NEB guidelines or approval conditions. Place warning signs (e.g., Warning - Construction in the Vicinity) in terrestrial and marine environments, near construction activities. Follow conditions of permit approvals granted by the NEB [Section 5.0 Westridge Marine Terminal EPP].

q) Notify appropriate regulatory authorities and licensees, and/or distribute a notification to the shipping industry in order to advise commercial and recreational marine operators of the Project schedule and construction activities at the Westridge Marine Terminal [Section 5.0 Westridge Marine Terminal EPP].

Notification of Interested Parties – Project Notice

r) Provide notification to residents of construction within urban areas through methods determined in collaboration with municipal and regional authorities [Section 5.0 Westridge Marine Terminal EPP].

s) Provide Project contact information to residents, land users and Aboriginal groups including for management of construction-related concerns [Section 5.0 Westridge Marine Terminal EPP].

t) Install signs at secondary road access points and within the vicinity of construction activities near secondary roads and highways to notify land users of construction activities [Section 5.0 Westridge Marine Terminal EPP].

Notification of Interested Parties – Aboriginal groups

u) Provide Aboriginal groups with the anticipated construction schedule and facility location maps, and install signage notifying of construction activities in the area, a minimum of 4 weeks prior to the commencement of construction in the vicinity of their respective communities [Section 5.0 Westridge Marine Terminal EPP].

Marine Fish and Fish Habitat* v) Ensure barges are anchored or spudded in appropriate areas with minimal effects to intertidal and subtidal marine habitats. Grounding is prohibited, unless authorized by Vancouver Fraser Port Authority (VFPA). Avoid sensitive marine habitats, where feasible [Section 8.0 Westridge Marine Terminal EPP].

Other Construction Measures w) Apply other measures in the Westridge Marine Terminal EPP pertaining to marine construction. Ensure compliance with all established legislation, including the Navigation Safety Regulations under the Canada Shipping Act, Fisheries Act and other applicable legislation [Application Volume 5B, Section 7.6.6.4].

Marine Restricted Areas x) Comply with VFPA’s Marine Restricted Area legislation, including Clear Narrows Regulations [Application Volume 5B, Section 7.6.6.4].

Construction Vessel Traffic y) Ensure Project construction vessels are equipped with appropriate navigation aids and marks. Project construction vessels will follow applicable navigation rules and carry a high frequency radio with appropriate channels to monitor vessel traffic in the Project area [Section 8.0 Westridge Marine Terminal EPP].

z) Ensure that construction vessel traffic is confined to the general work site, where feasible, and that vessel anchoring or other disturbance only occurs in Trans Mountain approved locations, unless required in an emergency situation [Section 8.0 Westridge Marine Terminal EPP].

aa) Operate Project-related construction vessels at slow speeds (<10 knots) and avoid rapid acceleration to limit the intensity of acoustic emissions (both above and below the water surface) and to decrease wake and the likelihood of striking marine mammals, infrastructure, or other vessels [Section 8.0 Westridge Marine Terminal EPP].

Public Marine Access bb) Discourage unauthorized marine vessel access at the Westridge Marine Terminal through use of signs, markers and/or buoys [Section 8.0 Westridge Marine Terminal EPP].

Marine Construction Safety Boom

cc) Install a floating marine safety boom around the entire Westridge Marine Terminal working zone during construction. The marine safety boom will consist of floats and suitable vertical panels. It will be moored using suitable anchors to withstand typical and worst case environmental conditions found in this area. It will be fitted with several gates to accommodate the passage of construction vessels and vessels coming to and from the existing Westridge Marine Terminal dock. It will be equipped with reflective placards on both the inside and outside so the marine safety barrier remains visible between the buoys. At night, as advised by the Canadian Coast Guard (CCG), the marine safety boom will be marked by navigation lights (flashing yellow one nautical mile range) on all offshore corners. Additional lights will be mounted on the ship gate buoys. Radar reflectors will be installed strategically to assist approaching traffic identify the safety boom on radar during night time and periods of reduced visibility (see Appendix E of this Plan for further details of the conceptual design and layout of the boom).

Additional Navigational Aids dd) Trans Mountain has received advice of the CCG on the additional navigation aids to provide at the facility post-construction, and this is being incorporated to the detailed engineering and design of the expanded Westridge Marine Terminal.

Navigation Simulation ee) Trans Mountain will carry out exercises entailing real time navigation simulation after completion of detailed design, such simulation maneuvers will be for the areas surrounding the Westridge Marine Terminal and will be carried out in consultation with VFPA, the Pacific Pilotage Authority, and BC Coast Pilots.

Notes: *This mitigation is also pertinent to navigation and navigation safety.

Page 172: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 12

Tables A-1, A-2 and A-3 in Appendix A note which of the mitigation measures outlined in Table 4 are pertinent to each navigable and potentially navigable watercourse crossed by the mainline construction right-of-way, power lines and marine terminal (respectively).

Table A-4 in Appendix A notes which mitigation measures are pertinent to each navigable and potentially navigable wetland crossed by the mainline construction right-of-way.

Table A-5 in Appendix A notes which of these mitigation measures are pertinent to each navigable or potentially navigable watercourse related to reactivation activities.

Table A-6 in Appendix A notes which mitigation measures are pertinent to navigable watercourses affected by contingency crossing routes.

Table A-7 in Appendix A notes which mitigation measures are pertinent to navigable watercourses affected by temporary or permanent bridge crossings.

For “potentially navigable” watercourses, mitigation measures specific to navigation (measures [j] through [n] in Table 4) will only be initiated in the event that instream vessels are encountered during Project activities, which would result in confirmation of a navigable determination at the time of activity.

In addition to these measures and commitments, the Project will be designed, constructed, operated, maintained, deactivated and abandoned in accordance with the NEB OPR, which incorporates, by reference, the Canadian Standards Association (CSA) Z662-11, Oil and Gas Pipeline Systems (CSA Z662). Where inconsistencies occur between the NEB OPR and CSA Z662, or any other codes, standards, specifications and recommended practices used in the design, construction, operations and maintenance of TMEP and the expanded TMPL system, the NEB OPR will prevail to the extent of the inconsistency.

It is anticipated that there will be localized areas along the pipeline route where physical conditions or construction circumstances are encountered that are not specifically or adequately addressed in sufficient detail within CSA Z662, the NEB OPR or any other codes, standards, specifications and recommended practices. These conditions and circumstances could include watercourse scour and erosion, among others. Where these conditions or circumstances are encountered, the appropriate qualified engineering specialists will evaluate and prepare detailed engineered designs so that the design, construction and operations of the pipeline will implicitly meet the safety and integrity requirements of CSA Z662 and the NEB OPR. All such designs will be reviewed by qualified professional engineers who are certified accordingly.

To ensure a consistent approach to pipeline watercourse crossings throughout Canada and to aid in developing a common understanding between industry, regulators and other stakeholders, Pipeline Associated Watercourse Crossings Guidelines, 4th Edition (Canadian Association of Petroleum Producers et al. 2012) will be used to assess, plan, construct, operate and maintain the pipeline associated watercourse crossings. All watercourse crossings will have either a site-specific engineered crossing design that will address navigability issues or will refer to a generic typical watercourse crossing design.

Page 173: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 13

5.0 SUMMARY Trans Mountain has undertaken detailed study to determine the navigability status of waterways interacting with the various components of the Project. Trans Mountain has developed numerous mitigation measures to address potential Project effects on navigation and navigation safety on affected navigable waterways.

This Plan provides an updated list of navigable and potentially navigable waterways (including watercourses and wetlands) that may be affected by the Project and a review of assessment outcomes and mitigation measures to address potential Project effects on navigation and navigation safety for each identified navigable waterway. The Plan also summarizes issues or concerns related to navigation and navigation safety raised through Trans Mountain’s stakeholder and Aboriginal engagement to-date and how the Project has addressed them and considered them in the Plan.

Page 174: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page 14

6.0 REFERENCES Canadian Association of Petroleum Producers, Canadian Energy Pipeline Association and Canadian Gas

Association. 2012. Pipeline Associated Watercourse Crossings Guidelines, 4th Edition. Prepared by TERA Environmental Consultants. Calgary, Alberta.

Government of Canada. 2009. Minor Works and Waters (Navigable Waters Protection Act) Order. Canada Gazette. Vol. 143, No 19.

Government of Canada. 2014. Order Amending the Minor Works and Waters (Navigable Waters Protection Act) Order. Canada Gazette. Vol. 148, No 16.

National Energy Board. 2015a. Filing Manual, Inclusive of Release 2015-01. Calgary, Alberta.

National Energy Board. 2015b. Frequently Asked Questions - Amendments to the National Energy Board Act and the Canada Oil and Gas Operations Act on Navigation and Navigation Safety, Environment. Website: https://www.neb-one.gc.ca/bts/ctrg/gnnb/nvgblwtrs/nvgtnfq-eng.html. Accessed February 2016.

Transport Canada. 2010. Minor Water User Guide 2010. TP 14838. 22 pp.

Page 175: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page A-1

APPENDIX A

NAVIGABLE AND POTENTIALLY NAVIGABLE WATERWAYS CROSSED BY THE PROJECT

Page 176: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-2

TABLE A-1

NAVIGABLE AND POTENTIALLY NAVIGABLE WATERCOURSES CROSSED BY THE PIPELINE CONSTRUCTION RIGHT-OF-WAY

KP (005) Watercourse Name

Watercourse Crossing ID PXID

Flow Regime

Class (BC) / Classification (Alberta)

Project Proposed Pipeline Crossing

Method

Recommended Vehicle Crossing Method

Flowing Navigability

Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See

Letter Referenced Mitigation in

Table 4) Watercourses - Alberta

0.5 Unnamed Tributary to North Saskatchewan

River

AB-0a W1.1 Perennial Class C (unmapped)

Isolated Trenched Existing Crossing, Clear-Span Bridge or Type 3

Culvert

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

24.2 Blackmud Creek AB-12 W27.4 Perennial Class C Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

28.0 Whitemud Creek AB-13 W28.4 Perennial Class B Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

33.6 North Saskatchewan River

AB-14 W29.5 Perennial Class C Trenchless Existing Crossing Navigable No Effects, due to Trenchless Crossing

N/A

59.4 Dog Creek AB-18 W38.4 Perennial Class C (unmapped)

Isolated Trenched Clear-Span Bridge, Type 3 Culvert or Type 5 Logfill/Swamp Mat

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

90.2 Unnamed Tributary to Kilini Creek

AB-33 W60.5 Perennial Class C (unmapped)

Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

91.3 Unnamed Tributary to Kilini Creek

AB-34 W61.3 Perennial Class C (unmapped)

Isolated Trenched Existing Crossing, Clear-Span Bridge, Type 3

Culvert or Type 5 Logfill/Swamp Mat

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

125.8 Unnamed Tributary to Isle Lake

AB-60 W103.5 Perennial Class C Isolated Trenched Existing Crossing or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

