Top Banner
D rilling E ngineering 1 Course 3 rd Ed. , 3 rd Experience
38
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 2: WELL COSTING

1. time estimatesA. Example of time-depth curve

2. Elements Of Well Costing3. Risk Assessment In Drilling Cost Calculations4. Drilling Contracting Strategies

Page 3: WELL COSTING
Page 4: WELL COSTING

Authorization For Expenditureelements which comprise the well cost: rig, casing, people, drilling equipment etc.

The final sheet summarizing the well cost is usually described as the AFE: “Authorization For Expenditure”. The AFE is the budget for the well. Once the AFE is prepared, it should then be approved and

signed by a senior manager from the operator.

The AFE sheet would also contain: project description, summary and phasing of expenditure,

partners shares and well cost breakdown. Details of the well will be attached to the AFE sheet as a form

of technical justification.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 4

Page 5: WELL COSTING

FACTORS AFFECTING WELL COST

Well costs for a single well depend on:Geographical location:

land or offshore, countryType of well:

exploration or development, HPHT or sour gas well

DrillabilityHole depth Well target(s)

Profile vertical/ horizontal/

multilateralSubsurface problemsRig costs:

land rig, jack-up, semi-submersible or drillship and rating of rig

Completion type Knowledge of the area:

wildcat, exploration or development

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 5

Page 6: WELL COSTING

time spent on a well

The time spent on a well consists of:Drilling times spent on making hole, including

circulation, wiper trips and tripping, directional work, geological sidetrack and hole opening.Flat times spent on running and cementing casing,

making up BOPS and wellheads.Testing and completion time.Formation evaluation time including coring, logging etc.Rig up and rig down of rig.Non-productive time.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 6

Page 7: WELL COSTING

time required to drill the well Before an AFE can be prepared,

an accurate “estimate” of the time required to drill the well must be prepared. The time estimate should consider:ROP in offset wells.

From this the total drilling time for each section may be determined.

Flat times for running and cementing casingFlat times for nippling up/down BOPs and nippling up

wellheadsCirculation times.BHA make up times.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 7

Page 8: WELL COSTING

DETAILED TIME ESTIMATE

Detailed time estimates can be prepared for each hole section by considering the individual operations involved. This exercise requires experience on part of the engineer

and also detailed knowledge of previous drilling experience in the area.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 8

Page 9: WELL COSTING

Detailed time estimate for 30” conductor

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 9

Page 10: WELL COSTING
Page 11: WELL COSTING

Calculation of time -depth curve

Assume the following well design for Well Pak-1:36” Hole / 30" Conductor 50 m BRT (below rotary table)26” Hole / 20" Casing 595 m BRT17.5”Hole / 13.375" Casing 1421 m BRT12.25” / 9.625" Casing 2334 m BRT8.5” Hole / 7" Casing 3620 m BRTTotal Depth 3620 m BRT

From three offset wells, the following data was established for average ROP for each hole section:36” Hole 5.5 m/hr26” Hole 5.5 m/hr17.5”Hole 7.9 m/hr12.25” 4.6 m/hr8.5” Hole 2.5 m/hr

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 11

Page 12: WELL COSTING

Calculation of time -depth curve (Cont.)

The expected flat times for this well are :

Calculate the total drilling time and plot the depth-time curve.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 12

Page 13: WELL COSTING

Calculations of planned drilling times

Solution: Example 17.1: Calculation of time -depth curve,

WEC PGO: 752

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 13

Page 14: WELL COSTING

Time-depth calculations

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 14

Page 15: WELL COSTING

Time-depth curve

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 15

Page 16: WELL COSTING
Page 17: WELL COSTING

ELEMENTS OF WELL COSTING

There are three main elements of the well cost. No matter what service or product is used, it will fall under one of the following three cost elements, namely:Rig costsTangiblesServices

For offshore wells there are other costs which must be included:Supply boatsStand-by boatsHelicopters

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 17

Page 18: WELL COSTING

RIG COSTSAs the name implies,

rig costs refer to the cost of hiring the drilling rig and its associated equipment. This cost can be up to

70% of well cost, especially for semi-submersible rigs or drilling ships.Rig cost depends entirely

on the rig rate per day, usually expressed as

$/day.Rig rate depends on:Type of rigMarket conditionsLength of contractDays on wellMobilization/

