Westar Energy Transmission Operations: An Update on Regional and Local Transmission Activity June 22, 2010 Presented to Attendees of Westar’s Transmission Formula Rate Meeting
Jan 19, 2016
Westar Energy Transmission Operations:An Update on Regional and Local
Transmission Activity
Westar Energy Transmission Operations:An Update on Regional and Local
Transmission Activity
June 22, 2010
Presented to Attendees of Westar’s Transmission Formula Rate Meeting
2
Transmission Formula Rate True-Up MeetingTransmission Formula Rate True-Up Meeting
Today’s AgendaTransmission Formula Rate
The Protocols of the Formula: How They Apply to YouA Discussion of the June 15 True-Up Calculation
An Update on Regional and Local Transmission Activity
Attachment AQ: New Delivery Point Addition Procedures
Today’s AgendaTransmission Formula Rate
The Protocols of the Formula: How They Apply to YouA Discussion of the June 15 True-Up Calculation
An Update on Regional and Local Transmission Activity
Attachment AQ: New Delivery Point Addition Procedures
3
The Many Facets of Transmission…The Many Facets of Transmission…
The Current “Hot Topics” at the Southwest Power Pool
Full Speed Ahead: Westar’s Transmission Construction Status
The Current “Hot Topics” at the Southwest Power Pool
Full Speed Ahead: Westar’s Transmission Construction Status
4
The Southwest Power Pool (SPP)The Southwest Power Pool (SPP)
Hot Topic #1: Making the System Study Process More Efficient
New transmission service requests New delivery points
Attachment AQ: The New Delivery Point Addition Procedures New generation interconnections
Attachment V: The New Generation Interconnection Procedures (GIP)
Which comes first, the wind or the wires?
Hot Topic #1: Making the System Study Process More Efficient
New transmission service requests New delivery points
Attachment AQ: The New Delivery Point Addition Procedures New generation interconnections
Attachment V: The New Generation Interconnection Procedures (GIP)
Which comes first, the wind or the wires?
5
Proposed Wind Projects in SPPProposed Wind Projects in SPP
6
The Southwest Power Pool (SPP)The Southwest Power Pool (SPP)
Hot Topic #2: Cost Allocation…Who Pays for What?
Highway/By-way RateFERC just approved on June 17, effective June 19,
2010Focuses on SPP Region as a wholeAllocation according to voltage
• > or = 300 kV is spread across entire region• > 100 kV < 300 kV is 1/3 region, 2/3 zone• < or = 100 kV is 100% to the zone
Zonal, Regional, Base Plan Funded, Economic…oh my!
Hot Topic #2: Cost Allocation…Who Pays for What?
Highway/By-way RateFERC just approved on June 17, effective June 19,
2010Focuses on SPP Region as a wholeAllocation according to voltage
• > or = 300 kV is spread across entire region• > 100 kV < 300 kV is 1/3 region, 2/3 zone• < or = 100 kV is 100% to the zone
Zonal, Regional, Base Plan Funded, Economic…oh my!
7
The Southwest Power Pool (SPP)The Southwest Power Pool (SPP)
Hot Topic #3: 765 kV…Truth or Myth?Prairie Wind Transmission
Joint Venture between Westar and American Electric Power (AEP)
First project of focus has been: Wichita-Medicine Lodge 765 kV
SPP has approved double-circuit 345 kV so farPWT is working with ITC to revise KCC settlement
agreement accordingly for 345 kV765 kV can still become a reality
• Integrated Transmission Plan (ITP) will be issued January 2011
• Would be operated at 345 kV for indefinite period
Hot Topic #3: 765 kV…Truth or Myth?Prairie Wind Transmission
Joint Venture between Westar and American Electric Power (AEP)
First project of focus has been: Wichita-Medicine Lodge 765 kV
SPP has approved double-circuit 345 kV so farPWT is working with ITC to revise KCC settlement
agreement accordingly for 345 kV765 kV can still become a reality
• Integrated Transmission Plan (ITP) will be issued January 2011
• Would be operated at 345 kV for indefinite period
8
Proposed 765 kV ProjectsProposed 765 kV Projects
9
Construction Status ReportConstruction Status Report
Westar is building more new transmission than ever Transmission service, reliability, generator interconnections Cost recovery via Transmission Formula Rate Example: $200+ million vs. $10 million in earlier years
TransCanada, TransCanada, TransCanada
Other major projects: Wichita-Reno 345 kV Reno-Summit 345 kV Rose Hill-Sooner 345 kV
Numerous other transmission projects…..
