WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman
18

WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Dec 17, 2015

Download

Documents

Bernice Pitts
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

WATER SUPPLY – FINAL PRESENTATIONAmelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman

Page 2: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Participants

SARAH WATZMAN - aka the girl who never frowns !- Third year ME- Bio-digester lead

LAURA REISENAUER- aka the girl who rarely drinks water!- Third year Env.E- Team lead

AMELIA QUILON - aka the girl who only eats peanut butter !- Third year ISE- Tilapia lead

RAYVION SANFORD- aka the girl who severely hates bugs!- Third year Chem.E- Communication lead

Page 3: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Problem

Main Problem• Scope: • MdL frequently loses electricity

that powers their lift pump and distribution pump.

• Objective: • Explore alternative energy

sources to either back-up pumps during power outages or replace grid.

• Increase water storage capacity to mitigate problems occurring when there’s no electricity.

Side Problems• Scope:• MdL has a non-functioning

biodigester.• MdL has a not fully

functional tilapia pond.

• Objective:• Find the root cause of the

biodigester’s problem.• Provide MdL a plan so that

the biodigester becomes a stable, functional piece.

• Repair the tilapia pond. • Develop a yearly schedule

for tilapia harvesting to maximize yield.

Page 4: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Pre-Pre Trip Work

Generator• Requirements: 20 kW

generator needed to overcome initial in-rush.

• $20,000 for 20 kW generator

• $600 for variable frequency driver (another pricey option!)

Additional Storage Capacity

• Cost: $5,000• Feasibility: • 900 pound tank• Support issues – 13,000

pound tank when full• Diameter and dimensions

(Saul confirmed this information)

Is this even a problem? MdL had only used a water truck 2 – 3 times over

several years!

Page 5: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Pre-Trip Work

Biodigester• Discoveries from last trip

– clogged, too many solids, too basic water

• Sump pump is on site• What does the

biodigester need before it can be fully operational?• Poop and H2O!

• Sustainability and training

Tilapia Pond• What has worked already

and what is currently working?• Section 1 is functional• Sections 2 and 3 are leaking

• How can MdL fully utilize the tilapia pond?• Protein source for the

children• Potential revenue

generator?

Page 6: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Objectives Achieved

Biodigester• Benefit analyzed• Contents fully removed • Composting pile

“organized” and dedicated to garden

• Manure on site• Composting posters

created• Gas line replaced• Staff trained and informed

Tilapia Pond• Sections 2 and 3 drained

and cleaned• Sections 2 and 3 patched• Could not be tested for leaks

due to water issues

• Pump has been spliced so it can be used in both sections

• Animal rescue!• Business plan• Rotation Schedule

Page 7: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Future Recommendations

Biodigester• Once enough manure is

obtained, initialize biodigester

• Put compost from kitchens directly into biodigester • For less confusion, only use

kitchen’s compost, not kids!

• Use existing compost pile for garden

• Gas lights by compost area

Tilapia Pond• MdL is already thinking of

re-surfacing the pond.• MdL should stagger each

section to increase the times each year they harvest.

• Use pump in middle section.

• Use spliced hose in large section.

Page 8: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Questions?

Page 9: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Appendix

Page 10: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Biogas Production Analysis

Assumptions: • One 100lb propane tank at MdL gets used every 15 days. • One bucket of compost (approx. 10 pounds) is added to biodigester daily.• 50.3 MJ/kg = energy density of propane (Wolfram Alpha)• 53 MJ/kg = energy density of methane (hypertextbook.com/facts/2004/Billywan.shtml• 265 cubic meters/ton = biogas production from food scrapsCalculations:

Methane:

(Wikipedia)

Propane:

Energy produced from methane created from food scraps is

1/3 of the energy MdL’s propane tanks provide.

Page 11: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Biogas Production Data

Page 12: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Manure Procured Analysis

Page 13: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Installation Volume Analysis

Page 14: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Tilapia Revenue Analysis

Tilapia Production (every 6 mo.)• I tilapia = 1 pound• Section 1: 50 pounds• Section 2: 300 pounds • Section 3: 300-500 pounds (with use of pump)Harvesting Schedule• Each section: 6 months or twice a yearPrice• 1 pound of tilapia = 27 Lempira Revenue

Page 15: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Tilapia Rotational Schedule

Section Jan Feb March April May June

1 Harvest! Stock Mo. 2 Mo. 3 Mo. 4 Mo. 5

2 Stock Mo. 2 Mo. 3 Mo. 4 Mo. 5 Harvest!

3 Mo. 4 Mo. 5 Harvest! Stock Mo. 2 Mo. 3

Section July Aug Sept Oct Nov Dec

1 Harvest! Stock Mo. 2 Mo. 3 Mo. 4 Mo. 5

2 Stock Mo. 2 Mo. 3 Mo. 4 Mo. 5 Harvest!

3 Mo. 4 Mo. 5 Harvest! Stock Mo. 2 Mo. 3

Page 16: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Composting Posters

• Good (Bueno)• Beans (frijoles)• plantains/bananas (platano)• watermelon (sandia)• tortilla (tortilla)• lettuce (lechuga)• tomato (tomate)• pineapple (pina)• rice (arroz)

• Bad (Mal)• Eggs (huevos)• bones (huesos)• meat (carne)• egg shells (cascarde de huevo)• paper (papel)• milk (leche)• cardboard (carton)• plastic (plastico)

Page 17: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Biodigester – Chamber Dimensions

Page 18: WATER SUPPLY – FINAL PRESENTATION Amelia Quilon, Laura Reisenauer, Rayvion Sanford, Sarah Watzman.

Biodigester – Gas Pipe Dimensions