134.0 Pembina River AB-66 W110.5 Perennial Class C Trenchless Existing Crossing Navigable No Effects, due to Trenchless Crossing

N/A

151.0 Unnamed Tributary to Chip Lake

AB-91 W138.3 Perennial Class C Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

172.7 Little Brule Creek AB-111 W160.5 Perennial Class C Isolated Trenched Existing Crossing or Clear- Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

177.9 Unnamed Tributary to Brule Creek

AB-114 W163.5 Perennial Class C (unmapped)

Isolated Trenched Existing Crossing Potentially Navigable

1 and 2 Mitigation Measures a) through i)

180.0 Brule Creek AB-116 W165.4 Perennial Class C Isolated Trenched Existing Crossing or Clear- Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

184.2 Lobstick River AB-117 W166.5 Perennial Class C Isolated Trenched Existing Crossing or Clear- Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

187.9 Unnamed Tributary to Lobstick River

AB-118 W169.3 Perennial Class C (unmapped)

Isolated Trenched Existing Crossing or Clear- Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

192.0 Carrot Creek AB-119 W170.5 Perennial Class C Isolated Trenched Existing Crossing or Clear- Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

201.5 Unnamed tributary to January Creek

AB-125 W176.4 Perennial Class C (unmapped)

Isolated Trenched Existing Crossing Potentially Navigable

1 and 2 Mitigation Measures a) through i)

Page 177: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-3

TABLE A-1 Cont'd

KP (005) Watercourse Name

Watercourse Crossing ID PXID

Flow Regime

Class (BC) / Classification (Alberta)

Project Proposed Pipeline Crossing

Method

Recommended Vehicle Crossing Method

Flowing Navigability

Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See

Letter Referenced Mitigation in

Table 4) 201.6 Unnamed Tributary to

January Creek AB-126 W177.4 Perennial Class C

(unmapped) Isolated Trenched Existing Crossing Potentially

Navigable 1 and 2 Mitigation Measures

a) through i) 219.3 Wolf Creek AB-129 W180.4 Perennial Class C Trenchless Clear-Span Bridge Navigable No Effects, due to

Trenchless Crossing N/A

222.7 McLeod River AB-131 W183.3 Perennial Class C Trenchless Existing Crossing Navigable No Effects, due to Trenchless Crossing

N/A

226.4 Bench Creek AB-132 W184.5 Perennial Class C Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

235.4 Bench Creek AB-136 W189.3 Perennial Class C Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

244.0 Little Sundance Creek AB-137 W190.5 Perennial Class C Isolated Trenched Existing Crossing or Clear- Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

246.7 Sundance Creek AB-138 W191.4 Perennial Class C Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

258.8 Unnamed tributary to McLeod River

AB-141 W195.4 Perennial Class C (unmapped)

Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

268.2 Unnamed tributary to McLeod River

AB-143 W197.2 Perennial Class C Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

293.9 Ponoka Creek AB-155 W211.3 Perennial Class C Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

326.2 Maskuta Creek AB-188 W255.3 Perennial Class C Isolated Trenched Existing Crossing or Clear- Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

Watercourses - BC

490.1 Baer Creek BC-3 W1002.4 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

491.1 Marathon Creek BC-5 W1004.4 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

518.1 Swift Creek BC-32 W1032.3 Perennial S1B Isolated Trenched Clear-Span Bridge or Access Both Banks

Navigable 1 and 2 Mitigation Measures a) through n)

526.8 Canoe River BC-36 W1036.3 Perennial S1B Isolated Trenched Clear-Span Bridge or Access Both Banks

Navigable 1 and 2 Mitigation Measures a) through n)

530.0 Camp Creek BC-38 W1038.4 Perennial S2 Isolated Trenched Clear-Span Bridge Navigable 1 and 2 Mitigation Measures a) through n)

541.4 Camp Creek BC-52 W1052.4 Perennial S2 Isolated Trenched Existing or Clear-Span Bridge

Navigable 1 and 2 Mitigation Measures a) through n)

543.1 Camp Creek BC-56 W1056.2 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

Page 178: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-4

TABLE A-1 Cont'd

KP (005) Watercourse Name

Watercourse Crossing ID PXID

Flow Regime

Class (BC) / Classification (Alberta)

Project Proposed Pipeline Crossing

Method

Recommended Vehicle Crossing Method

Flowing Navigability

Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See

Letter Referenced Mitigation in

Table 4)

548.0 Albreda River BC-65a W1066.3 Perennial S2 Isolated Trenched Clear-Span Bridge Navigable 1 and 2 Mitigation Measures a) through n)

548.6 Robina Creek BC-66 W1067.3 Perennial S5/S2 Isolated Trenched Clear-Span Bridge or Other

Regulatory Approved Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

554.9 Clemina Creek BC-76 W1078.4 Perennial S2 Isolated Trenched Existing or Clear-Span Bridge

Navigable 1 and 2 Mitigation Measures a) through n)

555.4 Dora Creek BC-78 W1080.3 Perennial S2 Isolated Trenched Existing or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

557.5 Albreda River BC-82a W1084.4 Perennial S2 Isolated Trenched Existing or Clear-Span Bridge

Navigable 1 and 2 Mitigation Measures a) through n)

559.7 Albreda River BC-85 W1087.4 Perennial S2 Isolated Trenched Clear-Span Bridge Navigable 1 and 2 Mitigation Measures a) through n)

563.7 Dominion Creek BC-93 W1096.1 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

568.0 Moonbeam Creek BC-94 W1097.2 Perennial S2 Isolated Trenched Clear-Span Bridge Navigable 1 and 2 Mitigation Measures a) through n)

572.3 Unnamed Channel BC-104 W1111.3 Perennial S5/S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

576.4 Serpentine Creek BC-110 W1118.2 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

Mitigation Measures a) through i)

577.1 North Thompson River BC-111 W1119.3 Perennial S1A Trenchless Access Both Banks Navigable No Effects, due to Trenchless Crossing

N/A

578.0 Chappell Creek BC-112 W1120.4 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

589.0 Miledge Creek BC-151 W1158.3 Perennial S1B Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

596.3 Thunder River BC-168 W1175.3 Perennial S1B Isolated Trenched Clear-Span Bridge Navigable 1 and 2 Mitigation Measures a) through n)

601.2 Whitewater Creek BC-173 W1180.3 Perennial S5/S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

605.5 Cook Creek BC-176 W1183.3 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

607.7 Cedar Creek BC-177 W1184.4 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

609.9 Blue River BC-178 W1185.4 Perennial S1B Trenchless Clear-Span Bridge or Access Both Banks

Navigable No Effects, due to Trenchless Crossing

N/A

615.9 Unnamed Channel BC-181 W1188.3 Seasonal S2 Trenchless Clear-Span Bridge; Swamp Mats may be Required

Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

Page 179: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-5

TABLE A-1 Cont'd

KP (005) Watercourse Name

Watercourse Crossing ID PXID

Flow Regime

Class (BC) / Classification (Alberta)

Project Proposed Pipeline Crossing

Method

Recommended Vehicle Crossing Method

Flowing Navigability

Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See

Letter Referenced Mitigation in

Table 4)

616.0 North Thompson River BC-182 W1189.4 Perennial S1A Trenchless Access Both Banks Navigable No Effects, due to Trenchless Crossing

N/A

622.7 Froth Creek BC-189 W1196.2 Perennial S2 Isolated Trenched Existing or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

629.3 Foam Creek BC-193b W1206.5 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

633.9 Finn Creek BC-201 W1215.4 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

643.3 Sundt Creek BC-224 W1240.3 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

644.2 Tumtum Creek BC-227 W1243.5 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

646.8 North Thompson River BC-236 W1252.3 Perennial S1A Trenchless Access both banks Navigable No Effects, due to Trenchless Crossing

N/A

658.6 Unnamed Channel BC-248 W1265.4 Seasonal S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

659.8 Sager Creek BC-249 W1266.3 Seasonal S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

667.5 Ivy Creek BC-258 W1275.4 Seasonal S5 Isolated Trenched Clear-Span Bridge or Other

Regulatory Approved Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

678.8 Mad River BC-275 W1292.5 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

681.9 Cove Creek BC-277 W1294.4 Seasonal S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

697.6 Peavine Creek BC-296 W1313.4 Seasonal S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

713.4 Raft River BC-309 W1326.3 Perennial S1B Trenchless Access Both Banks Navigable No Effects, due to Trenchless Crossing

N/A

721.4 Clearwater River BC-312 W1329.4 Perennial S1A Trenchless Access Both Banks Navigable No Effects, due to Trenchless Crossing

N/A

730.5 Mann Creek BC-315 W1334.4 Perennial S2 Trenchless Clear-Span Bridge Navigable No Effects, due to Trenchless Crossing

N/A

744.8 Lemieux Creek BC-330 W1348.5 Perennial S1B Isolated Trenched Existing or Clear-Span Bridge

Navigable 1 and 2 Mitigation Measures a) through n)

746.4 Nehalliston Creek BC-331 W1349.5 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

747.8 Eakin Creek BC-332 W1350.2 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

Page 180: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-6

TABLE A-1 Cont'd

KP (005) Watercourse Name

Watercourse Crossing ID PXID

Flow Regime

Class (BC) / Classification (Alberta)

Project Proposed Pipeline Crossing

Method

Recommended Vehicle Crossing Method

Flowing Navigability

Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See

Letter Referenced Mitigation in

Table 4)

756.6 Thuya Creek BC-338 W1356.3 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

763.8 Darlington Creek BC-343 W1361.4 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

764.1 Lindquist Creek BC-344 W1362.3 Seasonal S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

816.3 Jamieson Creek BC-371 W1389.4 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

821.5 Lanes Creek BC-376 W1394.4 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

842.9 Thompson River BC-413 W1431.2 Perennial S1A Trenchless Access Both Banks Navigable No Effects, due to Trenchless Crossing

N/A

889.4 Moore Creek BC-459 W1478.4 Perennial S2 Isolated Trenched Existing or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

912.6 Clapperton Creek BC-482 W1501.4 Perennial S2 Isolated Trenched Existing or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

924.7 Nicola River BC-504 W1524.5 Perennial S2 Trenchless Clear-Span Bridge Navigable No Effects, due to Trenchless Crossing

N/A

954.5 Coldwater River BC-548 W1570.4 Perennial S1B Trenchless Clear-Span Bridge or Access Both Banks

Navigable No Effects, due to Trenchless Crossing

N/A

954.7 Gillis Creek BC-549 W1571.4 Intermittent S3 Trenchless Clear-Span Bridge Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