Westar is building more new transmission than ever Transmission service, reliability, generator interconnections Cost recovery via Transmission Formula Rate Example: $200+ million vs. $10 million in earlier years
TransCanada, TransCanada, TransCanada
Other major projects: Wichita-Reno 345 kV Reno-Summit 345 kV Rose Hill-Sooner 345 kV
Numerous other transmission projects…..
10
TransCanada is Coming!TransCanada is Coming!• TransCanada will have six pumping stations in Kansas.
• Five of those stations are in the Westar Energy service area.
• Each station has at least two and up to five 6500 hp motors.
• Estimated peak load at each site will be 17-25 MW
•All locations expected to be on-line by the end of 2013
11
7³
7³
"S
"S
"S
")
"S
"S
"S
"S
"S
"F)
"S
"S
"S
"S
"F)
"F)
"S
"F)
"S"S
"S
"S
"S
"S
"S
"S
")B
"S")
"S
"S
"S
")
"S
"S
"S
"S
")B
"S
"+)
"S
"S
"S
"S
"F)
"S
"S
"S
")
"S
")
"S"S
"S
"S
"S
"S
"S
")B
"S
"S
"S")B
"S
"S
"S
"S
"S
"S
"S
"S
"S
")
")B
"S
"S
"S
"S
"S
"S
")
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"F)
"F)
"S
"S"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"F)
"S
"S
"S
"S
"S"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
WALTON
BENTLEY
ELBING
MT. HOPE
COLWICH
SOUTH HUTCHINSON
SEDGWICK
HALSTEAD
MOUNDRIDGE
INMAN
BUHLER
BURRTON
HAVEN
ANDALE
NORTH NEWTON
GOESSEL
WHITEWATER
WICHITA
HUTCHINSON
NEWTON
BEL AIRE
PARK CITY
MAIZE
KECHI
VALLEY CENTER
HESSTON
ANDOVER
YODER
FURLEY
MEDORA
ANNELLY
MC LAINE
PATTERSON
GREENWICH
ST MARK (UNION)
HEC
3VAN
RIPL
DAVI
CSTV
CENA
43LO
MAHA
18PL
HESS
COLE
COMO
FMON
GOLD
GRNT
HDRO
WICH
MDAM
LAKE
BENT
RENO
BURR
MOUNYOST
CHIS
SAVC
MUDC
2ELM
HALS
NEWT
GATZ
KSIR
BUHL
TVTH
HAVE
MEAV
CRPC
INMA
Emporia EC to Wichita 345
SG12 C
olwic
h t
o H
als
tead
Hals
tead t
o M
ound
ridge
Cir
cle t
o D
avi
s 34
5.1
9S
345.10A
13
8.1
113
8.1
4
138.09138.12
69.35
69.50
34
5.1
5B
115.80
69.74A
11
5.5
5
11
5.7
8
RENO
HARVEY
SEDGWICK
MCPHERSONMARION
RICE
BUTLER
GORD
MIWI
GORD
14LO
MASC
CIRC
MOUN
PHIL
HECGMDOW
11HL
345 kV Projects: Wichita-Reno-Summit345 kV Projects: Wichita-Reno-Summit
Stage 1: Gordon
Evans Energy Center to Reno Sub
Energized December
2009
12
"S
"S
"S
"S
"S
"S
"S
"F)
"S
"S
"S
"S"S
"S
"S
"S
"S
"S
"S
"S
")
"S
")
"S
"S
"S
"S
"S
")
"S
"S
"S
")
"S
"S
"S
")
"S
"S
"S
"S
")
")
"S ")B
")B
")B
"S
"S
"S
")
"S
"S
"S"S
"S
"S")B
"S
"S
"S
"S
"S
"S
"S
"S
"S
")
"S
")
"S
"S
"S
"S
"S
"S
"S
"S
"S"S
"S
"S
"S
"S
")
"S
"S
"S
"S "+)
"S"S
"S
"S
"S
"S
"S
"S
"S
")
"S
"S
")B
"S
")B
"S
"S
"S
"S
"S
"S
")"S
"S
")"S
"S
"S
"S
")
"S
")
