PROJECT AGREEMENT (REDACTED VERSION)
WEST PARK HEALTHCARE CENTRE
HOSPITAL DEVELOPMENT PROJECT
CONFIDENTIAL
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidentiali
TABLE OF CONTENTS
1. DEFINITIONS AND INTERPRETATION
................................................................................
2
1.1 Definitions and Interpretation
...................................................................................................
21.2 Conflict of Terms
......................................................................................................................
41.3 Conflict of Documents
..............................................................................................................
5
2. COMMERCIAL CLOSE AND FINANCIAL CLOSE
..............................................................
5
2.1 Effective Date
...........................................................................................................................
52.2 Standby Letter of Credit
...........................................................................................................
52.3 Financial Close
.........................................................................................................................
62.4 Disruption in Financial Markets
...............................................................................................
7
3. SCOPE OF AGREEMENT
..........................................................................................................
8
3.1 Scope of Agreement
..................................................................................................................
8
4. BUSINESS OPPORTUNITIES
....................................................................................................
8
4.1 Business Opportunities
.............................................................................................................
8
5. REPRESENTATIONS AND WARRANTIES
............................................................................
8
5.1 Project Co Representations and Warranties
..............................................................................
85.2 Contracting Authority Representations and Warranties
......................................................... 10
6. BACKGROUND INFORMATION
...........................................................................................
12
6.1 No Liability
.............................................................................................................................
126.2 No Warranty
...........................................................................................................................
126.3 No Claims
...............................................................................................................................
126.4 Technical Reports
...................................................................................................................
13
7. PROJECT DOCUMENTS
..........................................................................................................
13
7.1 Project Documents
..................................................................................................................
137.2 Ancillary Documents
..............................................................................................................
137.3 Changes to Lending Agreements and Refinancing
.................................................................
147.4 Compliance with Lending Agreements
..................................................................................
14
8. CONTRACTING AUTHORITY RESPONSIBILITIES
......................................................... 15
8.1 General
....................................................................................................................................
15
9. PROJECT CO RESPONSIBILITIES
.......................................................................................
15
9.1 Other Business
........................................................................................................................
159.2 General
....................................................................................................................................
169.3 Project Co Parties
....................................................................................................................
16
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidentialii
9.4 Permits, Licences, Approvals and Agreements
......................................................................
169.5 Safety and Security
.................................................................................................................
179.6 Additional Works
....................................................................................................................
189.7 Protection of Works and Property
...........................................................................................
219.8 Minimize Disturbance in Existing Facilities
...........................................................................
229.9 COR Certification
...................................................................................................................
229.10 Demolition Requirements
.......................................................................................................
24
10. REPRESENTATIVES
.................................................................................................................
26
10.1 Contracting Authority Representative
....................................................................................
2610.2 The Project Co
Representative................................................................................................
2710.3 Communications to Representatives
.......................................................................................
2710.4 Key Individuals
.......................................................................................................................
27
11. WORKS COMMITTEE
.............................................................................................................
28
11.1 Establishment
..........................................................................................................................
2811.2 Function and Role
...................................................................................................................
2911.3 Term of Works Committee
.....................................................................................................
3011.4 Replacement of Committee Members
....................................................................................
3011.5 Procedures and
Practices.........................................................................................................
3011.6 Proceeding at Risk
..................................................................................................................
31
12. FACILITIES MANAGEMENT COMMITTEE
.......................................................................
33
12.1 Establishment
..........................................................................................................................
3312.2 Function and Role
...................................................................................................................
3312.3 Replacement of Committee Members
....................................................................................
3412.4 Procedures and
Practices.........................................................................................................
34
13. QUALITY ASSURANCE
...........................................................................................................
35
13.1 Quality Plans and Systems
......................................................................................................
3513.2 Changes to Plans
.....................................................................................................................
3813.3 Quality Manuals and Procedures
............................................................................................
3813.4 Quality Monitoring
.................................................................................................................
38
14. LICENCE
.....................................................................................................................................
38
14.1 Licence to Site
........................................................................................................................
3814.2 Non-exclusive Licence/Development of Site
.........................................................................
3914.3 Limited Access Areas
.............................................................................................................
4014.4 Naming and Signage
...............................................................................................................
4014.5 No Interest in Land
.................................................................................................................
4014.6 Non-Disturbance Agreement
..................................................................................................
40
15. TITLE ENCUMBRANCES
........................................................................................................
40
15.1 Title Encumbrances
................................................................................................................
40
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidentialiii
15.2 No Site Encumbrances
............................................................................................................
4115.3 Construction Lien Act (Ontario)
.............................................................................................
41
16. SITE CONDITION
......................................................................................................................
42
16.1 Acceptance of Site Condition
.................................................................................................
4216.2 Contamination
.........................................................................................................................
4316.3 Items of Geological, Historical or Archaeological Interest
or Value ...................................... 44
17. CITY OF TORONTO AND THIRD PARTY FINANCIAL OBLIGATIONS
...................... 45
17.1 City of Toronto and Third Party Financial Obligations
.......................................................... 4517.2
Contracting Authority Financial Obligations
..........................................................................
45
18. DESIGN AND CONSTRUCTION OBLIGATIONS
................................................................
45
18.1 Overall Responsibility
............................................................................................................
4518.2 Complete and Operational Facility
.........................................................................................
4718.3 Development of Design
..........................................................................................................
4718.4 Start-Up Meeting
....................................................................................................................
4918.5 Design Workshops
..................................................................................................................
4918.6 Clinical Functionality
.............................................................................................................
5218.7 Performance of Design Obligations
........................................................................................
5318.8 General Construction Obligations
...........................................................................................
5318.9
Substitutions............................................................................................................................
5418.10 Change in Standards
...............................................................................................................
5418.11 Works Submittals
....................................................................................................................
5418.12 Cash Allowance Items
............................................................................................................
5418.13 Community Benefits and Apprenticeship Declaration, Plan and
Annual Report ................... 5618.14 Procurement Monitoring
and Implementation Plan
................................................................
58
19. CONTRACTING AUTHORITY ACCESS AND MONITORING
......................................... 58
19.1 Contracting Authority Access During the Works Phase
......................................................... 5819.2
Increased Monitoring
..............................................................................................................
5919.3 Right to Open Up
....................................................................................................................