966.9 Coldwater River BC-559 W1582.3 Perennial S1B Trenchless Clear-Span Bridge or Access Both Banks

Navigable No Effects, due to Trenchless Crossing

N/A

976.7 Coldwater River BC-570 W1593.3 Perennial S1B Trenchless Clear-Span Bridge or Access Both Banks

Navigable No Effects, due to Trenchless Crossing

N/A

977.7 Juliet Creek BC-571 W1594.5 Perennial S1B Isolated Trenched Clear-Span Bridge Navigable 1 and 2 Mitigation Measures a) through n)

983.9 Mine Creek BC-579 W1603.3 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

986.9 Coldwater River BC-582 W1607.4 Perennial S2 Trenchless Clear-Span Bridge Navigable No Effects, due to Trenchless Crossing

N/A

1000.0 Boston Bar Creek BC-591 W1622.4 Perennial S5 Isolated Trenched Clear-Span Bridge or Other

Regulatory Approved Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1001.6 Unnamed Channel BC-592 W1623.5 Perennial S5 Isolated Trenched Clear-Span Bridge or Other

Regulatory Approved Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

Page 181: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-7

TABLE A-1 Cont'd

KP (005) Watercourse Name

Watercourse Crossing ID PXID

Flow Regime

Class (BC) / Classification (Alberta)

Project Proposed Pipeline Crossing

Method

Recommended Vehicle Crossing Method

Flowing Navigability

Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See

Letter Referenced Mitigation in

Table 4)

1006.3 Unnamed Channel BC-595 W1626.5 Perennial S5 Isolated Trenched Clear-Span Bridge or Other

Regulatory Approved Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1008.0 Boston Bar Creek BC-596 W1627.3 Perennial S5 Isolated Trenched Clear-Span Bridge or other

regulatory approved crossing method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1012.4 Unnamed Channel BC-617 W1648.3 Seasonal S5 Isolated Trenched Clear-Span Bridge or Other

Regulatory Approved Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1016.0 Unnamed Channel BC-624 W1656.4 Perennial S5/S2 Isolated Trenched Existing or Clear-Span

Bridge or Other Regulatory Approved Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1016.8 Unnamed Channel BC-628 W1660.3 Perennial S5 Isolated Trenched Existing or Clear-Span

Bridge or Other Regulatory Approved Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1017.4 Ladner Creek BC-629 W1661.4 Perennial S2 Isolated Trenched Existing or Clear-Span Bridge

Navigable 1 and 2 Mitigation Measures a) through n)

1018.9 Coquihalla River BC-631 W1663.3 Perennial S1B Isolated Trenched Clear-Span Bridge or Access Both Banks

Navigable 1 and 2 Mitigation Measures a) through n)

1020.0 Dewdney Creek BC-632 W1664.3 Perennial S1B Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1021.6 Karen Creek BC-634 W1666.3 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1023.7 Coquihalla River BC-636 W1668.4 Perennial S1B Isolated Trenched Access Both Banks Navigable 1 and 2 Mitigation Measures a) through n)

1025.9 Coquihalla River BC-639 W1671.4 Perennial S1B Isolated Trenched Access Both Banks Navigable 1 and 2 Mitigation Measures a) through n)

1029.8 Coquihalla River BC-645 W1677.4 Perennial S1B Isolated Trenched Access Both Banks Navigable 1 and 2 Mitigation Measures a) through n)

1030.5 Railway Creek BC-646 W1678.3 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1040.4 Coquihalla River BC-654 W1686.4 Perennial S1B Isolated Trenched Access both banks Navigable 1 and 2 Mitigation Measures a) through i)

1041.8 Silverhope Creek BC-657 W1689.4 Perennial S1B Isolated Trenched Access Both Banks Navigable 1 and 2 Mitigation Measures a) through i)

1044.4 Chawuthen Creek BC-658 W1690.4 Seasonal S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1048.6 Hunter Creek BC-662 W1694.5 Perennial S1B Isolated Trenched Clear-Span Bridge Navigable 1 and 2 Mitigation Measures a) through n)

1052.6 Lorenzetta Creek BC-666 W1698.5 Perennial S2 Isolated Trenched Clear-Span Bridge Navigable 1 and 2 Mitigation Measures a) through n)

Page 182: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-8

TABLE A-1 Cont'd

KP (005) Watercourse Name

Watercourse Crossing ID PXID

Flow Regime

Class (BC) / Classification (Alberta)

Project Proposed Pipeline Crossing

Method

Recommended Vehicle Crossing Method

Flowing Navigability

Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See

Letter Referenced Mitigation in

Table 4)

1058.1 Wahleach Creek BC-668 W1700.4 Perennial S1B Isolated Trenched Clear-Span Bridge Navigable 1 and 2 Mitigation Measures a) through n)

1058.7 Unnamed Channel BC-676 W1711.4 Seasonal S5 Isolated Trenched Clear-Span Bridge or Other

Regulatory Approved Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1062.6 Unnamed Channel BC-685 W1719.4 Perennial S1B Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1068.3 Unnamed Channel BC-687 W1721.5 Seasonal S5/NCD-W (FB)

Isolated Trenched Ramp and Culvert or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1069.2 Unnamed Channel BC-688 W1722.5 Perennial S5/S2 Isolated Trenched Clear-Span Bridge or Other

Regulatory Approved Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1069.3 Unnamed Channel BC-689 W1723.4 Perennial S5/S2 Isolated Trenched Clear-Span Bridge or Other

Regulatory Approved Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1069.5 Unnamed Channel BC-690 W1724.5 Perennial S1B Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1069.8 Unnamed Channel BC-697 W1731.4 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1071.7 Anderson Creek BC-705 W1740.5 Seasonal S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1075.2 Unnamed Channel (Rogers Ditch)

BC-710a W1946.3 Seasonal S3 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1082.0 Elk Creek BC-713 (SAR) W1752.3 Perennial S3 Trenchless Clear-Span Bridge Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1084.9 Big Ditch Creek BC-713a W10091.2 Perennial S2 Trenchless Clear-Span Bridge Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1085.6 Unnamed Channel (Roadside Canal)

BC-713b W10053.2 Seasonal S3 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1085.8 Semmihault Creek BC-714 (SAR) W1753.3 Perennial S3 Trenchless Clear-Span Bridge Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1090.2 Chilliwack Creek BC-715 (SAR) W1754.3 Perennial S2 Trenchless Clear-Span Bridge Navigable No Effects, due to Trenchless Crossing

N/A

1091.5 Peach Creek BC-716 W1755.2 Perennial S1B Trenchless Clear-Span Bridge; Swamp Mats may be Required

Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1100.2 Chilliwack / Vedder River

BC-717 W1756.2 Perennial S1B Trenchless Access both banks Navigable No Effects, due to Trenchless Crossing

N/A

1100.4 Hopedale Slough BC-718 (SAR) W1757.2 Perennial S2 Trenchless Clear-Span Bridge Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

Page 183: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-9

TABLE A-1 Cont'd

KP (005) Watercourse Name

Watercourse Crossing ID PXID

Flow Regime

Class (BC) / Classification (Alberta)

Project Proposed Pipeline Crossing

Method

Recommended Vehicle Crossing Method

Flowing Navigability

Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See

Letter Referenced Mitigation in

Table 4)

1100.5 Browne Creek BC-719 W10042.1 Seasonal S2 Trenchless Clear-Span Bridge; Swamp Mats may be Required

Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1100.7 Unnamed Channel (Irrigation Canal)

BC-720d W10050.2 Perennial S3 Isolated Trenched Existing or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1102.4 Stewart Slough BC-720e W10029.2 Perennial S3 Trenchless Clear-Span Bridge Potentially Navigable

Mitigation Measures a) through i)

1102.7 Stewart Creek Branch B - South

BC-721a W10031.2 Perennial S3 Trenchless Clear-Span Bridge Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1103.5 Stewart Slough BC-722 W1761.3 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1104.1 Unnamed Channel (Irrigation Canal)

BC-722a W1871.3 Seasonal S3 Isolated Trenched Ramp and Culvert or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1106.6 Unnamed Channel (Roadside Canal)

BC-722a1 W10239.2 Seasonal S3 Trenchless Ramp and Culvert or Clear-Span Bridge

Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1107.2 Unnamed Channel (Roadside Canal)

BC-722a2 W10245.2 Seasonal S3 Trenchless Ramp and Culvert or Clear-Span Bridge

Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1107.2 Unnamed Channel (Roadside Canal)

BC-723 W1762.3 Seasonal S3 Trenchless Ramp and Culvert or Clear-Span Bridge

Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1108.2 Unnamed Channel (Roadside Canal)

BC-724 W1763.3 Seasonal S3 Trenchless Ramp and Culvert or Clear-Span Bridge

Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1108.3 Sumas Lake Canal BC-725 W1764.4 Perennial S1B Isolated Trenched Clear-Span Bridge or access both banks

Navigable 1 and 2 Mitigation Measures a) through n)

1108.8 Unnamed Channel (Irrigation Canal)

BC-725.1 W10257.2 Seasonal S3 Trenchless Existing or Ramp and Culvert or Clear-Span

Bridge

Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1109.4 Unnamed Channel (Roadside Canal)

BC-725b W1874.3 Seasonal S3 Trenchless Ramp and Culvert or Clear-Span Bridge

Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1110.5 Unnamed Channel (Irrigation Canal)

BC-725c W1875.3 Seasonal S3 Isolated Trenched Ramp and Culvert or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1111.0 Unnamed Channel (Irrigation Canal)

BC-725d W1876.3 Seasonal S3 Isolated Trenched Existing or Ramp and Culvert or Clear-Span

Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1111.4 Sumas River BC-726 W1765.3 Perennial S1B Trenchless Access Both Banks Navigable No Effects, due to Trenchless Crossing

N/A

1112.8 Unnamed Channel BC-729 W1768.3 Seasonal S5 Isolated Trenched Clear-Span Bridge or Other

Regulatory Approved Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1117.3 Clayburn Creek BC-731 W1770.3 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

Page 184: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-10

TABLE A-1 Cont'd

KP (005) Watercourse Name

Watercourse Crossing ID PXID

Flow Regime

Class (BC) / Classification (Alberta)

Project Proposed Pipeline Crossing

Method

Recommended Vehicle Crossing Method

Flowing Navigability

Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See

Letter Referenced Mitigation in

Table 4)

1120.9 Unnamed Channel (Roadside Canal)

BC-731b W10458.2 Seasonal S3 Trenchless Clear-Span Bridge Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1121.2 Clayburn Creek BC-732 W10460.2 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1121.9 Unnamed Channel (Irrigation Canal)

BC-732a W1899.3 Seasonal S3 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1122.1 Unnamed Channel (Roadside Canal)

BC-732a1 W10468.2 Seasonal S3 Trenchless Ramp and Culvert Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1122.4 Unnamed Channel (Irrigation Canal)

BC-732b W1900.3 Seasonal S3 Isolated Trenched Ramp and Culvert or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1122.9 Unnamed Channel (Tributary to Gifford