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S"S
"S
"S
"S
"S
"S
"S
"S
")
"S
"S
")B
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
BURNS
LEHIGH
CHASE
WALTON
RAMONA
TAMPA
ELBING
LITTLE RIVER
ALDEN
WINDOM
DURHAM
WILLOWBROOK
CARLTON
LINCOLNVILLE
LOST SPRINGS
NEW CAMBRIA
WOODBINE
LYONSMARIONHILLSBORO
STERLING
SOUTH HUTCHINSON
PEABODY
NICKERSON
MOUNDRIDGE
INMAN
BUHLER
HOPE
FLORENCE
BURRTON
MARIONGALVA
SOLOMON
CANTON
GENESEO
NORTH NEWTON
ENTERPRISE
BROOKVILLE
HILLSBORO
GYPSUM
GOESSEL
MARQUETTE
MARION
PEABODY
SALINA
HUTCHINSON
NEWTON
ABILENE
HESSTON
HERINGTON
KIPP
ELMO
LYONA
DILLON
SAXMAN
MEDORA
CANADA
PILSEN
AULINE
BAVARIA
DETROIT
ROXBURY
NAVARRE
JUNIATA
HOLLAND
MITCHELL
ANTELOPE
WESTFALL
CRAWFORD
GLENDALE
HEDVILLE
SHADY BROOK
AEC
3VAN
NSTR
PHLP
CENA
WHEA
CRFD
43LOHESS
GOLD
SUMM
MDAM
FLOJ
RENO
BURR
NOVW
CITS
PEAB
MOUNYOST
SAVC
MUDC
DOC
WATC
LEGH
COND
RDSO
ADSO
WIND
HRFH
CANT
BUHL
WALG
ENTE
DURH
MRFH
ELMO
HSFH
DSOSPDSO
FLCE
WABI
GYPS
MARQ
INMA
LSPR
Morris County to Summit
Summit to Smoky Hills
Abilene EC to Northview
345.07
230.1011
5.15
115.98
138
.14
115
.55
69.8
5
115
. 32
RICEMARION
SALINE
MCPHERSON
RENO
DICKINSON
ELLSWORTH
HARVEY
LINCOLN
BUTLER
MORRIS
GEARY
HEC
WMCP
DAVI
18PL
MIWI
EABI
FMON
EMCP
CITI
SHIL
14LO
SALM
CIRC
HILL
MOUN
HECG
EXID
SGAT
2ELM
SMOK
MDOW
11HLNEWT
GATZ
345 kV Projects: Wichita-Reno-Summit345 kV Projects: Wichita-Reno-Summit
Stage 2: Reno Sub to Summit Sub
Scheduled to be completed
September 2010
13
345 kV Projects: Rose Hill-Sooner345 kV Projects: Rose Hill-Sooner
Rose Hill Sub to OGE’s
Sooner Sub
Westar’s portion is
scheduled to be completed
mid-2012
7³7³
"S
"S"S
"S
")B
"S
"S
"F)
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S"S
"S
"S
")B
"S
"S"S
"S
"S
"S
"F)
")B
"S
"S
"F)
"S
"S
"S
"F)
"S
"S
"F)
")B
")
"F)
")B
"S
"S
"S
"S
"S
"F)
"F)
"S
"S"S
"S
"S
"S
"S
"S
"S
"F)
"S"S
"F)
"S
"S
"S
"F)
"S
"S
"S"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"F)
"S
"F)
"S
")B
"S
"S
"S
"S
"S
"F)
"S
"S
DEXTER
LATHAM
CAMBRIDGE
MULVANE
CLEARWATER
DOUGLASS
BURDEN
PARKERFIELD
BELLE PLAINE
ATLANTA
ROSE HILL
DOUGLASS
CLEARWATER
CLEARWATER
CLEARWATER
WICHITA
DERBY
WINFIELD
ARKANSAS CITY
HAYSVILLE
WELLINGTON
WACO
ROCK
PECK
AKRON
DALTON
FLORAL
WILMOT
SCHULTE
OAKLAWN
RIVERDALE
NEW SALEM
SILVERDALE
BAYNESVILLE
LIN
OAK
WACO
ROSEOATV STEA
TIMB
HAYS
HYDR
AKRO
BELL
MIDL
FARB
RAIN
PECK
MURR MAGN
FLOR
UDAL
ELPA
ARKAPARI
CAV6
CVC3
Latham to Rose Hill
Bel
l to
Pec
k
Tim
ber
Tap
to
Win
fiel
d
Bel
l to
SC3 M
iller
Wellington to SC4 Rome
69.9
9
345.11
69.4
2
345.16
138.13
138.