5919.4 No Relief from Obligations
....................................................................................................
59
20. WORKS SCHEDULE AND WORKS REPORT
......................................................................
60
20.1 Completion of Works
..............................................................................................................
6020.2 The Works Schedule
...............................................................................................................
6020.3 Changes to the Works Schedule
.............................................................................................
6220.4 Failure to Maintain Schedule
..................................................................................................
6220.4A Notification of Early Phase Completion
.................................................................................
6420.5 Notification of Early Substantial Completion
.........................................................................
6520.6 Works Report
..........................................................................................................................
65
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidentialiv
21. EQUIPMENT
...............................................................................................................................
66
21.1 Equipment Steering Committee
..............................................................................................
6621.2 Contracting Authority Equipment Responsibilities
................................................................
6721.3 Project Co Equipment Responsibilities
..................................................................................
6921.4 Additional Project Co Equipment Responsibilities
................................................................
7621.5 Minimizing Disruptions
..........................................................................................................
7621.6 Equipment Training
................................................................................................................
7621.7 Scheduling of Equipment and Existing Equipment Related
Activities .................................. 7721.8 Maintenance of
Equipment
.....................................................................................................
78
22. LEADERSHIP IN ENERGY & ENVIRONMENTAL DESIGN
............................................ 79
22.1 LEED Design and Construction Obligations
..........................................................................
7922.2 LEED Progress Reports
..........................................................................................................
7922.3 LEED Certification
.................................................................................................................
7922.4 Greenhouse Gas Credits
..........................................................................................................
7922.5 Energy Matters
........................................................................................................................
79
23. INDEPENDENT CERTIFIER
...................................................................................................
80
23.1 Appointment
...........................................................................................................................
8023.2 Role of Independent Certifier
.................................................................................................
8023.3 Changes to Terms of Appointment
.........................................................................................
8023.4 Right to Change Appointment
................................................................................................
8023.5 Cooperation
.............................................................................................................................
8023.6 Payment of Independent Certifier
...........................................................................................
8123.7
Replacement............................................................................................................................
81
24. COMMISSIONING AND
COMPLETION...............................................................................
87
24.1 Commissioning Activities
.......................................................................................................
8724.2 Final Commissioning Program
...............................................................................................
8724.3 Commencement of Project Co Commissioning
......................................................................
8824.4 Substantial Completion Certificate
.........................................................................................
8824.5 Operation and Maintenance Manuals and Warranties
............................................................ 9024.6
Hospital Commissioning
.........................................................................................................
9024.7 Countdown Notice
..................................................................................................................
9024.8 Minor Deficiencies
.................................................................................................................
9124.9 Rectification of Minor Deficiencies
........................................................................................
9224.10 Failure to Rectify Minor Deficiencies
....................................................................................
9224.11 Remaining Works Minor Deficiencies
...................................................................................
9224.12 Rectification of Remaining Works Minor Deficiencies
......................................................... 9324.13
Final Completion Countdown Notice
.....................................................................................
9324.14 Final Completion
Certificate...................................................................................................
9424.15 Effect of Certificates/Use
........................................................................................................
9524.16 Remaining Works Letter of Credit
.........................................................................................
9524.17 Transition
................................................................................................................................
9724.18 Transition Subcommittee
........................................................................................................
98
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidentialv
25. PROJECT CO SERVICE OBLIGATIONS
..............................................................................
98
25.1 Overall Responsibility
............................................................................................................
9825.2 Commencement of Services
...................................................................................................
9825.3 Coordination and No Disruption to Contracting Authority
.................................................... 9925.4 No
Closure of Existing Facilities or Facility
..........................................................................
9925.5 Equipment for Project Co Services
.........................................................................................
99
26. MAINTENANCE
.........................................................................................................................
99
26.1 Maintenance Plans
..................................................................................................................
9926.2 Revisions to Scheduled Maintenance Plan
...........................................................................
10026.3 Contracting Authority Change in Timing
.............................................................................
10126.4 Unscheduled Maintenance Work
..........................................................................................
10126.5 Emergency Maintenance Work
.............................................................................................
10126.6 Other Maintenance Work
......................................................................................................
10226.7 Plant Services
........................................................................................................................
10226.8 Performance Audits
..............................................................................................................
102
27. HUMAN
RESOURCES.............................................................................................................
103
27.1 Project Co Covenants with respect to Employment of the
Affected Employees .................. 10327.2 Project Co Covenants
with respect to Certain Terms and Conditions of Employment ........
10427.3 Transfer of Employees
..........................................................................................................
10527.4 Admittance of Personnel
.......................................................................................................
10527.5 Confirmation of Action
.........................................................................................................
10527.6 Notification of Personnel
......................................................................................................
10527.7 Finality as to Admission
.......................................................................................................
10627.8 Adherence to Policies
...........................................................................................................
10627.9 Change in Hospital Public Health Requirements Policies
.................................................... 10627.10 Staff
Competency
.................................................................................................................
10627.11 Convictions
...........................................................................................................................
10727.12 Effect of Convictions
............................................................................................................
10727.13 Notification of
Convictions...................................................................................................
10727.14 Disciplinary Action
...............................................................................................................
10727.15 Management Contact Information
........................................................................................
10827.16 Health Screening
...................................................................................................................
10827.17 Retention of Screening
Records............................................................................................
10827.18 Report on Screening
..............................................................................................................
10827.19 Health Risks
..........................................................................................................................
10927.20 Orientation Procedure
...........................................................................................................
10927.21 Labour Disruption
.................................................................................................................
10927.22 Material Changes to Terms and Conditions of Employment
................................................ 10927.23 Labour
Combination Variation
.............................................................................................
110
28. GOODS, EQUIPMENT, CONSUMABLES AND MATERIALS
......................................... 110
28.1 Standards
...............................................................................................................................
11028.2 Hazardous Substances and Materials
....................................................................................
11028.3 Change in Hospital Hazardous Materials Policies
................................................................
112
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidentialvi
29. MONITORING
..........................................................................................................................
112
29.1 Monitoring of
Performance...................................................................................................
11229.2 Failure Points
........................................................................................................................
11329.3 Warning Notices
...................................................................................................................
11329.4 Monitoring Notices
...............................................................................................................
113
30. CONTRACTING AUTHORITY’S REMEDIAL
RIGHTS................................................... 115
30.1 Exercise of Remedial Rights
.................................................................................................