Slough)

BC-733 W1772.3 Seasonal S3 Isolated Trenched Ramp and Culvert or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1123.8 McLennan Creek BC-734 W1773.3 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1126.3 Coligny Creek BC-736 W1775.3 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1128.4 Nathan Creek BC-747 W1787.3 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1136.6 West Creek BC-749 W1789.3 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1141.7 Salmon River BC-753 (SAR) W1793.3 Perennial S2 Trenchless Clear-Span Bridge Navigable No Effects, due to Trenchless Crossing

N/A

1146.1 West Munday Creek BC-767 W1798.2 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1153.5 Unnamed Channel BC-768b W1927.2 Perennial S2 Isolated Trenched Existing or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1155.7 Fraser River BC-780 W1810.2 Perennial S1A Trenchless Access Both Banks Navigable No Effects, due to Trenchless Crossing

N/A

1167.0 Port Mann Slough BC-780.1 W10901.1 Seasonal S2 Trenchless Clear-Span Bridge or other

regulatory approved crossing method

Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1167.7 Unnamed Channel BC-780a1 W1811.2 Perennial S2 Trenchless Clear-Span Bridge Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1167.8 Unnamed Channel BC-780a2 W1812.2 Perennial S2 Trenchless Clear-Span Bridge Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1168.1 Unnamed Channel (Roadside Canal)

BC-780a3 W1939.2 Seasonal S2 Isolated Trenched Clear-Span Bridge or Other Regulatory Approved

Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

Page 185: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-11

TABLE A-1 Cont'd

KP (005) Watercourse Name

Watercourse Crossing ID PXID

Flow Regime

Class (BC) / Classification (Alberta)

Project Proposed Pipeline Crossing

Method

Recommended Vehicle Crossing Method

Flowing Navigability

Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See

Letter Referenced Mitigation in

Table 4)

1168.3 Dawes Hill Creek BC-780b W1813.3 Perennial S2 Trenchless Existing or Clear-Span Bridge

Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1169.3

Como Creek BC-781 W1815.4 Perennial S2 No Instream Work Proposed; Crossing

Over/Under Channelized

Section

Existing or Clear-Span Bridge

Potentially Navigable

No Effects, due to No Instream work

N/A

1171.2 Unnamed Channel (Roadside Ditch)

BC-781a W10065.1 Seasonal S2 Isolated Trenched Existing or Other Regulatory Approved

Crossing Method

Potentially Navigable

1 and 2 Mitigation Measures a) through i)

1171.8 Nelson Creek BC-782 W1816.3 Perennial S2 Trenchless Clear-Span Bridge Potentially Navigable

No Effects, due to Trenchless Crossing

N/A

1172.2

Stoney Creek BC-785 W1820.2 Perennial S2 No Instream Work Proposed; Crossing

Over/Under Channelized

Section

Clear-Span Bridge Potentially Navigable

No Effects, due to No Instream work

N/A

Page 186: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-12

TABLE A-2

NAVIGABLE AND POTENTIALLY NAVIGABLE WATERCOURSES CROSSED BY POWER LINES

KP Watercourse Name Watercourse Crossing ID Flow Regime

Class (BC) / Classification

(Alberta)

Project Proposed Pipeline Crossing

Method

Recommended Vehicle Crossing Method Flowing

Navigability Status

Potential Residual Effects on Navigation and Navigation Safety (see Potential Residual

Effects in Table 3)

Mitigation Measures (See Letter Referenced Mitigation

in Table 4) N/A North Thompson River BCT-2 Perennial S1A Install Transmission

Poles Outside of Riparian Management

Area

Existing or Access Both Banks

Navigable No Effects, due to No Instream Work

N/A

TABLE A-3

NAVIGABLE AND POTENTIALLY NAVIGABLE WATERCOURSES CROSSED BY THE MARINE TERMINAL

KP Watercourse

Name Watercourse Crossing ID

Flow Regime

Class (BC) / Classification

(Alberta)

Project Proposed Pipeline Crossing

Method

Recommended Vehicle Crossing Method

Flowing Navigability

Status

Potential Residual Effects on Navigation and Navigation

Safety (see Potential Residual Effects in Table 3)

Mitigation Measures (See Letter Referenced Mitigation in Table 4)

N/A Burrard Inlet N/A N/A N/A N/A N/A Navigable 3 and 4 Mitigation measures o) through ee)

Page 187: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-13

TABLE A-4

NAVIGABLE WETLANDS CROSSED BY THE PIPELINE CONSTRUCTION RIGHT-OF-WAY

KP (005)

Wetland Unique Identifier

Flow Regime / Class (BC) /

Classification (Alberta)

Project Proposed Pipeline Crossing Method Recommended Vehicle Crossing Method Flowing

Navigability Status

Potential Residual Effects on Navigation and Navigation Safety (see Potential Residual

Effects in Table 3)

Mitigation Measures (See Letter Referenced Mitigation in

Table 4) Wetlands – Alberta

59.4 to 59.5

Edmo-Edso_WC42apoint6

Open Water Pond The majority of wetlands along the pipeline route will be crossed using

conventional trenched methods during pipeline construction. The approach taken to determine the specific crossing and mitigation

methods implemented for wetland crossings will be determined on a

case-by-case basis, in consideration of season, wetland

class, water depth, length and location of the crossing, vegetation

types, substrate type, season of construction, and buoyancy

requirements for the pipeline.1

Depending on the characteristics of a particular wetland, and the construction season, a decision will be made as to

the type of vehicle and equipment access required. In frozen winter conditions, many wetlands may be able to be

frozen solid enough to support construction equipment travel. Deeper wetlands or those with flowing water may not be frozen soils enough to provide winter access for

heavy equipment.2

Navigable 1 and 2 Mitigation measures a) through n)

65.5 to 65.6

Edmo-Edso_WC48apoint6

Open Water Pond Navigable 1 and 2 Mitigation measures a) through n)

85.1 to 85.2

Edmo-Edso_WC68point17

Open Water Pond Navigable 1 and 2 Mitigation measures a) through n)

90.2 to 90.3

Edmo-Edso_WC73bpoint4

Open Water Pond Navigable 1 and 2 Mitigation measures a) through n)

125.0to 125.9

Edmo-Edso_WC108point11

Emergent Marsh Navigable 1 and 2 Mitigation measures a) through n)

170.4 to 170.5

Edmo-Edso_WC153point33

Open Water Pond Navigable 1 and 2 Mitigation measures a) through n)

177.8 to 177.9

Edmo-Edso_WC160cpoint82

Open Water Component

Navigable 1 and 2 Mitigation measures a) through n)

235.0 to 235.5

Edso-Hint_WC217b Emergent Marsh Navigable 1 and 2 Mitigation measures a) through n)

Wetlands – BC 730.4 to

730.5 Blue-

Darf_WC707dpoint7 Open Water Pond

/ W1 The majority of wetlands along the pipeline route will be crossed using

conventional trenched methods during pipeline construction. The approach taken to determine the specific crossing and mitigation

methods implemented for wetland crossings will be determined on a

case-by-case basis, in consideration of season, wetland

class, water depth, length and location of the crossing, vegetation

types, substrate type, season of construction, and buoyancy

requirements for the pipeline.1

Depending on the characteristics of a particular wetland, and the construction season, a decision will be made as to

the type of vehicle and equipment access required. In frozen winter conditions, many wetlands may be able to be

frozen solid enough to support construction equipment travel. Deeper wetlands or those with flowing water may not be frozen soils enough to provide winter access for

heavy equipment.2

Navigable 1 and 2 Mitigation measures a) through n)

Notes: 1 Measures will be taken to mitigate effects of instream works conducted in open water areas (i.e., emergent marshes and open water ponds) using barriers and sediment controls. Salvaged surface material and trench spoil material will be used to construct a barrier/dam in moderate to deep water areas. Sediment barriers or curtains will also be utilized to provide sediment control. Alternate dam materials such as an Aquadam© or meter bags may also be used where warranted.

2 Ramp materials (e.g., wooden mats or log corduroy) may be used in both frozen and non-frozen conditions to facilitate access. In open water situations it may be necessary to combine culverts and/or temporary bridges in access ramps. It may also be necessary or preferred to construct a shoo-fly around the wetland for use by the majority of equipment and vehicles to travel on and restricting equipment access through the wetland to just the equipment needed to install the pipeline crossing.

Page 188: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-14

TABLE A-5

NAVIGABLE AND POTENTIALLY NAVIGABLE WATERCOURSES CROSSED BY REACTIVATION ACTIVITY

KP (TMPL) Watercourse Name

Watercourse Crossing ID

Flow Regime

Class (BC) / Classification

(Alberta)

Project Proposed Pipeline Crossing

Method Vehicle Crossing Method Flowing

Navigability Status

Potential Residual Effects on

Navigation and Navigation Safety

(see Potential Residual Effects in

Table 3)

Mitigation Measures (See Letter Referenced Mitigation in Table 4)

Watercourses - Alberta 360.2 Snaring River TMR-46 Perennial Class C Isolated Trenched Clear-Span Bridge Navigable 1 and 2 Mitigation measures a)

through n) 389.8 Minaga Creek TMR-72 Perennial Class C Isolated Trenched Clear-Span Bridge Potentially

Navigable 1 and 2 Mitigation measures a)

through i) 403.9 Miette River TMR-81 Perennial Class C Isolated Trenched Clear-Span Bridge Navigable 1 and 2 Mitigation measures a)

through n) Watercourses - BC

411.6 Rockingham Creek TMR-89 Perennial S1 Isolated Trenched Access from Either Bank, Adjacent Highway Bridge

Potentially Navigable

1 and 2 Mitigation measures a) through i)

416.3 Yellowhead Creek TMR-94 Perennial S1 Isolated Trenched Access from Either Bank

Potentially Navigable

1 and 2 Mitigation measures a) through i)

420.3 Ghita Creek TMR-98 Perennial S2 Isolated Trenched Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation measures a) through i)

423.8 Fraser River TMR-110 Perennial S1 Isolated Trenched Access from Either Bank

Navigable 1 and 2 Mitigation measures a) through n)

461.2 Fraser River TMR-228 Perennial S1 Open-Cut Access from Either Bank, or Clear-Span

Bridge

Navigable 1 and 2 Mitigation measures a) through n)

Notes: Based on known disturbance activity areas as of February 2017 specific to TMEP; not related to operations and maintenance of TMPL.