02
69.1
01
138.
30
T33S R01E
T29S R06E
T30S R07E
T29S R07ET29S R05E
T33S R06E
T34S R06E
T30S R06E
T31S R01ET31S R06E
T34S R05E
T32S R01E
T31S R04E
T33S R05E
T29S R02E
T32S R05E
T31S R05E
T29S R04E
T30S R05E
T32S R04E T32S R06E
T29S R01E
T33S R04E
T34S R04E
T30S R04E
T33S R07E
T31S R07E
T34S R07E
T32S R07E
T30S R01E
T29S R01W
T30S R02E
T31S R01W
T30S R01W
T28S R04E
T28S R05E
T28S R06E T28S R07E
T31S R02W
T30S R02W
T35S R07ET35S R06ET35S R05ET35S R04ET35S R03E
T29S R03E
T33S R03ET33S R02E
T32S R03E
T34S R03E
T31S R03ET31S R02E
T34S R02E
T32S R02E
T30S R03E
T28S R02E
T28S R03E
T28S R01W
T29S R08E
T30S R08E
T31S R08E
T32S R08E
T33S R08E
T34S R08E
T28S R08E
T35S R08E
COWLEYSUMNER
BUTLER
SEDGWICK
RICH
MACA
CRSW
VULC
OXFO
OAKL
59TH
PRLD
14
"S
"S ")
"S
"S
"S
"S
")
"S
"S
"S
"F)
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"F)
"S
"S
"S
"F)
"S
")
"S
"S
"S
"S
"S
"F)
BERN
ONEIDA
GOFF
BEATTIE
CORNING
SUMMERFIELD
SOLDIER
OKETO
VERMILLION
WHEATON
HAVENSVILLE
SENECA
BLUE RAPIDS
FRANKFORT
AXTELL
CENTRALIA
ONAGA
MARYSVILLEHOME
KELLY
DULUTH
LILLIS
NEMAHA
VLIETS
MARIETTA
WINIFRED
ST BENEDICT
AMERICA CITY
KIHI
SMIT
KNOB
SSEN
KELL
BLRA
BERN
BIGE
NCRA
FKFT
AXTL
BRCW
EMSV
BEST
SLDR
CNTL
NM 5 Smittyville to Knob Hill115.22
115.100T02S R08E
T04S R08E
T05S R08E
T03S R08E
T01S R08E
T04S R11E
T05S R11E
T03S R11E
T02S R11E
T04S R07E
T05S R09ET05S R07E T05S R12E
T03S R07E
T04S R09E
T02S R09E
T05S R10E
T04S R12ET04S R10E
T03S R09ET03S R12E
T02S R12E
T01S R09E
T02S R10E
T03S R10E
T02S R07E
T01S R07E
T01S R10E T01S R11E
T02S R13E
T03S R13E
T01S R12E T01S R13E
T04S R13E
T05S R13E
T06S R12ET06S R08E
T06S R11ET06S R10ET06S R09E
T06S R13ET06S R07E
T03S R06E
T06S R06E
MARSHALL
NEMAHA
POTTAWATOMIERILEY JACKSON
Other Projects: North-Central KansasOther Projects: North-Central Kansas
Rebuilding Kelly-S.
Seneca 115 kV and
building a new 115 kV
line from Knob Hill Sub to the
State border
Both scheduled to be completed by Dec 2010
15
7³
")
"S
"S
"S
"S
")B
"S
"S
"S
"S
"S
LEAVENWORTH
LANSING
STRA
HALL
SPRU
THOR
WADS
Jar
balo
to
NW
Lea
venw
orth
Str
ange
r Cre
ek
to P
latt
e Cit
y
Jar
bal
o to
Hal
lmar
k
J arb
alo
J ct. to
Mar
ion
Stre
et
115.
