Top Banner
Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 [email protected] 407.893.3325
33

Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 [email protected] 407.893.3325.

Dec 15, 2015

Download

Documents

Moises Storm
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Water Main Extension Permits

Interplan LLCRichard Lott, P.G., P.E.

Program Manager-Drinking WaterFebruary 18, 2008

[email protected]

Page 2: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Central District Staff

• Vivian F. Garfein, Director, Central District• Christianne C. Ferraro, P.E. • Administrator, Water Resource Management

Page 3: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

CD Drinking Water Staff

• Kim Dodson – Environmental Manager (Compliance/Enforcement & Monitoring)

• Richard Lott (Permitting) - Richard Lott (WTP)

– Cary Padell – water main extension permits & clearances

Page 4: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

CD Drinking Water Permits

• CD issues 25% of all of Florida’s PW permits;

• This translates to 1350 permits/year in addition to letters, TO, date extensions, etc.

Page 5: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Permit Determinations

• Submit to Cary Padell;• Send hard copy of site map showing

connections to existing water main and full distribution system;

• No Faxes or PDFs;• Provide e-mail address for

response;

Page 6: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Permit “Status” Requests• Let N = the date that your application is

received by DEP;• Let A = 30 days before we review your

application;• Let D = Date you should ask for status

report.

• D = N + A + 1 = N + 31

Page 7: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Prioritizing Permits

• We only prioritize permits for health reasons or if the permit application is in the public interest, i.e. affordable housing, schools opening, etc.

• We do NOT prioritize permits because your contractor is ready to start construction or it is simple in nature!

Page 8: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Permit PrioritizationThe order of permit review is dictated

solely by the Clock (when it comes in) and NOT by the complexity of the situation.

Page 9: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Did We Receive your Permit Package?

If you want assurance that we received your permit package or response, send it by certified mail .

ORYou can try the following website:

http://www.dep.state.fl.us/secretary/info/permitting.htm

Page 10: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Submission of Permit Packages

• Separate Potable Water (PW) package from Domestic Waste Water (DW) application packages;

• Submit different Checks for PW and DW or if using one check, make note that the total amount is for the [type of permit]PW permit and the [type of permit]DW permit and give each amount;

Page 11: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

What Are the 2 Types of Water Main Extension Construction Permits?

•Specific Permit - previously referred to as “Individual” or “Long-form” Permit;

General “Permit” or “GP” - previously referred to as “Short-form ‘Permit’”;

Page 12: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

PW WME Specific Permits

• DEP can write RAI letters and place Specific Conditions in a Specific Permit;

• $500 Application Fee for CWS projects;• Must submit plans, specs, and

construction notes, etc. (or preliminary design report) and they must be in conformity with the rules of FAC Chapters 62-555 and 62-550.

• Takes 3-5 months to get;

Page 13: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

When Do I Use the WME Specific Permit?

• Water main extensions that:– are dry lines;– are in areas containing petroleum- or

solvent-contamination;– interconnect previously separated

PWSs;– convey raw or partially-treated

drinking water-now or in the future or “reuse” at a later date;

– use conflict manholes;

Page 14: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

What is a General “Permit”?

For a GP, you are really notifying the DEP that you believe that the project meets the criteria so that a Specific Permit is not needed. DEP issues a document, based upon the information provided to us, that we either agree with you (you are authorized to use the GP) or disagree with you (you are not authorized).

Page 15: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

PW General “Permits”

• DEP CANNOT write RAI letters nor place Specific Conditions in a General “Permit”.

• Can issue more than one clearance;• Is evaluated on the quality of the submittal -

no phone calls or e-mails regarding clarification SHOULD be made;

• Requires: (1) fee; (2) completed application; and (3) sketch; (4) hydraulic analysis if <3”.

Page 16: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Dudley Doright Says…

“Use General Permits for appropriate

Water Main extensions; Use Specific Permits for Inappropriate Projects.”

Page 17: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Water Main Extensions - General “Permits”

• Requires advanced notice of AT LEAST 30 DAYS (no expediting permits);

• $250 Application Fee for projects designed by PE;

• Does NOT require PE signature (may be designed by public officer) if total project cost <$10,000;

• Fill in ALL blanks;

Page 18: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Richard’s Top Ten Ways to Submit a Correct General Permit Application

Page 19: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Number 10

Do NOT place construction notes and details on your sketch.

Page 20: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Number 9

Do NOT initial everything in the General Permit checklist.

Page 21: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Number 8

Submit only ONE copy of everything.

Page 22: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Number 7

Construction plans do not take the place of

the Sketch.

Page 23: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Number 6

Make sure that the Sketch includes the locations of valves, pipes, fire hydrants,

etc

Page 24: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Number 5

The Sketch does NOT have to be 81/2 x 11” but it does need to be legible!

Page 25: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Number 4

Make sure that the Utility has filled in the application with the correct information and signed it.

Page 26: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Number 3

Do NOT forget to sign and seal the

application in the two places where they are

required.

Page 27: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Number 2

Do NOT leave anything blank!

Page 28: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Number 1

Submit the correct fee for WM extensions:

GP = $250SP = $500

Page 29: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Clearances

Page 30: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

What is the first thing to do when it is time to submit theCertification of Completion?

Make sure that you read the permit which tells you what to submit!

Page 31: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Where do Contractors Enter In?

• Permit signed by:– Professional Engineer– Applicant– Utility– No Contractor!!!!!!!!!!!!!!!!!!!!!!!!!!!

NOT!

Page 32: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.

Contractors and Permits

ContractorEngineer

Page 33: Water Main Extension Permits Interplan LLC Richard Lott, P.G., P.E. Program Manager-Drinking Water February 18, 2008 Richard.Lott@dep.state.fl.us 407.893.3325.