Page 189: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-15

TABLE A-6

NAVIGABLE AND POTENTIALLY NAVIGABLE WATERCOURSES CROSSED BY CONTINGENCY ROUTES

KP Watercourse Name Watercourse Crossing ID PXID

Flow Regime

Class (BC) / Classification

(Alberta)

Project Proposed Contingency Pipeline

Crossing Method

Recommended Vehicle Crossing Method Flowing

Navigability Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See

Letter Referenced Mitigation in

Table 4) Watercourses - Alberta 134.4 Pembina River

(Alternate) AB-66P2 PRC-

W001 Perennial Class C Isolated Trenched or

Open-Cut Inside the Least Risk Biological

Window

Existing Crossing Navigable 1 and 2 Mitigation measures a) through n)

Watercourses - BC TBD Raft River (Alternate) BC-309a RRC-

W001 Perennial S1B Trenchless Access Both

Banks Navigable No Effects, due to

Trenchless crossing N/A

TABLE A-7

NAVIGABLE AND POTENTIALLY NAVIGABLE WATERCOURSES CROSSED BY NEW TEMPORARY OR PERMANENT BRIDGE CROSSINGS

Watercourse Name Watercourse Crossing ID AXID Flow

Regime Class (BC) /

Classification (Alberta)

Existing Structure

Type

Existing Crossing Structure Condition

Recommended Vehicle Crossing Method

Navigability Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See Letter Referenced Mitigation in Table 4)

Alberta

None N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A

BC

Peavine Creek BCVA-91 4-B-72-A-2-W01 Seasonal S2 - - Clear-Span Bridge Potentially

Navigable 1 and 2 Mitigation measures a)

through i)

Nehalliston Creek BCVA-104a 4-B-120-C-2-W01 Perennial S2 - - Clear-Span Bridge Potentially

Navigable 1 and 2 Mitigation measures a)

through i)

Lemieux Creek BCVA-105 4-B-128-B-3-W01 Perennial S1B Bridge Functional Existing or Clear-Span

Bridge Potentially Navigable

1 and 2 Mitigation measures a) through i)

Moore Creek BCVA-194 5-B-51-885.7-1-

W01 Perennial S2 Bridge - Existing or Clear-Span

Bridge Potentially Navigable

1 and 2 Mitigation measures a) through i)

Moore Creek BCVA-200 5-B-52-C-4-W01 Perennial S2 Bridge Moderate Existing or Clear-Span

Bridge Potentially Navigable

1 and 2 Mitigation measures a) through i)

Page 190: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

Page A

-16

TABLE A-7 Cont’d

Watercourse Name Watercourse Crossing ID AXID Flow

Regime Class (BC) /

Classification (Alberta)

Existing Structure

Type

Existing Crossing Structure Condition

Recommended Vehicle Crossing Method

Navigability Status

Potential Residual Effects on Navigation

and Navigation Safety (see Potential Residual Effects in

Table 3)

Mitigation Measures (See Letter Referenced Mitigation in Table 4)

Coldwater River BCVA-246 5-C-77-B-3-W01 Perennial S1B Bridge Functional

Existing or Clear-Span Bridge or Access Both

Banks Navigable

1 and 2 Mitigation measures a) through n)

Boston Bar Creek BCVA-263 5-D-97-G-3-W01 Perennial S5 - - Clear-Span Bridge Potentially

Navigable 1 and 2 Mitigation measures a)

through i)

Unnamed Channel BCVA-264 5-D-97-H-2-W01 Perennial S5 - - Clear-Span Bridge Potentially

Navigable

1 and 2 Mitigation measures a) through i)

Unnamed Channel BCVA-281 5-D-106-C-2-W01 Seasonal S5 - -

Clear-Span Bridge or Other Regulatory Approved

Crossing Method Potentially Navigable

1 and 2 Mitigation measures a) through i)

Unnamed Channel BCVA-282 5-D-107-A-4-W01 Seasonal S5 - -

Clear-Span Bridge or Other Regulatory Approved

Crossing Method Potentially Navigable

1 and 2 Mitigation measures a) through i)

Karen Creek BCVA-289 6-A-6-B-5-W01 Perennial S2 Bridge Moderate Existing or Clear-Span

Bridge Potentially Navigable

1 and 2 Mitigation measures a) through i)

Unnamed Channel BCVA-306 6-A-63-C-2-W01 Perennial S5/S2 - -

Clear-Span Bridge or Other Regulatory Approved

Crossing Method Potentially Navigable

1 and 2 Mitigation measures a) through i)

Unnamed Channel BCVA-307 6-A-64-B-1-W01 Perennial S1B Culvert Moderate Existing or Clear-Span

Bridge Potentially Navigable

1 and 2 Mitigation measures a) through i)

Browne Creek BCVA-312 W11474.0 Seasonal S2 - - Clear-Span Bridge Potentially Navigable

1 and 2 Mitigation measures a) through i)

Unnamed Channel (Irrigation Ditch) BCVA-313 W11473.0 Seasonal S3 Culvert Moderate Existing or Ramp and

Culvert Potentially Navigable

1 and 2 Mitigation measures a) through i)

Unnamed Channel BCVA-314 W11475.0 Perennial S3 Culvert Moderate Existing or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation measures a) through i)

Unnamed Channel BCVA-314a W12470.0 Perennial S3 Culvert Functional Existing or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation measures a) through i)

Bon Accord Creek BCVA-315 W11476.0 Perennial S3 Culvert Functional Existing or Clear-Span Bridge

Potentially Navigable

1 and 2 Mitigation measures a) through i)

Page 191: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page B-1

APPENDIX B

CONSULTATION AND ENGAGEMENT Consultation and engagement activities related to the Navigation and Navigation Safety Plan were completed with Appropriate Government Authorities, potentially affected Aboriginal groups as well as commercial and recreational waterway users. Opportunities to discuss navigation and navigation safety and to identify issues or concerns were also provided to public stakeholders during meetings, workshops and ongoing engagement activities. Consultation and engagement opportunities began in May 2012 with the Project announcement and are ongoing.

1.0 Consultation and Engagement Overview: Draft Plan Development Reports on public consultation activities completed between May 2012 and June 30, 2015 were filed with the National Energy Board (NEB) and are available in the Application (Volume 3A: Stakeholder and Volume 3B: Aboriginal; Filing ID A55987) as well as in Consultation Update No. 1 and Errata, Technical Update No. 1 (Filing ID A59343) / Consultation Update 2 (Filing IDs A62087 and A62088), Consultation Update 3 (Filing IDs A4H1W2 through A4H1W8) and Consultation Update 4 (Filing ID A72224). These reports include results of consultation conducted to date, identification of issues and concerns as well as Trans Mountain’s response and are included below. Where appropriate, Trans Mountain’s response has been updated to reflect information developed since the original response was provided during the NEB proceeding for the Project.

Consultation and engagement activities completed between July 1, 2015 and December 16, 2016 have not been filed on the public record with the NEB. Any new issues and concerns identified during this period, as well as Trans Mountain’s response, are described below.

2.0 Consultation and Engagement Overview: Draft Plan The draft Plan was released for review and feedback on September 16, 2016. The comment period closed on December 16, 2016. Email or mail notification regarding the Plan was sent to 141 public stakeholders, 17 government authorities, 114 Aboriginal groups and key affected commercial and recreational waterway user organizations. The notification included a summary description of the Plan, a request for review, the timing of the comment period and contact information. Aboriginal groups were offered the opportunity for an in-person meeting to review the Plan. See Appendix C for a complete list of notified stakeholders. In addition to direct notification, the online posting of each Plan was promoted through Trans Mountain's weekly e-newsletter, Trans Mountain Today, which provides Project updates, regulatory information, stories and interviews to more than 6,000 subscribers. Each week Trans Mountain Today included a focus on a specific plan, or group of plans, as well as a reminder of all plans available for review.

2016 • September 22 - Wildlife Mitigation and Habitat Restoration Plans • September 29 - Pipeline Environmental Protection Plans • October 6 - Air Quality Management Plans • October 13 - Watercourse and Water Ecosystems Plans • October 20 - Vegetation Management Plans • October 27 - Air Quality Plans • November 3 - Socio-Economic Effects Monitoring Plan • November 10 - Access Management Plan • December 22 - General promotion all plans • December 29 - General promotion all plans

2017 • January 5 - General promotion all plans • January 12 - General promotion all plans

Page 192: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page B-2

Trans Mountain is committed to ongoing engagement throughout the life of the Project. The start and end date for the review and comment period for each environmental management plan is defined. These timelines are required to allow time for preparation of the final Plan in order to meet regulatory requirements and NEB submission dates. Although a formal review period may be closed, each plan remains available for review on transmountain.com.

3.0 Consultation and Engagement: Activities and Feedback

Consultation and engagement activities completed with identified stakeholder groups are described below, including: public stakeholders (Section 3.1); Appropriate Government Authorities and waterway users (Section 3.2); and Aboriginal groups (Section 3.3).

Feedback on the draft Plan, Trans Mountain’s response, and where each issue or concern is addressed in the Plan has been outlined in each section.

3.1 Public Consultation

3.1.1 Public Consultation Summary – May 2012 to June 2015 No public feedback regarding navigation and navigation safety issues pertinent to this Plan was received between May 2012 and June 30, 2015.

3.1.2 New Interests, Issues, Concerns and Response – July 2015 to January 2017 Table B-1 includes new interests, issues and concerns, as well as Trans Mountain’s response with respect to navigation and navigation safety aspects pertinent to this Plan identified through public consultation and engagement activities between July 2015 and January 2017.

TABLE B-1

NEW INTERESTS, ISSUES, CONCERNS FROM PUBLIC CONSULTATION RELATED TO NAVIGATION AND NAVIGATION SAFETY PLAN (JULY 2015 TO JANUARY 2017)

Stakeholder Name

Method of Contact

Date of Consultation

Activity Issue or Concern Trans Mountain Response Where Addressed in this

Plan N/A Westridge Marine

Terminal/Burnaby Terminal Workshops

11/24/2016 Consider Automatic Identification Systems (AIS) as best practice for navigation (discussion required with VFPA)

TMEP followed up with the CCG. In the opinion of the CCG, AIS marking for the dock in the sheltered confines of the Burrard Inlet was unnecessary.

N/A

3.2 Appropriate Government Authority and Waterway User Consultation Through the course of Trans Mountain’s extensive engagement program, a range of issues and concerns were raised by various government authorities and waterway users about the navigational use of certain navigable waterways.

3.2.1 Appropriate Government Authority and Waterway User Consultation Summary – May 2012 to June 2015 Consultation feedback applicable to navigation and navigation safety pertinent to this Plan received during consultation and engagement activity with government authorities and waterway users between May 2012 and June 30, 2015 is summarized in Table B-2, which focuses on waterways of stakeholder interest, associated issues raised and how Trans Mountain has responded to them.

Page 193: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page B-3

TABLE B-2

SUMMARY OF ISSUES AND CONCERNS RELATED TO NAVIGATION AND NAVIGATION SAFETY (MAY 2012 TO JUNE 2015)

Watercourse Issue/Concern Stakeholder Group Trans Mountain Response Appropriate Government Authorities Thompson River Construction impacts to

Kamloops Water Aerodrome activity. Will require NAV CANADA notification.

