Top Banner
NOAA COMMAND AND DATA ACQUISITION STATION NOAA COMMAND AND DATA ACQUISITION STATION
13

Wallops report presentation (1)

Jul 12, 2015

Download

Documents

ateichner
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Wallops report presentation (1)

NOAA COMMAND AND DATA ACQUISITION STATIONNOAA COMMAND AND DATA ACQUISITION STATION

Page 2: Wallops report presentation (1)
Page 3: Wallops report presentation (1)

DCS POINT OF CONTACT

• WCDA Station’s first point of contact for help is the DCS Help Desk at 757-824-7450 or 7451

• Email is [email protected] with copies to [email protected]

• Contact Phil Whaley at (757) 824-7331 or Al McMath at (757) 824-7316

•Wallops supports 24/7 operations

Page 4: Wallops report presentation (1)

DCS Configuration

• Wallops now supports demods for two complete spacecraft (120 channels each)

• One spare drawer on site (40 channels)

• To date three demod failures

• Preliminary testing has been conducted on the 100/300 baud concept (using the spare demods).

Page 5: Wallops report presentation (1)

Wallops LRGS Configuration

• The demodulators for both East and West continue to feed the LRGS directly.

• This means that the primary LRGS (cdadata) is not dependent on DAPS. Use this as primary.

• The receive site (drot) gets its data from the DOMSAT downlink which is heritage DAPS data.

• We now have a third site (cdabackup).• Wallops supported the STWIG sub-committee

considering LRGS configuration, distribution, etc.• Sites and IPs:

– http://cdadata.wcda.noaa.gov (205.156.2.174)– http://drot.wcda.noaa.gov (205.156.2.186)– http://cdabackup.wcda.noaa.gov (205.156.2.189)

Page 6: Wallops report presentation (1)

LRIT Status

• LRIT traffic to Suitland is dependent on the Internet• Transfer of data to Suitland continues to be a “double”

single point failure• LRIT data is returned to Wallops via T-1 lines. LRIT is an

advantage to international users because DOMSAT is limited to CONUS.

• LRIT now has full East/West data streams • An automatic re-transmission (one time) has been

implemented.• 1 meter antenna receives full LRIT stream• There are no re-occurring costs associated with LRIT

reception.

Page 7: Wallops report presentation (1)

Current Spacecraft Status• GOES-12 remains primary (75) for East• GOES-11 has been transitioned as primary

West (135) spacecraft• GOES-10 is positioned (60) for the South

American mission. Imagery operations began in Nov 06

• GOES-9 was de-commissioned on 14 Jul 07• GOES-13 was tested and placed in storage. It

was brought out of storage in July 07 for testing. • GOES-O launch is scheduled for Summer 08.

Page 8: Wallops report presentation (1)

Wallops Backup

• A second pilot remains active (channel 0) at the WBU. The frequency is 401.7MHz.

• Wallops staff has remote control/status capability of the WBU systems including the pilot from Wallops.

Page 9: Wallops report presentation (1)

DOMSAT Frequency Change

• The final transition to the new DOMSAT frequency was June 13, 2007

• New frequency is 11,817.5Mhz.• All other parameters (pointing angles, modem

settings, etc.) remain the same.• Transition went smoothly.

Page 10: Wallops report presentation (1)

DAPS

• Wallops has experienced data base issues (mid November). Updates had to be re-entered.

• DAPS-B is now primary and has been since November.

• Still supporting telnet (205.156.2.173/178)• Working with OSDPD in the migration to 300/1200

baud channels. • The Weather Service link has been transitioned to

the MPLS (8 Jan 08). We are seeing fewer dropouts.

• Wallops Operations verifies the DCS pilot daily.• No problems during the end-of-year transition.

Page 11: Wallops report presentation (1)

GOES-12 Anomaly

• A North/South maneuver in November resulted in an anomaly of GOES-12.

• A leak in a thruster line resulted in the spacecraft being out of service for more than a week.

• During this time GOES-10 was used for DCPR

• In addition EMWIN and LRIT products were transmitted through GOES-10

Page 12: Wallops report presentation (1)

DADDS

• The DCS Alternate Data Distribution System (DADDS) provides a separate means to distribute data from the demods should DAPS A & B fail.

• Testing was conducted at Wallops Oct 07.• The system has been used on an as-needed

basis.• Currently DADDS will support NWSTG and

DOMSAT traffic.• Training for Wallops Operations staff is

scheduled for the week of 4 Feb.

Page 13: Wallops report presentation (1)

Multiple Data Sources

• We currently support-– DOMSAT (primary)

– LRGS (cdadata, cdabackup, drot)– Telnet (data base updates)– LRIT– NWS Telecommunications Gateway– Dial-in