Page 1: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

WECC Standards CommitteeJoint Session

Webinar Meeting

September 5, 2013

Page 2: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

2

• SAR initiated in response to RCWG recommendations to RPIC

• Tier 1 analysis conducted by RS– Evaluate and recommend how documents should be Categorized– Dependencies on other efforts– Scope of drafting effort– Timeline

• Recommendation to WSC June 2013– Retirement of WR1, WR2, WR4, WR5– Project WECC-0100 SDT formed under WSC to determine

disposition of WR3 and respond to comments from ballot.

System Performance Criteria - TPL-001-WECC-RBP-2

Page 3: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

3

RS prepared the document “WECC-0100 Tier 1 Evaluation and Recommendations” dated May 31, 2013

System Performance Criteria - TPL-001-WECC-RBP-2

Standard or Criterion Reference Recommendation Supporting DocumentationFAC-010/-011 Regional Differences

NERC Eliminate White Paper

N-2 for Adjacent Circuits on Separate Structures

WR1.1 Eliminate FAC-010/-011 White Paper

G-2 not addressed by NERC TPL Category C

WR1.2 Eliminate or Revise FAC-010/-011 White Paper

Multiple Bus Sections (B-2)

WR1.3 Eliminate Less stringent than existing and future NERC TPL requirements

Table W-1PerformanceAdjustment with WECC Board Approval

WR1.4 Make Table W-1 a Guideline for future use with NERC TPL-001-4 R5 when it becomes effective

Coordinate with WECC RC SOL Methodology which provides minimum acceptable performance criteria for each TOP.

Voltage Stability WR3 RS divided as to whether to make a standard or a guideline; this should be resolved by the drafting team

Coordinate with WECC RC SOL Methodology to ensure common definition for SOLs and IROLs

Unsuccessful Reclosing WR4 Eliminate Will be covered by future NERC TPL-001-4 R4.3.1.1

Actual Cascading Events

WR5 Eliminate Actual events are investigated by WECC/NERC/FERC; recommendations from these investigations address this requirement.

Performance Category Upgrade Request Process

  Tied to the outcome of WR1.1 and the FAC-010/-011 Regional Differences

 

Page 4: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

4

• Requirement WR1 requires Planning Coordinators and Transmission Planners to comply with the WECC Disturbance Performance Table W-1 of allowable effects on other systems for all NERC TPL planning events.

• Discussion –– New NERC TPL-001-4 Table 1 replaces Cat. A-C with P0-7.

Expands contingency simulations and required performance.– NERC TPL-001-4 requirement R5 will require PC/TP’s to have

criteria for ... transient voltage response.o Table W-1 more of a guideline today, 57 exceptions.o RS will be developing Vdip Guideline PC/TP’s will be able to use for

NERC TPL-001-4 R5.

TPL-001-WECC-RBP-2 ... WR1

Page 5: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

5

• The NERC Category C.5 initiating event of a single-line-to- ground fault with normal clearing shall also apply to the common mode contingency of two Adjacent Transmission Circuits on separate towers — unless the Mean Time Between Failure (MTBF) is determined to be greater than 30 years (i.e., outage frequency is less than 0.033 outages per year).

• Discussion –– Double-circuit line outage rate 1.8 times two circuits on separate

structures on common ROW.– Outage rate not on common ROW 1.4 times on common ROW.– Two circuits not on common ROW covered by NERC Table 1.– Recommendation to Retire

TPL-001-WECC-RBP-2 ... WR1-R1.1

Page 6: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

6

• Discussion Continued –

TPL-001-WECC-RBP-2 ... WR1-R1.1

Table 1

Western Interconnection

Average Data 2008-2012

Circuits on Common Structure

Circuits on Common Right-of-

Way Separate Structure

Circuits not on Common ROW or

Structure

Transmission Miles 8,822 14,782 51,649

Number of Events/year

24 22 103

No. of Outages/

100 miles of line/year

0.271 0.147 0.207

1. Outage comparison of circuits on common ROW and/or structures when 2 or more circuits went out of service.

2. From WECC Transmission Reliability Data.

Page 7: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

7

• The common mode simultaneous outage of two generator units connected to the same switchyard, not addressed by the initiating events in NERC Category C, shall not result in cascading.