11530.2 Emergency
............................................................................................................................
11730.3 Rectification
..........................................................................................................................
11730.4 Costs and Expenses
...............................................................................................................
11830.5 Reimbursement Events
.........................................................................................................
11830.6 Reimbursement if Improper Exercise of Rights
...................................................................
119
31. PAYMENT
.................................................................................................................................
119
31.1 Payments During the Construction Period
............................................................................
11931.2 Monthly Service Payments
...................................................................................................
11931.3 Payment Adjustments
...........................................................................................................
12031.4 Payment Commencement
.....................................................................................................
12031.5 Adjustments to Payment Periods
..........................................................................................
12031.6 Invoicing and Payment Arrangements
..................................................................................
12031.7 Electronic Invoicing
..............................................................................................................
12231.8 Final Payment Periods
..........................................................................................................
12231.9 Disputes
................................................................................................................................
12331.10 Payments
...............................................................................................................................
12431.11 Manner of Payment
...............................................................................................................
12431.12 Intentionally Deleted
.............................................................................................................
12431.13 Set-Off
..................................................................................................................................
12431.14 Effect of Payment
.................................................................................................................
12431.15 Audit of Performance of Project
Operations.........................................................................
12431.16 No Other Entitlement
............................................................................................................
125
32. TAXES
........................................................................................................................................
126
32.1 Taxes
.....................................................................................................................................
12632.2 Changes in Scope of Taxation
..............................................................................................
12632.3 Changes in Recoverability of Tax Credits
............................................................................
12632.4 Information and Assistance Provided by Project Co
............................................................
12732.5 Residency – Income Tax Act (Canada)
.................................................................................
12732.6 Taxes – General
....................................................................................................................
12732.7 Taxes – Indemnity
................................................................................................................
127
33. FINANCIAL MODEL
...............................................................................................................
128
33.1 Appointment of Custodian
....................................................................................................
12833.2 Delivery and Use of Financial Model
...................................................................................
128
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidentialvii
34. RECORDS, INFORMATION AND AUDIT
...........................................................................
129
34.1 Records Provisions
...............................................................................................................
12934.2 Information and General Audit Rights
.................................................................................
12934.3 Delivery of Reports to IO
.....................................................................................................
130
35. CHANGES IN LAW
..................................................................................................................
130
35.1 Performance after Change in Law
........................................................................................
13035.2 Works Change in Law
..........................................................................................................
13035.3 Relevant Change in Law
.......................................................................................................
131
36. VARIATIONS
............................................................................................................................
133
36.1 Variation Procedure
..............................................................................................................
13336.2 Innovation and Value Engineering
.......................................................................................
133
37. DELAY EVENTS
......................................................................................................................
135
37.1 Definition
..............................................................................................................................
13537.2 Consequences of a Delay Event
............................................................................................
13637.3
Mitigation..............................................................................................................................
139
38. COMPENSATION EVENTS
...................................................................................................
140
38.1 Definition
..............................................................................................................................
14038.2 Consequences of a Compensation Event
..............................................................................
14038.3
Mitigation..............................................................................................................................
14038.4 Insured Exposure
..................................................................................................................
14138.5 Delivery of Works Schedule
.................................................................................................
141
39. EXCUSING CAUSES
................................................................................................................
141
39.1 Definition
..............................................................................................................................
14139.2 Consequences of an Excusing Cause
....................................................................................
14339.3
Mitigation..............................................................................................................................
14439.4 Insured Exposure
..................................................................................................................
144
40. RELIEF EVENTS
......................................................................................................................
144
40.1 Definition
..............................................................................................................................
14440.2 Consequences of a Relief Event
...........................................................................................
14540.3 Mitigation and Process
..........................................................................................................
14640.4 Insured Exposure
..................................................................................................................
146
41. FORCE MAJEURE
...................................................................................................................
147
41.1 Definition
..............................................................................................................................
14741.2 Consequences of Force Majeure
...........................................................................................
14741.3 Mitigation and Process
..........................................................................................................
14841.4 Insured Exposure
..................................................................................................................
148
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidentialviii
41.5 Modifications
........................................................................................................................
149
42. PROJECT CO DEFAULT
........................................................................................................
149
42.1 Project Co Events of Default
................................................................................................
14942.2 Notification of Occurrence
...................................................................................................
15342.3 Right to Termination
.............................................................................................................
15342.4 Remedy Provisions
...............................................................................................................
15342.5 Replacement of Non-Performing Service Provider
..............................................................
15442.6 Contracting Authority’s Costs
..............................................................................................
15542.7 No other Rights to Terminate
...............................................................................................
155
43. CONTRACTING AUTHORITY DEFAULT
.........................................................................
156
43.1 Contracting Authority Events of Default
..............................................................................
15643.2 Project Co’s Options
.............................................................................................................
15643.3 Project Co’s Costs
.................................................................................................................
15743.4 No Other Rights to
Terminate...............................................................................................
157
44. RELIEF EVENT AND NON-DEFAULT TERMINATION
................................................. 157
44.1 Termination for Relief Event
................................................................................................
15744.2 Termination for Force Majeure
.............................................................................................
15744.3 Termination for Convenience
...............................................................................................
15744.4 Automatic Expiry on Expiry Date
........................................................................................
158
45. EFFECT OF TERMINATION
.................................................................................................
158
45.1 Termination
...........................................................................................................................
15845.2 Continued Effect – No Waiver
.............................................................................................
15845.3 Continuing Performance
.......................................................................................................
15845.4 Consequences of
Termination...............................................................................................
15845.5 Ownership of
Information.....................................................................................................
16045.6 Provision in Subcontracts
.....................................................................................................
16145.7 Transitional
Arrangements....................................................................................................
16145.8 Termination upon Aforesaid Transfer
..................................................................................
16245.9 Survival
.................................................................................................................................
162
46. COMPENSATION ON TERMINATION
...............................................................................
162
46.1 Compensation on Termination
..............................................................................................
16246.2 Full and Final Settlement
......................................................................................................
162
47. EXPIRY TRANSITION PROCEDURE
..................................................................................
163
47.1 Expiry Transition
..................................................................................................................
163
48. INTELLECTUAL PROPERTY
...............................................................................................
