Top Banner
H.-S. Bosch, 23/09/05 1 Max-Planck Institut für Plasmaphysik WENDELSTEIN 7-X Overview and Status of Construction H.-S. Bosch on behalf of the W7-X team Max-Planck-Institute for Plasma Physics, IPP-Euratom Association, D-17491 Greifswald Presentation at PPPL, Princeton, New Jersey, September 23, 2005 Introduction overview of W7-X device assembly of W7-X
44

WENDELSTEIN 7-X Overview and Status of Construction

Feb 14, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 1

Max-Planck Institutfür Plasmaphysik

WENDELSTEIN 7-XOverview and Status of Construction

H.-S. Bosch on behalf of the W7-X team

Max-Planck-Institute for Plasma Physics,IPP-Euratom Association, D-17491 Greifswald

Presentation at PPPL, Princeton, New Jersey, September 23, 2005

Introduction overview of W7-X device assembly of W7-X

Page 2: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 2

IPP at Greifswald

W7-X torus hall

NBI, cryogenics

assembly, ICRH

ECRH

diagnostics

Page 3: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 3

Stellarator WENDELSTEIN 7-X,the physicists view

Scientific goals of W7-X- Demonstrate the stellarator`s reactor potential - steady state operation ⇒ superconduction magnet system, cw heating

Latest step in the IPP-line of stellaratorsEURATOM approval in March 1996,new buildings in Greifswald opened in 2000

Stellaratorsonly external coils required to create the magnetic field+ no current-driven MHD+ steady state operation intrinsically available- loss of axisymmetry

Page 4: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 4

Stellarator WENDELSTEIN 7-X,the engineers version

some parametersMajor radius: 5.5 mMinor radius: 0.53 mPlasma volume 30 m3

Non-planar coils: 50Planar coils: 20Number of ports: 299Rot. transform: 5/6 - 5/4Induction on axis: < 3TStored energy: 600 MJHeating power 15 - 30 MWPulse length: 30 minEnergy turn around: 18GJ

Machine height: 4.5 mMachine diameter: 16 mMachine mass: 725 tCold mass: 425 t

Page 5: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 5

WENDELSTEIN 7-Xplasma and magnetic field

Fully optimized stellarator, J. Nührenberg et al.

Optimisation criteria small neo-classical transport good confinement of fast particles minimised bootstrap current good MHD stability good finite β-equilibria feasible modular coils

Page 6: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 6

WENDELSTEIN 7-Xin-vessel components (divertor)

10 separate divertor units 2 in each of the 5 modules heat flux not uniform

KiP project, IPP Garching

Page 7: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 7

WENDELSTEIN 7-Xprinciple

5.2 5.6 6.0 6.40

0.5

1.0Targets

Baffles

major radius R/m

Z/m Pump chamberintrinsicislands

horizontal target

vert. target

middle part(clamped tiles)

high iota

low iota

standard case

wetted areas (β = 0)

Page 8: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 8

WENDELSTEIN 7-Xin-vessel components (divertor)

target elements (10 MW/m2) baffles (1.0 MW/m2) first wall B4C (0.2 MW/m2) control coils cryo pumps Instrumentation and diagnostics about 1 Million parts

Page 9: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 9

WENDELSTEIN 7-Xdivertor module

10 MW/m2

10 MW/m21 MW/m2

parallel water-cooling through ports

Target Baffle• Max. P/A 10 MW/m2 1 MW/m2

• Total area 19 m2 5.6 m2

• Target modules 100 20• Target elements 890 240

Page 10: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 10

WENDELSTEIN 7-XDesign of target and baffle elements

Cross section

20

1010

50

52-57

Graphite

Papyex® interlayer

CuCrZr heat sink

1 MW/m1 MW/m22 loaded target element loaded target elementDesign (similar to baffle and wall protection)Heat sink CuCrZrPlasma facing material GraphiteJoining CFC-Heat sink clampedInterlayerCFC-Heat sink Papyex®Cooling tube brazed stainless steel

10 MW/m10 MW/m22 loaded (HHF) target element loaded (HHF) target elementDesignHeat sink CuCrZrPlasma facing material CFC Sepcarb® NB31Joining CFC-Heat sink AMC® / EBW or HIPInterlayer CFC-Heat sink pure CuCooling tube swirl

