WEEKLY REPORT St. Philip’s College THCA August 17—23rd This week activities: Next week activities: • SPC THCA Building: • Continue with punch list levels 1-4. • Continue with inspections and closing permits. • Continue installing OFOI/OFCI items. • Installed gate at CPS gas meter screen wall. • Completed alcove for the dryer/washer. • Continue sealing concrete floors. • Finish installing grass and rocks. • Owner’s training/demonstration — Elevator Click here for drone footage! SPC THCA Building: • Continue with punch list levels 1-4. • Continue with inspections and closing permits. Fire final second half 08/26. • Continue installing OFOI/OFCI items. • Paint gate at CPS gas meter screen wall. • Exterior building plaque delivery. • Finish installing border tile in all restrooms. • Owner’s training — Landscape Irrigation