163
48.1 Representation and Warranty
................................................................................................
16348.2 Delivery of Project Data and Intellectual Property Rights
................................................... 163
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidentialix
48.3 Licence of Project Data and Intellectual Property Rights
..................................................... 16348.4
Jointly Developed Materials
.................................................................................................
16448.5 Maintenance of Data
.............................................................................................................
16448.6 Claims
...................................................................................................................................
16548.7 Contracting Authority Trade-Marks
.....................................................................................
16548.8 Confidential Information
......................................................................................................
16548.9 Government Use of Documents
............................................................................................
165
49. CONFIDENTIALITY / COMMUNICATIONS
.....................................................................
166
49.1 Disclosure
.............................................................................................................................
16649.2 Redaction
..............................................................................................................................
16649.3 Disclosure to Government
....................................................................................................
16749.4 Freedom of Information and Protection of Privacy Act
....................................................... 16749.5 Use
and Disclosure of Confidential Information
..................................................................
16749.6 Exceptions
.............................................................................................................................
16849.7 Survival of Confidentiality
...................................................................................................
16949.8 Communications
...................................................................................................................
169
50. PERSONAL INFORMATION
.................................................................................................
169
50.1 General
..................................................................................................................................
16950.2 Protection of Patient
Information..........................................................................................
16950.3 Survival
.................................................................................................................................
170
51. INSURANCE AND PERFORMANCE SECURITY
..............................................................
170
51.1 General Requirements
...........................................................................................................
17051.2 No Relief from Liabilities and
Obligations...........................................................................
170
52. TITLE
.........................................................................................................................................
170
52.1 Title
.......................................................................................................................................
170
53. INDEMNITIES
..........................................................................................................................
170
53.1 Project Co Indemnities to Contracting Authority
.................................................................
17053.2 Contracting Authority Indemnities to Project Co
.................................................................
17253.3 Conduct of Claims
................................................................................................................
17353.4 Mitigation – Indemnity Claims
.............................................................................................
175
54. LIMITS ON LIABILITY
..........................................................................................................
175
54.1 Indirect Losses
......................................................................................................................
17554.2 No Liability in Tort
...............................................................................................................
17554.3 Sole Remedy
.........................................................................................................................
17554.4 Maximum Liability
...............................................................................................................
17654A. Liquidated Damages
.............................................................................................................
176
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidentialx
55. DISPUTE RESOLUTION PROCEDURE
..............................................................................
177
56. ASSIGNMENT, SUBCONTRACTING AND CHANGES IN CONTROL
.......................... 177
56.1 Project Co Assignment
.........................................................................................................
17756.2 Contracting Authority Assignment
.......................................................................................
17856.3 Subcontractors
......................................................................................................................
17856.4 Changes in Ownership and Control
......................................................................................
17956.5 Contracting Authority Due Diligence
...................................................................................
18056.6 Gain
Share.............................................................................................................................
181
57. PROHIBITED ACTS
................................................................................................................
181
57.1 Definition
..............................................................................................................................
18157.2 Remedies
...............................................................................................................................
18257.3 Permitted Payments
..............................................................................................................
18357.4 Notification
...........................................................................................................................
18357.5 Replacement of Project Co Party
..........................................................................................
183
58. NOTICES
...................................................................................................................................
183
58.1 Notices to Parties
..................................................................................................................
18358.2 Notices to Representatives
....................................................................................................
18458.3 Facsimile
...............................................................................................................................
18458.4 Change of Address
................................................................................................................
18458.5 Deemed Receipt of Notices
..................................................................................................
18458.6 Service on Contracting Authority
.........................................................................................
185
59. GENERAL
..................................................................................................................................
185
59.1 Amendments
.........................................................................................................................
18559.2 Waiver
...................................................................................................................................
18559.3 Relationship Between the
Parties..........................................................................................
18559.4 General Duty to Mitigate
......................................................................................................
18659.5 Actual Knowledge
................................................................................................................
18659.6 Entire Agreement
..................................................................................................................
18659.7 No
Reliance...........................................................................................................................
18659.8 Severability
...........................................................................................................................
18759.9 Enurement
.............................................................................................................................
18759.10 Governing Law and Jurisdiction
...........................................................................................
18759.11 Cumulative Remedies
...........................................................................................................
18759.12 Further Assurance
.................................................................................................................
18759.13 Costs
.....................................................................................................................................
18759.14 Language of Agreement
........................................................................................................
18859.15 Proof of Authority
.................................................................................................................
18859.16 Counterparts
..........................................................................................................................
18859.17 Government Entities as Third Party Beneficiaries
................................................................
188
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidentialxi
SCHEDULES
Schedule 1 - Definitions and Interpretation Schedule 2 -
Completion Documents Schedule 3 - Custody Agreement Schedule 4 -
Lenders’ Direct Agreement Schedule 5 - Direct Agreements Schedule 6
- Independent Certifier Agreement Schedule 7 - Intentionally
DeletedSchedule 8 - Intentionally Deleted Schedule 9 - Key
Individuals Schedule 10 - Review Procedure Schedule 11A - Design
Quality Plan and Construction Quality Plan Schedule 11B - Service
Quality Plan Outline Schedule 12 - Works Scheduling Requirements
Schedule 13 - Project Co Proposal Extracts Schedule 14 - Outline
Commissioning Program Schedule 15 - Output Specifications Schedule
16 - Title Encumbrances Schedule 17 - Employee Transition Schedule
18 - Communications Schedule 19 - Construction Period Payments
Schedule 20 - Payment Mechanism Schedule 21 - Procurement
Monitoring and Implementation Plan Schedule 22 - Variation
Procedure Schedule 23 - Compensation on Termination Schedule 24 -
Expiry Transition Procedure Schedule 25 - Insurance and Performance
Security Requirements Schedule 26 - Record Provisions Schedule 27 -
Dispute Resolution Procedure Schedule 28 - Refinancing Schedule 29
- Remaining Works Letter of Credit Schedule 30 - Insurance Trust
Agreement Schedule 31 - Project Co Information Schedule 32 -
Financial Model Extracts Schedule 33 - Trust Account Agreement
Schedule 34 - Works Report Requirements Schedule 35 - Site Schedule
36 - Energy Matters Schedule 37 - Cooperation Agreement Schedule 38
- Reports Schedule 39 - Contractor Site Specific Safety Manual
Requirements Schedule 40 - Community Benefits and Apprenticeship
Declaration
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidential1
THIS PROJECT AGREEMENT is made as of the 8th day of August,
2018
BETWEEN:
WEST PARK HEALTHCARE CENTRE, a non-share capital corporation
incorporated under the laws of Ontario
(the “Contracting Authority”)
AND:
ELLISDON INFRASTRUCTURE WPHC GENERAL PARTNERSHIP, [REDACTED]
(“Project Co”)
WHEREAS:
A. Contracting Authority, with the assistance of IO, wishes to
redevelop its existing hospital in Toronto, Ontario.
