Top Banner
1 Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND DESCRIPTIONS OF MATERIALS AND WORKMANSHIP APPLICABLE TO ALL SECTIONS OF THIS SCHEDULE 1. GENERAL PRINCIPLES 1.1 The items contained within this document are described in such a way as to reflect its use as a Schedule or Rates for reactive maintenance work and are, therefore, not strictly in accordance with any Standard Method of Measurement. 1.2 Notwithstanding (1.1) the items of work have generally been divided into trade order and measured on an operational basis so that each rate reflects a complete operation of repair work. 1.3 The Schedule of Rates items are based upon historic data obtained from the Authority’s records of previous years’ reactive maintenance and, as such, is deemed to represent the type of work likely to be encountered in a typical calendar year. 1.4 In order for the Authority to obtain the most economic rates for work of this nature, certain operations of work have been sub-divided into varying quantities of work relating to the basic repair operation. The Contractor is to note that the spread of each quantity has been calculated by the Authority to be that giving the greatest economy scale with regard to the nature of the work and the relatively small individual quantitates involved. (see also Clauses 2.1 and 3.9). The schedule of rates item used to value work completed will be the unit rate that corresponds to the total measured quantity of work undertaken per order. This principle of measurement and valuation will be applied to measure, value and reimburse all work and shall apply to the use of all schedule rates. 1.5 Where a scheduled operation in this document states or implies an “average” measurement or operation of work, it is intended that an individual order to carry out such works may involve more or less work than average to be executed, but that the rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or implied. The final discretion as to whether a variation on any item of work executed has occurred, however, shall lie with the Contact Administrator whose decision shall be final and binding. 1.6 The Contractor shall acquaint himself with the measures described in the booklet “Winter Building” (published on behalf of the DETR by and obtained from HM Stationary Office) for maintaining continuity of work and productivity during inclement weather. All rates shall be deemed to include taking such measures as are described in this booklet whenever applicable or required and having regard to the nature, scope and programme of the works. Such measures should normally include provision of site lighting, shelter and screens for the protection of workpeople and the works and the protection of materials and plant from the effects of the weather.
113

Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

Jan 20, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

1

Volume 2 Schedules 4 and 5

GENERAL PREAMBLES AND DESCRIPTIONS OF MATERIALS AND

WORKMANSHIP APPLICABLE TO ALL SECTIONS OF THIS SCHEDULE

1. GENERAL PRINCIPLES

1.1 The items contained within this document are described in such a way as to reflect

its use as a Schedule or Rates for reactive maintenance work and are, therefore, not strictly in accordance with any Standard Method of Measurement.

1.2 Notwithstanding (1.1) the items of work have generally been divided into trade order

and measured on an operational basis so that each rate reflects a complete operation of repair work.

1.3 The Schedule of Rates items are based upon historic data obtained from the

Authority’s records of previous years’ reactive maintenance and, as such, is deemed to represent the type of work likely to be encountered in a typical calendar year.

1.4 In order for the Authority to obtain the most economic rates for work of this nature,

certain operations of work have been sub-divided into varying quantities of work relating to the basic repair operation. The Contractor is to note that the spread of each quantity has been calculated by the Authority to be that giving the greatest economy scale with regard to the nature of the work and the relatively small individual quantitates involved. (see also Clauses 2.1 and 3.9).

The schedule of rates item used to value work completed will be the unit rate that corresponds to the total measured quantity of work undertaken per order.

This principle of measurement and valuation will be applied to measure, value and reimburse all work and shall apply to the use of all schedule rates.

1.5 Where a scheduled operation in this document states or implies an “average”

measurement or operation of work, it is intended that an individual order to carry out such works may involve more or less work than average to be executed, but that the rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or implied. The final discretion as to whether a variation on any item of work executed has occurred, however, shall lie with the Contact Administrator whose decision shall be final and binding.

1.6 The Contractor shall acquaint himself with the measures described in the booklet

“Winter Building” (published on behalf of the DETR by and obtained from HM Stationary Office) for maintaining continuity of work and productivity during inclement weather. All rates shall be deemed to include taking such measures as are described in this booklet whenever applicable or required and having regard to the nature, scope and programme of the works. Such measures should normally include provision of site lighting, shelter and screens for the protection of workpeople and the works and the protection of materials and plant from the effects of the weather.

Page 2: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

2

2. GENERAL DEFINITIONS

2.1 Where classification is given in this document as being between as being between two limiting dimension and quantities, then the interpretation shall be exceeding the first dimension or quantity and not exceeding the second.

2.2 The references “BS” and “CP” refer to the “British Standards” and “Codes of

Practise” respectively and the appropriate published version current at the time work is carried out will apply. Where, without prejudice to legally binding national rules and insofar as the British Standards and Codes or Practice are compatible with community law this shall include equivalent European Standards, European technical approval and common technical specifications of the EEC in respect of material, safety, reliability, function compatibility with existing construction or installations, availability of compatible accessories and where relevant appearance.

2.3 The standard of “Workmanship” will be deemed to mean the minimum acceptable

standard conforming to the relevant British Standard or Code of Practice. Where, without prejudice to legally binding national rules and insofar as the British Standards and Codes of Practice are compatible with community law this shall include equivalent European Standards, European technical approval and common technical specifications of the EEC.

2.4 The standard of “materials” will be deemed to mean the minimum acceptable

standard appropriate for the specified purpose and conforming to the relevant British Standard and shall meet the requirements of the Sale and Supply of Goods Act 1994. Where, without prejudice to legally binding national rules and insofar as the British Standard and Codes of Practice are compatible with community law this shall include also equivalent European Standards, European technical approval and common technical specifications of the EEC.

2.5 The term “Manufacturer” or “Supplier” will be deemed to mean the firm under whose

name the particular product is marketed or its equivalent. The term “Reference” means the proprietary brand name or its equivalent and/or reference by which the particular product is identified. Materials and goods are used or fixed strictly in accordance with the manufacturer’s instructions printed or in writing and current at the date of supply. In the Contract in order to identify a particular style or quality or material trades names have been used but in all cases an equivalent will be acceptable (See also 2.6)

2.6 Where the terms “similar”, “equivalent”, “equal and approved”, “other approved” and

“or the like” have been used, they shall be deemed to mean that materials of different manufactures but of the same quality and standard may be substituted if prior approval has been obtained from the Contract Administrator. The rates or prices, however, will be deemed to be the same as for the material or materials specified within the Schedule of Rates. The Contractor may substitute materials of a higher quality but at no additional cost to the Council.

2.7 Where the term “pre-exposed” has been used in an operation, it shall be deemed to

mean that an item of work has been measured elsewhere in the Schedule for exposing the item, work or material under consideration and both items shall be regarded as one operation for the purposes of complying with an order to carry out work issued by the Contract Administrator.

2.8 Where the term “standard” has been used in relation to a material or commodity, the

rate against the item shall be deemed to include for all standard size material or commodity under consideration.

Page 3: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

3

2.9 The following measurement terms shall apply:-

Lm - Linear Metre m² - Metre squared m³ - Metre cubed Item - Carrying out all the work described in the operation irrespective of the quantity. No/ - Per primary unit of work e.g. per tile, per brick

2.10 With the exception of wall tiles which when “m²” shall be measured to the nearest “0.10m²”, where a “fraction” of a quantity shall apply to any completed work the Contractor shall measure and invoice to the nearest “0.5”, for “Lm” or “m²” and to the nearest “0.10” for M³. “Items” “each” or “No” shall be as the actual number used or pro-rata to the quantity of work actually undertaken except to the extent that when the schedule of rates description specifically details an average range of measurements the “item”, “each” or “No” shall be measured and reimbursed in full.

Page 4: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

4

3. ALL RATES TO INCLUDE

Notwithstanding and in addition to any specific instructions contained within the Schedule of Rates or elsewhere in the tender documents, the Contractor is to note that each individual rate will be deemed to include the cost of the following:-

3.1 All provisions contained within each Preamble Section. (The Contractor is to note that he is not given the opportunity to price directly against the preamble items).

All provisions contained within the Preliminaries Section including but not limited to all general obligations, liabilities and risks implied or expressed in the Contract or Contract documents.

3.2 For carrying out each operation of work at whatever height or location it may be encountered on any individual property to which it may relate including for the provision, erection and removal of all necessary scaffolding, towers, platforms, ladders, roofing ladders and the like that may be required to execute the works, up to second storey eaves level including adjacent roofs.

3.3 Labour and all costs in connection therewith including supervision and management

costs.

3.4 Materials, goods and all costs in connection therewith including the costs of water and power.

3.5 Fitting, erecting and fixing materials and goods in position.

3.6 Plant, tools, equipment and all costs in connection therewith.

3.7 Waste of materials howsoever occurring.

3.8 Establishment charges, all overhead charges, costs and profit, including the cost of

Depot provision, vehicles, transport, communications and the like.

3.9 The cost of carrying out any quantity of work contained within the range of quantities where items are described in accordance with Clauses 1.4 and 2.1 of the general preambles.

3.10 Submitting samples of materials and workmanship if and when requested by the

Contract Administrator who shall have the power to reject any materials or workmanship which do not meet with his approval and/or do not correspond with the approved samples.

3.11 The loading and carting away to the Contractor’s tip/or licensed waste disposal site

of any spoil, waste or material described as “removed”. No burning on site of waste will be allowed under any circumstances. The cost of all charges and taxes in relation to landfill and removing waste to a licensed tip including compliance with the requirements of the Environmental Protection Act.

3.12 The cost of tidying up and cleaning the working environment at each cessation of

work, howsoever causes, to a standard not less than that displayed elsewhere within the building or encountered prior to the commencement of work subject to the final approval of the Contract Administrator including all temporary works and reinstatements.

3.13 The cost of protecting all work and the surrounding working environment by whatever

means may be deemed necessary including, but not limited to, sheeting, screens, dust sheets and the like.

Page 5: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

5

3.14 All square cutting, curved cutting or raking cutting (rough or fair) of materials and all junctions between curved or straight work and/or new or old work.

3.15 Applying one coat of wood primer to any timber (not described as sawn or

impregnated) in any trade sections on backs and edges prior to fixing and on exposed faces after fixing ready to receive a permanent decoration.

3.16 Working in isolated patches, narrow widths or the like or in areas or conditions that

would normally give rise to a premium on standard measured work.

3.17 The total costs of carrying out any operation of work or item at any location within the defined geographical area covered by this Contract (subject to any provisions contained elsewhere within these documents) in relation to travelling costs and time and waiting time.

3.18 The costs in any schedule of fully complying with Health and Safety at Work

Regulations, including but not limited to training and the provision of personal protective clothing except where elsewhere specifically allowed for within the schedule of rates. For the avoidance of doubt the minimum operational standard shall be as described in H.S.E. publication “Health and Safety in Construction” (ISBNO-7176-1143-4).

3.19 Notwithstanding and in addition to any specific instructions contained within the

schedule descriptions or preambles each individual rate shall be deemed to include for the cost of any or all of the following “labours” or “builder’s” work in connection” wherever applicable.

3.20 Concrete Work – For cutting all rough and fair cutting, eaves filling, cutting or

forming chases, forming cavities in hollow walls, closing around openings, arches, grooves, holes, matrices, sinking’s, raking out joins, cutting grooves for flashings, cutting and pinning or building in ends of members and the like, bedding and pointing plates and frames and making good walls and fair face on facings in connection with

Page 6: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

6

DESCRIPTION OF WORKS AND

SCHEDULE OF RATES

SECTION 1

CONCRETE AND OTHER GENERAL EXTERNAL WORKS

Page 7: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

7

CONCRETE AND OTHER GENERAL EXTERNAL WORKS

1. EXCAVATION AND EARTHWORK

1.1 Owing to the restricted nature of this type of work, a proportion of excavation will be by hand digging only and this is deemed to be allowed for in all rates containing excavation work together with the cost of such mechanical plant as the Contractor may deem necessary, and appropriate.