Kamloops Airport Authority • TMEP will ensure that all NAV CANADA notifications are carried in accordance with the applicable Navigation Protection Program requirements.

Fraser River Concern about existing pipeline crossing of Fraser River – pipe is suspended and boats could get caught on pipe at low water. Not sure if pipe is TMPL.

City of Coquitlam • In use and decommissioned TMPL are buried at crossing location. TMEP will also be buried at crossing location.

• Follow-up within Trans Mountain showed that the TMPL is not suspended. The suspended pipe noted by stakeholder is not the TMPL.

Pembina River Impacts to commercial recreation businesses.

Parkland County • Planned crossing of Pembina River is trenchless. No anticipated impacts to navigation or fishing activities.

Burrard Inlet Interest in enhancements to Westridge Marine Terminal navigation aids for recreational vessels.

Village of Belcarra • Navigational aids are not in the Application now but will be placed depending on dock layout. See discussion of marine construction safety boom in Table 4 (point dd) and Appendix E of this Plan.

Ensure lighting at Westridge Marine Terminal meets requirements and does not interfere with navigation.

Vancouver Fraser Port Authority (VFPA)

• Recommendations and best practices have been applied in the current design and assessment to minimize lighting and light impact while meeting regulatory requirements for both navigation and industrial lighting for operational purposes. Trans Mountain has engaged with regulators including the Canadian Coast Guard, the Pacific Pilotage Authority, the VFPA and Transport Canada and reviewed with BC Coast Pilots regarding the plans for Westridge Marine Terminal’s navigational light marks.

• The Project will continue to engage with stakeholders such as local residents and neighbouring municipalities regarding the overall lighting plan.

• As per NEB Condition 82, Trans Mountain is developing a Light Emissions Management Plan for the Westridge Marine Terminal

Waterway Users Upper Fraser River

Concern regarding interruption to recreation business due to open cut of Fraser River at Rearguard Station.

Commercial recreation tenure holders (Stellar Descents Backcountry Adventures, Mount Robson White Water Rafting and Maligne Rafting Adventures)

• TMEP proposed revised pipeline corridor no longer crosses the Upper Fraser River (see Part 2, Technical Update #4, filed December 2014).

Winter construction preferred; do not want to be shut-down during short summer season.

Fraser River Concern about construction impact on shrimp trawlers on Fraser River.

Pacific Coast Shrimper's Association

• Planned crossing of Fraser River is trenchless. No anticipated impacts to navigation or fishing activities.

Burrard Inlet Increased risk of marine vessel collisions near Westridge Marine Terminal due to expanded dock.

North Shore No Pipeline Expansion

• The shortest distance that will occur between a tanker docked at Westridge Marine Terminal and: - the navigation beacon at Roche Point will be

approximately 850 m; - the high tide line at the boat launch at Cates Park will be

approximately 1,020 m; and - the southeast corner of the dock at Cates Park will be

approximately 1,000 m. • The siting of the dock and the clearances noted above will

not impede recreational boaters or commercial traffic. • Trans Mountain continues to work with the VFPA (previously

referred to as the Port Metro Vancouver) on permitting and design requirements of the Westridge Marine Terminal.

Coordinating movement of vessels from all the different docks.

Marine Studies Workshop participant

• Effects related to the movement of tankers and tugs to and from the Westridge Marine Terminal are outside the scope of this Plan; however, there are a series of checks and balances involving VFPA, vessels communicating with each other and the CCG.

Page 194: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page B-4

3.2.2 Feedback Regarding the Draft Plan A summary of consultation feedback from Appropriate Government Authorities and waterway users related to the draft Plan is provided in Table B-3.

TABLE B-3

SUMMARY OF APPROPRIATE GOVERNMENT AUTHORITY AND WATERWAY USER CONSULTATION FEEDBACK RELEVANT TO NAVIGATION AND NAVIGATION SAFETY PLAN

(JULY 2015 TO FEBRUARY 2017)

Invited Stakeholder Group/

Agency Name Method of Contact

Date of Consultation

Activity Feedback/Stakeholder Response Trans Mountain Response

Where Addressed in

the Plan BC Oil and Gas Commission

Email December 16, 2016 Noted that in Table A‐4, “Navigable Wetlands Crossed By The Pipeline Construction Right‐of‐Way” is not referenced in Section 3.1 of the document, unlike all other items listed Table A‐4.

The Plan has been updated to reflect this change; now also referencing Table A-4 (wetlands) in Section 3.1 of the document.

Section 3.1 of this Plan

Transport Canada Email March 17, 2017 Inquired regarding the installation and operation of a barrier around Westridge Marine Terminal during construction.

Barriers were not discussed in part of the NEB hearings, however, Trans Mountain will have a marine safety construction boom around Westridge Marine Terminal during construction to safeguard marine shipping and construction activities.

Table 4, point cc) of this Plan. Also, Appendix E of this Plan.

Trans Mountain has also conducted ongoing engagement with appropriate government authorities and marine commercial and recreation waterway users pertinent to Burrard Inlet in the context of its general marine safety program, which will inform the future NEB Condition 131 Marine Public Outreach Plan. This engagement information has been filed with the preliminary application for the Westridge Marine Terminal expansion to the VFPA and is attached as Appendix F of this Plan. While no additional issues or concerns pertinent to this Plan have emerged, it provides an overview of the range of government authorities and marine commercial and recreation waterway users pertinent to Burrard Inlet that have been engaged and will continue to be engaged by the Project.

3.3 Aboriginal Engagement Since April 2012, Trans Mountain has engaged with Aboriginal groups who might have an interest in the Project or have Aboriginal interests potentially affected by the Project, based on the proximity of their community and their assertion of traditional and cultural use of the land along the proposed pipeline corridor to maintain a traditional lifestyle. The objectives of Aboriginal engagement are to:

• have an open, transparent and inclusive process that seeks to exchange information in a respectful manner;

• address concerns shared by those who might have an interest in the Project or have Aboriginal interests potentially affected by the Project;

• incorporate feedback into Project planning and execution; and

• provide opportunities to maximize Project benefits to Aboriginal communities and Aboriginal groups.

A comprehensive Aboriginal engagement process is lead by experienced engagement advisors in Alberta and BC, specialized in the areas of Aboriginal relations, law, economic development, education, training, employment and procurement. Trans Mountain’s engagement process for the Project is flexible, allowing each community and group to engage in meaningful dialogue in the manner they choose and in a way to meet their objectives and values.

Page 195: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page B-5

Each community has the opportunity to engage with Trans Mountain, depending on Project interests and potential effects. The following opportunities to engage have been provided:

• Project announcement;

• initial contact with Aboriginal community or Aboriginal group;

• meetings with Chief and Council and meetings with staff;

• host community information session(s);

• conduct Traditional Land Use studies and socio-economic interviews;

• identify interests and concerns; and

• identify mitigation options.

Issues and concerns related to navigation and navigation safety pertinent to this Plan raised during Aboriginal engagement from between early 2012 to February 2017 are summarized in Table B-4.

TABLE B-4

SUMMARY OF ABORIGINAL CONCERNS REGARDING NAVIGATION AND NAVIGATION SAFETY

Issue or Concern Summary Trans Mountain Response

Where Addressed Summary Aboriginal Group

Requests more information regarding NEB Condition 48

Pacheedaht First Nation NEB Condition 48 and NEB Condition 131 - Marine Public Outreach Program will be provided to the community and there is opportunity for a follow-up meeting at the request of the community.

Appendix D

Trans Mountain continues its liaison with Indigenous and Northern Affairs Canada, the Government of Canada’s Major Projects Management Office, the BC Ministry of Aboriginal Relations and Reconciliation, and the Alberta Ministry of Aboriginal Affairs to provide updates regarding Trans Mountain’s engagement activities with Aboriginal groups.

Identifying Aboriginal Groups for Consultation Trans Mountain used the First Nations Consultative Area Database Public Map Service to identify the Aboriginal groups with traditional territories that cross navigational waterways. Appendix D lists the Aboriginal groups identified for consultation. Throughout regular engagement with TMEP, any Aboriginal groups were added to the list if they identified navigation on navigable waters as a concern.

Consultation Activities A letter was sent to the Aboriginal groups listed in Appendix D with a copy of the draft Plan on September 16, 2016. Trans Mountain followed up with each Aboriginal group by telephone, email or in person to ensure No feedback was received on this Plan.

This final Navigation and Navigation Safety Plan will be shared with the Aboriginal groups at the same time as the Plan is filed with the NEB in 2017.

Page 196: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page C-1

APPENDIX C

RECORD OF STAKEHOLDER NOTIFICATIONS OF DRAFT PLAN

TABLE C-1

RECORD OF NOTIFICATION

Government Authority/Stakeholder Group Contact Name (if applicable) Date Method of Contact

Aboriginal Groups (please refer to Appendix D) N/A September 26, 2016 Letter

Vancouver Fraser Port Authority Tim Blair September 20, 2016 Email Jasper National Park of Canada Mayabe Dia September 20, 2016 Email Alberta Environment and Parks Corinee Kristensen September 20, 2016 Email Ministry of Transportation and Infrastructure Lisa Gow September 20, 2016 Email

BC Parks Ken Morrison September 20, 2016 Email BC Oil and Gas Commission Brian Murphy September 20, 2016 Email Ministry of Natural Gas Development Linda Beltrano September 20, 2016 Email BC Forests, Lands and Natural Resource Operations Andrea Mah December 22, 2016 Email

BC Forests, Lands and Natural Resource Operations Susan Fitton September 20, 2016 Email

FVAQC Roger Quan October 21,, 2016 Email Environment and Climate Change Canada (ECCC) Phil Wong October 21, 2016 Email

ECCC Rachel Mayberry October 28,, 2016 Email ECCC Coral Deshield December 21,, 2016 Email ECCC Phil Wong December 21, 2016 Email Vancouver Fraser Port Authority Patrick Coates September 20, 2016 Email Department of Fisheries and Oceans Sandra Hollick-Kenyon December 3, 2016 Email Department of Fisheries and Oceans Alston Bonamis December 3, 2016 Email City of Edmonton N/A September 19 – 23, 2016 Letter City of Spruce Grove N/A September 19 – 23, 2016 Letter Municipality of Jasper N/A September 19 – 23, 2016 Letter Parkland County N/A September 19 – 23, 2016 Letter Strathcona County N/A September 19 – 23, 2016 Letter Town of Edson N/A September 19 – 23, 2016 Letter Town of Hinton N/A September 19 – 23, 2016 Letter Town of Stony Plain N/A September 19 – 23, 2016 Letter Village of Wabamun N/A September 19 – 23, 2016 Letter Yellowhead County N/A September 19 – 23, 2016 Letter City of Kamloops N/A September 19 – 23, 2016 Letter City of Kamloops Royal Canadian Mounted Police (RCMP) Detachment

