© 2010 Westinghouse Electric Company LLC. All Rights Reserved.Westinghouse Non-Proprietary Class 3

Westinghouse Electric Company:Committed to Providing Sensible Energy

Solutions for the Czech Republic

Kerry Hanahan

Project Development Director

Czech Republic

Page 2: Westinghouse

2

Westinghouse Electric Company

Headquarters

Cranberry Township Pennsylvania, USA

Westinghouse Electric Company

provides fuel, services, technology,

plant design, and equipment to utility

and industrial customers in the

worldwide commercial nuclear

electric power industry

Westinghouse Electric Company

Nearly 50 percent of the nuclear

power plants in operation

worldwide are based on

Westinghouse technology

Page 3: Westinghouse

3

Westinghouse is Committed to Serving Europe

● ~ 5,000 Employees in EU

● Two nuclear fuel facilities in EU

● Supplier of 25 nuclear

units in EU

● Designer of 86

licensed nuclear

units in EU

● Legacy forms our

platform for

future AP1000TM

deliveries in EU

Page 4: Westinghouse

4

© 2010 Westinghouse Electric Company LLC. All Rights Reserved.Westinghouse Non-Proprietary Class 3

Westinghouse Proprietary4

Does not represent actual plant locations.

Services Fuel New Plants

Westinghouse

Americas Europe Asia

Today’s Regional Operating ModelYesterday’s Operating Model

Westinghouse

Center Led-HQ

Global Products and Services

Page 5: Westinghouse

5

Focused on operating plant

success through reliable

operation, maximized power

output and better (shorter,

more predictable) outages

A single-source

fuel provider for

PWR, BWR,

VVER, AGR and

Magnox reactors

worldwide

Specializing in

the technology

of new nuclear

power plants and

component

manufacturing

Westinghouse Electric Company Four Product Lines

Nuclear Services

Nuclear

Power PlantsNuclear Fuel

Nuclear

AutomationInstrumentation and control

solutions to enhance the

reliability of nuclear plant

control and safety systems

One

Westinghouse

Page 6: Westinghouse

6

AP1000TM: Designed for Greater Certainty Simple, Practical, Standardized and Innovative

• Passive Safety replace

mechanical & electrical systems

-- results in fewer materials and

equipment

• Modular design drives faster,

predictable construction

schedule

• Reduced Operations and

Maintenance Cost versus other

plant designs

• Majority of design utilizes

proven Westinghouse

experience and technology

Result:

Reduced Construction Time, Greater Schedule Certainty, and Lower Costs

Greater Levels of Safety and Quality

Page 7: Westinghouse

7

● ~30% less operating staff

● ~40 – 50% less safety-related equipment

● 60-year design life

● Design capacity factor of 93%

● Designed for outage duration of 17 days

AP1000TM: Designed for Greater Certainty Long-lasting benefits from a simple design

Page 8: Westinghouse

8

Evaporation

Condensation

Natural Circulation

Compressed gasses

(nitrogen, air)

System performance has

been proven by extensive

testing and approved by the

U.S. NRC

1,100 Mwe supports the

existing Czech grid

AP1000TM: Designed for Greater Certainty Simplicity in Safety Design

Passive Technology Employs Natural Forces.

Page 9: Westinghouse

9

AP1000 – Dark Red and Light Red

Typical PWR – Dark Blue and Light Blue

•Dark colors denote safety-related footprint

•AP1000 has significantly less safety-related area, equipment and components

•AP1000 construction schedule 48 months from 1st nuclear concrete to substantial completion

AP1000TM: Designed for Greater Certainty Smaller footprint for improved economics

Page 10: Westinghouse

10

● 1300 man year design and testing effort over 20 years

● US NRC review process

– Independent, confirmatory plant analysis and testing

– AP1000 certified January 2006 with Design Control Document

(DCD) Rev 15

– DCD amendments for aircraft crash resistance, among others,

currently under review by NRC

● Approved for construction in China

● EU Compliance Certificate received, May 15, 2007

● Being reviewed by UK regulator

AP1000TM: Designed for Greater Certainty Licensing maturity means less risk

Page 11: Westinghouse

11

Shorter schedule & Increased safety & Improved quality

Modular Construction means more work done in parallel

AP1000TM: Designed for Greater Certainty Modular construction makes a difference

Page 12: Westinghouse

12

AP1000TM: Designed for Greater Certainty Positive Effects of Modular Construction

Feb 2007 plan Actual Delta

First Concrete Milestone Completed 31-Mar-09 26-Mar-09 0

Auxiliary Building Module Set in Place 31-May-09 29-Jun-09 1

CV Bottom Head Set in Place 31-Jun-09 21-Dec-09 6

CV 1st Ring Set in Place 31-Dec-09 18-Mar-10 3

CV 2nd Ring Set in Place 31-May-10 2-Jun-10 0

With the setting of the CV 2nd

Ring, against the

construction schedule

milestones Sanmen Unit 1

has basically recovered the 6

month delay in setting the

CVBH.