36
115.
06
115.42
115
.92
345.0611
5.0
6
115
.92
LEAVENWORTH
Other Projects: Northeast KansasOther Projects: Northeast Kansas
Building a new 115 kV line between
Stranger Creek and Thornton
Subs
Scheduled to be completed by Dec 2010
167³7³
7³
"S")B
"S
"S
"S
"S
"F)"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
")B
"S
"S
"S
"S
"S
"S
"S"S
"S
")B
"S
"S
")B
"S
"S
"S
"S
"S
"S"S
"S
"S
"S
"S
"S
"F)
"F)
")B
"S
")B
"S
"S
"S
"F)
"S
"S
"S
"F)
"S
"S
"S
")B
"S
"S
"S
"S
"S
"S
"S
"F)
"S
"F)
"S
"S
"S
"S
"S
")B
"S
"S
"S
"F)
"S"S
"F)
"S
"S
"S
"S
"S
"S
"F)"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S"S
"S
"S
"S
"F) "S
"S
"S
"S
"S
"S"S
"S
"S
"S
"S
"S
"F)
"F)
"S
"S
"S
"S
"F)
"S
"S
"S
"F)
"S
"S
"S
"S
"S
"S
"S
"S
"S
"S
"F)
"S
"S
"F)
"S
"S
"S
"S
"S
")B
"S
"S
"S
"S"S
"F)
"S
DEXTER
MAYFIELD
MULVANE
LEON
CLEARWATER
DOUGLASS
BURDEN
BELLE PLAINE
ATLANTA
EASTBOROUGH
ROSE HILL
DOUGLASS
CLEARWATER
CLEARWATER
CLEARWATER
WICHITA
DERBY
WINFIELD
ANDOVER
HAYSVILLE
WELLINGTON
AUGUSTA
GODDARD
WACO
ROCK
PECK
ANSONAKRON
DALTON
FLORAL
WILMOT
SCHULTE
OAKLAWN
RIVERDALE
NEW SALEM
BAYNESVILLE
LIN
MOBIFOWL
WASS
ROSE
WHIT
INTE
RUTA
OATV
MOSS
HOOV
TIMB
HAYS
VIST
CENT
BELL
BEECCOWS
MIDL
ANDO
CLWA
MURR
LEON
OLIV
UDAL
ELPA
HARR
WACO
BOEI
STEA
64TH
HYDR
AKRO
FARB
RAIN
PECK
SDAL
MAGN
FLOR
SHER
CAV6
Latham to Rose Hill
Wolf Cree
k to R
ose H
ill
Bel
l to
Pec
kBel
l to
SC3 M
iller
69.9
9
345.1113
8.02
138.18
69.4
2
138.13
345
.10
B
69.1
00
A
138
.22
A
138
.27
138
.30
69.46
69.100B
69.58
69.58C
T29S R06E
T28S R06E
T29S R05E
T30S R06E
T31S R01E
T28S R02E
T31S R06E
T28S R05E
T32S R01E
T28S R03E
T31S R04E
T29S R02E
T32S R05E
T31S R05E
T29S R04E
T30S R05E
T31S R02E
T28S R04E
T32S R04E T32S R06E
T29S R01E
T30S R04E
T32S R02E
T28S R01E
T30S R01E
T29S R01W
T30S R02E
T31S R01W
T30S R01W
T27S R03E
T27S R01W T27S R04E
T27S R05E T27S R06E
T31S R02W
T30S R02W
T28S R02W
T33S R06E
T27S R02W
T33S R05E
T33S R04ET33S R01E
T33S R02E
T29S R03E
T32S R03E
T31S R03E
T30S R03E
T28S R01W
T27S R02E
T29S R02W
T28S R07E
T29S R07E
T27S R07E
T30S R07E
T31S R07E
T32S R07E
T33S R07E
COWLEY
BUTLER
SUMNER
SEDGWICK
MEAD
OSAG
RICH
WEBS
OXFO
WEST
59TH
KENM
GLEN
NORT
EAST
MACA
SENE
VULC
TYLE
RIVE
OAKL
CANAGRED
WEAV
PLAZ
17TH
MINN
Other Projects: South-Central KansasOther Projects: South-Central KansasRebuilding the 69
kV lines from Gill-Peck,
Weaver-Rose Hill Junction, Timber Junction-Winfield
All scheduled to be
completed in 2010
Building the new 138 kV line
from Sumner Co. to Timber
Junction
17
"S
"F)
"F)
")B
"F)"S
"S
"S")B
"S
"F)
"S
BASSETT
LEROY
YATES CENTER
NEOSHO FALLS
IOLA
PIQUA
VERNON
GENEVA
GREE
ORCH
ATHE OWLC
Athens to Orchard
CC4 V
erno
n to
Gre
enA
then
s to
CC4 V
erno
n69
.27
T23S R16E
T24S R16E
T24S R17E
T23S R17ET23S R18E
T24S R18E
T24S R15E
T23S R15E
T25S R17ET25S R16E
T22S R16E T22S R17E
T25S R18E
T22S R18E
T25S R15E
T22S R15E
WOODSONALLEN
COFFEYANDERSON
Other Projects: Southeast KansasOther Projects: Southeast Kansas
Rebuilding the 69 kV line from Green to
Athens Subs
Scheduled to be completed Spring 2011
18
The New Delivery Point Addition/Modification ProcessThe New Delivery Point Addition/Modification Process
