WATERBAY TOWER PROGRESS REPORT About the Project: Project Developer Bin Faqeeh Real Estate Investment Company S.P.C. Title of Project Waterbay Project Reference BFWB/25/0104-3004/2018 Design & Supervision Consultant Arab Architects Interior Design Consultant (West) Dar Al Décor | (Middle) Horizon Interiors | (East) Dar Al Décor Main Contractor Al Jameel Construction S.P.C. About Progress Report: Title of Document Progress Report of Waterbay Reporting Period April 1, 2018 to April 30, 2018 Authors & project role Al Jameel Construction S.P.C. Date May 6, 2018
8
Embed
WATERBAY TOWER PROGRESS REPORT About the Project15. Concreting for grade slab 100% Completed 16. Suspended slab on level +2.80m 100% Completed 17. Concrete for columns and retaining
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
WATERBAY TOWER PROGRESS REPORT About the Project:
Project Developer Bin Faqeeh Real Estate Investment Company S.P.C.
Title of Project Waterbay
Project Reference BFWB/25/0104-3004/2018
Design & Supervision Consultant
Arab Architects
Interior Design Consultant
(West) Dar Al Décor | (Middle) Horizon Interiors | (East) Dar Al Décor
Main Contractor Al Jameel Construction S.P.C.
About Progress Report:
Title of Document Progress Report of Waterbay
Reporting Period April 1, 2018 to April 30, 2018
Authors & project role Al Jameel Construction S.P.C.
9. Blinding for Tile beams 100% Completed 10. Blinding under slab on grade 100% Completed 11. Shuttering block for pile caps and retaining wall strip footing 100% Completed 12. Shuttering block for tie beams 100% Completed 13. Back filing, leveling and compaction under the grade slab 100% Completed 14. Waterproofing 100% Completed 15. Steel fixing then concrete pouring for slab on grade, pile caps,
tie beams and strip footings 100% Completed
16. Retaining wall, Adjoined shoring piles and concrete columns 100% Completed 17. Suspended Slab 100% Completed 18. Concrete for columns and retaining walls 100% Completed 19. Suspended Slab 100% Completed 20. Columns and retaining wall 100% Completed 21. Ground floor slab including swimming pool area 100% Completed 22. Structural 1st and 6th Floors 100% Completed 23. Structural 7th and 9nd Floors 50% In Progress 24. Structural 10th Floor and Roof Floor 0% In Progress 25. Block Works
a. Basement – 1,2 and 3 100% Completed b. Basement GF, 1st and 2nd Floor 0% In Progress
26. Plastering Works a. Basement 3 100% Completed b. Basement 2 90% Completed c. Basement 1 80% In Progress d. Basement GF, 1st and 2nd Floor 0% In Progress
27. Primer, Putty and 1st Coat Paint a. Basement 3 20% In Progress b. Basement 2 60% In Progress c. Basement 1 80% In Progress
d. Ground Floor, 1st Floor and 2nd Floor 0% In Progress TOWER B (FRONT AND REAR PORTIONS)
SUB STRUCTURE 1. Excavation 100% Completed 2. Piling “219 piles” 100% Completed 3. Pile Trimming 100% Completed 4. Blinding and shuttering block for pile caps, tie beam and
retaining wall 100% Completed
5. Dewatering trenches 100% Completed 6. Dewatering horizontal system 100% Completed 7. Tower Crane Pile cap (TC1) 100% Completed 8. Tower Crane Pile cap (TC2) 100% Completed 9. Tower Crane “C1” installation 100% Completed 10. Tower Crane “C2” installation 100% Completed 11. Guniting 100% Completed 12. Blinding under slab on grade 100% Completed 13. Waterproofing 100% Completed 14. Reinforcement steel for slab on grade 100% Completed 15. Concreting for grade slab 100% Completed 16. Suspended slab on level +2.80m 100% Completed 17. Concrete for columns and retaining walls 100% Completed 18. Suspended slab on level (+5.80) 100% Completed 19. Columns and retaining wall 100% Completed 20. Ground floor slab including swimming pool area 100% Completed