1.2 The rates are deemed to include for digging in whatever ground is encountered and

for grubbing up and removing any obstruction that may be met with, including roots. The rates are also deemed to include for throwing out and wheeling or other method of removal and for the increase in bulk of all excavated material.

1.3 All surplus excavated material, unless otherwise described, is to be carted away to a

tip to be provided by the Contractor.

1.4 The price of disposal of excavated material is deemed to be included in the rates and for all necessary re-digging and double handling temporary spoil heaps or the like.

1.5 Excavation may be the net width of any concrete or the like but the Contractor is

deemed to have allowed for any additional working space that may be required and also for making good any slips that may occur.

1.6 The Contract Administrator reserves the right to inspect or test the bottom of any

excavation and to test or alter the depth or excavation prior to commencement of concreting or the like or filling in the Contractor shall notify the Contract Administrator prior to such excavation commencing or his intention to start work.

1.7 Any antiques or articles or interest found in any excavations are to be handed over

immediately to the Contract Administrator.

1.8 All bottoms of excavations are to be on firm strata, levelled and compacted and filling with excavated material shall be selected excavated material well water and rammed. Rates are also deemed for excavation to falls where required.

1.9 The rates for exaction are deemed to include for providing everything requisite to

uphold the sides of excavations by whatever means necessary and for digging and backfilling working space as required. Providing always that any subsidence or damaged caused by omission of or inadequate earthwork support or any other-excavating shall be filled with concrete of a relevant specification or as directed by the Contract Administrator at the Contractor’s expense.

1.10 Excavated top soil is to be spread and levelled where directed by the Contract Administrator.

1.11 The rates are deemed to include for all profiles, rods or the like and for all pumping and baling which may be required to maintain excavations free from found or surface water.

1.12 The Contractor is to give notice at his own expense to the respective Service Companies should any services be exposed by excavation and to respond to their instructions.

Page 8: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

8

1.13 Notice concerning disruption to or temporary disconnection of electric, gas, telephone or water services to adjoining properties shall be given by the Contractor at his own expense at least five days prior to commencement of any work or as soon as soon as is reasonably practicable in the event of an emergency.

1.14 Where excavation commences through turf, the turf shall be cut back carefully and

set aside prior to commencement, protected during the works and re-laid on completion including punning and watering. All rates for excavation shall be deemed to include this provision and for the protection of all plants, shrubs, trees or the like.

1.15 Disruption to or temporary disconnection of statutory services required by the

excavation works will be kept to a minimum by prior arrangement with the contract administrator. Any reasonable temporary connections in order to ensure the continuation of services will be undertaken by the contractor at his own expense.

2. FILLING MATERIALS

2.1 Granular fill shall be well graded gravel and lie within the following graded limits. B.S. Sieve Size Percentage by Weight Passing 75 mm 100 38 mm 85 - 100 10 mm 45 - 100 5 mm 25 - 85 No. 25 8 - 45 No. 200 0 – 10 This particle size shall be determined in accordance with the requirements of the appropriate BS.

2.2 Samples of the granular fill to be used in the works shall be submitted to the Contract

Administrator as and when requested.

2.3 Hardcore is to consist of large screen ballast, hard bricks, stone or other hard incompressible inert material broken to pass a 75 mm ring.

2.4 The thickness of all hardcore beds is the finished thickness after consolidation.

2.5 The price of all hardcore included rates shall be deemed to include for well ramming

and consolidating in layers not exceeding 150 mm thick.

2.6 Any filling to make up levels due to over-excavating shall be made up with hardcore at the Contractor’s expense.

Page 9: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

9

3. IN-SITU CONCRETE WORK

3.1 The cement is to be ordinary Portland cement complying in all aspects with the BS

cement shall be used fresh upon delivery and shall be stored in a dry area free from moisture. Cement that has deteriorated shall be discarded.

3.2 Sand is to be river or pit sand to the appropriate BS, clean, sharp and free from any saline or other deleterious matter and shall be washed if required.

3.3 All aggregate shall comply in all respects with the BS and shall be graded as Table 1

to pass a 20 mm ring and is to be free from all impurity or deleterious matter.

3.4 Water shall be fresh, clean and free of deleterious matter and shall be obtained from a mains supply.

3.5 All concrete mixes are to be suitable for the purpose for which they are intended and

strictly in accordance with the BS.

3.6 Where weak mix or lean concrete is specified by volume it shall be mixed in the proportion of Concrete 1:17 – 50 kg of concrete to 0.59m³ of all in aggregate.

3.7 The workability of any concrete shall not exceed 50 mm slump in accordance with

the BS and shall be such that it can be readily worked around any obstructions or the like without segregation.

3.8 Concrete shall be well tamped thoroughly worked into all corners and around all

obstructions and solidly compacted: surface treatment shall be by means of a steel trowel or wood float or as otherwise specified in the Schedule.

3.9 Compaction, whether by hand or by mechanical vibration, is to continue until a dense

homogenous mass, free from voids is obtained and which on striking the formwork presents a face free from honeycombing, cracks or excessive dusting. Any concrete which is honeycombed or otherwise unsatisfactory is to be cut out and re-executed or otherwise remedied to the satisfaction of the Contract Administrator.

3.10 Ready-Mix concrete shall not be used without the prior written consent of the

Contract Administrator and all mechanical mixing of concrete shall be by an approved batch mixer, which should ensure a uniform distribution of material throughout the mass and is also capable of discharging the mixture without segregation. The mixing of concrete on site should comply with the BS.

3.11 Hand mixing will only be permitted for small items of concrete and is to be done on a

watertight platform with edging boards in such a manner as to ensure uniform distribution of materials throughout the mass. Mixing is to continue until a homogenous mixture is obtained. The cement content for hand mixing is to be increased by 10% and the extra cost is deemed to be included in the rates.

3.12 Mixing machines platforms, barrows and areas where mixing has been undertaken

are to be cleaned on every cessation of the work.

3.13 Where concrete is laid on hardcore or other absorbent material, the bottom shall be suitable and adequately wetted before the concrete is deposited.

3.14 Where concrete is laid on or next to existing concrete the surface of the existing

concrete shall be hacked back to expose the aggregate to form a key and well

Page 10: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

10

wetted prior to commencing new work. All rates for concrete work shall be deemed to include for the cost of this preparation.

3.15 Traffic or loading must not be allowed on the concrete until the concrete is

sufficiently matured, and in no case shall traffic or loading be of such magnitude as to cause deflection or other movement in the formwork or damage to concrete members.

3.16 When the temperature of the air is near or below freezing point of water or where

there is a likelihood of frost or cold wind, concreting will not be permitted except at the entire risk of the Contractor, who will take all necessary and adequate precautions as referred to under “Winter Building” in the General Preamble, to protect the new concrete and that recently laid from damage.

3.17 Precautions against freezing shall be such as to ensure that the concrete at no time

during mixing, depositing and setting is at a temperature of or below 5ºC.

3.18 When concreting takes place after frost, aggregates must be adequately thawed out and warmed, and the mixers and other plant free from ice and frost.

3.19 Periods of frost shall be entirely disregarded in computing the age of concrete for

striking of formwork.

3.20 All formwork is to be supplied and designed by the Contractor and shall be deemed to be included in the rates of any concrete work.

3.21 All formwork is to be constructed so as to safely support the concrete in its fluid state

and construction loads without appreciable movement or defection. It is to be sufficiently tight to present loss of liquid cement from the concrete and so constructed that it can be removed without undue vibration or shock. Where formwork is supported from existing parts of the structure it is to be so arranged to form a solid bed. Immediately before the concrete is placed, all formwork is to be cleaned thoroughly and all rubbish, chippings, shavings and sawdust are to be well wetted or treated with a composition approved by the Contract Administrator. Retarding or accelerating liquids are to be used only where specifically approved.

3.22 All formwork is to be removed without undue vibration or shock and without damage

to the concrete, proper precautions being taken to allow for the decrease in rate of hardening that occurs in all cements in cold weather.

3.23 The price of all items of formwork included in the rates is to include for all splayed

edges, notchings allowances for overlaps and passings at angles, battens, strutting, bolting, wedging, casing, striking and removing.

3.24 The description “wrought formwork” shall mean formwork so constructed as to give

true profiles and arises to the concrete members and shall be deemed to include for all necessary rubbing down with carborundum to remove board marks, ridges, etc and all necessary stopping off of air holes etc, whilst the concrete is still new to give a true and perfect face, and the rates shall be deemed to allow for this accordingly.

3.25 Expansion joints shall be formed where necessary or as directed by the Contract

Administrator using “Flexcell” or similar approved materials.

3.26 Bar reinforcement shall conform to the BS 4449. Fabric reinforcement shall comply with BS.

Page 11: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

11

4. SCOPE OF THE WORK The Contractor should note that individuals works identified in advance as being above the highest quantity shown in any band in this section of the schedule will be deemed not to be reactive maintenance work and as such would not normally be ordered under the scope of this contract, except at the discretion of the Contract Administrator. (The Contractor may, however, be required to provide a quotation for such larger scale work on an individual order basis and such work will be treated as a variation order).

Page 12: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

12

Prefix No. PC01000 SOR No.

Description

Unit

Rate £

Rate P (pence)

001

CONCRETE WORK Paths and Pavings Patch area of concrete path floor or the like not exceeding 1m² with situ concrete 1:3:6 – 20mm aggregate trowelled smooth to match existing finish.

Item

002

75mm thick bad plain concrete grade 1:3:6 – 20mm aggregate laid level on existing sub-base including all necessary preparation of sub base, formwork expansion joints, surface treatment with a float and trowelled margins (complete operation). Isolated areas not exceeding 10m².

003

Excavate to reduce levels, average 150mm deep including loading, carting away to contractors tip and aggregate laid level on and including average 75mm thick bed of compacted hardcore including all necessary formwork, expansion joints surface treatment with a float and trowelled margins (complete operation). Isolated areas not exceeding 10m².

004

GENERAL EXTERNAL WORKS Excavation and the Like Break up and cart away plain surface concrete or the like in small isolated areas (internal or external) average 150mm think including all labours (complete operation).

005

Filling Hardcore filling in making up levels and compacting in layers not exceeding 250mm thick.

006

Blind surface of hardcore with sand 25mm thick

007

Lean Mix concrete filling to excavation 150mm thick.

008

Concrete Work Plain in-situ concrete (1:3:6 – 40mm aggregate) in foundation in trench 150 – 300mm thick.

009

Plain in-situ concrete (1:2:4 – 20mm aggregate) in foundation in trench 150 – 300mm thick. Reinforced in-situ concrete (1:2:4 0 200mm)

Page 13: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

13

010

100 – 150mm thick

011

150 – 300mm thick

012

Sundries Break up existing floor to form new access for service pope or the like, including forming ducts as necessary, breaking through external wall or the like all making good to wall floors and floor finishing’s. (Complete operation).

Lm

013

Remove existing concrete or timber step form new threshold with insitu concrete 1:3:4 – 20mm aggregate complete with galvanised waterbar, including all wrought formwork, weathered and trowelled smooth top surface, adjusting rebates to door as required and striking formwork, average size 200mm x 1000mm x 100mm (complete operation).

Item

014

Supply and fix in position new PCC plinth or step average size 750mm x 600mm x 50mm thick fair faced on all exposed surfaces bedded in cement mortar (1:3).

Item

015

To repair crack in concrete, cut out to form groove 25mm x 25mm clean away dust and debris and fill mortar.

Lm

016

Take up existing broken paving slabs and dispose. Renew with precast concrete paving slabs to match existing.

