Estimating costs: developing an approximation or estimate of the costs of the resources needed to complete a project Determining the budget: allocating the overall cost estimate to individual work items to establish a baseline for measuring performance Controlling costs: controlling changes to the project budget Information Technology Project Management, Sixth Edition 1
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Estimating costs: developing an approximation or estimate of the costs of the resources needed to complete a project
Determining the budget: allocating the overall cost estimate to individual work items to establish a baseline for measuring performance
Controlling costs: controlling changes to the project budget
Information Technology Project Management, Sixth Edition 1
Project cost control includes:◦ Monitoring cost performance◦ Ensuring that only appropriate project changes
are included in a revised cost baseline◦ Informing project stakeholders of authorized
changes to the project that will affect costs Many organizations around the globe have
problems with cost control
Information Technology Project Management, Sixth Edition 2
Track actual cost by establishing a system to collect data on funds actually expended.
Periodically assign a portion of the total committed cost to actual cost.
Cumulative actual cost (CAC) should be calculated.
Total actual and committed cost by work package for comparison to the cumulative budgeted cost (CBC).
Earned value is the value of the work actually performed.
Determine earned value by collecting data on the percent complete for each work package.
Convert this percentage to a dollar amount by multiplying the Total Budgeted Cost (TBC) of the work package by the percent complete.
◦ FCAC = CAC + Re-estimate of remaining work to be performed
EVM is a project performance measurement technique that integrates scope, time, and cost data
Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals
You must enter actual information periodically to use EVM
More and more organizations around the world are using EVM to help control project costs
Information Technology Project Management, Sixth Edition 9
The planned value (PV), formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period
Actual cost (AC), formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period
The earned value (EV), formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed
EV is based on the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date
Information Technology Project Management, Sixth Edition 10
Rate of performance (RP) is the ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity
Brenda Taylor, Senior Project Manager in South Africa, suggests this term and approach for estimating earned value
For example, suppose the server installation was halfway completed by the end of week 1: the rate of performance would be 50% because by the end of week 1, the planned schedule reflects that the task should be 100 percent complete and only 50 percent of that work has been completedInformation Technology Project
Management, Sixth Edition 11
Information Technology Project Management, Sixth Edition 12
Information Technology Project Management, Sixth Edition 13
Negative numbers for cost and schedule variance indicate problems in those areas
CPI and SPI less than 100% indicate problems Problems mean the project is costing more than
planned (over budget) or taking longer than planned (behind schedule)
The CPI can be used to calculate the estimate at completion (EAC), an estimate of what it will cost to complete the project based on performance to date; the budget at completion (BAC) is the original total budget for the project
Information Technology Project Management, Sixth Edition 14
Information Technology Project Management, Sixth Edition 15
Performance Assessment ◦Purpose: determine current status of
project with respect to schedule and budget
Earned value method◦Combine % complete, schedule, and cost
information to assess current status of project
Total Expenditure Budget to date
A 1000 1000B 2000 2050C 1000 250
4000 3300
Earned Value Concept (EV)Status Date
100%
50%
75%
A
C
B
How well is this project doing?
Example, project with three tasks, A, B, and C
◦ Task A is on schedule, on budget
◦ Task B is behind schedule, under budget
◦ Task C is ahead of schedule, under budget
How well is the project doing?
Earned Value Concept (EV)Status Date
100%
50%
75%
A
C
B
(a) Total (c) Percent (a) x (c)= (d) Percent (a) x (d)= Budget (b) AC Scheduled PV Completed EV
A 1000 1000 100 1000 100 1000
B 2000 2050 100 2000 50 1000
C 1000 250 50 500 75 750
4000 3300 3500 2750
Definitions
◦ PV = planned value (also called BCWS: budgeted cost of work scheduled)
◦ AC = actual cost (or ACWP: actual cost of work performed)
◦ EV= earned value (or BCWP: budgeted cost of work performed)
(a) x (d)=
Total (c) Percent (a) x (c)= (d) Percent (EV) Budget (b) ACWP Scheduled BCWS Complete BCWP
A 1000 1000 100 1000 100 1000
B 2000 2050 100 2000 50 1000
C 1000 250 50 500 75 750
4000 3300 3500 2750
Earned Value Concept (EV)Status Date
100%
50%
75%
A
C
B
Budget AC PV EV 4000 3300 3500 2750
• Since EV < PV, project is behind schedule in terms of value of work (ignores critical path)• Since AC > EV project is over budget in terms of value of work completed
Second example◦ Assess not only current state of the project but
also the project’s likely completion cost.
Definitions
◦ CPI= cost performance index= EV/AC
◦ ETC= estimated cost to complete project
= (BAC - EV)/CPI
BAC = budgeted cost at completion
◦ EAC= estimated cost of project at completion
= AC + ETC
Budget
%
Scheduled
PV %
Complete
EV
AC
A A 220 100 220 100 220 240
B B 190 100 190 100 190 180
C C 250 100 250 50 125 150
D D 90
100 90 100 90 110
E E 350 100 350 50 175 190
F F 400 50 200 100 400 380
G G 250 0 0 0 0 0
H H 140 0 0 0 0 0
I I 240 0 0 0 0 0
1 2 3 4
5 6 7 weeks 2,130 1,300 1,200 1,250
Second Example
Status summary analysis, end of week 4:
1. Project Cost to date $1,250
2. Value of work completed, EV = $1,200
3. Value of work remaining,
$2,130 – $ 1,200 = $930
3. CPI = 1,200/1,250 = 0.96
4. Likely cost to complete project
930/0.96 = $969
Second Example (cont’d) Likely project cost at completion