WEEKLY REPORT St. Philip’s College THCA August 17—23rd This week activities: Next week activities: SPC THCA Building: Continue with punch list levels 1-4. Continue with inspections and closing permits. Continue installing OFOI/OFCI items. Installed gate at CPS gas meter screen wall. Completed alcove for the dryer/washer. Continue sealing concrete floors. Finish installing grass and rocks. Owner’s training/demonstration — Elevator Click here for drone footage! SPC THCA Building: Continue with punch list levels 1-4. Continue with inspections and closing permits. Fire final second half 08/26. Continue installing OFOI/OFCI items. Paint gate at CPS gas meter screen wall. Exterior building plaque delivery. Finish installing border tile in all restrooms. Owner’s training — Landscape Irrigation
3

WEEKLY REPORT...• Owner’s training — Landscape Irrigation . West Elevation Overview East Elevation Overview . THCA West Elevation Gas Meter Gate Installation Lecture Hall LVT

Oct 07, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: WEEKLY REPORT...• Owner’s training — Landscape Irrigation . West Elevation Overview East Elevation Overview . THCA West Elevation Gas Meter Gate Installation Lecture Hall LVT

WEEKLY REPORT St. Philip’s College THCA

August 17—23rd

This week activities: Next week activities:

• SPC THCA Building:

• Continue with punch list levels 1-4.

• Continue with inspections and closing permits.

• Continue installing OFOI/OFCI items.

• Installed gate at CPS gas meter screen wall.

• Completed alcove for the dryer/washer.

• Continue sealing concrete floors.

• Finish installing grass and rocks.

• Owner’s training/demonstration — Elevator

Click here for drone footage!

SPC THCA Building:

• Continue with punch list levels 1-4.

• Continue with inspections and closing permits. Fire final second half 08/26.

• Continue installing OFOI/OFCI items.

• Paint gate at CPS gas meter screen wall.

• Exterior building plaque delivery.

• Finish installing border tile in all restrooms.

• Owner’s training — Landscape Irrigation

Page 2: WEEKLY REPORT...• Owner’s training — Landscape Irrigation . West Elevation Overview East Elevation Overview . THCA West Elevation Gas Meter Gate Installation Lecture Hall LVT

West Elevation Overview

East Elevation Overview

Page 3: WEEKLY REPORT...• Owner’s training — Landscape Irrigation . West Elevation Overview East Elevation Overview . THCA West Elevation Gas Meter Gate Installation Lecture Hall LVT

THCA West Elevation

Gas Meter Gate Installation Lecture Hall LVT Flooring