Page 14: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

14

DESCRIPTION OF WORKS AND

SCHEDULE OF RATES

SECTION 2

DRAINAGE

Page 15: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

15

DRAINAGE

1. DRAIN RUNS AND MANHOLES

1.1 In addition to the specific requirements of the Drainage Section Preambles, any “Excavation and Earthwork”, “Filling”, “Concrete Work” or “Brickwork” carried out in conjunction with or during “Drainage Works” shall comply in every respect with the preambles for those specific sections of the schedule.

1.2 Prior notice of the commencement of all proposed drainage works must be given to the Contract Administrator who reserves the right to inspect and test (and reject as applicable) any drainage work at the appropriate time. The Contractor is to note that the rates for all drainage work are deemed to include for testing with water and the Contractor shall provide all necessary testing apparatus and attendance.

1.3 The Contractor is to note that no distinction is made in the schedule between

work to “FOUL” or “SURFACE WATER” drains and that the rates are deemed to include for work to either category.

1.4 All drain trenches are to have firm bottoms and drains are to be laid in straight

lines from point to point, to the correct falls. The rates shall be deemed to include for grading and compacting bottoms, carting away surplus spoil to the Contractor’s tip, backfilling select excavated material above granular fill where applicable, earthwork support, working space (and backfilling) and for keeping excavations free from ground or surface water.

1.5 The depths of excavations for all drain trenches, manholes and the like have

been taken as commencing as existing ground level.

1.6 All pipes and fittings are to be Vitrified clay drainage systems or equivalent to BS 65. Pipes and fittings are to be laid strictly in accordance with the manufacturer’s instructions and are to be jointed with push-fit polypropylene flexible couplings. Joints to existing pipework or fittings are to be by means of “flexible” adapters or equivalent, the cost of which are to be deemed to be included within the rates.

1.7 The rates for all pipes and the like shall be deemed to include for sweeping out

and flushing with clean water on completion of all pipes are to be left free from internal obstructions to the satisfaction of the Contract Administrator.

1.8 No right angle junctions are to be used and all bends are to be easy bends.

1.9 Where pipes or fittings pass through walls or manhole walls, they are to be built in

and protected by means of arches, reinforced concrete lintels or pope sleeves. The Contractor is to note that where the term “build-in” is used within the description of the work, the provisions and cost of this item shall be deemed to be included within the rates.

1.10 Where applicable granular material for bedding and surrounding drain pipes shall

be gravel passing 10mm sieve and retained on a 4mm sieve and sufficient coarse sand shall be mixed thoroughly with this material so that the proportion of sand to stone shall not exceed 40% by weight.

1.11 Where applicable, the rate for any description containing granular beds or

surrounds shall be deemed to include for compacting and grading the surface to receive pipes and for granular filling over and around pipes to a minimum height of 100mm above the crown of the pipe to prevent displacement of the pipe.

Page 16: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

16

(Notwithstanding the provisions of this clause the Contractor is to note the manufacturer’s instructions for laying).

1.12 All manhole channel fittings are to be vitrified clay to the appropriate BS and are

to be obtained from an approved manufacturer and laid strictly in accordance with the manufacturer’s instructions.

1.13 Manhole covers and frames are to be to the appropriate BS sealed in grease and

sand and are to be left clean and accessible and painted or supplied with one coat of bitumastic paint.

1.14 Works to drains (clearing etc.) is deemed to include for all associated items and

labour required and no extra payments will be made where conditions dictate that additional labour is required.

1.15 The Contractor will only be required to unblock drains up to and including the first

manhole outside the toilet building.

Page 17: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

17

Prefix No. PC02000 SOR No.

Description

Unit

Rate £

Rate P (pence)

001

Drainage Trenches Excavate trench by hand not exceeding 750mm deep x 500mm (average) wide, including load cart away surplus spoil, dump at contractors tip return fill and ram selected excavated material reinstate existing finishes. Cover any size pipe with approved granular material as required and supply and erect all safety barriers, coverings and lighting as may be necessary (complete operation).

Lm

002

Ditto, as Item 001 but exceeding 750mm and not exceeding 1000mm deep x 600mm (average width).

Lm

003

Pipes, Fittings and Accessories Break out and remove existing defective (pre-exposed) pipe and surround temporarily divert or stop flow. Supply and lay 100mm Supersleeve VCD or similar push fit polypropylene flexible couplings including all necessary adaptors and cutting and jointing to existing drain run or manhole. Reconnect flow and test.

Lm

004

Extra over last item for breaking out and removing existing defective (pre-exposed) pipe bend and surround and supply and lay 100mm internal diameter Supersleeve or similar easy bend to radius required with push fit polypropylene flexible couplings including all necessary adaptors and cutting and joint to existing drain. (per bend).

005

Extra over item 003 for breaking out and removing existing defective (pre-exposed) restbend, oblique junction, saddle or the like and surround, supply and lay 100mm internal diameter Supersleeve or similar replacement as required with polypropylene flexible couplings including all necessary adaptors and cutting and joint to existing drain run (per fitting).

Item

006

Break out and remove existing defective (pre-exposed) gully/trap and surround supply and bed in position vitrified clay stoneware gully/trap (entry as existing) with 150mm square top complete with 150mm x 150mm gully grating and 100mm outlet including jointing to drain and wastes as necessary and surround in 150mm thick concrete, 1:3:6 – 20mm aggregate (complete operation).

Item

Page 18: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

18

007

Manholes and Associated Work Break out and remove defective manhole cover and frame. Supply and fit new 610mm x 475mm clear opening – 32kg rectangular cast iron inspection chamber cover and frame to the appropriate British Standard including bedding and haunching frame in cement mortar (1:3) sealing cover in grease and sand and painting all surfaces with one coat of bitumastic paint and clean out manhole (complete operation).

Item

008

Ditto, all as item 007 but 750mm x 600mm clear opening – 75kg rectangular cast iron inspection cover and frame.

Item

009

Ditto, all as item 007 but internal recessed double seal manhole cover and frame, size and quality to match existing, including making good to all surrounding finished and infill to cover (complete operation).

Item

010

Ditto, all as item 007 but 5 tonne galvanised screw down type inspection chamber cover and frame.

Item

011

Break out and remove defective benching in manhole (any size) and bench in finch concrete (1:3:6) including working between channels and branches to give smooth finish.

Item

012

Break out defective haunching around manhole cover and frame (any size and rehaunch in cement mortar (1:2)).

Item

013

Sundries Remove existing gully kerb and replace with new pre-cast concrete, brickwork and render in cement mortar (1:2) up to 0.25m². Clear up and test.

Item

014

Ditto over 0.25m²

Item

015

Provide and fit new 150mm x 150mm galvanised gully grating.

Item

016

Renew metal drain/gully grid )size 225mm x 225mm) with galvanised grating to match.

Item

017

Clear blockage in WC pan, soil and vent pipe, drainage run or the like with or without the use of rods including flushing through (complete operation including lifting and replacing manhole covers). Drain run not exceeding 30m and not beyond the first manhole from the building.

Item

018

Clear blockage in urinal, (bowl or slab type) soil and vent pipe, drainage run or the like with or without use of rods including flushing through (complete operation including lifting and replacing manhole covers). Drain run not exceeding 30m and not beyond the first manhole from the building.

Item

019

Treat urinal fully or trap with suitable acid wash to remove build-up of scale. Include for all necessary safety

Item

Page 19: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

19

precautions.

020

Visually inspect and report condition of the drainage run at any unit. Include for lifting and replacing all covers to manholes and inspection chambers up to and including the first cover outside the building.

Item

021

Jet out urinal tap or drainage run using mechanical jetter.

Item

022

Acid clean and jet wash rinse to tiled floors. Unit per toiler floor.

Item

Page 20: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

20

DESCRIPTION OF WORKS AND

SCHEDULE OF RATES

SECTION 3

BRICKWORK AND BLOCKWORK

Page 21: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

21

BRICKWORK & BLOCKWORK

1. MORTAR

1.1 In addition to the specific requirements of this section of the preambles, the Contractor’s attention is drawn to the provisions contained within the “Concrete Work” Preambles which shall equally apply to this section where applicable.

1.2 The mortar for brickwork and Blockwork is generally to be composed of one part masonry cement by volume and three parts of clean building sand by volume or as otherwise required by BS. Sand for mortar shall be to the BS. Cement shall be Portland Cement to the BS.

1.3 The materials for mortar shall be thoroughly hand mixed twice dry and continually

mixed whilst sufficient clean mains water is added from a rose on a watertight platform with edging boards. Alternatively, mixing may be carried out in a mortar mill or an approved mortar mixer.

1.4 Mortar shall be made in batches as required for immediate use within 20 minutes

of mixing before the commencement of any set. Mortar that has commence to set shall be discarded and removed from site and under no circumstances shall it be re-tempered or used. Ready mixed mortar and pre-packed dry mortar may be used and shall comply with the appropriate British Standards and shall be used strictly in accordance with the manufacturer’s instructions.

1.5 Pointing shall be to match existing pointing or as otherwise directed by the

Contract Administrator.

1.6 Where an order for repointing is given, the Contractor is to rake out all joints to a depth not less than 12mm deep remove all dust and loose material. The joints shall be well wetter prior to pointing which shall be finished to match the existing or as directed by the Contractor Administrator.

1.7 No work is to be carried out on brick work or Blockwork during frost weather and

all brickwork, pointing or the like shall be covered up with felt, sacking or other suitable protective material whenever necessary to prevent damage by frost or wet weather. Any work found to be defective by failure to properly protect work from exposure to frost or by any other cause shall be re-executed by the Contractor at his own expense to the satisfaction of the Contract Administrator.

2. BRICKWORK AND BLOCKWORK

2.1 The Contractor is to note that the rates for brickwork are deemed to include bonding and pointing to match existing work and that no distinction is made in the rates for operations to walls of differing bond, pointing or for work to bands, dpc courses or the like.

2.2 All materials and workmanship shall comply with the relevant British Standards and Codes of Practice or equivalent in particular BS 3921.

2.3 All bricks are to be sound, hard, well shaped and burnt and obtained from an

approved manufacturer and no brick shall absorb more than one sixth of its dry weight during for hours’ immersion in water.

2.4 Common bricks are to be best quality Phorpes Peterborough Flettons or

equivalent unless otherwise directed by the Contract Administrator.

Page 22: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

22

2.5 Facing bricks shall be of the best quality obtainable and are to match as near as possible the facing bricks that may be encountered on each separate order from the Contract Administrator, or as otherwise directed. The Contractor’s attention is particularly drawn to the fact that no particular facing brick is specified in the schedule nor PC sum for facing bricks given and that the rates are deemed to include for providing and laying any single facing brick that may be encountered within the course of this maintenance contract.

2.6 Engineering bricks shall be best quality Class B blue or red engineering bricks to

match the existing or as directed by the Contract Administrator. The Contractors is to note that it is likely that superstructure work carried out in “Engineering Bricks” within this contract will be to bands, copings, dpc courses or the like and the rates shall be deemed to allow for this provision accordingly. Engineering bricks shall be to the BS.

2.7 The Contract Administrator reserves the right to request samples of any brick (or

block) or standard 1m² sample panel or work prior to the commencement of any work and to reject same if unsatisfactory and the Contractor is to comply with such a request the cost of which shall be deemed to be included within the rates.

2.8 All new bricks, tops of walls left unfinished or attached to existing brick-work are

to be well wetted before commencement of any new work. Bricks are to be laid frog up and the frog is to be completely filled with mortar.

2.9 All brickwork, Blockwork (or the like) is to be kept level, straight and perpendicular

and the joints in each course are to be well flushed up as the work proceeds. Brickwork is to be carried up regularly with no four courses rising more than 300mm and no work shall rise to exceed another by more than 900mm in height (except in glabes).

2.10 All new brickwork, Blockwork (or the like) shall be properly covered to prevent

damage by rain or frost and all facework shall be protected and cleaned to remove mortar stains or the like. Existing brickwork and all cavities shall be protected from mortar droppings or the like which if occurring, shall be cleaned off at the Contractors expense.