B. Contracting Authority provides the Hospital Services at the
Existing Facilities and will provide such services at the Facility.
Project Co will provide the Project Operations, which include the
design, construction, financing and maintenance of the Facility
(the “Project”).
C. Contracting Authority and Project Co wish to enter into this
project agreement (the “Project Agreement”), which sets out the
terms and conditions upon which Project Co shall perform the
Project Operations.
D. The overriding priorities of Contracting Authority in
entering into and implementing this Project Agreement are the
health and safety of the patients and staff of the Existing
Facilities and the Facility, the patients’ healthcare needs, and
the provision of first-rate healthcare services and Project Co
recognizes and understands that the health and safety of the
patients and staff of the Existing Facilities and the Facility are,
at all times, paramount.
E. The Project will proceed as an alternative financing and
procurement project and complies with the principles set out in
MOI’s Building a Better Tomorrow: An Infrastructure Planning,
Financing and Procurement Framework for Ontario’s Public Sector
(the “IPFP Framework”).
F. The IPFP Framework establishes 5 fundamental principles which
guide the financing and procurement of public infrastructure
projects in Ontario:
1. The public interest is paramount.
2. Value for money must be demonstrable.
3. Appropriate public control/ownership must be preserved.
4. Accountability must be maintained.
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidential2
5. All processes must be fair, transparent and efficient.
G. The IPFP Framework states that, consistent with the principle
of appropriate public ownership/control, public ownership of assets
will be preserved in the hospital sector.
H. MOHLTC is responsible for the development, coordination,
maintenance, and funding of health services, including a balanced
and integrated system of hospitals, nursing homes, laboratories,
ambulances, other health facilities and providers to meet the
health needs of the people of Ontario.
I. There are a number of statutes which govern the operation and
administration of hospitals in Ontario. Under the Public Hospitals
Act (Ontario), certain actions of hospitals can only be undertaken
with the approval of the Minister of Health and Long-Term Care.
Subsection 4(3) of the Public Hospitals Act (Ontario) states that
no additional building or facilities shall be added to a hospital
until the plans therefore have been approved by the Minister. Under
subsection 4(2) of the Public Hospitals Act (Ontario), no
institution, building or other premises or place shall be operated
or used for the purposes of a hospital unless the Minister has
approved the operation and or use of the premises or place for that
purpose.
J. The Minister of Health and Long-Term Care has powers to
protect the public interest regarding matters relevant to the
quality of the management and administration of a hospital, the
proper management of the health care system in general, the
availability of financial resources for the management and delivery
of health care services, the accessibility of services in the
community where the hospital is located and the quality of care and
treatment of patients.
K. Project Co recognizes and understands that Contracting
Authority is a public hospital under the Public Hospitals Act
(Ontario) and is, therefore, subject to a highly regulated legal
and operational environment.
L. With a view to ensuring that both Parties are able to
properly and effectively discharge their respective duties,
functions and responsibilities under Applicable Law, it is the
intent that Contracting Authority and Project Co work
collaboratively, responsibly and cooperatively throughout the
Project Term.
NOW THEREFORE in consideration of the mutual covenants and
agreements of the Parties hereinafter contained and for other good
and valuable consideration, the receipt and sufficiency of which
are hereby acknowledged, the Parties covenant and agree as
follows:
1. DEFINITIONS AND INTERPRETATION
1.1 Definitions and Interpretation
(a) This Project Agreement shall be interpreted in accordance
with Schedule 1 – Definitions and Interpretation.
(b) This Project Agreement is comprised of this executed
agreement and the following documents, all of which are hereby
incorporated by reference into and form part of this Project
Agreement:
Schedule No. Description Schedule 1 - Definitions and
Interpretation
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidential3
Schedule 2 - Completion Documents Schedule 3 - Custody Agreement
Schedule 4 - Lenders’ Direct Agreement Schedule 5 - Direct
Agreements Schedule 6 - Independent Certifier Agreement Schedule 7
- Intentionally Deleted Schedule 8 - Intentionally Deleted Schedule
9 - Key Individuals Schedule 10 - Review Procedure Schedule 11A -
Design Quality Plan and Construction Quality Plan Schedule 11B -
Service Quality Plan Outline Schedule 12 - Works Scheduling
Requirements Schedule 13 - Project Co Proposal Extracts Schedule 14
- Outline Commissioning Program Schedule 15 - Output Specifications
Schedule 16 - Title Encumbrances Schedule 17 - Employee Transition
Schedule 18 - Communications Schedule 19 - Construction Period
Payments Schedule 20 - Payment Mechanism Schedule 21 - Procurement
Monitoring and Implementation Plan Schedule 22 - Variation
Procedure Schedule 23 - Compensation on Termination Schedule 24 -
Expiry Transition Procedure Schedule 25 - Insurance and Performance
Security Requirements Schedule 26 - Record Provisions Schedule 27 -
Dispute Resolution Procedure Schedule 28 - Refinancing Schedule 29
- Remaining Works Letter of Credit Schedule 30 - Insurance Trust
Agreement Schedule 31 - Project Co Information Schedule 32 -
Financial Model Extracts Schedule 33 - Trust Account Agreement
Schedule 34 - Works Report Requirements Schedule 35 - Site Schedule
36 - Energy Matters Schedule 37 - Cooperation Agreement Schedule 38
- Reports Schedule 39 - Contractor Site Specific Safety Manual
Requirements Schedule 40 - Community Benefits and Apprenticeship
Declaration
(c) The documents comprising this Project Agreement are
complementary and what is called for by any one of them shall be
interpreted as if called for by all, except in the event of
ambiguities, conflicts or inconsistencies, in which case Section
1.2 shall apply.