This would not have been

achievable if it were not for

modular construction.

Page 13: Westinghouse

13

Committed to Delivering the AP1000TM

AP1000TM projects are progressing

Setting of the

Containment Vessel

Second Ring

Sanmen Unit 1

First AP1000

in the World:

On Schedule

For 2013

Page 14: Westinghouse

14

Committed to Delivering the AP1000TM

Sanmen Units 1 & 2

Page 15: Westinghouse

15

Committed to Delivering the AP1000TM

Haiyang Units 1 & 2

Page 16: Westinghouse

16

Module Assembly Bldg Pad InstallationSite Aerial View – January 2010

Committed to Delivering the AP1000TM

First New U.S. Construction in 30 Years Has Begun

Southern Nuclear Vogtle Units 3 & 4

Page 17: Westinghouse

17

SCANA VC Summer

Committed to Delivering the AP1000TM

First New U.S. Construction in 30 Years Has Begun

Page 18: Westinghouse

18

Westinghouse Supports Supply ChainSupply Chain Development is Critical To The Czech Republic

• Our progress and success on existing projects

relies upon the localization of supply chain

• High quality, delivery assurance

• Capable of and experienced with development

of new suppliers

• We Buy Where We BuildTM part of our success

in the Czech Republic

Page 19: Westinghouse

19

Immediate opportunities for Czech Suppliers…

Component manufacturing

Equipment supply

Module construction and

logistics

Construction

Civil works

Construction management

Project Management Transportation / Misc.

…and potential partnership with Westinghouse in the

AP1000™ Integrated Global Supply Chain Network.

Commitment to Localization of Supply Supply chain solutions: think global, act local

Page 20: Westinghouse

20

Westinghouse Nuclear Power PlantsA Long-Term Partner for Czech Energy Solutions

• The right choice for inherently safe technology…

• Passive Gen III+ is the most advanced

• Safe, Simple, Standardized and Innovative

• Modular construction for a shorter schedule

• The right choice for greater energy security…

• Commitment to serving Europe

• Greater diversity of fuel and supply chain

• The right choice for economic responsibility…

• Simplification for greater project certainty

• ”Fits” the existing grid – 1,110 MWe

• Proven project execution excellence

Page 21: Westinghouse

21

•The right choice for a long-term partnership…

• Commitment to the

Czech community

• Localization with Czech

industry as the base

• Job creation

• Cornerstone for Europe

• Technology exchange

We Are Committed to the Czech RepublicA Long-Term Partner for Czech Energy Solutions

A Westinghouse – Czech relationship means safe,

secure and economically responsible energy

in the Czech Republic for the next 100 years!

Page 22: Westinghouse

22

Thank You!

Page 23: Westinghouse

23

Westinghouse

Electric Company

Operating Committee Members

Effective October 2010

July 2010

Senior Vice President

Nuclear Fuel*

Joe Belechak

Senior Vice President

Nuclear Services*

Nick Liparulo

Senior Vice President

Nuclear Power Plants*

Deva Chari

President

Europe, Middle East

and Africa*

Anders Jackson

President

Americas*

Jim Ferland

President

Asia*

Jack Allen

Senior Vice President

Operations Support*

Dan Lipman

Senior Vice President

Human Resources &

Corporate Relations

Tony Greco

Senior Vice President,

Research & Technology,

and Chief Technology

Officer

Kate Jackson

Senior Vice President,

Finance, and Chief

Financial Officer

Masayoshi Hirata

Senior Vice President

and Chief Coordination

Officer

Tetsuya Noda

Senior Vice President,

Legal & Contracts,

Environment, Health &

Safety, and General Counsel

Ramsey Coates

President and Chief

Executive Officer*

Aris Candris

Senior Vice President

Nuclear Automation*

David Howell

President

Operations*

Ric Pérez

*

Page 24: Westinghouse

24

Westinghouse NPP Top Five Priorities

1. Successfully Deliver on our Commitments

2. Successfully Capture New Markets

3. Continuously Improve Operations and Project

Execution

4. Enhance Organizational Effectiveness

5. Build Strategy for the Future

Page 25: Westinghouse

25

Westinghouse NPP Vision and Mission

NPP VisionNPP will be the global supplier of choice in delivering

new nuclear power plant projects to meet the world’s

growing need for energy

NPP MissionWe will realize this vision by …

• Leading the industry with new and innovative technology

• Maintaining world-class safety and quality performance

• Successfully delivering projects on time and within budget

• Offering innovative solutions to our customers

• Leveraging the capabilities of Toshiba/Shaw to maximize our

Global Market Share

• Developing and empowering our employees

• Leveraging C1st to differentiate ourselves in the marketplace

Page 26: Westinghouse

26

Four China AP1000TM Units Under Construction

Sanmen 1 – RV to set in April 2011 Haiyang Unit 1 – CVBH Set April 2010

Haiyang Unit 2 – FCD June 20thSanmen 2 - CVBH Set June 2010