• Discussion –– Common mode outage in the substation (breaker failures) already

covered by NERC Table 1.– Interpretation is confusing. No known common mode outage

between units on the generator side.– Recommendation to Retire

TPL-001-WECC-RBP-2 ... WR1-R1.2

Page 8: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

8

• The loss of multiple bus sections, as a result of a failure or delayed clearing of a bus tie or bus sectionalizing breaker, shall meet the performance specified for Category D of Table W-1.

• Discussion –– Less stringent that existing NERC TPL-003, C.2 and C.9.– More definitive performance requirement in NERC TPL-001-4,

Table 1, P.4.– Recommendation to Retire.

TPL-001-WECC-RBP-2 ... WR1-R1.3

Page 9: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

9

• For contingencies involving existing or planned facilities, the Table W-1 performance category can be adjusted based on actual or expected performance (e.g., event outage frequency and consideration of impact) after receiving Board approval to change the Performance Level Adjustment Record.

• Discussion –– Historically used to adjust WR1.1 contingencies from Cat. C to D.

Essentially an exception process for WR1.1.– Requirement for WECC Board approval retained in “Seven Step

Process for Performance Category Upgrade Request “.– Recommendation to Retire.

TPL-001-WECC-RBP-2 ... WR1-R1.4

Page 10: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

10

• Individual systems or a group of systems may apply requirements that differ from specific requirements in Table W-1 for internal impacts. If the individual requirements are less stringent, other systems are permitted to have the same impact on that part of the individual system for the same category of disturbance. If these requirements are more stringent, these requirements may not be imposed on other systems.

• Discussion –– Policy statement tied to Table W-1, not a measurable Standard.

– NERC TPL-001-4 Requirement R5 requires PC/TP’s to have criteria for ... transient voltage response. Results in similar study results to the intent of WR2.

– Recommendation to Retire.

TPL-001-WECC-RBP-2 ... WR2

Page 11: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

11

• Reactive power resources, with a balance between static and dynamic characteristics, shall be planned and distributed throughout the interconnected transmission systems to ensure system performance... defines real power margin for Category A, B, and C contingencies.

• Discussion –– The RS continues to discuss whether to reclassify this requirement

as a Regional Standard or as a Guideline. Project WECC-0100 SDT formed to formulate a decision that will be balloted for wider approval.

– Recommend to be addressed by SDT.

TPL-001-WECC-RBP-2 ... WR3

Page 12: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

12

• The Planning Coordinators and Transmission Planners shall meet the same performance category for unsuccessful reclosing, as that required for the initiating disturbance without reclosing.

• Discussion –– Addressed by NERC TPL-001-4, R4.3.1.1 that states “The analysis

shall include the impact of subsequent: Successful high speed reclosing and unsuccessful high speed reclosing into a fault where high speed reclosing is utilized.”

– Recommendation to Retire.

TPL-001-WECC-RBP-2 ... WR4

Page 13: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

13

• For any event that has actually resulted in cascading, action must be taken so that future occurrences of the event will not result in cascading; or it must demonstrate that the Mean Time Between Failure (MTBF) is greater than 300 years (frequency less than 0.0033 outages/year) and approved by PCC.

• Discussion –– NERC performance standards are deterministic and provide

specific performance requirements for specific events.– Event reporting required by NERC EOP-004. Actual events are

investigated by WECC, NERC, FERC or some combination.– Corrective actions required by NERC TOP-004-2 regardless of

MTBF.– Recommendation to Retire.

TPL-001-WECC-RBP-2 ... WR5

Page 14: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

14

• Shall requirement WR1 including Table W-1be retired upon approval of a Voltage Performance Guideline?– Part 1.1 be retired effective on the date of WECC Board approval– Part 1.2 be retired effective on the date of WECC Board approval– Part 1.3 be retired effective on the date of WECC Board approval– Part 1.4 be retired effective on the date of WECC Board approval

• Shall requirement WR2 be retired effective on the date of WECC Board approval?

• Shall requirement WR4 be retired effective on the date of WECC Board approval?

• Shall requirement WR5 be retired effective on the date of WECC Board approval?

TPL-001-WECC-RBP-2 ... Retirement Ballot

Page 15: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

15

Review of Action Items

Action Item Status Completion Date

Page 16: WECC Standards Committee Joint Session Webinar Meeting September 5, 2013.

Questions?