8

≥ 3

33

19

CFC

AMC® Cu

CuCrZrØ 9.5

4.5 ≥ 3

50 - 61.5

Page 11: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 11

WENDELSTEIN 7-XPrototypes of target elements and wall protection panels

Page 12: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 12

WENDELSTEIN 7-Xplasma vessel and thermal shield

volume 110 m3

surface 200 m2

mass 33 t + 15 t vacuum < 10-8 mbar baking up to 150o C tolerances < ± 2 mm

Deggendorfer Werft, Germany

Page 13: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 13

W 7-X Vacuum Vessel

Page 14: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 14

W 7-X Vacuum Vessel

Plasma vessel with cooling pipes(MAN DWE)

Page 15: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 15

W 7-X Thermal Insulation

Multi-Layer Insulation 20 layers of crinkled Kapton foil Al-coating for reflection

Thermal shield glass fibre (robust, small tolerances) to be Al-coated He-cooled (gas)

Page 16: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 16

W 7-X Vacuum Vessel and Thermal Insulation

Glass fibre panel with MLI Al-coated Cu-braids for connection to He-cooling pipe

Thermal shield (right) above Multi-Layer Insulation (middle) on vacuum vessel with water cooling pipes (left)

Page 17: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 17

W 7-X Vacuum Vessel and Thermal Insulation

Page 18: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 18

WENDELSTEIN 7-XMagnet system

magn. field on plasma axis 2.5 T (< 3T) magn. field at coil 6.8 T magnetic energy 600 MJ NbTi superconductor (>3.4 K) 50 non-planar coils (5 types) 20 planar coils (2 types)

BNN, G / Ansaldo, I / Tesla, GB

Page 19: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 19

WENDELSTEIN 7-X magnets superconductor

StrandNi and Cu

0,58

cabling

Cable-in-Conduit (Coextrusion)

243 single strands (3 x 3 x 3 x 3)

In up to 17.6 kA

Page 20: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 20

WENDELSTEIN 7-X non-planar coilswindings and casings

cast casing after tempering(Österby, Sweden)

Winding of a coil(ABB, Augsburg)

Page 21: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 21

WENDELSTEIN 7-X non-planar coilscoil assembly

Winding pack and casing

Overview ofProduction hall

(BNN, Zeitz)

Page 22: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 22

WENDELSTEIN 7-X non-planar coilsaccuracy of winding packs

0

0,5

1

1,5

2

2,5

3

3,510

11

20

21

30

31

40

41

50

51

12

19

22

29

42

52

59

13

18

23

28

43

53

58

14

17

24

27

44

47

54

57

15

16

25

26

35

36

45

46

55

56

Coil AAB #

mm

Type 1Type 2

Type 3

Type 4

Type 5

Average Deviationsof

Non-planar Coils

to CAD-data

To average

High accuracy of the field required: ΔB/B00 < 2⋅10-4

Page 23: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 23

WENDELSTEIN 7-X non-planar coilsthe first coil, AAB18

99% of superconductor produced 43 out of 50 winding packs finished all 50 casings cast, 44 casings finished 27 coils embedded 7 coils delivered (now about 2 per month) 3 coils tested at 4 K 2 coils assembled

Page 24: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 24

WENDELSTEIN 7-X non-planar coilsPaschen tests

critical scenario: air influx into outer vessel causes pressure increase and quenching of a coil. During a quench, high voltages arise – at increased pressure Therefore all coils are tested under Paschen conditions (between 0.001 and 100 mbar) with 9 kV This has also proven to be a good procedure to verify a good insulation.

Page 25: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 25

W 7-X planar Coils

Planar Coil(Tesla, UK)

same superconductor, supply finished bolted casings, presently being reinforced with 300 shear pins per coil all winding packs finished 8 coils embedded 1 coil delivered (now about 1 per month) 1 coil tested at 4 K

Page 26: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 26

CEA Saclay, FranceCoil test

2 cryostats handle 2 coils each full current tests at 5 K quench test to check margin about 2 coils per month facility running routinely

Page 27: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 27

W 7-X bus-bar System

Manufactured by the Research Centre Jülich (FZJ, Germany) Superconducting bus-bar system

between coils and between coils and power supplies

bifilar winding to avoid error fields design and qualification almost finished, fabrication will start soon

Page 28: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 28

WENDELSTEIN 7-Xcentral support structure and support elements

mass 71 t

Ensa, Spain

Page 29: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 29

W 7-X support structure

Welded construction in 10 half-modules, supports the whole magnets system final machining before assembly garantues exact shape structural calulations of the complete system important a reinforcement of the central ring is presently performed first segment to be delivered early in 2006

Page 30: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 30

W 7-X support structure

Central Supports long extensions for coil fixation large forces and moments a bolted solution was found

The coils are fixed to the central support structure byCentral Support Elements (CSE) and interlinked byNarrow Support Elements (NSE)Lateral Support Elements (LSE)