2.11 The rates for all brickwork, Blockwork (or the like) shall be deemed to include for

cut tooth and bonding new existing work.

2.12 Where described as “cut out existing” or “remove” the rates for all brickwork, Blockwork (or the like) shall be deemed to include for carefully cutting out (as required) by whatever means necessary, areas of defective brickwork (or other brickwork as directed by the Contract Administrator) so as to cause the minimum amount of disturbance and damage to the surrounding brickwork, finishing’s or the like. Damage caused by failure to observe this clause shall be made good by the Contractor at his own expense to the satisfaction of the Contract Administrator.

2.13 Blocks for use in walls and partitions are to conform to the appropriate BS and

shall be to Building Regulations standards with regards to insulation properties.

2.14 Blocks must not be wetted before use.

2.15 All rates contained within the “Brickwork and Blockwork” section of this schedule are deemed to include for the cost of working at whatever height or location may be ordered and for the provision, erection and removal of all necessary scaffolding, towers, platforms, ladders, roofing ladders or the like that may be required to execute the works, up to the second storey eaves level including adjacent roofs.

Page 23: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

23

2.16 Scope of Work

The Contractor should note that the individual works identified in advance as being above the highest quantity shown in any band in this section of the schedule will be deemed bit to be reactive maintenance work and as such would not normally be ordered under the scope of this contract, except at the discretion of the Contract Administrator. (The Contractor may, however, be required to provide a quotation for such larger scale work on an individual order basis and such work will be treated as a variation order).

Page 24: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

24

Prefic No. PC03000 SOR No.

Description

Unit

Rate £

Rate p (pence)

001

Brickwork and Blockwork Walls Carefully remove bricks from wall for inspection of cavity or the like, clean out as necessary (in area of opening) relay new bricks in cement mortar (1:3) including pointing to match existing (complete operation). Single area 1 – 4 no. bricks.

Item

002 Ditto, as item 001 but single area 5 – 8 no. bricks. Item

003 Ditto, as item 001 but single area 9 – 11 no. bricks. Item

004

Remove defective area of brickwork and prepare surface, supply and lay new bricks bedded and jointed in cement mortar (1:3) bonded and pointed (as work proceeds) to match existing, including galvanised steel twisted pattern wall ties to the appropriate British Standard as necessary (complete operation). Isolated areas up to 10 no. bricks, common.

Item

005 Ditto, as item 004 but facing brick. Item

006 Ditto, as item 004 but engineering brick. Item

007 Ditto, as item 004 but isolated areas 11 – 20 no. common bricks.

Item

008 Ditto, as item 007 but facing bricks. No.

009 Ditto, as item 007 but engineering bricks. No.

010 Ditto, as item 004 but isolated areas 21 – 40 no. common bricks.

No.

011 Ditto, item 010 but facing bricks. No.

012 Ditto, as item 010 but engineering bricks. No.

013

Rake out loose and defective pointing to brick or Blockwork, not less than 12mm deep brush out loose material wet walls and repoint in cement mortar (1:3) to match existing (complete operation). Isolated areas not exceeding 1m².

Item

014 Ditto, as item 013 but no area’s exceeding 1m². m²

015

Air Bricks and Vents Prepare opening in 275mm thick wall and build in 75mm x 225mm terra cotta cavity liner and square hole pattern air brick with plastic “mapvent” internally and make good surround in cement mortar (1:3).

Item

016 Ditto, all as item 015 but 225mm x 225mm ditto. Item

017 Ditto, all as item 015 but 300mm x 150mm ditto. Item

018 Remove existing plaster or plastic louvered vent supply and fix new and make good cement in mortar (1:3).

Item

019 Ditto, as item 018 but enlarge opening and supply and fit new 225mm x 225mm vent ditto.

Item

020

Copings and Like Remove existing defective tile creasing to sills or the like construct new double thickness plain tile creasing course laid in cement mortar (1:3) average projection 37mm to front edge and average 50mm return at ends including all cutting and pointing.

Lm

021 Prepare top of wall, clean off existing mortar bed or the like and lay precast concrete coping to the appropriate British Standard average size 75mm x 200mm, pattern to match existing coping and bed joint in cement mortar (1:3).

Lm

022 Take off and re-bed and point concrete or stone coping to parapet wall at high level.

Lm

023

Remove defective or broken glass brick 150mm x 150mm prepare surface and replace with brickwork – make good to all finishes. Isolated area per glass brick.

No.

Page 25: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

25

024 Ditto, as item 023 but 225mm x 225mm. No.

025 Ditto, as item 023 but 300mm x 300mm. No.

026 Ditto, as item 023 but any size and replacing with brickwork and making good to all finishes.

027

Sundries Apply mastic compound by gun to crack or joint in brickwork/Blockwork up to 6m length and smooth over solution.

Lm

028 As item 027 but joint over 6m long in total. Lm

029

Replace down corning/silicone/sealant to edge of fitting and the like, including rake out existing sealant, prepare and apply new joint up to 6m long in total.

Lm

030 As 027 but joint over 6m long in total. Lm

031

General Brickwork Rebuild existing wall to match existing, including demolish existing portion of wall, salvage reusable bricks where possible, obtaining new bricks to closely match existing. Cut, tooth and bond new brickwork to old in gauged mortar. Brickwork to be pointed to match existing. Clear away all rubble. Common bricks, half brick thick wall.

032 Ditto, as item 031 but one brick this wall. m²

033 Ditto, as item 031 but facing bricks, half brick this wall. m²

034 Ditto, as item 033 but one brick this wall. m²

035

Damp Proof Courses Replace defective damp proof course with 112.5mm wide hessian based damp proof course to the appropriate British Standard lapped at joints including bedding horizontally in cement mortar (1:3) and pointing including cutting out adjacent brickwork, replacing with new bricks to match existing and pointing. Isolated lengths up to 3m.

Lm

036 Ditto, as item 035 but 225mm ditto. Isolated lengths up to 3m. Lm

037

Pointing Repairs Rake out joints of stonework and re-point in cement mortar regular courses. Decayed mortar.

038 Ditto, as item 037 but hard mortar. m²

039 Rake out joints of stonework and re-point in cement mortar random rubble. Decayed mortar.

040 Ditto, as item 039 but hard mortar. m²

041

Remove dressed stone or concrete coping, clean off, prepare top of wall, re-lay and point in mortar not exceeding 500mm wide.

Lm

042

Remove dressed stone coping to gable end wall, clean off, prepare top of wall and re-lay stone including new stainless steel fixing cramps mortised to stoves and re-point in mortar not exceeding 500mm wide.

Lm

043

Attendance Provide a bricklayer for attendance or inspection of works on buildings as requested or instructed by the Contract Administrator for a period not exceeding 15 minutes.

Item

044 Ditto, as item 043 but for each subsequent 15 minute period. Item

Page 26: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

26

DESCRIPTION OF WORKS AND

SCHEDULE OF RATES

SECTION 4

ROOFING

Page 27: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

27

ROOFING

1. GENERALLY

1.1 The Contractor is to note that the work within this section is primarily work of a “patching nature” and as such the rates are deemed to include for the cost of working on roofs of whatever pitch or storey height may be encountered and for the provision, erection and removal of all necessary scaffolding, towers, platforms, ladders, roofing ladders and the like that may be required to execute the works, up to second storey eaves level including adjacent roofs.

1.2 The Contractors attention is particularly drawn to certain units of measurement of the work in this section, which has been chosen to reflect the “patching” nature of the work. The Contractor is to note that the rates for roofing work are deemed to include providing and fixing tiles so as to match as near as possible those existing in terms of quality, size, type and colour and to the same gauge and lap (as applicable). The rates are also deemed to include for all labours, all cutting and all extra work that may be required to eaves, verges, abutments or the like.

1.3 The Contractor is to note that the rates for operations of work to tiles do not

include for “re-felting”, “renewing battens” or “completely re-roofing properties” as such major works are deemed to be outside the scope of this reactive maintenance schedule.

1.4 At the cessation of any roofing work, the Contractor is to ensure that all gutters,

rainwater heads, downpipes or the like are cleaned of debris arising from the work to the satisfaction of the Contract Administrator and all rates shall be deemed to include for this provision.

2. TILES

2.1 The fixing of all tiles shall comply with the provisions of the appropriate British

Standards and Codes of Practice.

2.2 Plain tiles shall be of the best quality obtained from Redland Tiles Ltd or other approved manufacturer to the appropriate BS and shall be in either clay or concrete (as applicable) to match those existing in all respects. Tiles shall be fixed in accordance with the manufacturer’s instructions with 38mm x 12g aluminium alloy nails to the appropriate BS to a lap and gauge to match the existing. The Contractors attention is particularly drawn to the need to use appropriate clay tiles on listed buildings or in conservation areas.

2.3 Concrete Interlocking tiles shall be of the best quality to the appropriate BS and

are to match as near as possible the interlocking tiles that may be encountered on each separate order from the Contract Administrator or as otherwise directed. Tiles shall be fixed in accordance with the manufacturer’s instructions with aluminium allow nails to a lap and gauge to match the existing. The contractor’s attention is particularly drawn to the fact that no particular concrete interlocking tile is specified in the schedule not PC Sum for tiles given and that the rates are deemed for providing and fixing any type, size or colour of concrete interlocking tile (to match the existing) that may be encountered within the course of this maintenance contract.

2.4 Eave tiles are to be fixed so as to form a double courses at eaves or in

accordance with the manufacturer’s instructions. Verges are to be formed in tile

Page 28: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

28

and a half fixed in alternate courses or in accordance with the manufacturer’s instructions.

2.5 Existing tiles shall not be refixed except on the express order of the Contract

Administrator. Tiles described as “refixed” shall be sound (in the opinion of the Contract Administrator) and the rates are deemed to include for carefully removing, cleaning off, denailing, stacking and refixing to match the surrounding tiles to a standard not less than is required for fixing new work.

2.6 The Contract Administrator reserves the right to request samples of any tile prior

to the commencement of any work and to reject same as unsatisfactory. The Contractor is to comply immediately with such a request which shall be deemed to be included within the rates.

2.7 Mortar for bedding or pointing tiles or slates shall be comprised of one part

Portland Cement or equivalent to three parts sharp sand by volume. (See also Concrete and Brickwork Preambles). Surplus mortar is to be struck off to give a smooth finish and pointing is not to be carried out with separate material. In dry weather all units to be bedded or pointed shall be soaked with water prior to work commencing.

2.8 The Contractor shall make all necessary arrangements and take all possible

precautions to ensure that rain, debris, dust or other rubbish does not enter into buildings during the carrying out of any roofing work. He shall protect all surrounding structures or finishes from mortar droppings or other damage during roofing work which, if occurring shall be cleaned off or made good at his own expense to the satisfaction of the Contract Administrator.

3. FLASHINGS

3.1 The Contractor is to note that all lead removed form buildings is to be deemed

“scrap” and his rate shall be deemed to include the appropriate credit.

3.2 All new lead shall be best quality Code 4 English soft pig milled lead to the appropriate BS fixed in accordance with the appropriate Code of Practice.

3.3 Flashings are to be turned down 25mm into brick joints and wedged at 450mm

centres with lead wedges. Stepped flashings are to be wedged at every step.

3.4 No flashings or apron shall be in single lengths longer than 2100mm and must lap at least 150mm at all junctions and angles or over the first adjacent rib of roofing tiles and the rates shall be deemed to include for the cost of this provision.

4. BUILT UP ROOFING

4.1 Bitumen felt roofing shall be an approved built up system such as Anderson HT

Elastomeric M/S as made by D Anderson and Son Ltd., Stretford, Manchester, M32 OYL or similar and approved shall comply with the appropriate British Standard.