SUPER STRUCTURE 1. Structural 1st to 10th Floors 100% Completed 2. Structural Roof Floors 50% In Progress 3. Block Works
a. Basement 1, 2 and 3 100% Completed b. Ground Floor 5% In Progress c. 1st Floor and 2nd Floor 100% Completed d. 3rd Floor, 4th Floor and 5th Floor 95% In Progress e. 6th Floor 85% In Progress f. 7th Floor 45% In Progress g. 8th Floor 10% In Progress
4. Plastering Works a. Basement 1, 2 and 3 100% Completed b. Ground Floor, 1st Floor, 2nd Floor 0% In Progress
5. Primer, Putty and 1st Coat Paint a. Basement 1, 2 and 3 100% Completed b. Basement 2 90% In Progress c. Basement 1 95% In Progress d. Ground Floor, 1st Floor, 2nd Floor 0% In Progress
6. MEP Services (Walls) a. Basement 1, 2 and 3 30% In Progress b. 1st Floor and 2nd Floor 25% In Progress c. 3rd and 7th Floor 10% In Progress
7. MEP Services (Ceiling) a. Basement 1, 2 and 3 40% In Progress b. Ground Floor 5% In Progress c. 1st Floor to 5th Floor 20% In Progress d. 6th Floor 10% In Progress e. 7th Floor 5% In Progress
8. MEP Services a. Basement 1, 2 and 3 30% In Progress
TOWER C SUB STRUCTURE 1. Excavation 100% Completed 2. Piling “197 piles” 100% Completed 3. Piling Trimming 100% Completed 4. Blinding and shuttering block for pile caps, tie beam and
retaining wall 100% Completed
5. Blinding for under the grade slab 100% Completed 6. Dewatering trenches 100% Completed 7. Dewatering horizontal system 100% Completed 8. Water Proofing 100% Completed 9. Protection Screed 100% Completed 10. Reinforcement Steel 100% Completed 11. Concreting of slab on grade 100% Completed 12. Columns and retaining walls up to +3.70m 100% Completed 13. Ramp Area 100% Completed 14. Slab on level +4.00m 100% Completed 15. Retaining wall adjoined the shoring pile 100% Completed 16. Slab on level +7.00 and 7.25m 100% Completed 17. Columns and retaining wall (level +7.00 up to +12.30m) 100% Completed 18. Ground Floor slab including swimming pool area 100% Completed
SUPER STRUCTURE 1. Structural 1st Floor to 10th Floor 100% Completed 2. Structural Roof Floor 100% Completed 3. Block Works 100% Completed
a. Basement 1, 2 and 3 100% Completed b. Ground Floor 5% In Progress c. 1st Floor and 2nd Floor 95% In Progress d. 3rd Floor 85% In Progress e. 4th Floor to 5th Floor 80% In Progress
f. 6th Floor 60% In Progress g. 7th Floor 7% In Progress
4. Plastering Works a. Basement 1, 2 and3 95% In Progress b. Ground Floor, 1st Floor 90% In Progress
5. Primer, Putty and 1st Coat Paint a. Basement 3 100% Completed b. Basement 2 95% In Progress c. Basement 1 95% In Progress d. Ground Floor, 1st Floor 0% In Progress
6. MEP Services (Walls) a. Basement 1, 2 and 3 30% In Progress b. Ground Floor to 2nd Floor 30% In Progress c. 3rd Floor to 4th Floor 20% In Progress d. 5th Floor to 7th Floor 10% In Progress
7. MEP Services (Ceiling) a. Basement 1, 2 and 3 50% In Progress b. Ground Floor 30% In Progress c. 1st Floor 50% In Progress d. 2nd Floor 22% In Progress e. 3rd Floor to 5th Floor 20% In Progress f. 6th Floor to 7th Floor 10% In Progress
8. MEP Services a. Basement 2 and 3 30% In Progress b. Basement 1 20% In
On-site photos:
Zone A and A1
(Steel & shuttering works floor Slab-Front) (Steel & Shuttering works for slab - Rear)
(Painting works for ceiling and walls in Basement)
Zone B and B1
(Concrete Pouring for Roof floor slab - Rear) (Block Works in 6F - Front)
(Plastering Works in 1F – Rear) (Installation of MEP Services 8F - Front)