Delivery Point Addition Task Force createdDid so pre-emptively to assure customer voice representedWorked diligently to make process more efficient and fair
Depicted in Attachment AQ of the SPP Tariff
Went into effect May 1, 2010
Much more formal, with SPP involved
Applies to all wholesale entities wanting to connect to Transmission Owners’ facilitiesKEPCo, KPP, Westar Genco
Delivery Point Addition Task Force createdDid so pre-emptively to assure customer voice representedWorked diligently to make process more efficient and fair
Depicted in Attachment AQ of the SPP Tariff
Went into effect May 1, 2010
Much more formal, with SPP involved
Applies to all wholesale entities wanting to connect to Transmission Owners’ facilitiesKEPCo, KPP, Westar Genco
Customer sends Request for Change in Local Delivery
Facilities to SPP and Host TO
Add orModify DeliveryPoint(s)
Is TC an Existing
SPPCustomer?
GFAConversion/
Rollover?
New TransmissionService Request
Y
N Y
New TransmissionService Request
Aggregate StudyProcess
PTP orNITS
Request?
New or UpdatedNITSA
New or Updated
PTP
ConstructionRequired?
New or Updated
Interconnection
Delivery PointNetworkStudy
(DPNS)
DP LetterAgreement
N
Y
SPP
PreliminaryReview by
TO
ConstructionRequired?
Load ConnectionStudyBy TO
N
Y
TO
Existing Tariff
N
NITS
PTP
PreliminaryReview by SPP
SignificantImpact
to System?
Y
N
Host TO Review
DeliveryPointAdditionProcess
20
Overview of the Westar-Customer Process…Overview of the Westar-Customer Process…
1. Customer submits request to WR and SPP.
2. All related WR departments are notified.
3. Appropriate engineering group performs preliminary study and notifies SPP.
4. If necessary, a Load Connection Study Agreement is issued to Customer.
5. Once executed, WR performs LCS and issues LCS Report within 60 days of LCS Agreement’s execution.
1. Customer submits request to WR and SPP.
2. All related WR departments are notified.
3. Appropriate engineering group performs preliminary study and notifies SPP.
4. If necessary, a Load Connection Study Agreement is issued to Customer.
5. Once executed, WR performs LCS and issues LCS Report within 60 days of LCS Agreement’s execution.
6. Once SPP is satisfied with all necessary studies, a Delivery Point Agreement is issued to the Customer.
7. Once executed, WR and the Customer work closely together to determine milestones and the project scope.
8. If applicable, Regulatory assures FERC is notified and that all related agreements are updated.
9. If applicable, Customer is notified of related Wholesale Distribution Charge.
10. WR and Customer work together to assure timely completion.
6. Once SPP is satisfied with all necessary studies, a Delivery Point Agreement is issued to the Customer.
7. Once executed, WR and the Customer work closely together to determine milestones and the project scope.
8. If applicable, Regulatory assures FERC is notified and that all related agreements are updated.
9. If applicable, Customer is notified of related Wholesale Distribution Charge.
10. WR and Customer work together to assure timely completion.