N/A September 19 – 23, 2016 Letter

Kamloops Hotel Association N/A September 19 – 23, 2016 Letter Kamloops Chamber of Commerce N/A September 19 – 23, 2016 Letter Kamloops Ministry of Jobs, Tourism, Skills Training

N/A September 19 – 23, 2016 Letter

City of Merritt N/A September 19 – 23, 2016 Letter City of Merritt RCMP Detachment N/A September 19 – 23, 2016 Letter Clearwater Employment Services N/A September 19 – 23, 2016 Letter Tourism Wells Grey N/A September 19 – 23, 2016 Letter Clearwater Chamber of Commerce N/A September 19 – 23, 2016 Letter District of Clearwater N/A September 19 – 23, 2016 Letter District of Clearwater RCMP Detachment

N/A September 19 – 23, 2016 Letter

Interior Health N/A September 19 – 23, 2016 Letter Merritt Chamber of Commerce N/A September 19 – 23, 2016 Letter Northern Health N/A September 19 – 23, 2016 Letter

Page 197: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page C-2

TABLE C-1 Cont’d

Regulator/Stakeholder Group Contact Name (if applicable) Date Method of Contact Regional District of Fraser Fort George

N/A September 19 – 23, 2016 Letter

Thompson Nicola Regional District N/A September 19 – 23, 2016 Letter Town of Blue River N/A September 19 – 23, 2016 Letter Venture Kamloops N/A September 19 – 23, 2016 Letter Village of Valemount N/A September 19 – 23, 2016 Letter Village of Valemount RCMP Detachment

N/A September 19 – 23, 2016 Letter

Valley District N/A September 19 – 23, 2016 Letter Valemount Learning Centre N/A September 19 – 23, 2016 Letter Work Skills BC- Valemount N/A September 19 – 23, 2016 Letter Valemount and Area Recreation Development Association (VARDA)

N/A September 19 – 23, 2016 Letter

Valemount Chamber of Commerce N/A September 19 – 23, 2016 Letter Grassland’s Conservation Council N/A September 19 – 23, 2016 Letter Abbotsford Chamber of Commerce N/A September 19 – 23, 2016 Letter Abbotsford Police Department N/A September 19 – 23, 2016 Letter ASCA N/A September 19 – 23, 2016 Letter BC Invasive Species N/A September 19 – 23, 2016 Letter BC Ministry of Children and Family Development

N/A September 19 – 23, 2016 Letter

BC Ministry of Social Development N/A September 19 – 23, 2016 Letter BC Nature N/A September 19 – 23, 2016 Letter BC Wildlife Federation N/A September 19 – 23, 2016 Letter Burnaby Board of Trade N/A September 19 – 23, 2016 Letter Burnaby RCMP Detachment N/A September 19 – 23, 2016 Letter Chilliwack Chamber of Commerce N/A September 19 – 23, 2016 Letter Chilliwack Economic Partners N/A September 19 – 23, 2016 Letter City of Abbotsford N/A September 19 – 23, 2016 Letter City of Burnaby N/A September 19 – 23, 2016 Letter City of Chilliwack N/A September 19 – 23, 2016 Letter City of Coquitlam N/A September 19 – 23, 2016 Letter City of New Westminster N/A September 19 – 23, 2016 Letter City of Port Coquitlam N/A September 19 – 23, 2016 Letter City of Port Moody N/A September 19 – 23, 2016 Letter City of Surrey N/A September 19 – 23, 2016 Letter Coquitlam RCMP Detachment N/A September 19 – 23, 2016 Letter Corporation of Delta N/A September 19 – 23, 2016 Letter District of Hope N/A September 19 – 23, 2016 Letter Eagle Creek N/A September 19 – 23, 2016 Letter Fraser Valley Invasive Plant Council N/A September 19 – 23, 2016 Letter Fraser Valley Regional District N/A September 19 – 23, 2016 Letter Glen Valley Watershed Society N/A September 19 – 23, 2016 Letter Hope Chamber of Commerce N/A September 19 – 23, 2016 Letter Hope Community Policing Office N/A September 19 – 23, 2016 Letter Langley Chamber of Commerce N/A September 19 – 23, 2016 Letter LEPS N/A September 19 – 23, 2016 Letter LFVAQCC N/A September 19 – 23, 2016 Letter Metro Vancouver N/A September 19 – 23, 2016 Letter Newton RCMP Detachment N/A September 19 – 23, 2016 Letter RCMP Division ‘E’ N/A September 19 – 23, 2016 Letter Sapperton Fish and Game N/A September 19 – 23, 2016 Letter Stoney Creek N/A September 19 – 23, 2016 Letter Surrey Board of Trade N/A September 19 – 23, 2016 Letter Surry Environmental Partners N/A September 19 – 23, 2016 Letter Surrey RCMP Detachment N/A September 19 – 23, 2016 Letter Township of Langley N/A September 19 – 23, 2016 Letter Township of Langley RCMP Detachment

N/A September 19 – 23, 2016 Letter

TriCities Chamber of Commerce N/A September 19 – 23, 2016 Letter Upper Fraser Valley Regional Detachment

N/A September 19 – 23, 2016 Letter

Village of Anmore N/A September 19 – 23, 2016 Letter Village of Belcarra N/A September 19 – 23, 2016 Letter Yorkson N/A September 19 – 23, 2016 Letter ACGI Shipping N/A September 19 – 23, 2016 Letter

Page 198: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page C-3

TABLE C-1 Cont’d

Regulator/Stakeholder Group Contact Name (if applicable) Date Method of Contact Barnett Marine Park N/A September 19 – 23, 2016 Letter BC Ambulance N/A September 19 – 23, 2016 Letter BC Chamber of Shipping N/A September 19 – 23, 2016 Letter BC Coast Pilots N/A September 19 – 23, 2016 Letter BROKE (Burnaby Residents Opposed to Kinder Morgan Expansion)

N/A September 19 – 23, 2016 Letter

Canadian Pacific (CP) Rail N/A September 19 – 23, 2016 Letter Canexus- Ero- Newalta-Univar Community Advisory Panal (CAP)

N/A September 19 – 23, 2016 Letter

Canexus Chemicals N/A September 19 – 23, 2016 Letter Chevron N/A September 19 – 23, 2016 Letter Canadian National (CN) Rail N/A September 19 – 23, 2016 Letter Council of Marine Carriers N/A September 19 – 23, 2016 Letter District of North Vancouver N/A September 19 – 23, 2016 Letter Empire Shipping N/A September 19 – 23, 2016 Letter Erco Worldwide N/A September 19 – 23, 2016 Letter First Nation Emergency Services Society (FNESS)

N/A September 19 – 23, 2016 Letter

First Nation Health Authority N/A September 19 – 23, 2016 Letter Fraser Health Authority N/A September 19 – 23, 2016 Letter Inchcape Shipping N/A September 19 – 23, 2016 Letter Island Tug and Barge N/A September 19 – 23, 2016 Letter Kask Brothers N/A September 19 – 23, 2016 Letter Ledcor Resources and Transportation Limited Partnership

N/A September 19 – 23, 2016 Letter

Mason Agency (Shipping Service) N/A September 19 – 23, 2016 Letter MLA- Burnaby Lougheed N/A September 19 – 23, 2016 Letter MLA- Burnaby North N/A September 19 – 23, 2016 Letter MLA- Coquitlam – Burke Mountain N/A September 19 – 23, 2016 Letter MLA- North Vancouver Lonsdale N/A September 19 – 23, 2016 Letter MLA- North Vancouver Seymour N/A September 19 – 23, 2016 Letter MLA- Port Moody- Coquitlam N/A September 19 – 23, 2016 Letter MP- Delta N/A September 19 – 23, 2016 Letter MP- North Burnaby Seymour N/A September 19 – 23, 2016 Letter MP- North Vancouver N/A September 19 – 23, 2016 Letter MP- Vancouver Centre N/A September 19 – 23, 2016 Letter MP- Vancouver East N/A September 19 – 23, 2016 Letter MP- Vancouver Quadra N/A September 19 – 23, 2016 Letter MP- West Vancouver – Sunshine Coast – Sea to Sky Country

N/A September 19 – 23, 2016 Letter

North Shore No Pipeline Expansion (NOPE)

N/A September 19 – 23, 2016 Letter

North Vancouver Chamber of Commerce

N/A September 19 – 23, 2016 Letter

Pacific Coast Terminal N/A September 19 – 23, 2016 Letter Pacific Pilotage Authority N/A September 19 – 23, 2016 Letter Pacific Wildlife Foundation N/A September 19 – 23, 2016 Letter Peter Kiewit Infrastructure Co. N/A September 19 – 23, 2016 Letter Seaspan N/A September 19 – 23, 2016 Letter Shell Terminal N/A September 19 – 23, 2016 Letter Simon Fraser University N/A September 19 – 23, 2016 Letter SMIT Marine N/A September 19 – 23, 2016 Letter Suncor Terminal N/A September 19 – 23, 2016 Letter University of British Columbia Stellar Sea Lion (Marine Mammal) Research Centre

N/A September 19 – 23, 2016 Letter

Vancouver Aquarium N/A September 19 – 23, 2016 Letter Vancouver Board of Trade N/A September 19 – 23, 2016 Letter Vancouver Coastal Health Authority N/A September 19 – 23, 2016 Letter Vancouver Pile and Dredge N/A September 19 – 23, 2016 Letter West Vancouver Chamber of Commerce

N/A September 19 – 23, 2016 Letter

Westward Shipping N/A September 19 – 23, 2016 Letter Wild Bird Trust N/A September 19 – 23, 2016 Letter Metro Vancouver Regional District Ali Ergudenler September 19 – 23, 2016 Email Metro Vancouver Regional District Roger Quan September 19 – 23, 2016 Email

Page 199: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page D-1

APPENDIX D

ABORIGINAL GROUPS ENGAGED ON THE NAVIGATION AND NAVIGATION SAFETY PLAN

• Adams Lake Indian Band

• Aitchelitz First Nation (Stó:lō)

• Alexander First Nation

• Alexis Nakota First Nation

• Aseniwuche Winewak Nation

• Ashcroft Indian Band (Nlaka’pamux Nation)

• Asini Wachi Nehiyawak

• Boothroyd Band (Nlaka’pamux Nation)

• Boston Bar Band (Nlaka’pamux Nation)

• British Columbia Métis Federation

• Canim Lake Band (Tsq’escen')

• Canoe Creek (Stswecem'c Xgat'tem) Indian Band

• Chawathil First Nation (Stó:lō)

• Cheam First Nation (Stó:lō)

• Clinton Indian Band / Whispering Pines First Nation

• Coldwater Indian Band (Nlaka’pamux Nation)

