Top Banner
Municipal Corporation of Greater Mumbai, India “Managing Mithi Drainage Basin To Enhance Flood Resiliency”
30

Watershed ppt (Final)

Feb 14, 2017

Download

Documents

hoangkhanh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • Municipal Corporation of

    Greater Mumbai, India

    Managing Mithi Drainage Basin

    To Enhance Flood

    Resiliency

  • Mumbai Topography and Drainage

    Merger of 7 islands in Island City, 4

    islands in Suburban District.

    Surrounded by water on three sides.

    Much of the area is close to sea level.

    Gravity drainage system affected by

    high/low tides.

    During high tide ingress of sea water.

    Island City has no natural drainage

    outlet.

    Mithi largest river flowing in Suburban

    District

    Catchment area 7265 hectares

    Length approx. 17.9 km

    Storm Water Drainage Network is

    more than 150 years old designed for

    rainfall of 25 mm per hour and run off

    co-efficient of 0.5.

  • Rainfall Characteristics

    Watershed degradation

    Inadequate Storm Water

    Drainage System

    Increase in Impermeable

    Surface Cover

    944 mm in 24 hrs.944 mm in 24 hrs.On 26On 26thth July 2005July 2005

    Vulnerability of MUMBAI

    To Flooding

  • Urbanisation has increased vulnerability of

    Mumbai to floods

    Narrowing of banks for housing and slums

    Reclamation of river beds by industrial units

    Diversion of course of the river for construction of the

    airport

    Main river has been forced to turn 900 four times in

    quick succession.

    Some sections are bunded with walls and

    embankments on both sides.

    Reclamation of natural ponds

    Reclamation of mangroves for construction of Bandra

    Kurla complex.

  • Moraraji Nagar Slum EncroachmentMoraraji Nagar Slum Encroachment

  • Mithi on Kurla Mithi on Kurla Saki Naka RoadSaki Naka Road

  • Land use changes have increased

    vulnerability of Mumbai to floods

    Change in land use pattern has led to an increase in

    run off coefficient to almost 1.0

  • Mithi River Flooding Mithi River Flooding 2626thth July 2005July 2005

  • Recommendation: Do not obstruct water flow of the

    river

    Initiatives taken since 2006

    Widening & deepening of Mithi River is almost completed

    940,406 cubic meters of silt and 492,000 cubic meters of hard rock

    has been excavated from the river bed till 31st March 2011

    Construction of R.C.C. retaining wall of 7.8 km length on both the

    banks along with 6 to 12 mtr wide service roads.

    Two weirs have been completed along the river.

    4922 (residential & non residential) structures have been

    demolished for widening the river, 663 structures remain to be

    demolished

    Expenditure incurred till 31st March 2011 69.8 Million Euros

    Expected expenditure to complete the remaining work approx 71

    Million Euros

    Target date of completion December 2012

  • SAKINAKASAKINAKA

  • Weir Wall at BamandayaWeir Wall at Bamandaya

  • New Bridge At Kranti Nagar

  • Upstream of Kranti Nagar Bridge

    Before

  • Upstream of Kranti Nagar Bridge

    After

  • BEFORE

  • AFTER

  • Recommendation: Develop Early Warning Systems

    Installation of 35 automatic

    weather stations at 28 locations

    Console gives audible alarm

    when the rainfall exceeds 10mm

    in 15 minutes

    Rainfall data is transmitted every

    15 minutes to the EOC, MCGM

    Flow Gauges have been installed

    upstream of Mithi River and a

    measuring scale has been marked

    on the existing pier of

    Krantinagar Bridge to indicate the

    level of water in the Mithi river

    and issue warning to the

    population living downstream20

  • KRANTINAGAR

  • FLOODING SPOTS

    CATCHMENT

    BOUNDRY

    IRLA PUMPING

    IRLA NALLA

    IRLA NALLA Br-A

    IRLA NALLA Br-BGARWARE NALLA

    IRLA NALLA Br-C

    Recommendation: Augment the capacity of the storm water drainage system to cater to the increase in runoff

    ABHISHEK NALLA

    Nalla training work

    completed Work under SRA

    development

    FLOODING SPOTS

    1 Milan Subway

    2 VM Road

    3 Near Cooper Hospital

    4 JVPD Area

    5 Near Vile Parle Station

    6 Sahar Road Junction

    1

    2

    3

    4

    5

    6

    Work of training yet to

    start (funded by

    MCGM)

    Work of training under

    progress

    Existing Trained

    KOLE DUNGARI NALLA

  • Pumping Stations

    Storm Water Pumping Station at Irla

    Capacity 48 Cubic Meter / Second

    No. of Pumps 8

    Capacity of each pump 6 Cubic Meter / Second

  • Progress Inlet channel - Irla

  • Progress Irla

  • Recommendation: Prepare detailed Contour Maps to

    identify the sub-catchment and low lying areas

    A contour map of Mumbai with 0.2 m interval has been

    completed

  • Recommendations

    Conserve wet lands

    The reclamation of mangroves

    for construction of the

    Bandra Kurla complex has

    increased the likelihood of

    flooding.

    Promote recreational

    activities along the banks

    of the river

  • GOALS OF DRMMP

    Recommendation: Preparation of a comprehensive

    Disaster Risk Management Master Plan

  • Policy Recommendations

    Make flood risk and flood hazard

    assessments an integral part of the

    master planning process

    Record construction details along with

    the plinth and ground level in a master

    inventory

    Provide flood-resistant temporary

    shelters

  • Municipal Corporation Of Greater Mumbai

    Thank You

    Making Mumbai a better and safe place to live in