Demobilization of rig and equipmentSupervisionAdditional rig charges

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 18

Page 19: WELL COSTING

TANGIBLES

Tangibles refer to the products used on the well. These include:Casing

For an example: length of casing and selecting the appropriate casing grades/weights for each hole section

Tubing/ completion equipment

Wellhead/accessoriesBitsCoreheadsCement productsMud productsSolids control

consumablesFuel and lubesOther materials and

supplies

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 19

Page 20: WELL COSTING

SERVICESThis group of costs refers

to any service required on the well. Services include:CommunicationsRig positioning

usually required in offshore operations

Logging (wireline) both open & cased hole

logsMWD/ LWDDownhole MotorsSolids Control EquipmentMud EngineeringDirectional Engineering

Surveying determination of

hole angle and azimuth.includes the cost of single

shots, magnetic multi-shots (MMS) and gyros

CementingMud LoggingFishing

only included if experience in the area dictates that fishing may be required in some parts of the hole

Downhole tools including jars, shock subs

Casing services

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 20

Page 21: WELL COSTING

NON PRODUCTIVE TIME (NPT)The time required for any routine or abnormal

operation which is carried out as a result of a failure is defined as Non Productive Time (NPT)Non-Productive Time (NPT) in drilling operations

currently account for 20% of total drilling time. the NPT is calculated as the time

from when the problem occurred to the time when operations are back to prior to the problem occurring. The NPT time includes normal operations

such as POH, RIH, circulating etc.

standby time Waiting on weather or waiting on orders, people or

equipment is not NPT. This is standby time.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 21

Page 22: WELL COSTING

CLASSIFICATION OF NPTRig equipment (Down time due to: Mud

pumps, generators, shakers, rotary table, top drive/Kelly, hoist, drilling line, gauges, compressors and anchors.Note that within the rig

contract a fixed time is allowed for rig repairs/ maintenance. The NPT rig time should be the time recorded above the agreed fixed repair time).

Surface EquipmentDownhole EquipmentDrillstring Equipment

Logging equipmentStuckpipe and Fishing of

BHA equipmentCasing Hardware and

Cementing EquipmentFluidsHole problemsWell ControlTesting and Completion

NPT

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 22

Page 23: WELL COSTING
Page 24: WELL COSTING

two major elements of well cost estimatesit is essential that cost

estimates are made realistic, as low as possible and produced in a consistent manner. These criteria are

achieved through the application of risk assessment.

Well cost estimates are made up of two major elements:Time dependent costs

Rig costs and services are greatly impacted by the time estimate.

Tangible costsTangible costs can be

estimated at the budgetary stage (before a detailed well plan is made) or at the AFE stage after the detailed well plan is made.

The risk involved in estimating tangibles is usually small.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 24

Page 25: WELL COSTING

levels of risksRisk assessment is defined in terms of the

probability of meeting a given target. There are three levels of risks:P10 (only a 10% chance of being achieved)This is a highly optimistic estimate which can only be

achieved under exceptional circumstances.As there is no exact method for estimating P10, it is now

customary to base P10 value on the best possible performance on any operation on any well in the area.the total P10 value for a given section will be the best

individual values from several wells for all operations required to drill, case and cement the given hole section.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 25

Page 26: WELL COSTING

levels of risks (Cont.)

P50This is the key figure in most well cost estimates. This estimate will be based on known information

derived from offset data.

P90This is an estimate of well cost which is likely to be met

90% of the time and that well costs can not be exceeded except under exceptional cases. This estimate was widely used in the oil industry before

accurate cost estimating was introduced in the early 1990’s.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 26

Page 27: WELL COSTING

COST REDUCTIONThere are two elements of costs which must be

controlled:Capital Expenditure (Capex): This includes the cost of finding and developing an

oil/gas field. The cost of drilling operations is the major cost element

and must be kept to an acceptable value.Operating Cost (OPEX): This includes the actual cost of production: cost of

maintaining the platform, wells, pipelines etc. We will not be concerned with these costs as they are

part of production operations.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 27

Page 28: WELL COSTING

Price of oil productionjudging a minimum

price per barrel of oil (2002): In the North Sea, it is accepted

that the principle of 1/3/3 results in a profitable operation. $1 for finding,

$3 for developing and $3 for production.

combined cost of $7 per barrel In the Middle East, this

combined cost can be as low as $2 for some giant fields.

