    Project management plans

  • 8/6/2019 Week-3- Project Management Plans

    4/87

    WhyWhat

    How

    WhenWho

  • 8/6/2019 Week-3- Project Management Plans

    5/87

    WhyWhat

    How

    WhenWho

    Why is this project happening?

    Why now?

    Why us?

  • 8/6/2019 Week-3- Project Management Plans

    6/87

    WhyWhat

    How

    WhenWho

    What solution needs to be put in

    place to achieve the goals?

    What work needs to happen to build

    the solution?

  • 8/6/2019 Week-3- Project Management Plans

    7/87

    WhyWhat

    How

    WhenWho

    How do we get this solution in place?

    How do we know when were done?

  • 8/6/2019 Week-3- Project Management Plans

    8/87

    WhyWhat

    How

    WhenWho

    When do work activities happen?

    What do we need to do first?

    Whats last?

  • 8/6/2019 Week-3- Project Management Plans

    9/87

    WhyWhat

    How

    WhenWho

    Who do we need to deliver thisproject successfully?

  • 8/6/2019 Week-3- Project Management Plans

    10/87

    And what will it cost?

    $

  • 8/6/2019 Week-3- Project Management Plans

    11/87

    Course objectives

    Implement IT project planning andselection techniques

    Appreciate the importance of projectportfolio management

  • 8/6/2019 Week-3- Project Management Plans

    12/87

    The project management plan

    Benefits of planning

    What to consider in your plan

    Guidelines

    Reviewing a plan

  • 8/6/2019 Week-3- Project Management Plans

    13/87

  • 8/6/2019 Week-3- Project Management Plans

    14/87

    Plans are useless.

    Planning isindispensible

    Dwight Eisenhower

  • 8/6/2019 Week-3- Project Management Plans

    15/87

    The project management plan

    Benefits of planning

    What to consider in your plan

    Guidelines

    Reviewing a plan

  • 8/6/2019 Week-3- Project Management Plans

    16/87

    http://flickr.com/photos/xabier-martinez/225627841/

    Why plan?Why plan?

  • 8/6/2019 Week-3- Project Management Plans

    17/87

    http://flickr.com/photos/xabier-martinez/225627841/

    The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

    Changes once you start

  • 8/6/2019 Week-3- Project Management Plans

    18/87

    http://flickr.com/photos/xabier-martinez/225627841/

    The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

    Changes once you start

    Guides you activities

  • 8/6/2019 Week-3- Project Management Plans

    19/87

    http://flickr.com/photos/xabier-martinez/225627841/

    The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

    Changes once you start

    Guides you activities

    Makes you think ahead

  • 8/6/2019 Week-3- Project Management Plans

    20/87

    http://flickr.com/photos/xabier-martinez/225627841/

    The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

    Changes once you start

    Guides you activities

    Makes you think ahead

    Helps you work out who you

    need to hire

  • 8/6/2019 Week-3- Project Management Plans

    21/87

    http://flickr.com/photos/xabier-martinez/225627841/

    The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

    Changes once you start

    Guides you activities

    Makes you think ahead

    Helps you work out who you

    need to hire

    Works out the timeline and

    budget

  • 8/6/2019 Week-3- Project Management Plans

    22/87

    http://flickr.com/photos/xabier-martinez/225627841/

    The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

    Changes once you start

    Guides you activities

    Makes you think ahead

    Helps you work out who you

    need to hire

    Helps manage expectations

    Works out the timeline and

    budget

  • 8/6/2019 Week-3- Project Management Plans

    23/87

    http://flickr.com/photos/xabier-martinez/225627841/

    The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

    Changes once you start

    Guides you activities

    Makes you think ahead

    Helps you work out who you

    need to hire

    Helps manage expectations

    Works out the timeline and

    budget

    Helps understand the effects of

    changes

  • 8/6/2019 Week-3- Project Management Plans

    24/87

    http://flickr.com/photos/xabier-martinez/225627841/

    The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

    Changes once you start

    Guides you activities

    Makes you think ahead

    Helps you work out who you

    need to hire

    Helps manage expectations

    Makes sure you are doing the right

    thing

    Works out the timeline and

    budget

    Helps understand the effects of

    changes

  • 8/6/2019 Week-3- Project Management Plans

    25/87

    The project management plan

    Benefits of planning

    What to consider in your plan

    Guidelines

    Reviewing a plan

  • 8/6/2019 Week-3- Project Management Plans

    26/87

  • 8/6/2019 Week-3- Project Management Plans

    27/87

    ?