(d) Except for those parts of Project Co’s proposal which are
incorporated by reference into this Project Agreement by the
Project Co Proposal Extracts, on Financial Close, the Request for
Proposals and Project Co’s proposal shall be superseded entirely by
this Project Agreement and rendered null and void, and shall not be
relied upon or used by Project Co, Contracting Authority or anyone
else (including anyone pursuant to Schedule 27 – Dispute Resolution
Procedure or any arbitral body or any court) in any
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidential4
way to interpret or qualify the scope of the Project Operations,
any obligations or liabilities of Project Co, or anything else
contained in this Project Agreement.
(e) Unless it is specifically provided that a consent, approval
or satisfaction is in the sole discretion of Contracting Authority,
no consent, approval or satisfaction of Contracting Authority or
the Contracting Authority Representative shall be unreasonably
withheld or delayed.
(f) Unless it is specifically provided that a consent, approval
or satisfaction is in the sole discretion of Project Co, no
consent, approval or satisfaction of Project Co or the Project Co
Representative shall be unreasonably withheld or delayed.
1.2 Conflict of Terms
(a) In the event of ambiguities, conflicts or inconsistencies
between or among any of the provisions of this Project Agreement,
the provisions shall govern in the following order of precedence
with each taking precedence over those listed subsequently:
(i) the provisions of amendments in writing to this Project
Agreement signed by the Parties and Variation Confirmations shall
govern and take precedence only over those specific provisions of
this Project Agreement expressly amended thereby;
(ii) any provision establishing a higher standard of safety,
reliability, durability, performance or service shall take
precedence over a provision establishing a lower standard of
safety, reliability, durability, performance or service;
(iii) the body of this Project Agreement;
(iv) Schedule 1 Definitions and Interpretation;
(v) Schedule 27 Dispute Resolution Procedure;
(vi) Schedule 20 Payment Mechanism;
(vii) Schedule 15 Output Specifications;
(viii) Schedule 25 Insurance and Performance Security
Requirements;
(ix) Schedule 22 Variation Procedure;
(x) Schedule 10 Review Procedure;
(xi) Schedule 14 Outline Commissioning Program;
(xii) Schedule 11A Design Quality Plan and Construction Quality
Plan;
(xiii) Schedule 28 Refinancing;
(xiv) Schedule 23 Compensation on Termination;
(xv) Schedule 26 Record Provisions;
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidential5
(xvi) Schedule 24 Expiry Transition Procedure;
(xvii) the other Schedules in the order in which they are listed
in Section 1.1(b); and
(xviii) Schedule 13 Project Co Proposal Extracts.
(b) Subject to Section 1.2(a), if the ambiguity, conflict or
inconsistency is between a provision of general application and a
provision that applies only to a specific part of the Project
Operations, the provision that applies to the specific part of the
Project Operations shall govern for that specific part of the
Project Operations.
(c) If any ambiguity, conflict or inconsistency is not readily
resolved by the foregoing provisions of this Section 1.2, then
Project Co or Contracting Authority, upon discovery of same, shall
immediately give notice to the Contracting Authority
Representative. The Contracting Authority Representative shall,
within 10 Business Days after such notice, make a determination of
which provision governs and give notice of such determination, in
writing, to Project Co.
(d) Contracting Authority and Project Co shall comply with the
determination of the Contracting Authority Representative pursuant
to this Section 1.2 unless Contracting Authority or Project Co
disputes the decision of the Contracting Authority Representative
in which event such Dispute may be referred for resolution in
accordance with Schedule 27 – Dispute Resolution Procedure.
1.3 Conflict of Documents
(a) In the event of any ambiguity, conflict or inconsistency
between the provisions of this Project Agreement and the Lenders’
Direct Agreement, the provisions of the Lenders’ Direct Agreement
shall prevail and govern to the extent of such ambiguity, conflict
or inconsistency.
1.4 Joint and Several Liability
(a) Each of the Project Co Partners hereby acknowledges and
agrees to and in favour of Contracting Authority that the Project
Co Partners are jointly and severally liable for the due and
punctual payment of all indebtedness of, and performance and
discharge of all covenants, obligations, agreements and
undertakings (including indemnity obligations) of, Project Co under
or pursuant to this Project Agreement now or hereafter
existing.
2. COMMERCIAL CLOSE AND FINANCIAL CLOSE
2.1 Effective Date
(a) The provisions of Sections 1 to 11, 13, 15 to 23, 27, 28,
32, 34 to 36 and 48 to 59, and Schedules 1 to 3, 7, 9 to 11, 13, 16
to 19, 21, 22 and 25 to 27 will come into effect on the date of
this Project Agreement. All other provisions of this Project
Agreement will come into effect only on Financial Close. The
provisions of this Project Agreement will terminate on the
Termination Date.
2.2 Standby Letter of Credit
(a) [Intentionally Deleted]
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidential6
(b) Unless a Standby Letter of Credit is drawn by Contracting
Authority in accordance with the provisions of this Project
Agreement, Contracting Authority shall release and deliver the
Standby Letter(s) of Credit to Project Co on Financial Close.
(c) Project Co shall ensure that the Standby Letter(s) of Credit
(and any replacement therefor) is renewed prior to its expiry date
if, as at such date, Financial Close will not, or may reasonably be
expected not to, have occurred.
(d) If Project Co delivers multiple Standby Letter(s) of Credit
from multiple Letter of Credit Providers in accordance with Section
9.1(2) of the Request for Proposals, Project Co acknowledges and
agrees that:
(i) Contracting Authority may draw upon any Standby Letter of
Credit provided by any Letter of Credit Provider in any specified
rateable amount;
(ii) Contracting Authority may draw on any Standby Letter of
Credit provided by any Letter of Credit Provider in a
disproportionate amount to such Letter of Credit Providers’
contribution to security;
(iii) Contracting Authority may draw upon any Standby Letter of
Credit provided by any Letter of Credit Provider even in the event
that such Letter of Credit Provider is no longer a Project Co
Party; and
(iv) the provision of multiple Standby Letters of Credit shall
not in any way prejudice or adversely affect the rights of
Contracting Authority to draw on the Standby Letter(s) of Credit in
accordance with this Project Agreement, including in a circumstance
where the default giving rise to Contracting Authority’s right to
draw on the Standby Letter(s) of Credit is not the result of any
act or omission of the Letter of Credit Provider(s) whose Standby
Letter of Credit is drawn upon.