In general the more remote the area the more expensive is the final cost of barrel of

oil. This is particularly true for

deep waters in hostile environments.

The following is a list of measures to reduce costs:Technical innovationProductivity improvement:

e.g. faster drilling operations Increased operational

effectiveness Incentive contracts

(sharing gains and pains)Less people

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 28

Page 29: WELL COSTING
Page 30: WELL COSTING

types of contractsThere are basically four types of contracts which are

currently used in the oil industry:ConventionalIntegrated Services (IS)Integrated Project Management (IPM)Turn Key

The type of drilling contract used can mean the difference between an efficient and a less efficient operation. Indeed, going for one type, say turn key, can mean that the

operator has no control over the operation whatsoever and has no means of building knowledge for future operations.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 30

Page 31: WELL COSTING

CONVENTIONAL CONTRACTIn this type of contract, the E&P company does every thing using

its own staff or contractors. This is the most involved type of contract and can mean handling up to 100 contracts per well. the operator has total control over the operation and carries full risk. The contractor has no risk and it could be argued that

the contractor has no incentive in speeding up the operation.

This type of contract has the advantage that lessons learnt during drilling operations are kept within the company

and used to improve future operations. Nowadays, only large operators opt for this type of contract.A variation of the above contract is to include an incentive clause

for completing operations early or if a certain depth is reached within an agreed time scale. The contractor will be paid a certain percentage of the savings made if

operations are completed ahead of the planned agreed drilling time.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 31

Page 32: WELL COSTING

INTEGRATED SERVICES (IS)

In this type of contract, major services are integrated under two or three main contracts. These contracts are then given to lead contractors who,

in turn, would subcontract all or parts of the contract to other subcontractor. The lead contractor hold total responsibility for his

contract and is free to choose its subcontractors.

The operator still holds major contracts such as rig, wellheads and casing. Also the operator appoints one of its staff to act as a

coordinator for the drilling operation.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 32

Page 33: WELL COSTING

INTEGRATED PROJECT MANAGEMENT (IPM)In this type of contract, a main contractor is chosen. This contractor is the Integrated Project Management (IPM)

contractor. The contractor is responsible for 20-30 service companies.

• Service companies may be responsible for other service companies.

The drilling operation will be controlled by a representative from the IPM contractor.The operator may hold one or two major contracts.It is one of the worst kind of contracts for the operator

because:There is virtually no learning for the operator. The incentive contract is built on a time-depth curve

developed and based on the contractor’s experience. Use of better equipment and personnel may beat the IPM contractor’s time-curve.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 33

Page 34: WELL COSTING

TURN KEY CONTRACTThis is the easiest of all the above contracts. The operator chooses a contractor.

The contractors submits a lump sum for drilling a well: • from spud to finish with operator virtually not involved.

The contractor carries all risks if the well comes behind time and also gains all benefits if he should drill the well faster.

Contractors only opt for this type of contract if they know the area extremely well or

during times of reduced activities. The operator opts for this type of contract if he has a limited budget or

has no knowledge of drilling in the area.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 34

Page 35: WELL COSTING

CURRENT AND FUTURE TRENDS IN DRILLING CONTRACTS There are two new development in drilling and

production contracts:Production Sharing Agreement

It stipulates that the contractor will be paid a certain percentage of the produced fluids (oil or gas) in return for the services of the contractor in drilling and producing the wells.

• The agreement may be time-dependent running for a fixed number of years or may include an initial payment for the contractor in addition to a percentage of the production.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 35

Page 36: WELL COSTING

CURRENT AND FUTURE TRENDS IN DRILLING CONTRACTS (Cont.)Capital Return Agreement Plus Agreed Production

It stipulates that the contractor will develop a field using his own finance. In return, the operator (or national oil company) will pay the contractor all his capital expenditure plus an agreed percentage of the production.

• In Iran where this type of contract is used, the agreed production is limited to a fixed number of years. The ownership of the field and its facilities always remain with the operator.

These new types of contracts were initially initiated in some Middle Eastern countries attempting to draw western investment. These contracts are still developing in nature and have

now been used by a number of third world countries.

Fall 14 H. AlamiNia Drilling Engineering 1 Course (3rd Ed.) 36

Page 37: WELL COSTING

1. (WEC) Rabia, Hussain. Well Engineering & Construction. Entrac Consulting Limited, 2002.Chapter 17

Page 38: WELL COSTING