Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall Regeneration Company 2010
15

Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Dec 17, 2015

Download

Documents

Lesley Cole
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Walsall Regeneration Company

New Focus

Presentation to Walsall Partnership Board12th April 2010

Akshay Parikh – Chief Operating Officer

Copyright Walsall Regeneration Company 2010

Page 2: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Background

• WRC established in 2004

• Membership: Walsall Council, AWM, HCA, Business Sector, Walsall Partnership

• Defined operational area

Copyright Walsall Regeneration Company 2010

Page 3: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.
Page 4: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Key Issues to Address

• Continuing demographic decline

• Low levels of skills

• Poorly performing town centre

• Inadequate economic structure for the 21st century

• Poor quality of public realm

Copyright Walsall Regeneration Company 2010

Page 5: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Delivery so far

- Opening of largest town centre Asda store in 2007

- IMI Copper Works acquisition/pilot remediation 2009

- New Walsall College opened in 2009

- New Tesco store construction commenced 2010

- New Manor Hospital construction approaching completion

- Waterfront South scheme construction commenced in 2010

Copyright Walsall Regeneration Company 2010

Page 6: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

1) Walsall Waterfront (North, South & West)Project Lead – WRC

2) Darlaston Regeneration AreaProject Lead – WRC

3) Walsall Gigaport. Project Lead – WRC

4) New Walsall Town Centre. Project Lead - Walsall Council

Production of New Walsall Town Centre Regeneration Framework StrategyProject Lead - WRC

Copyright Walsall Regeneration Company 2010

Programme priorities & focus January 2010 onwards

Page 7: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Copyright Walsall Regeneration Company 2010

WRC Project Priorities

Page 8: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Walsall Waterfront

• North (Urban Splash)- Homes, Offices, Hotel, Car Park

• South (Jessup & others)- Town Houses, Key Worker Accommodation, Retail & Offices

• West- Business, Healthcare cluster, Leisure

Copyright Walsall Regeneration Company 2010

Page 9: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Waterfront South

• Phase 1- 158 homes

- £8.5M HCA investment - 120 key worker homes - Accord investment - completion Q2 2011

• Phase 2 - 164 homes

- £6.5M HCA investment - completion Q2 2012

Copyright Walsall Regeneration Company 2010

Page 10: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

New Walsall Town Centre

• Public Realm / Movement

• Leisure / Retail Offer

• St Matthew’s Quarter

• The Market

• Public Transport / Parking

• Animation & Events / Culture Offer

• Safety & Behaviour

• Access to Health Services

• Youth Quarter

Copyright Walsall Regeneration Company 2010

Page 11: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Darlaston Regeneration Area

• Strategic Development Area (SDA)IMI remediation / enterprise development /

skills & jobs / infrastructure & access / low carbon energy

Linking with:

• Strategic Regeneration Framework• Alumwell BSF• Willenhall AAP

Copyright Walsall Regeneration Company 2010

Page 12: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Walsall Gigaport

• New Office Quarter

• Next Generation Access Broadband infrastructure platform

• Public sector shared service / co-location opportunities

• 21st Century Business Base

• Synergies from the New Walsall College

• Live-work accommodation

• Business Incubation

Copyright Walsall Regeneration Company 2010

Page 13: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Working in Partnership

• Walsall Council, AWM, HCA

• British Waterways, Environment Agency, Centro, Highways Agency

• Business Sector

• Investors & Developers

• Think Walsall

• Walsall Partnership

Copyright Walsall Regeneration Company 2010

Page 14: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Key target milestones over next 12 months• Construction to commence on Waterfront North

• Completion of first phase of Waterfront South development

• Development of Waterfront Public Realm / Public Art delivery plan

• Production of delivery plan for DSDA including IMI site

• Selection of preferred delivery partners for Walsall Gigaport scheme, through close working with local partners

• Establishment of delivery plan for New Walsall Town Centre Regeneration Framework, through close working with local partners and others, eg Centro

• Integration of WRC agenda with broader agenda’s - HCA’s Single Conversation, Local Economic Assessment

Copyright Walsall Regeneration Company 2010

Page 15: Walsall Regeneration Company New Focus Presentation to Walsall Partnership Board 12 th April 2010 Akshay Parikh – Chief Operating Officer Copyright Walsall.

Questions