2.3 Financial Close
(a) No later than 30 days prior to the Financial Close Target
Date, Project Co will deliver to Contracting Authority drafts of
all documents referred to in Section 1 of Schedule 2 – Completion
Documents.
(b) On or before the Financial Close Target Date:
(i) Project Co shall deliver to Contracting Authority the
documents referred to in Section 1 of Schedule 2 – Completion
Documents; and
(ii) Contracting Authority shall deliver to Project Co the
documents referred to in Section 2 of Schedule 2 – Completion
Documents.
(c) If Project Co fails to deliver to Contracting Authority any
of the documents referred to in Section 1 of Schedule 2 –
Completion Documents by the Financial Close Target Date (other than
as a direct result of a breach by Contracting Authority of its
obligations under Section 2.3(b)(ii)) and Contracting Authority
does not waive such requirement, Contracting Authority will be
entitled to draw on the Standby Letter of Credit and to retain the
proceeds thereof as liquidated damages and may terminate this
Project Agreement in its entirety by written notice having
immediate effect. The Parties agree that such liquidated damages
are not a penalty but represent a genuine and reasonable
pre-estimate of the damages
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidential7
that Contracting Authority will suffer as a result of the
happening of the specified event and would be difficult or
impossible to quantify such damages upon the happening of the
specified event. Such payment shall constitute full and final
settlement of any and all damages that may be claimed by
Contracting Authority as a result of Project Co not achieving
Financial Close. The Parties agree that such liquidated damages
shall be payable whether or not Contracting Authority incurs or
mitigates its damages, and that Contracting Authority shall not
have any obligation to mitigate any such damages.
(d) If Contracting Authority fails to deliver to Project Co any
of the documents referred to in Section 2 of Schedule 2 –
Completion Documents by the Financial Close Target Date (other than
as a direct result of a breach by Project Co of its obligations
under Section 2.3(b)(i)) and Project Co does not waive such
requirement, Project Co will be entitled to the return of the
Standby Letter of Credit and to terminate this Project Agreement in
its entirety by written notice having immediate effect.
2.4 Disruption in Financial Markets
(a) If Financial Close cannot be achieved by the Financial Close
Target Date by reason solely of a Severe Market Disruption, subject
to Project Co’s obligation to renew the Standby Letter of Credit,
pursuant to Section 2.2, the Financial Close Target Date will be
extended until the date falling 10 Business Days (or such other
period as the Parties agree, acting reasonably) after the date on
which such Severe Market Disruption ceases.
(b) If a Severe Market Disruption exists, then, at any time
before such Severe Market Disruption ceases and prior to Financial
Close, Contracting Authority may in its sole discretion either:
(i) terminate this Project Agreement in its entirety by written
notice having immediate effect; or
(ii) direct Project Co to assign to IO and IO will assume:
(A) the Project Agreement, and all of Project Co’s right, title
and interest in the Project Data, the Intellectual Property Rights
and the Project Co Permits, Licences, Approvals and Agreements;
and
(B) those contracts between Project Co and any Project Co Party
which IO elects to be assigned.
(c) If Contracting Authority exercises its rights pursuant to
Section 2.4(b), and, provided Project Co has, if directed,
delivered the assignments provided for in 2.4(b)(ii)(A) and
2.4(b)(ii)(B) above, Project Co will be entitled to the return of
its Standby Letter of Credit and to payment of an amount equal to
the Design and Bid Fee pursuant to Section 10.3.2 of the Request
for Proposals plus [REDACTED] of such fee. Contracting Authority’s
obligation to return the Standby Letter of Credit and to pay such
fee shall be contingent on the receipt of a waiver, in form and
substance satisfactory to Contracting Authority, that such fee
represents full and final satisfaction of any obligation or
liability of Contracting Authority, IO and any other Government
Entity to Project Co and any Project Co Parties in connection with
the Project Agreement and the Request for Proposals.
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidential8
3. SCOPE OF AGREEMENT
3.1 Scope of Agreement
(a) Project Co shall undertake the Project and perform the
Project Operations in accordance with and subject to the provisions
of this Project Agreement.
(b) Project Co shall exercise its rights and perform its
obligations at its own cost and risk without recourse to
Contracting Authority, except as otherwise provided in this Project
Agreement. Project Co shall not have recourse to any Government
Entity with respect to the subject matter of this Project
Agreement.
4. BUSINESS OPPORTUNITIES
4.1 Business Opportunities
(a) Project Co acknowledges that Contracting Authority reserves
the right to all commercial and other opportunities (including, for
greater certainty, all retail and parking operations) in the
Facility and the Existing Facilities and at the Site (“Business
Opportunities”). Contracting Authority may, as set out in this
Project Agreement, grant rights in the Business Opportunities to
Project Co.
(b) To encourage the development of Business Opportunities,
Project Co may, from time to time, propose Business Opportunities
for Contracting Authority’s consideration. All such proposals shall
describe the Business Opportunity in full with the expected
financial and other advantages to both Parties. Contracting
Authority may accept any such proposal in its sole discretion and
subject to such terms and conditions as Contracting Authority may
require.
(c) Notwithstanding that Project Co has proposed a Business
Opportunity to Contracting Authority for its consideration, Project
Co acknowledges that Contracting Authority reserves the right to
proceed with such Business Opportunity or any similar Business
Opportunity with Project Co or with any third party, and may
initiate a separate procurement process for the development of any
Business Opportunity.
(d) In determining whether to accept any proposal in respect of
a Business Opportunity, Contracting Authority shall consult with
and take into account the views of MOHLTC, and shall, if so
required by MOHLTC, submit the relevant proposal to MOHLTC for
consideration.