  • 8/6/2019 Week-3- Project Management Plans

    28/87

    Who will read it?

    What do they need to know?

    Do they come in cold?

  • 8/6/2019 Week-3- Project Management Plans

    29/87

    What is your project going to deliver?

    Scope

    The work to be done = The target product

  • 8/6/2019 Week-3- Project Management Plans

    30/87

    Hunt, B. et al. (2003). Project charter. Retrieved January 23, 2006 fromhttp://webpages.charter.net/hafox/pm/docs/charter.doc (partial)

    http://webpages.charter.net/hafox/pm/docs/charter.dochttp://webpages.charter.net/hafox/pm/docs/charter.doc
  • 8/6/2019 Week-3- Project Management Plans

    31/87

  • 8/6/2019 Week-3- Project Management Plans

    32/87

    What is your project going to deliver?

    Definition

    The work to be done =?= The target product

  • 8/6/2019 Week-3- Project Management Plans

    33/87

    What is your project going to deliver?

    Change control

    The work to be done =?= The target product

  • 8/6/2019 Week-3- Project Management Plans

    34/87

    What is your project going to deliver?

    Value?

    The work to be done =?= The target product

  • 8/6/2019 Week-3- Project Management Plans

    35/87

    The WBS

  • 8/6/2019 Week-3- Project Management Plans

    36/87

    The rightway

    The

    wrongway

  • 8/6/2019 Week-3- Project Management Plans

    37/87

    Focus ondeliverables Focus onprocesses

  • 8/6/2019 Week-3- Project Management Plans

    38/87

    Align tovalue

    Align to

    processstages

  • 8/6/2019 Week-3- Project Management Plans

    39/87

    Why? Why not?

  • 8/6/2019 Week-3- Project Management Plans

    40/87

    Figure 5.2 Sample hierarchical WBS organized by phase(Schwalbe, 2006, p176)

    The wrongway?

    Note theLayers

  • 8/6/2019 Week-3- Project Management Plans

    41/87

    Table 5.3Table 5.3 Sample tabular WBSSample tabular WBS(Schwalbe, 2006, p176)(Schwalbe, 2006, p176)

    1.0 Concept1.1 Evaluate current systems1.2 Define requirements

    1.2.1 Define user requirements1.2.2 Define content requirements1.2.3 Define system requirements1.2.4 Define server owner

    requirements

    1.3 Define specific functionality1.4 Define risks and risk management

    approach1.5 Develop project plan1.6 Brief Web development team

    2.0 Web Site Design3.0 Web Site Development4.0 Roll Out5.0 Support

  • 8/6/2019 Week-3- Project Management Plans

    42/87

    http://images.google.com.au/images?hl=en&q=wbs&btnG=Search+Images&gbv=2

    http://images.google.com.au/images?hl=en&q=wbs&btnG=Search+Images&gbv=2http://images.google.com.au/images?hl=en&q=wbs&btnG=Search+Images&gbv=2
  • 8/6/2019 Week-3- Project Management Plans

    43/87

    Document your assumptions

    Very little

    knowledge

    Complete

    knowledge

    Degree of knowledge over time

  • 8/6/2019 Week-3- Project Management Plans

    44/87

    OBS

  • 8/6/2019 Week-3- Project Management Plans

    45/87

    Figure 9.2 Sample Project Organizational Chart(Schwalbe, 2006, p358)