4.2 Insulated roof decking shall be purldek as made by Coolag Limited or similar approved.

4.3 Where specified by the C.A. roof decking shall be plywood WBP grade to

BS1455, clipboard type 11/11 to BS5669 or woodwool slabs to BS1105.

4.4 The built up roofing system shall be installed in strict accordance to the manufacturers technical specification and conditions of workmanship. The roofing

Page 29: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

29

system shall include for all the necessary materials and accessories to provide a sound and watertight covering.

5. MEASUREMENT

5.1 The measurement expression (per pitch) shall mean that the total aggregate

quantity of work carried out on each individual roof pitch of the public convenience to which an order relates. The total aggregate quantity of work shall be used to determine the band and hence the rate to be used to value the work. Should the total quantity of work per pitch in an order exceed in any item the highest band shown in the rates, the rate in the highest band shall be deemed to apply.

6. SCOPE OF WORK

6.1 The contractor should note that individual works identified in advance as being

above the highest quantity shown in any band in this section of the schedule will be deemed not to be reactive maintenance work and as such would not normally be ordered under the scope of this Contract, except at the discretion of the Contract Administrator. (The Contractor may, however, be required to provide a quotation for such larger scale work on an individual order basis and such work will be treated as variation order).

Page 30: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

30

Prefix No. PC04000 SOR No.

Description

Unit

Rate £

Rate p (Pence)

001

ROOFING Tiled Roofs Remove defective roof tiles supply and fix new 265mm x 165mm concrete plain tile to match existing fixed with aluminium alloy nails as required including all labours and cutting (per pitch). 1 – 5 tiles (per pitch).

Item

002 Ditto, as item 001 but 6 – 10 tiles (per pitch). Item

003 Ditto, as item 001 but 11 – 20 tiles (per pitch). Item

004

Remove defective roof tiles supply and fix new 265mm x 165mm smooth faced clay plain tiles to match existing fixed with aluminium alloy nails as required including all labours and cutting (per pitch). 1 – 5 tiles (per pitch).

Item

005 Ditto, as item 004 but 6 – 10 tiles (per pitch). Item

006 Ditto, as item 004 but 11 – 20 tiles (per pitch). Item

007

Remove defective roof tiles supply and fix new interlocking concrete roof tiles size colour and pattern to match existing including fixing with aluminium alloy nails as required including all labours and cutting (per pitch). 1 – 5 tiles (per pitch).

Item

008 Ditto, as item 007 but 6 – 10 tiles (per pitch). Item

009 Ditto, as item 007 but 11 – 20 tiles (per pitch). Item

010

Carefully remove slipped or dislodged roof tiles (any size pattern) clean, denial and refix in position including nailing as required and removal/reinstatement of adjacent tiles as necessary per pitch. 1 – 5 tiles (per pitch).

Item

011 Ditto, as item 010 but 6 – 10 tiles (per pitch). Item

012 Ditto, as item 0010 but 11 – 20 tiles (per pitch). Item

013

Flashing and the Like Redress lead flashings to roof, valley or the like including all wedges and fixing as necessary.

Lm

014

Remove defective lead flashings, supply and fix new (code 5) lead flashings including dressing to valleys or the like, including renewing lead wedges and any other fixings, all cutting and forming of angles and the like, removing and replacing tiles and boarding as may be necessary and repointing flashings on completion all to the appropriate British Standard. Maximum girth 500mm (complete operation).

Lm

015

Clean off defective area of sheet lead work and repair by means of soldered dots of the like. Dots in areas average 0.01m² (per plot).

Item

016

Sundries Rake out defective pointing to ridge or hip tiles or the like (any pattern or materials) and repoint in cement mortar (1:3) including all labours. 1 – 10 tiles (per roof).

Item

017 Ditto, as item 016 but 11 – 20 tiles (per roof). Item

018 Ditto, as item 016 but 21 – 30 tiles (per roof). Item

Remove defective ridge or hip tile of the like clean off

Page 31: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

31

019 and refix existing or renew to match existing including bedding jointing and pointing in cement mortar (1:3) including all labours and cutting. 1 – 5 tiles (per roof).

Item

020 Rake out defective pointing to verge or the like and repoint in cement mortar (1:3) including all labours. Lengths 1 – 6m (per roof).

Item

021 Ditto, as item 020 but lengths 7 – 12m (per roof). Item

022

Remove defective bonnet hip tiles clean off and refix existing renew to match existing including bedding jointing and pointing in cement mortar (1:3) including all labours and cutting. 1 – 5 tiles (per roof).

Item

023

Felt Roofing Repairs Temporary repair area of built up felt roofing, sweep clean, cutting out defective layers, rebinding to adjacent layers and covering with single layer felt, dressing with compound and recovering with chippings. Per public convenience, areas up to 1m².

Item

024 Ditto, as item 023 but per public convenience, areas over 1m².

025

Surface dressing to area of felt roofing any size, including clearing away stone chippings, dressing with compound and recovering with chippings. Per public convenience, areas average 1m².

Item

026 Ditto, as item 025 but areas over 1m². m²

027 Take up and renew T & G flat roof boarding with 19mm chipboard not exceeding 5m².

028

Refelt roof with 3 layers of bitumen built up felt, each layer bedded in hot bitumen and top surfaced with granite chippings. Per public convenience, area up to 1m².

Item

029 Ditto, as item 028 but areas over 1m². m²

030 Repair crack in felt roof, lengths 1 – 5m (per public convenience).

Lm

031 Ditto, as item 030 but lengths 1 – 5m (per public convenience).

Lm

032

Sweep clean, remove existing defective asphalt skirting any height and up to 5m in length, reform with new material to match existing; including dressing over splayed fillet, turning into groove in brickwork, repointing and rebounding to adjacent asphalt. Per length 1 – 5m.

Lm

033

Clean off surface (any material) and apply ASP or similar roof tight sealer in accordance with manufacture instructions to roofs including filler to all cracks and the like. Areas not exceeding 1m² (per public convenience).

Item

034 Ditto, as item 033 but areas over 1m² (per public convenience).

035

Clean off surface (any material) and apply Isoflex or similar waterproof sealer in accordance with manufacturer’s instructions to gutters and the like. Per length not exceeding 1m (per public convenience).

Item

036 Ditto, as item 035 but lengths exceeding 1m (per public convenience).

Lm

037 Clean off surface and apply Thompsons Water Sealer or similar to masonry or brickwork.

Page 32: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

32

DESCRIPTION OF WORKS AND

SCHEDULE OF RATES

SECTION 5

CARPENTRY AND JOINERY

Page 33: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

33

CARPENTRY AND JOINERY

1. GENERALLY 1.1 The Contract Administrator reserves the right to request full details of any timber to

be used prior to the commencement of any work and to reject same if unsatisfactory. The Contractor where required shall furnish documentary and mark evidence that any timber is as specified and all rats shall be deemed to include for complying with this provision.

1.2 The Contractor is to note that all rates within this Section where applicable shall be deemed to include for all labours, holes, cuttings, notching, halving, scarfing, morticing, tenoing, wedging and all items of a like nature required including holes for pipes and access boards.

1.3 Where in the execution of any repairs or alterations evidence of substantial live dry rot, wet rot or insect attack on timber is discovered the Contractor is to immediately inform the Contract Administrator, suspend all work likely to be affected and await further instructions.

1.4 The Contractor’s attention is particularly drawn to the fact that no detailed joinery drawings will generally be issued and that where applicable the rates shall be deemed to include for designing items of joinery which unless otherwise directed by the Contract Administrator shall be to match those they are to replace or those existing. Where no method of joining or form of construction is described within this Schedule it shall be deemed to be at the discretion of the Contractor.

1.5 Unless otherwise stated within individual descriptions the rates for all items shall be deemed to include for fixing with nails.

1.6 Notwithstanding specific instructions contained within these preambles, the Contractor is to note that all timber shall be properly kiln dried and stored so as to have the correct moisture content when incorporated into works.

1.7 All rates contained within the “Carpentry and Joinery” section of the schedule are deemed to include working at whatever height or location may be ordered and for the provision erection and removal of all necessary scaffolding, towers, platforms, ladders or the like that may be required to execute the works up to second storey eaves level including adjacent roofs.

2. CARCASSING 2.1 Timber shall comply with the appropriate Code of Practice for the Structural Use of

Timber, and unless otherwise directed by the Contract Administrator is to be classified in accordance with the Code of Practice and shall be European Redwood or equal and approved. The stress grades for timber specified in these Schedules refer to those designations determined in accordance with the appropriate British Standards on Timber Grades for Structural Use, and shall be as follows:- SS/MSS Grade – applies to all structural loadbearing members including floor joists, ceiling joists, trimmers, lintels, beams, common rafters and trussed rafters, collars, purlings, hangers, posts, struts, binders, hips, valleys, bracing, ridges, members in stud partitions.

MGS/GS Grade – applies to all non-loadbearing members including wall plates,

roof, boarding, floor boarding, noggins, grounds, packing, herringbone or solid strutting between floor joists.

Page 34: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

34

2.2 Notwithstanding the above, all timber is to be straight, sound, of bright colour and

mature growth, well-conditioned and properly seasoned, and protected prior to incorporation in any works, and must have not less than eight annual rings per 25mm. it must be clean, sawn, with square edges, free from injurious shakes, splits, warp, wane, dead knots, soft knots, rot, incipient decay, or live insect attack or any defect that may render it unserviceable for its particular purpose. Timber for carcassing work is to hold the full sizes specified. For all structural softwood the moisture content shall not exceed 20 per cent at the time of installation. Where wrought, the timber is to be selected to have the minimum number of knots.

2.3 All timber to be used in any work which will not be painted and all eaves, roof, boarding, battens, eaves and gable soffit boards, fascia’s, bargeboards, bed moulds, skirting’s and window boards is to be pre-treated with pressure impregnated, (such as “Tanalith” or “Celcure”, or a treatment to the appropriate British Standard or Protimes (dipped method) or “Proteme”), woodwork and dry rot preservative. The rates are also deemed to include for treating by hand on site all cut surfaces and ends etc. (before being jointed together) with similar preservative. Copies of relevant Preservation Treatment Certificates should be forwarded to the Contract Administrator.

2.4 Items described as “plugged” are to include for the requisite plugs conforming to British Standards.

2.5 Nails and screws are to conform to the appropriate British Standards Screws for fixing to hardwood are to be non-ferrous. Bolts and nuts are to conform to the appropriate British Standards. Other fixing accessories shall comply with BS.

2.6 Wherever possible all carcassing timber is to be fixed in one length, but where joints are unavoidable the timbers are to be properly halved and spiked, scared and spiked or bolted as applicable. Scarfing are to be 450mm long and placed at the mm (no butt joints will be permitted).

3. JOINERY, FIRST, SECOND FIX AND COMPOSITE ITEMS

3.1 All timber shall be softwood unless otherwise described, or as directed by the

Contract Administrator.

3.2 Softwood shall be unsorted grade to comply with the appropriate British Standard having straight grain and not less than 12 annual rings per 25mm. Flooring shall comply with the appropriate Code of Practice.

3.3 For internal woodwork the moisture content shall not exceed 12 percent at the time of fabrication or installation and for external joinery work 18 percent.

3.4 Hardwood shall not be used unless no other alternative is available, shall comply with the appropriate British Standard and shall be best commercial grade and shall be equal to samples to be submitted to approved by the Contract Administrator. Unless otherwise instructed all hardwood shall be kiln dried to a moisture content not exceeding 12 percent. Only hardwood from accredited sustainable sources will be permitted to be used on the contract.

3.5 All joinery is to be cut and framed together in the best manner as soon after the commencement of work as possible, but not glued and wedged until the works are ready to receive the same. All framings are to be properly stored before wedging, glued joints are to be cross-tongued and mouldings are to be worked on the solid. All framings shall be put together with well-fitting mortice and tenon joints wedged up solid. All linings are to be properly tongued at angles and intersections. All arises of woodwork shall be slightly rounded. Adhesives are to comply with BS Part I Type WBP for external work and Type MR for internal.