Page 31: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 31

W 7-X support elements

Narrow Supports on inner side sliding connection forces up to 1.5 MN contact must allow sliding (<5 mm) and tilting (<1o). Al-bronce pad with MoS2 layer

Lateral Supports on outer side Rigid (bolted/welded) connection

Page 32: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 32

W 7-X Narrow Support Elementsdesign principle

Pad framestainless steel

sliding padAl-bronce

slidingsurface

Rz 0.6

Page 33: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 33

W 7-X Planar Support Elementsdesign principle

Bolted Supportwith Pad frame

sainless steel

sliding padAl-bronce

sliding surfaceon planar coil

Rz 0.6

Page 34: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 34

WENDELSTEIN 7-Xouter vessel and ports

DWE, Germany

volume 525 m3

surface 480 m2

mass 170 t vacuum < 10-5 mbar openings ~1200 number of ports 299

Romabau,Switzerland

ROMABAU

Page 35: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 35

WENDELSTEIN 7-Xouter vessel

Laser cutting in a half shell(DWE, G)

domes and ports 10 module half-shells welded 4 half-shells have been milled 2 half-shells equipped with about 60% of the domes/flanges first module to be delivered by the end of 2005 last module to be delivered in July 2007

Page 36: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 36

WENDELSTEIN 7-Xports

299 ports, 190 for diagnostics, 19 for heating, 20 for pumping and 70 for divertor supply 226 delivered fixed to both vessels, flexible mebranes in between final delivery in March 2006

Supply port(Romabau, CH)

Page 37: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 37

WENDELSTEIN 7-X constructionPre-assembly phase – mounting of 5 magnet modules

Mounting stand Iamagnet

half-module

Mounting stand Ibflip-symmetric

magnethalf-module

Mounting stand IImagnetmodule Experimental hall

(final assembly)

Metrology centre

Page 38: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 38

WENDELSTEIN 7-X constructionFinal assembly phase – torus assembly

5 x 2 half-shellsof the outer vessel with

thermal insulation, shield

299 ports with thermal insulation

Periphery (cooling, electric, auxiliary supplies)

W 7-X – basic machine with heatingsystems and diagnostics

Machine base , in-vessel components, instrumentation, current feed-through, joints, …

5 magnetmodules

Page 39: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 39

WENDELSTEIN 7-X constructionStart of assembly, 7 April 2005

Page 40: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 40

WENDELSTEIN 7-X constructionSimulation of coil threading

Page 41: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 41

WENDELSTEIN 7-X constructionThreading trial of first planar coil, July 2005

Page 42: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 42

W 7-X Project ScheduleStatus of 4/05

1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

Magnets Non-plana coils

Planar coils

Coil tests

Support structure

Power Supplies

Cryostat Plasma vessel

Outer vessel

Ports

Thermal Insulation

In-vessel components

Assembly 1. module

2. module

3. module

4. module

5. module

in-vessel comp.

diagnostics

Commissioning START COMMISSIONING

Outer vacuum Design by IPP

Cooling magnets Preparation of fabrication in industry

inner vacuum Fabrication in industry

Magnetic fields IPP-assembly and commissioning

START PLASMA OPERATION

2009 20102005 2006 2007 20082001

2011 201220042000 2002 2003

Page 43: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 43

IPP branch institute Greifswald

Page 44: WENDELSTEIN 7-X Overview and Status of Construction

H.-S. Bosch, 23/09/05 44

WENDELSTEIN 7-X,Organigram, 9/05

Ressort W7-XT. KlingerR. Haange

ProjectCoordination

H.-S. Bosch

Basic Device

M. Wanner

SystemEngineeringM. GasparottoD. Hartmann

Assembly

L. Wegener

Physics

F. Wagner

Project Control

A. Lorenz

SystemCoordination

R. Brakel

QualityManagement

J.-H. Feist

Documentation

J. Maier

Power Supplies

T. Rummel

Cryostat

A. Cardella

In-VesselComponents

B. Streibl*

Cryogenics

F. Schauer

VacuumTechnology

H. Grote

DesignOffice

J. Tretter

ElektromagneticCalculationsJ. Kißlinger*

DesignEngineering

V. By kov

SystemIntegrationC. Damiani

On SiteCoordination

S. Gojdka

DeviceAssembly

K.-H. Oelgemöller

Periphery

R. Krampitz

AssemblyTechnology

F. Hurd

DataAquisitionG. Kühner

Diagnostics

H.-J. Hartf uß

ECRH

V. Erckmann

ICRH

D. Hartmann

NBI

E. Speth*

Device Control

J. Schacht

Magnet Systems

C. Sborchia

* in Garching