• Cook’s Ferry Indian Band (Nlaka’pamux Nation)

• Enoch Cree Nation

• Ermineskin First Nation

• Foothills Ojibway Society

• High Bar

• Horse Lake First Nation (Treaty 8)

• Kanaka Bar

• Katzie First Nation

• Kelly Lake Cree Nation

• Kelly Lake First Nation

• Kelly Lake Métis Settlement Society

• Ktunaxa Nation

• Kwantlen First Nation (Stó:lō)

• Kwaw-kwaw-Apilt First Nation (Stó:lō)

• Kwikwetlem First Nation

• Leq’a:mel First Nation (Stó:lō)

• Lheidli-T’enneh First Nation

Page 200: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page D-2

• Lhtako Dene Nation

• Little Shuswap Indian Band

• Louis Bull Tribe

• Lower Nicola Indian Band (Nlaka’pamux Nation)

• Lower Similkameen Indian Band

• Lyackson First Nation

• Lytton First Nation (Nlaka’pamux Nation)

• Matsqui First Nation (Stó:lō)

• Métis Nation of Alberta Gunn Métis Local 55

• Métis Nation of British Columbia

• Métis Regional Council Zone IV of the Métis Nation of Alberta

• Michel First Nation

• Montana First Nation

• Musqueam Indian Band

• Nakcowinewak Nation of Canada

• Neskonlith Indian Band

• Nicola Tribal Association (Shackan Indian Band, Nooaitch Indian Band and Nicomen Indian Band);

• Nicomen Indian Band (NTA)

• Nooaitch Indian Band (Nlaka’pamux Nation)

• O’Chiese First Nation

• Okanagan Indian Band (added by OGC)

• Oregon Jack Creek Band (Nlaka’pamux Nation)

• Pacheedaht First Nation2

• Paul First Nation

• Pauquachin First Nation

• Penelakut First Nation

• Penticton Indian Band

• Peters Band (Stó:lō)

• Popkum First Nation (Stó:lō)

• Qayqayt First Nation (New Westminster)

• Saddle Lake Cree

• Samson Cree Nation

• Scowlitz First Nation (Stó:lō)

• Seabird Island Band (Stó:lō) 2 Pacheedaht First Nation expressed interest in this Plan subsequent to its draft distribution and will be included in final Plan

distribution.

Page 201: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page D-3

• Sechelt

• Semiahmoo First Nation

• Sencoten Alliance

• Shackan Indian Band (Nlaka’pamux Nation)

• Shuswap Indian Band

• Shuswap Nation Tribal Council

• Shxw’ōwhámel First Nation (Stó:lō)

• Shxwha:y Village (Stó:lō)

• Simpcw First Nation

• Siska Indian Band (Nlaka’pamux Nation)

• Skawahlook First Nation (Stó:lō)

• Skeetchestn First Nation

• Skowkale First Nation (Stó:lō)

• Skuppah Indian Band (Nlaka’pamux Nation)

• Skwah First Nation (Stó:lō)

• Soowahlie Indian Band (Stó:lō)

• Splatsin First Nation

• Spuzzum First Nation (Nlaka’pamux Nation)

• Squamish Nation

• Squiala First Nation (Stó:lō)

• St'at'imc Chiefs Council

• Stó:lō Collective

• Stoney Nakoda First Nation

• Sts'ailes Band (Chehalis Indian Band) (Stó:lō)

• St'uxwtews (Bonaparte Indian Band)

• Sucker Creek First Nation

• Sumas First Nation (Stó:lō)

• Sunchild First Nation

• Tk'emlups te Secwepemc (Kamloops)

• Toosey Indian Band

• Treaty 8 Nations of Alberta

• Tsartlip First Nation

• Tsawout First Nation

• Tsawwassen First Nation

• Tseycum First Nation

• Tsilhoqu'tin National Government

• Ts'kwaylaxw (Pavilion Indian Band)

Page 202: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page D-4

• Tsleil-Waututh Nation

• Tsuu T'ina First Nation

• Tzeachten First Nation (Stó:lō)

• Union Bar Indian Band (Stó:lō)

• Upper Nicola Band (Nlaka’pamux Nation)

• Upper Similkameen Indian Band

• Whitefish (Goodfish) Lake First Nation

• Williams Lake (T'exelc) Band

• Xatśūll First Nation (Soda Creek)

• Yakweakwioose Band (Stó:lō)

• Yale First Nation (Stó:lō)

Page 203: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

Trans Mountain Pipeline ULC Navigation and Navigation Safety Plan Trans Mountain Expansion Project April 2017

01-13283-GG-0000-CHE-RPT-0010 R1

Page E-1

APPENDIX E

WESTRIDGE MARINE CONSTRUCTION SAFETY BOOM

Page 204: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

TRANSMOUNTAIN EXPANSION PROJECT

Westridge Marine CONSTRUCTION SAFETY

BOOM Page E-2

WESTRIDGE MARINE CONSTRUCTION SAFETY BOOM

A. Background As required by the National Energy Board a Navigation and Navigation Safety Plan (NNSP)3 has been prepared. The NNSP notes that there is potential of Project construction affecting navigation and navigation safety. This includes disruptions to users during construction or maintenance activities and safety of users entering the construction zone. Therefore, in anticipation of construction pile driving for the Westridge Terminal commencing in the fall of 2017, plans are in hand to install a floating marine construction safety boom around the entire Westridge working zone. The marine construction safety boom, a key element of the NNSP, will be designed to ensure the safety of commercial and recreational users of the local marine area, and the safety of workers working within a clearly demarcated working zone. The overall Westridge area working zone is shown in Figure 1 and is expected to encompass waters covering the future Westridge water lot lease area plus an additional temporary working space.

3 https://www.transmountain.com/navigation-safety-plan

Page 205: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

TRANSMOUNTAIN EXPANSION PROJECT

Westridge Marine CONSTRUCTION SAFETY BOOM

Page E-3

Figure 1: Proposed marine construction safety boom showing shipgate (concept only, actual layout might be different)

Page 206: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

TRANSMOUNTAIN EXPANSION PROJECT

Westridge Marine CONSTRUCTION SAFETY BOOM

Page E-4

1. Westridge Marine Construction Safety BoomThe marine construction safety boom will consist of floats and suitable vertical panels. Once deployed itwill extend from the high water mark west of the facility, out and around the entire construction footprintincluding the existing ship berth and tying back into the shore on the east side of the facility. The layout ofthe floating safety boom will be configured according to the construction operations and schedule and itslayout during the first and second years of construction are shown as Phase 1 and Phase 2 respectively.

This boom will be moored using suitable anchors to withstand typical and worst case environmental conditions found in this area. It will be fitted with several access points or gates to accommodate the passage of construction vessels and vessels coming to and from the existing Westridge dock. The existing terminal will remain in operation for the majority of the construction period.

The marine construction safety boom will be staged at a nearby yard in the Burrard Inlet. From here it will be assembled and launched.

2. Navigation marksThe marine construction safety boom will be highly visible during the day. The structure will be equipped with reflective placards on both the inside and outside so the marine construction safety boom remains visible between the buoys. At night, in accordance with general Canadian Coast Guard requirements, the boom will be marked by navigation lights (Flashing yellow one nautical mile range) on all offshore corners. Additional lights will be mounted on the ship gate buoys. Radar reflectors will be installed strategically to assist approaching traffic identify the boom on radar during night time and periods of reduced visibility.

3. Phased implementationPhase 1: Late Summer 2017 to August 1, 2018 | Construction activities planned for this period include driving pipe piles for the Berth 1 & 2 dolphins, and driving sheet piles for the foreshore. During this period oil cargo vessels will access the existing dock through a ship gate placed at the eastern side of the marine construction safety boom. The actual layout and deployed extent of the boom may vary from the preliminary working layout shown in Figure 1; however, the minimum distance of the Phase 1 deployed boom from the centerline of the normal shipping route taken by passing vessels will be approximately 313 m (see Figure 2).

Phase 2: August 1, 2018 to December 31, 2019 | Berth 3 construction and the completion of Berths 1 & 2 will be undertaken during this period. During this phase the minimum distance of the deployed boom from the centerline of the normal route taken by passing vessels will be about 217 m (see Figure 2).

During the latter part of this period, cargo oil transfer operations will be shifted to the new Berth 1. Depending on requirements at that time, the ship gate for oil cargo vessels to access the dock will be shifted to the western side of the marine construction safety boom in order to allow access of those vessels to Berth 1. Such a Phase 3 iteration of the marine construction safety boom will be developed based on working experience with the use of the Phase 1 marine construction safety boom.

Page 207: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

TRANSMOUNTAIN EXPANSION PROJECT

Westridge Marine CONSTRUCTION SAFETY BOOM

Page E-5

Figure 2: Eastern Burrard Inlet showing current and proposed Westridge dock area with the marine construction safety boom

Page 208: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

TRANSMOUNTAIN EXPANSION PROJECT

Westridge Marine CONSTRUCTION SAFETY

BOOM Page E-6

4. Operations During Phase 1, the ship gate will swing inward toward an anchor buoy located by the future Berth 3. The opening will be approximately 180 m wide and if necessary it is anticipated that the opening could be further expanded by about 10 m on its southern side by installing mechanism to pull the inshore ship gate buoy toward shore.

A ship gate size of 180 m is proposed which is expected to be compatible with the results of the desk top navigation simulations previously undertaken by Lantec4,5 and submitted to the TMEP TERMPOL Review Committee and the NEB. Lantec carried out the simulations on a Kongsberg desktop simulator using Aframax vessels with typical worst case environmental conditions by applying wind from the northeast at 25 knots and tidal stream values as per spring tide conditions. Early verification of gate size compatibility and adequacy of maneuvering room has been made by Lantec by carrying out replays of two of the runs after having marked the Phase 1 and Phase 2 marine construction safety boom layout with ship gate coordinates to the simulation, see Figure 3 and Figure 4. Please note that Berth 3 will remain partially built while the existing dock is in operation with construction of the eastern dolphins deferred till after cargo operations have been transferred to new Berth 1 in 2019.

Figure 3: Arriving Aframax - Approaching existing berth through the marine construction safety boom shipgate (new berth 3 eastern dolphins will be constructed after existing berth operations have been transferred to new Berth 1)

4 Summary Report of Manoeuvring Assessment, Westridge Terminals Vancouver Expansion, 4 October 2013 5 Summary Report of Manoeuvring Assessment, Westridge Terminals Vancouver Expansion, 13 August 2014

Page 209: WESTRIDGE MARINE TERMINAL UPGRADE AND ...

TRANSMOUNTAIN EXPANSION PROJECT

Westridge Marine CONSTRUCTION SAFETY

BOOM Page E-7

Figure 4: Departing Aframax – Departure from existing berth through the marine construction safety boom shipgate