Page 35: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

35

3.6 All sixes shall be deemed to be basic (nominal) sizes unless stated as finished sizes.

Timber for joinery is to hold the full sizes specified when fitted less 3.2mm for each planed surfaced.

3.7 All joinery shall be stored and protected from the weather prior to and after delivery to any site and the Contractor shall take all necessary precautions in stacking and storing joinery to prevent distortion of damage. All floor boarding or the like shall be stacked face downwards and be protected from the weather. Floor boarding shall be to BS. Chipboard shall comply with the BS moisture resistant to Grade V313. Plywood and Blockboard shall be to BS.

3.8 All joinery is to be either delivered from the manufacturer ready primed, or is to be knotted and receive one coat of wood primer on backs and edges prior to fixing and on exposed faces after fixing ready to receive a permanent decoration. The Contractor is to note that all joinery rates are deemed to include the cost of complying with this provision.

3.9 Should any woodwork shrink, warp, fly or wind more than 3mm it shall be removed and replaced with new at the Contractor’s expense, together with all other work affected or entailed, to the satisfaction of the Contract Administrator.

3.10 Doors generally shall be of not less quality and standard than the relevant section of British Standards and fire checked doors to be and fitted with identification marks. Hardboard shall be standard type conforming to British Standard plywood shall conform to British Standard interior quality and shall be type MT Bonded; MR Bonded having kiln dried softwood core synthetic resin adhesives shall conform to British Standard for exterior work and type MR for interior work.

3.11 Door frames and linings shall comply with and be constructed to BS. Frames for fire doors shall comply with the BS.

4. IRONMONGERY 4.1 All items of ironmongery unless otherwise specified within an operation of work within

this Schedule are to be similar and equal in quality to those which they are to replace. Rates that include items of ironmongery are deemed to include for flush or surface fixing (as required) with a full set of matching screws of the correct gauge, length and material (brass or steel) fit for the purpose for which they are required.

4.2 New or existing ironmongery shall be properly protected and masked and if necessary, to avoid damage removed and subsequently refixed during or near the completion of any work.

4.3 Under no circumstances is the contractor to refix salvaged ironmongery unless expressly required to do so by an operation of work contained within this Schedule or on the instructions of the Contract Administrator.

4.4 All items of existing ironmongery that are permanently removed from any works shall be deemed “scrap”.

5. SUNDRIES

5.1 Plastic faced boards or worktops are to be as Formica standard board and shall consist of a constructional blockboard complete with Formica or equal approved covered to surface, edges and all other surfaces that will be exposed when the works are complete. The fixing of this material is to be strictly in accordance with the manufacturer’s instructions and with the recommended adhesive.

Page 36: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

36

5.2 Fibre Glass Insulation quilt to the appropriate British Standard shall be laid between joists, flat and well butted up at joints. The Contractor’s attention is drawn to good practice with regard to not insulating under tanks or the like and to the provisions regarding a free flow of air into the roof space at the eaves level, and shall comply in all respects with these provisions.

5.3 All work to receive mastic sealant shall be properly cleaned prior to application. The mastic sealant pigmented as required shall be of a type fit for the purpose intended and applied with a cartridge gun strictly in accordance with the manufacturer’s instructions with the appropriate nozzle to give a neat joint.

Page 37: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

37

Prefix No. PC05000 SOR No.

Description

Unit

Rate £

Rate p (pence)

001

CARPENTRY AND JOINERY SC4 Structural Timber/Roofs Cut out defective structural timber not exceeding 2 metres long and replace with impregnated sawn softwood including all labours (isolated work). Timber section 50mm x 150mm.

Item

002 Ditto, as item 001 but timber section 50mm x 200mm. Item

003 Ditto, as item 001 but timber section 50mm x 225mm. Item

004 Ditto, as item 001 but timber section 75mm x 150mm. Item

005 Ditto, as item 001 but timber section 75mm x 200mm. Item

006 Ditto, as item 001 but timber section 75mm x 225mm. Item

007

Cut out defective timber (any size) in roof and replace with 50mm x 100mm impregnated sawn softwood not exceeding 2m long including all labours (isolated work).

Item

008 Ditto, as item 007 but 75mm x 225mm timber section. Item

009 Ditto, as item 007 but 50mm x 200mm timber section. Item

010

Cut out defective bargeboard and replace with wrought softwood bargeboard to match existing including all labours. Isolated lengths not exceeding 1m.

Item

011 Ditto, as item 010 but lengths exceeding 1m. Lm

012 Extra over bargeboard for forming and fixing shaped end including all labours and gluing and screwing.

Item

013

Cut out defective facia or soffit and replace with wrought softwood boarding to match existing including all labours. Isolated lengths not exceeding 1m.

Item

014 Ditto, as item 013 but lengths exceeding 1m. Lm

015

Cut out and remove defective timber boarding or the like and replace with wrought impregnated tongued and grooved board to match existing including all labours.

016 Ditto, as item 015 but replace with 18mm thick chipboard. m²

017

Skirtings and the like Remove defective skirting or the like, any size or pattern and fix new skirting to existing design, including all labours up to 100mm x 20mm sectional size.

Item

018 Doors and Associated Works Drill plug and screw door frame or lining to brickwork or concrete (per frame).

Item

019 Repair split door frame or lining including gluing and screwing (per jamb).

Item

020

Remove defective timber and splice door frame on opening jamb to existing design wrought soft wood not exceeding 300mm and cross-sectional area not exceeding 0.0075m².

Item

021

Remove defective timber and splice door frame or lining on opening edge jamb to existing design with wrought softwood not exceeding 1500mm long and cross sectional area not exceeding 0.0075m².

Item

022 Ditto, as item 021 but to hanging side jamb including fixing new butts as required, recommission door test.

Item

023

Remove defective opening jamb of frame or lining and renew to existing design with wrought softwood not exceeding 2500mm long and cross sectional area not exceeding 0.0075m².

Item

024 Ditto, as item 023 but to handing jamb including fixing new butts as required, recomimission door test.

Item

Remove defective door frame complete, supply and fix new

Page 38: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

38

025 quality standard size frame, complete, recommission existing door including all making good and test.

Item

026

Remove defective door lining complete including architrave stops and timber step make up and fix average 150mm x 25mm wrought softwood door lining, recommission existing door, including refixing all stops, architraves, timber step as necessary, make good and test.

Item

027

Remove door stop de-nail, clean off excess paint and fix new 25mm x 50mm (maxiumum) wrought softwood stop (per set) (any size opening).

Item

028 Ditto, as item 027 but per jamb. Item

029

Ditto, as item 027 but new 25mm x 25mm (finished) stops glued and screwed to fire door, frames at 225mm centres (per set) (any size opening).

Item

030 Ditto, as item 029 but per jamb. Item

031 Remove door stop, de-nail, clean off excess paint, adjust position and refix existing (per jamb).

Item

032 Ditto, as item 031 but per set. Item

033

Remove architrave or the like, de-nail, clean off excess paint, adjust position and refix (any size) (per jamb) (one side opening only).

Item

034 Ditto, as item 033 but per set. Item

035

Remove defective architrave of the like and fix new 25mm x 75mm (maximum) wrought softwood architrave including all labours (per jamb) (one side of opening).

Item

036 Ditto, as item 035 but per set. Item

037

Rehang existing door including altering handing removing and refixing existing stops, ironmongery and the like, make good and test complete.

Item

038

Remove defective boarding to framed ledged and braced door or the like, not exceeding 1m², replace with 100mm x 19mm wrought tongued and grooved match boarding including priming all joints and backs before fixing and test operation of door.

039 Refix loose board to framed ledge and braced door or the like. Average size 900mm x 2100mm (overall).

Item

040

Remove defective weather board not exceeding 1m and replace with 75mm x 75mm wrought softwood weatherboard, once splayed rebated and grooved and counter suck, screwed to face of door, including bedding in mastic.

Item

041

Ease and adjust any door in position, lubricate hinges and apply one coat primer once u/c plus gloss coat to bare wood as required and leave in working order.

Item

042

Ease and adjust ledge braced door (any size) involving removal, lubricate hinges and apply one coat primer, one under coat plus gloss coat to all bare wood as required and leave in working order.

Item

043 Ditto, as item 042 but standard door. Item

044

Remove existing door and fittings, supply and fit new 44mm thick half hour fire resisting standard size to match existing flush door including 1½ pairs 100mm brass butts, mortice lock, SAA furniture adjust stops as required and leave in working order.

Item

045

Remove existing door complete, supply and fix new standard framed ledge and braced matchboard door (Bolton and Paul or equivalent) size to match existing complete with 1½ pairs 100mm brass buts, Union dead/mortice lock 2177 all to pass on M117m Key and 2

Item

Page 39: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

39

keys, escutcheon, 1 set external quality metal lock furniture, weatherboard (as necessary) including applying one coat of primer, all labours adjusting all stops or rebated and the like, test and leave in working order.

046

Remove existing door complete, supply and fix new standard ledge and braced matchboard door (Bolton and Paul or equivalent) size to match existing complete with Suffolk latch, pair 450mm tee hinges, including applying one coat of primer, all labours, adjusting all stops rebated and the like, test and leave in working order.

Item

047

Extra overhaul all new doors for preparing and fixing salvaged, bolts, hooks, numerals, closures and the like to new or existing door (per set).

Item

048 Take off door, repair and rehang including renewing 1 no. 100mm brass butts.

Item

049

Ease service and adjust any standard door or cupboard lock, latch or the like including lubricating, adjusting keep as necessary, testing and leave in sound working order (per complete door set).

Item

050 Service overhaul and adjust door stay or closure (any type) test and leave in sound working order (per closure).

Item

051

Remove existing and make up and fix new cupboard shelf average size 800mm x 800mm with 25mm x 50mm wrought softwood slats countersunk screwed to bearers at 75mm centres including 2 no. bearers plugged and screwed to walls.

Item

052

Cut out defective panel and fix new 9mm thick WBP marine quality plywood infill panel average size 600mm x 600mm to door or the like including pinned quadrant mould.

Item

053 Remove existing, supply, position and fit new toilet cubicle door bolt and indicator.

Item

054 Remove existing, supply and fit new 150mm (average) SAA barrel and bolt keep.

Item

055 Remove existing, supply and fit new 200mm (average) black japanned tower bolt.

Item

056 Remove existing, fit black japanned 150mm door hook and eye.

Item

057

Remove existing fitting complete, position and fit new 200mm (average) black japanned padlock bolt and padlock or hasp staple and padlock as required.

Item

058 Remove existing defective “T” hinges position and fit new pair 450mm (average) black japanned “T” hinges (per set).

Item

059

Cut existing padlock (any size or pattern) from fitting, fir new 50mm (average) galvanised case, 4 level 12 differs padlock and test. Padlock to be supplied by C.A.

Item

060 Remove exiting and fir pair new 100mm brass buts (per door).

Item

061 Ditto, as item 060 but 1½ pairs new 100mm brass butts (pre door).

Item

062 Ditto, as item 060 but 1½ pairs new 100mm brass butts. Item

063

Remove existing mortice lock and furniture and replace with new Union dead/mortice 2177 all to pass on M117m key and 2 keys.

Item

064 Remove existing cylinder lock and replace with Union or equivalent brass faced cylinder lock.

Item

065

Remove existing rim lock and furniture and fit new union or equivalent 3 lever rim lock or deadlock metal rim lock furniture.

Item

066 Remove existing position and fit new Briton 2000 series or Item

Page 40: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

40

equivalent overhead door closer size and handing as required and test operation of door.