  • 8/6/2019 Week-3- Project Management Plans

    46/87

    Task 1

    Task 2

    Task 3

    Task 4

    Task 5

    Task 6

    Person 1 Person 2 Person 3 Person 4

  • 8/6/2019 Week-3- Project Management Plans

    47/87

    http://ww

    w.win

    ningwith ad

    d.com/orga

    niza

    tion

    /

    http://www.winningwithadd.com/organization/
  • 8/6/2019 Week-3- Project Management Plans

    48/87

    Figure 9.6 Sample Resource Histogram(Schwalbe, 2006, p362)

  • 8/6/2019 Week-3- Project Management Plans

    49/87

    tools

    rasci(aka raci)

    ram

  • 8/6/2019 Week-3- Project Management Plans

    50/87

    http://makeitstrategic.com/index.php?blog=5&cat=18

    http://makeitstrategic.com/index.php?blog=5&cat=18http://makeitstrategic.com/index.php?blog=5&cat=18http://makeitstrategic.com/index.php?blog=5&cat=18
  • 8/6/2019 Week-3- Project Management Plans

    51/87

    r

    a

    s

    c

    i

    responsible

    accountable

    supportive

    consulted

    informed

  • 8/6/2019 Week-3- Project Management Plans

    52/87

  • 8/6/2019 Week-3- Project Management Plans

    53/87

    Task 1

    Task 2

    Task 3

    Task 4

    Task 5

    Task 6

    Person 1 Person 2 Person 3 Person 4

    R

    R

    R

    R

    R

    R

  • 8/6/2019 Week-3- Project Management Plans

    54/87

    Figure 9.4 Sample Responsibility Assignment Matrix (RAM)(Schwalbe, 2006, p360)

    OBS: Organizational Breakdown Structure

    WBS: Work Breakdown Structure

  • 8/6/2019 Week-3- Project Management Plans

    55/87

    One and only one person can be accountable. Multiple peoplecan be responsible and certainly others can be informed andconsulted.Source: Glen B Alleman, (2007) Responsibility Assignment Matrix, Herding Catshtt ://herdin cats.t e ad.com/m weblo /2007/02/res onsibilit .html retreived 2/8/08

    http://herdingcats.typepad.com/my_weblog/2007/02/responsibility_.htmlhttp://herdingcats.typepad.com/my_weblog/2007/02/responsibility_.html
  • 8/6/2019 Week-3- Project Management Plans

    56/87

    One and only one person can be accountable. Multiple peoplecan be responsible and certainly others can be informed andconsulted.Source: Glen B Alleman, (2007) Responsibility Assignment Matrix, Herding Catshtt ://herdin cats.t e ad.com/m weblo /2007/02/res onsibilit .html retreived 2/8/08

    http://herdingcats.typepad.com/my_weblog/2007/02/responsibility_.htmlhttp://herdingcats.typepad.com/my_weblog/2007/02/responsibility_.html
  • 8/6/2019 Week-3- Project Management Plans

    57/87

    Project organisations go farther than workers

    and work

  • 8/6/2019 Week-3- Project Management Plans

    58/87

    1. Project Team structure

    Project Sponsor

    Project Manager

    Craig Brown

    Working Group: Design focus OLA decisions and choices Formal review & validation of

    deliverables Business input and SME access

    Steering Committee: Governance focus Approval of project strategy &

    plans Endorsement of key OLA

    decisions Final approval of the OLA

    Business case and Solution Design Removal of major roadblocks &

    prioritisation

    Analysts

    Testers

    Designer

    Change consultants

    Working GroupMarketing

    Product ManagementLegal

    Finance

    SalesCustomer Service

    Steering CommitteeHead of Marketing and Sales

    Head of Product Management

    Head of Customer Service

    Head of Finance

    Developers

  • 8/6/2019 Week-3- Project Management Plans

    59/87

    Remember this?

  • 8/6/2019 Week-3- Project Management Plans

    60/87

    You might break down the workby phases

  • 8/6/2019 Week-3- Project Management Plans

    61/87

    Why?

