1 WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT RISK PROJECT NOS. WS85509007-1 & WS85509011-1 November 22, 2016 Pre-Submittal Meeting
19

WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

Jul 05, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

1

WATER MAIN REPLACEMENT

CONSTRUCTION MANAGER AT RISK

PROJECT NOS. WS85509007-1 & WS85509011-1

November 22, 2016

Pre-Submittal Meeting

Page 2: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

2

� Clayton Freed, Project ManagerWater Services Department

� Matthew Woodland, CE IIIWater Services Department

� Emeka Ekpe, Contracts Specialist Street Transportation Department

Welcome and Introductions

Page 3: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

3

� Sign-in please…copies of sign in sheet will be available on website:

http://phoenix.gov/streets/procurement/current-opportunities

� Please hold questions until the Q&A period.

� This is the ONLY opportunity to discuss this project with City staff.

Meeting Overview

Page 4: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

4

� Project Description

� Project Scope of Work

� Questions?

� Submittal Requirements

� Selection Schedule

� Questions?

Agenda

Page 5: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

Water Main Replacement in the Area bounded by:McDowell Rd to Oak St and 16th St to 20th St

� New Installation:� 1,844 LF of 12” DIP� 5,313 LF of 8” DIP� 20,336 LF of 6” DIP� 14 LF of 4” DIP� 30 Fire Hydrants� 24 Cut and Plugs� 489 Service Connections

Project Description WS85509007-1

Page 6: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

Project DescriptionWS85509011-1

Water Main Replacement in the Area bounded by:Glendale Ave to Orangewood Ave and 12th St to 16th St

� New Installation:� 5,307 LF of 12” DIP� 1,424 LF of 8” DIP� 11,464 LF of 6” DIP� 1,040 LF of 4” DIP� 48 Fire Hydrants� 50 Cut and Plugs� 230 Service Connections

Page 7: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

May include, but not limited to:

� Design Phase Services

� Constructability review of plans

� Cost estimating

Scope of Work

Page 8: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

May include, but not limited to:

� GMP Preparation

� Set goals for local SBE participation and implement

� Development of a subcontractor selection plan

� Preparation of a Guaranteed Maximum Price (GMP) for construction that meets the approval of the City

Scope of Work

Page 9: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

May include, but not limited to:

� Construction Phase Services

� Installation of new water main system and connections

� Abandonment of existing water main system

� Disinfection and flushing of the pipeline prior to startup

� Traffic Control

� Public Outreach assistance

� Roadway Restorations

� Bond and insure the construction

� Address all federal, state and local permitting requirements

� Maintain a safe work site for all project participants

Scope of Work

Page 10: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

QUESTIONS?

Page 11: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

11

� General Information – 15 points

� Experience & Qualifications of the Firm – 20 points

� Experience of Personnel Assigned To Project - 25 points

� Project Understanding and Approach - 30 points

� Overall Evaluation Of Firm – 10 points

Statement of Qualifications Criteria

Page 12: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

12

� Cover Letter (company name, address and contact information)

� Evaluation Criteria (including project organizational chart)

� Additional Content (resumes or other information)

� MAXIMUM pages permitted is 13 pages:

Statement of Qualifications Criteria (Continued)

Page 13: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

13

� Each page side with criteria information will be counted.

� Pages that have photos, charts, and graphs will be counted toward maximum number of pages.

� Front and back cover, Table of Contents and tab dividers will NOT be counted toward the maximum page limit, UNLESS they include information that may be considered by the selection panel.

Statement of Qualifications Criteria (Continued)

Page 14: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

14

� Submit 6 copies of the SOQ.

� SOQ due: 12:00pm Noon – Arizona local timeFriday, December 2, 2016Phoenix City Hall200 West Washington Street, 6th FloorSubmittal Box

Statement of Qualifications Criteria (Continued)

Page 15: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

15

� Grounds for Disqualification:

� Receipt of submittal after specified cut-off date and time.

� Too few copies of the submittal.

� Deposit of submittal in the wrong location.

� Violating “Contact with City Employees” policy.

Statement of Qualifications Criteria (Continued)

Page 16: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

16

� SOQs due at 12:00 P.M. December 2, 2016

� Selection Notification December 22, 2016

� Scope Meeting January 2017

Selection Schedule

Page 17: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

17

� Request for Qualifications

� Notifications

� Plan Holder List

� Pre-submittal Power Point Presentation and Sign-In

� Award

http://phoenix.gov/streets/procurement/current-opportunities

STREET TRANSPORTATION –

PROCUREMENT SECTION WEBPAGE

Page 18: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

18

QUESTIONS?

Page 19: WATER MAIN REPLACEMENT CONSTRUCTION MANAGER AT … · Water Main Replacement in the Area bounded by: McDowellRdtoOakStand16 th Stto20 th St NewInstallation: 1,844LFof12”DIP 5,313LFof8”DIP

19

Emeka Ekpe, Contracts Specialist

Project Name: Water Main Replacement CMAR

WS85509007-1 & WS85509011-1

[email protected]

QUESTIONS AFTER TODAY