067 Supply and fit new 200mm (average) monkey bolt. Item

068 Supply and fit new 150mm (average) SAA barrel bolt and keep.

Item

069 Supply and fix new 50mm screw fixed numberals. Item

070 Supply and fit new 150mm (average) SAA “D” handle. Item

071 Ditto, but new 300mm (average) SAA ”D” handle. Item

072 Supply and fit 150mm SAA bow handle. Item

073 Supply and fit new SAA 305mm (average) finger plate. Item

074 Supply and fit tubular steel catch or roller catch. Item

075 Fix toilet roll holder as supplied by C.A. including screwing to any background.

Item

076

Supply and fit lockable chrome toilet roll holder as manufactured by A-Z Ltd including plugging and screwing to any background.

Item

077 Supply and fit new Union dead/mortice lock 2177 all to pass on M117m key and hand over 2 no. keys on completion.

Item

077A Ditto, as item 077 but R.A.D.A.R. lock. Item

078 Supply and fit Yale lock 3200 series cylinder mortice dead lock compatible with Euro-profile cylinder with thumbturn as instructed by C.A.

Item

079 Supply and fit Yale lock 3200 series with thumbturn. Item

080 Supply key to fit Yale 3200 cylinder. Item

081 Supply and fix new “Perko” or similar door closer, complete and test door operation.

Item

082 Supply and fix padbolt oval (as Nichols and Clarke H04960.01 or similar approved).

Item

083 Supply and fix Hasp and Staple as (Nichols and Clarke H01675.03 or similar approved).

Item

084 Supply and fix metal pull handle/or push plate – any size. Item

085

Windows and Associated Work Remove casement or fanlight window remove defective hinges supply and fix 1 pair new 64mm steel hinges or stormproof type and test (complete operation).

Item

086

Remove existing casement stay any size or type supply and fix new 254mm long (average) white epoxy finish zinc alloy stay with 2 no. pins complete with matching screws and test.

Item

087 Ditto, as item 086 but casement fastener. Item

088

Remove existing casement stay (any size or pattern) from metal window, supply and fix new 254mm long (average) standard type “Crittall” or equivalent replacement stay and test.

Item

089 Ditto, as item 088 but “Crittall” or equivalent casement fastener.

Item

090

Ease casement sash or fanlight timber or metal type any size including lubricating hinges, remove excess paint, with or without removal spot prime as necessary and test (complete operation).

Item

091

Cut out defective timber to frame or sub-frame splice in new wrought softwood to match existing design including gluing and screwing and all labours in lengths not exceeding 1m and cross sectional area not exceeding 0.0075m².

Item

092

Ditto, all as item 091 including removing and renewing glass with 6mm G.W.C. to match existing (new glass not exceeding 0.75m²) and test (complete operation).

Item

093 Ditto, all as item 092 but renewing but meshlite. Item

094 Ditto, all as item 092 but renewing with macralon. Item

Page 41: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

41

095 Ditto, all as item 092 but splice mullion or transom or the like up to 2m length.

Item

096

Cut out defective timberfrom window sill (part section) splice in new wrought softwood to match existing design including gluing and screwing and all labours in lengths not exceeding 2m and cross section not exceeding 0.0075m².

Item

097

Cut out defective timber from sub-frame including removing metal window or the like not exceeding 1.5m² (overall), renew sill or the like in new wrought softwood to match existing design cross sectional area not exceeding 0.0075m², including refixing window in and bedding and pointing external joints with polysulphide mastic all labours and test (complete operation).

Item

098 Ditto, all as item 097 but metal window or the like over 1.5m² but not exceeding 3m².

Item

099

Remove glass cut out defective timber from window sash (any pattern), renew bottom rail or the like in new wrought softwood to match existing design including all labours in lengths not exceeding 1.5m and cross sectional area not exceeding 0.0075m² refix sash and test (complete operation). (Note: reglazing measured elsewhere).

Item

100

Remove existing casement sash or fanlight make up new to existing design including hinges, stays, fasteners, glass and glazing and fitting and fixing and test in areas not exceeding 0.5m² (complete operation).

Item

101 Ditto, as item 100 but in areas over 0.5m² but not exceeding 1.5m².

Item

102

Cut out defective timber from window louver. Splice in new wrought softwood to match existing design including gluing and screwing and all labours, cross section area not exceeding 0.0075m².

Lm

103

Minor repairs to Crittall type metal casement windows: Ease and adjust metal casement window including overhaul ironmongery, straighten and adjust stays, fastenings, hinges, adjust opening casement to close properly and securely without any excessive gaps around the frame and leave in good working order, including touching up decorations. Casement window per casement.

Item

104 Ditto, as item 103 but to window with meshlite glazing. Item

105

Major repairs to Crittall type metal casement windows: Repair to metal casement window including piece in damaged area of softwood sub frame, take off and renew opening casement, provide new ironmongery all as necessary, renew broken glass, to existing glazed panes, including touching up decorations. Casement window per casement and frame.

Item

106 Ditto, as item 105 but to window with meshlite glazing. Item

107

Remove existing defective timber window frame complete make up new non standard size to match existing design cross section areas of timbers not exceeding 0.02m² including all making good, and polysulphide pointing to external joints (complete operation). In opening not exceeding 1.5m² (overall).

Item

108 Ditto, as item 107 but including provision of louvre slats to match existing.

Item

109 Ditto, as item 107 but in openings over 1.5m² but not exceeding 3m² (overall).

Item

110 Ditto, as item 107 but including provision of louvre slats to match existing.

Item

Page 42: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

42

111 Ditto, as item 107 but to replace with UPVC lourved window to match existing profile and specification.

112

Tank Platforms Make up and fix tank platform comprising 50mm x 125mm impregnated sawn softwood bearers 5033 x 75mm impregnated sawn softwood cross bearers and grooved boarding. In areas up to 1m² average.

Item

113

Make up and fix header tank platform comprising 50mm x 50mm impregnated sawn softwood legs 2 no. rows of 50mm x 25mm impregnated sawn softwood rails and 25mm x 100mm tongued and grooved boarding. In areas up to 0.25m².

Item

114

Worktops Supply and fix readymade worktop comprising 30mm thick blockboard plastic laminated faced to approved pattern exposed edges to be lipped with plastic laminate. Not exceeding 600mm width including all labours.

Lm

115

Supply and fix cubicle Systems Ltd budget range worktop with melamine finish as manufactured by Cubicle Systems 1-3 Nova Business Unit, Gore Road Industrial Estate, New Milton BH25 6RR.

Lm

116 Extra over item 115 and 114 cutting out to inset basin. Item

117

Metal Doors Repair metal door or metal faced door and frame any size, straighten door and frame, piece in damaged section of sub-frame, take off rehang door as necessary, overhaul or renew ironmongery make good to decorations and leave in good working order.

Item

118

Renew standard metal door and frame, remove old door and frame and supply and fix only new metal door and frame any type, any size together with all necessary new ironmongery, glaze and paint and make good all work disturbed.

Item

119

Cover existing door with 18g galvanised sheeting face fixed to door with anti-vandal screws. Alter and adapt door frame, stops and lock to suit – Price per door face.

Item

120 Cover cubicle wall with 18g galvanised sheeting face fixed to wall with anti-vandal screws.

121

Pipe Casings and the like Carefully remove existing pipe casing any girth for inspection of pipes (by others) and refix with brass cups and screws (per storey height).

Item

122

Fit new pipe casing or the like not exceeding 600mm firth (overall) comprising 38mm x 38mm impregnated sawn softwood framing plugged and screwed to brickwork (as required) 38mm x 38mm ditto, noggins at 500mm centres, faced with 6mm thick plywood including drilling and screwing to framing with brass cups and screws to framing with brass cups and screws, all labours including angles, cutting round pipes and the like and apply one coat primer on completion.

Lm

123

Sundries Supply and fit wrought softwood batten to any surface, including plugging and screwing as required removing existing as necessary all chamfers splay cuts and other labours. In isolated lengths average timber size 50mm x 25mm.

Lm

124 Ditto, all as item 123 but timber size average 100mm x 25mm including all labours.

Lm

Page 43: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

43

125 Ditto, all as item 123 but impregnated sawn softwood battens 25mm x 50mm.

Lm

126 Ditto, all as item 123 but impregnated sawn softwood battens 25mm x 100mm.

Lm

127

Supply and fix toilet sign size to match existing to the appropriate British Standard to brickwork or the like including plugging and screwing as necessary.

Item

128

Fix toilet sign supplied by CA of any dimension to masonry or wood surface as directed including plugging, screwing or gluing.

Item

129 Supply and fix 50mm x 50mm mopstick handrail including brackets at 900mm centres including all labours.

Lm

130

Supply and fix 18mm waterproof bonded polymer plywood to the appropriate British Standard as infill average size 150mm wide x 600mm deep on and including 25mm x 50mm wrought softwood bearers as necessary including all labour.

Item

131 Ditto, as item 130 but as face panel size 150mm wide and 900mm high leave ready to receive painting (by others).

Item

132

Provide a carpenter for attendance or inspection of works as requested or instructed by the C.A. for a period not exceeding 15 minutes.

Item

134

Minor repairs to toilet cubicles including repairing ironmongery locks and hinges repairs to feet and angle member (where replacement available) cleaning and making good to affect surfaces upon completion, single cubicle set.

Item

135 Ditto, as item 134 but double cubicle set. Item

136 Extra over for addition cubicles. No.

137

Grab Rails Supply and fit the following grab rails to any surface. All fittings to comply with part M of the Building Regulations. These rails are for physical support and must therefore be fixed securely in accordance with the manufacturers instructions. Straight rail with two fixings any length.

Item

138 Ditto, as item 137 but straight rail with three fixings any length.

Item

139 Ditto, as item 137 but angle rails with two wall fixings any length.

Item

140 Ditto, as item 137 but angle rails with three wall fixings any length.

Item

141 Ditto, as item 137 but angle rails floor/wall fixing any length. Item

142 Ditto, as item 137 but toilet backrest with two wall fixing any length.

Item

143 Ditto, as item 137 Armitage Shanks Devon Drop down grab rail with support leg.

Item

144 Dismantle and remove defective grab rail or disabled fitting clean and prepare surface.

Item

145

Slatted Timber Seating Replace slat to timber seating, take off defective or broken slat, supply and fix new (any size) all to be fixed with screws or bolts to match existing (complete operation). Single softwood slat.

Lm

146 Ditto, as item 145 but single hardwood slat. Lm

147

Security Boarding Supply and fix security boarding to doors or windows in 18mm external quality plywood, securely fixed allowing minimal damage to self-finished frames. Single door (any size)

Item

Page 44: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

44

148 Ditto, as item 147 but window (any size). m²

149

Ditto, as item 147 but include removal of security boarding clear away and make good damaged finishes. Single door (any size).

Item

150 Ditto, as item 149 but window (any size). m²

151

Public Convenience Closure/Opening This item to be read in conjunction with similar items in section 6 & 7. Supply and fix 15mm plywood including timbers if necessary and boar dup and make secure public convenience. Per public convenience.

152

Carefully remove 15mm plywood including timbers and arrange for suitable storage of plywood for reuse. Per public convenience.

153

Fix previously removed and stored 15mm plywood including timbers if necessary and make secure public convenience. Per public convince.

154

Remove existing door complete. Supply and fix new non-standard door to match existing complete with 1½ pair of brass butts, lock and furniture to approval of C.A., including weatherboard (if necessary) and applying base priming coat for decoration.

Item

155

Remove existing door lock and furniture and replace with new non-standard lock and furniture as directed and supplied by C.A.

Item

156 Supply and fix new aluminium indicator bolt and keep to match existing (as made and supplied by Fleet Ltd).

Item

157

Supply and fix timber battening and plywood 12.5m exterior quality ply to construct full boxing to house a concealed flush unit high or low level.

Item

158 Supply and fit timber battening and conti board to construct full boxing to house a concealed flush unit high or low level.

Item

159

Take out old sash window, fanlight or the like and fit new louvers to window including all cutting out to existing frame area up to 0.5m².