5. REPRESENTATIONS AND WARRANTIES
5.1 Project Co Representations and Warranties
(a) Project Co represents and warrants to Contracting Authority
that as of the date of this Project Agreement:
(i) Project Co [REDACTED] and has all the requisite power and
authority to own its properties and assets, to carry on its
business as it is currently being conducted, and to enter into this
Project Agreement and to perform its obligations hereunder;
(ii) [REDACTED];
(iii) [REDACTED];
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidential9
(iv) [REDACTED];
(v) [REDACTED]
(vi) Project Co and the Project Co Parties, collectively, have
extensive experience and are knowledgeable in the design,
construction and maintenance of hospital facilities and have the
required ability, experience, skill and capacity to perform the
Project Operations in a timely and professional manner as set out
in this Project Agreement;
(vii) Project Co has the requisite power, authority and capacity
to execute and deliver and perform this Project Agreement, and to
do all acts and things, and execute, deliver and perform all other
agreements, instruments, undertakings and documents as are required
by this Project Agreement to be done, executed, delivered or
performed;
(viii) no steps or proceedings have been taken or are pending to
supersede or amend the constating documents, articles or by-laws of
Project Co in a manner that would impair or limit its ability to
perform the obligations of Project Co under this Project
Agreement;
(ix) this Project Agreement has been duly authorized, executed,
and delivered by Project Co and constitutes a legal, valid, and
binding obligation of Project Co, enforceable against Project Co in
accordance with its terms, subject only to:
(A) limitations with respect to the enforcement of remedies by
bankruptcy, insolvency, moratorium, winding-up, arrangement,
reorganization, fraudulent preference and conveyance and other laws
of general application affecting the enforcement of creditors’
rights generally; and
(B) general equitable principles and the fact that the
availability of equitable remedies is in the discretion of a court
and that a court may stay proceedings or the execution of
judgments;
(x) the execution, delivery, and performance by Project Co of
this Project Agreement does not and will not violate or conflict
with, or constitute a default under:
(A) its constating, formation or organizational documents,
including any by-laws;
(B) Applicable Law; or
(C) any covenant, contract, agreement, or understanding to which
it is a party or by which it or any of its properties or assets is
bound or affected;
(xi) no Project Co Event of Default has occurred and is
continuing;
(xii) all of the information regarding Project Co set out in
Schedule 31 – Project Co Information is true and correct in all
material respects;
(xiii) there are no actions, suits, proceedings, or
investigations pending or threatened against Project Co or, to
Project Co’s knowledge, any Project Co Party at law or in equity
before any Governmental Authority or arbitral body (whether or not
covered by insurance) that individually or in the aggregate could
result in any material adverse effect on the business, properties,
or assets, or the condition, financial or otherwise, of Project Co
or in any impairment of its ability to perform its obligations
under this Project Agreement, and Project Co has no knowledge of
any violation or default
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidential10
with respect to any order, writ, injunction, or decree of any
Governmental Authority or arbitral body that could result in any
such material adverse effect or impairment;
(xiv) Project Co has carefully reviewed the whole of this
Project Agreement, and all other documents made available to
Project Co by or on behalf of Contracting Authority, and, to
Project Co’s knowledge, nothing contained herein or therein
inhibits or prevents Project Co from completing the Works or
performing the Project Operations in accordance with this Project
Agreement in a good and safe manner so as to achieve and satisfy
the requirements of this Project Agreement;
(xv) Project Co is able to meet its obligations as they
generally become due;
(xvi) Project Co is registered under Division V of Part IX of
the Excise Tax Act (Canada) and its HST registration number is
[REDACTED];
(xvii) the Scheduled Phase Completion Date is a realistic date
and is achievable by Project Co performing the Works in accordance
with this Project Agreement;
(xviii) the Scheduled Substantial Completion Date is a realistic
date and is achievable by Project Co performing the Works in
accordance with this Project Agreement;
(xix) Project Co is not a Non-Resident;
(xx) no Restricted Person has Direct or Indirect Power or
Control over any member of the Project Co Group in relation to the
decisions, management, actions or policies of Project Co [REDACTED]
or in relation to the operation, management and ownership of the
Project;
(xxi) to the knowledge of Project Co, no Restricted Person has
directly or indirectly an Economic Interest in Project Co,
[REDACTED] or the Project;
(xxii) the COR-Certified Construction Project Co Party is in
possession of its COR Certification in good standing as required
under this Project Agreement and has the ability to maintain such
COR Certification in good standing at all times during the
performance of the Works in accordance with its terms, provisions
and conditions, or the COR-Qualified Construction Project Co
Party:
(A) is in possession of its OHSAS 18001 Accreditation which
remains in good standing and has the ability to maintain such OHSAS
18001 Accreditation in good standing at all times during the
performance of the Works until such COR-Qualified Construction
Project Co Party receives its COR Certification as required under
this Project Agreement, and
(B) has made an application to the IHSA for its COR
Certification as required under this Project Agreement;
(xxiii) the COR Certification of EllisDon Corporation extends
and applies to the Construction Contractor.
5.2 Contracting Authority Representations and Warranties
(a) Contracting Authority represents and warrants to Project Co
that as of the date of this Project Agreement:
-
West Park Healthcare Centre Project Agreement Hospital
Development Project Redacted Version
Queen’s Printer for Ontario © Copyright 2018 – This document
must not be copied or reproduced in any manner without the written
permission of Ontario Infrastructure and Lands Corporation.
Confidential11
(i) Contracting Authority is a non-share capital corporation
incorporated and validly existing under the laws of the Province of
Ontario, is in good standing with the Ministry of Government and
Consumer Services of Ontario with respect to the filing of annual
reports, and has all the requisite corporate power and authority to
own its properties and assets, to carry on its business as it is
currently being conducted, and to enter into this Project Agreement
and to perform its obligations hereunder;
(ii) Contracting Authority has the requisite power, authority
and capacity to execute, deliver and perform this Project
Agreement, and to do all acts and things, and execute, deliver and
perform all other agreements, instruments, undertakings and
documents as are required by this Project Agreement to be done,
executed, delivered or performed;
(iii) no steps or proceedings have been taken or are pending to
supersede or amend its constating documents, letters patent or
by-laws in a manner that would impair or limit its ability to
perform its obligations under this Project Agreement;
(iv) this Project Agreement has been duly authorized, executed,
and delivered by Contracting Authority and constitutes a legal,
valid, and binding obligation of Contracting Authority, enforceable
against Contracting Authority in accordance with its terms, subject
only to:
(A) limitations with respect to the enforcement of remedies by
bankruptcy, insolvency, moratorium, winding-up, arrangement,
reorganization, fraudulent preference and conveyance and other laws
of general application affecting the enforcement of creditors’
rights generally; and
(B) general equitable principles and the fa