  • 8/6/2019 Week-3- Project Management Plans

    62/87

    http://flickr.com/photos/pshan427/2382209408/

  • 8/6/2019 Week-3- Project Management Plans

    63/87

    So now you know what needs to be done

  • 8/6/2019 Week-3- Project Management Plans

    64/87

    So now you know what needs to be done

    and who is going to do it.

  • 8/6/2019 Week-3- Project Management Plans

    65/87

    So now you know what needs to be done

    and who is going to do it.

    But what about when?

  • 8/6/2019 Week-3- Project Management Plans

    66/87

    Schedule

  • 8/6/2019 Week-3- Project Management Plans

    67/87

    http://www.edwardtufte.com/bboard/q-and-a-fetch-msg?msg_id=000076

  • 8/6/2019 Week-3- Project Management Plans

    68/87

    Figure 3.3Figure 3.3 Sample network diagram (partial)Sample network diagram (partial)(Schwalbe, 2006, p211)(Schwalbe, 2006, p211)

  • 8/6/2019 Week-3- Project Management Plans

    69/87

    Table 3.10 Sample milestone report (partial)(Schwalbe, 2006, p100)

  • 8/6/2019 Week-3- Project Management Plans

    70/87

  • 8/6/2019 Week-3- Project Management Plans

    71/87

    http://www.edwardtufte.com/bboard/q-and-a-fetch-msg?msg_id=000076

  • 8/6/2019 Week-3- Project Management Plans

    72/87

  • 8/6/2019 Week-3- Project Management Plans

    73/87

    Why

    What

    How

    When Who

  • 8/6/2019 Week-3- Project Management Plans

    74/87

    And what will it cost?

    $

  • 8/6/2019 Week-3- Project Management Plans

    75/87

  • 8/6/2019 Week-3- Project Management Plans

    76/87

  • 8/6/2019 Week-3- Project Management Plans

    77/87

  • 8/6/2019 Week-3- Project Management Plans

    78/87

  • 8/6/2019 Week-3- Project Management Plans

    79/87

  • 8/6/2019 Week-3- Project Management Plans

    80/87

    Galloway, M. (2004).Galloway, M. (2004). Status reportStatus report. Retrieved January 23, 2006 from. Retrieved January 23, 2006 from

    http://web.augsburg.edu/~oie/mis376/documents/SR1.dochttp://web.augsburg.edu/~oie/mis376/documents/SR1.doc (partial)(partial)

    http://web.augsburg.edu/~oie/mis376/documents/SR1.dochttp://web.augsburg.edu/~oie/mis376/documents/SR1.dochttp://web.augsburg.edu/~oie/mis376/documents/SR1.doc
  • 8/6/2019 Week-3- Project Management Plans

    81/87

    Risk management

    Degree of knowledge over time

  • 8/6/2019 Week-3- Project Management Plans

    82/87

  • 8/6/2019 Week-3- Project Management Plans

    83/87

    The project management plan

    Benefits of planning

    What to consider in your plan

    Guidelines

    Reviewing a plan

  • 8/6/2019 Week-3- Project Management Plans

    84/87

    Six-Step Proven Path for Schedule DevelopmentRudi van den Berg, Pcubed, Inc.http://www.pcubed.com/Solutions/SolSixStep.asp

    http://www.pcubed.com/Solutions/SolSixStep.asphttp://www.pcubed.com/Solutions/SolSixStep.asp
  • 8/6/2019 Week-3- Project Management Plans

    85/87

    The project management plan

    Benefits of planning

    What to consider in your plan

    Guidelines

    Reviewing a plan

  • 8/6/2019 Week-3- Project Management Plans

    86/87

    http

    ://thinh1808.files.wordpress.com/2007/1

    2/projplan_sample_20050610_144024.pdf

    http://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdfhttp://thinh1808.files.wordpress.com/2007/12/projplan_sample_20050610_144024.pdf
  • 8/6/2019 Week-3- Project Management Plans

    87/87

    BetterProjects.net

    Titl i f & CC @ Fli k