Item

160 Ditto, as item 159 but area 0.5 – 1.0m². Item

161 Take out damaged lourve and replace with new timber to match existing, per lourve.

Lm

162

Fencing Remove defective fence panel and supply and fix new 1800mm x 1800mm interwoven or lap type panel to match existing including 1 coats wood preservative on completion (per panel).

Item

163

Remove existing defective post including breaking out as required supply and fix new 75mm x 75mm oak post 2400mm long including excavation backfill and remove surplus spoils, surround base in concrete apply 2 coats wood preservative and refix panel, fence or the like on competition (per post).

Item

164 Ditto, all as item 163 but new pre-cast concrete post 100mm x 100mm x 2400mm long (per post).

Item

165

Supply and erect 100mm x 100mm x 2400mm reinforced pre-cast concrete post, 0.45m deep in concrete at 2.4m intervals with 3 horizontal rails, 75mm x 75mm, feather edged close bordered fence 1.65 high and creosoted.

Lm

166 Supply and fix 150mm x 25mm x 1500mm sawn and treated feather edged boarding. Up to 5.

No.

167 Ditto, as item 166. More than 5. Lm

168 Supply and fit arris rails for close boarded fencing. Lm

169 Supply and fit galvanised arris rail fixing brackets. Item

Page 45: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

45

170 Minor repairs to doors i.e. repair split panel and or apply ply panel to damaged area.

Page 46: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

46

DESCRIPTION OF WORKS AND

SCHEDULE OF RATES

SECTION 6

PLUMBING

Page 47: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

47

PLUMBING

1. GENERALLY 1.1 All rates contained within the “Plumbing” section of this schedule are deemed to

include for the cost of working at whatever height or location may be ordered and for the provision, erection and removal of all necessary scaffolding, towers, platforms, ladders or the like that may be required to execute the works up to second storey eaves height.

1.2 The Contractor’s attention is particularly drawn to the fact that no plumbing layout drawing will generally be issued and that where applicable the rates shall be deemed to include for designing plumbing layouts or systems which unless otherwise directed by the Contract Administrator shall be to match those they are to replace.

1.3 Notwithstanding anything contained within this schedule, all plumbing work shall comply with the Acts and Byelaws (current at the date work is undertaken) of the Tendring Hundred Water Services Ltd and the rates are deemed to include for this provision and for giving all notices demandable under such Acts and Byelaws and obtaining certification of works as and when required. Systems shall be installed so that they comply with BS and free leaks and water hammer, where appropriate all items shall be “Kitemark” certified.

1.4 The Contractor’s attention is particularly drawn to the relevant Safety Regulations regarding the removal of existing Asbestos based products, the cost of complying with which is deemed to be included within the rates.

1.5 The rates for plumbing operations where applicable are deemed to include the following:- (1) Assembling and jointing together the component parts of composite units and

providing any necessary connecting flanges and jointing material.

(2) All patterns, moulds, templates and the like. (3) Fixing to whatever background may be encountered with the correct fastenings

and any necessary drilling to include:-

(a) Building-board which shall be deemed to include hardboard, fibre cement sheet, plasterboard, fibreboard and similar materials which do not drip wood-screws.

(b) Timber which shall be deemed to include softwood, hardwood, blockboard, plywood and similar materials which will grip wood-screws when a lead-hole has been drilled.

(c) Metal-faced or composition-faced timber which shall be deemed to include

faced blockboard, faced plywood and similar materials which will grip wood-screws when a lead-hole and shank clearance hole have been drilled.

(d) Brickwork, concrete or stonework which shall be deemed to include

reinforced concrete, Blockwork and similar materials which require plugging irrespective of any plaster, glazed tiles, composition or other finish (excluding glass) to the surface.

(4) Working on internal or external locations.

(5) All temporary work, removing same and making good after, including lifting and

replacing floorboards or the like.

Page 48: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

48

(6) Connections to existing work including cutting or breaking into existing pipes where necessary.

(7) Shutting off valves isolating or draining down and refilling and restoring the water

supply and completion to such portions of the system that me be required to execute the works (See also 7.1 and 7.2)

(8) All “Builders work in connection” (with regard to the nature of the work) including

bedding and pointing components or units, cutting and pinning ends of supports, cutting away for and making good all holes, mortices, sinkings, chases or the like, cutting floorboards, notching joints or the like.

(9) Testing of all work to ensure satisfactory operation on completion of any item of

work to the satisfaction of the Contract Administrator and/or tenant and advising the tenant of the correct operating procedure. (See also 7.1 and 7.2).

1.6 All items of existing non ferrous material that are permanently removed from any

works shall be deemed a “scrap” and shall become the property of the Contractor who shall be deemed to have allowed in his rates for any credit from salvaged materials.

2. GUTTERS AND DOWNPIPES

2.1 The Contractor is to note that no gutter or downpipe “colour”, “shape” or “section” id

given in any description of gutter work and that the rates are deemed to include for providing and fixing any standard “colour”, “shape” or “Section” of gutter or downpipe that may be encountered within the course of this maintenance contract, so as to

match that existing. (Or as otherwise directed by the Contract Administrator). It is

envisaged, however, that the majority of the work will be in standard half round gutter and that complete replacement wherever required will be in standard PVC-U half round gutter unless otherwise directed by the Contract Administrator. Downpipes will generally be round.

2.2 All gutters and downpipes shall be fixed and jointed strictly in accordance with the manufacturer’s instructions and to the correct line and falls. The rates for replacing lengths of gutter are deemed to include for all standard fittings that may be required, all joints, joints to existing work and complete fixing by means of the relevant standard gutter brackets or pipe clips to fascia’s or the like.

2.3 Cast iron gutters, downpipes, fittings and accessories shall comply with the appropriate BS and joints shall be made with gutter mastic.

2.4 Plasticised PVC-U gutters, downpipes, fittings and accessories shall comply with the appropriate BS and joints shall be made with rubber sealing joints and solvent cement in accordance with the manufacturer’s instructions.

3. UNDERGROUND SERVICES 3.1 Underground water mains shall be laid strictly in accordance with the Byelaws of the

Tendring Hundred Water Services Ltd and shall be in high density polythene to the appropriate BS.

3.2 All joints in underground services shall be only by means of “Prestex” (Plegers) or equal and approved compression fittings complying with the appropriate BS.

3.3 Copper pipe for underground work shall conform to the appropriate British Standards.

Page 49: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

49

4. SOIL AND VENT PIPES 4.1 PVC soil and ventilation pipes and fittings shall conform to the requirements of the

appropriate BS and shall be “Osma” type or other approved and fixed strictly in accordance with the manufacturer’s instructions.

4.2 All joints between PVC soil pipes and drainage pipes shall be made with patent drain connectors and all waste connections between PVC and CPVC tubing shall WC connectors assembled and fitted in accordance with the manufacturer’s instructions.

4.3 PVC ventilation pipes shall be carried up above rood level in accordance with current building regulations and offset below roof level as required so that the pipes pass through the pan of the roof tiles and a lead slate formed and dressed over the tiles and adjacent tile ribs in accordance with the manufacturer’s instructions. PVC balloons are to be of the type produced by the pipe manufacturer.

4.4 Testing: Test all soil and waste pipes to the requirements of the Local Authority.

4.5 Waste Pipes: To be as soil pipes in plastic as required. If internal, connect to the soil stack and if external to either the soil stack or to the back inlet of an open fully. The fully used shall have trap and the waste discharging into it placed so that it discharges above the level of the trap but below any grating or cover to the gully. The joint to the gully to be appropriate for the material.

4.6 Water Supplies: The internal plumbing work to be done to the satisfaction of and in accordance with the regulations of the Tendring Hundred Waterworks Company. Where there are found to be a variance with any clause or description in this Specification, immediate notice shall be given to the C.A. The whole of the work is to be tested at the Contractor’s expense, at such time and in such a manner as required by the C.A. and the Water Company.

5. SANITARY FITTINGS, WC OR STORAGE CISTERNS AND ASSOCIATED WORK 5.1 The rates for all sanitary fittings are deemed to include for assembling and jointing

component parts all in strict accordance with the manufacturer’s instructions.

5.2 WC cisterns shall conform to the appropriate BS. Ball valves shall be Portsmouth type (low pressure) unless otherwise described and shall conform to the appropriate BS. Floats shall be plastic complying with the appropriate BS.

5.3 WC plans shall be vitreous china conforming to the appropriate BS and include a suitable seat “Celmac” or equal and approved to the appropriate British Standard.

5.4 Wash basins shall be vitreous china conforming to the appropriate BS with “Osma” or other approved waste fittings to BS.

5.5 Taps shall be specified and shall conform to the appropriate BS.

5.6 Cole water supply cisterns, shall be kite marked and to the appropriate BS. High marked and to the appropriate BS. High pressure Portsmouth pattern ball valves with plastic floats shall be to the appropriate BS.

5.7 Care shall be taken not to damage existing wall tiles when removing sanitary ware. Where wall tiles are unnecessarily damaged by the removal of sanitary ware they shall be replaced by the Contractor at his own expense.

5.8 Sanitary fittings: The Contrator shall provide complete with all necessary fittings and fixtures necessary for the proper installation, all sanitary ware and take delivery unload, store, assemble, protect, distribute, hoist, manhandle and fix in position all sanitary ware specified later.

Page 50: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

50

Generally, all sanitary ware and fittings shall be made to the relevant British Standards and be of British manufacture. The Contractor shall allow for all fixings and connections to services as necessary and leave all sanitary ware in a thoroughly clean condition and in good working order upon completion.

6. COPPER PIPES, FITTINGS AND ASSOCIATED WORK 6.1 All pipework is to be executed in a neat and efficient manner, properly set out with the

minimum length of pipe runs and wherever possible bends shall be formed.

6.2 Copper pipe shall be to the appropriate BS.

6.3 All copper pipework is to be fixed with “Prestex” (Pegler) or equal and approved compression fittings and joints to be appropriate BS.

6.4 All rates for copper pipework are deemed to include for fixing to surfaces with pipe clips and spacers at maximum 1.80m centres or as required, made bends and short lengths, all compression joints in the running length, all compressions jointed fittings as may be required including, but not limited to, joints, tees, crosses, bends, elbows, reducers, connectors or the like, all cutting and any other necessary labours.

6.5 All stop taps and valves are to conform to the appropriate BS and the rates for all valves or the like are deemed to include for jointing to pipework.

6.6 Gate valves shall conform to the appropriate BS and all other fittings shall be of the type and material specified (or other equal and approved).

6.7 Indirect and direct copper cylinders shall be kite marked, fully tested and conform to the appropriate BS and both shall be of the type specified and shall be supplied with foamed insulation.

6.8 Indirect and direct copper cylinders shall be kite marked, fully tested and conform to the appropriate BS and both shall be of the type specified and shall be supplied with foamed insulation.

6.9 Immersion heaters shall be titanium sheathed and shall conform with the appropriate BS and thermostat and be “BEAB” approved.

6.10 Replacement insulation jackets for copper cylinders shall be 80mm (nominal) thick plastic faces Crown Fibreglass or equal and approved fire and vermin proof to suit relevant tank size and shall be secured in accordance with the manufacturer’s recommendations.

6.11 Pipe insulation shall be “Armaflex” or equal and approved preformed pipe insulation and shall be fixed to all pipework likely to be exposed to frost damaged or as directed by the Contract Administrator and the rates are deemed to include for working over all fittings.

6.12 Cold water storage tanks shall comply with the BS and shall be fitted complete with lids, Byelaw “303” kits and insulations sets.

7. DRAINING DOWN, ISOLATING AND REFILLING

7.1 The Contractor is to note that the rates for each item of plumbing work are

deemed to include for shutting off, isolating or draining down and refilling, restoring water supply and testing on completion such portions of the system that may be necessary to execute the works and that a separate rate for “draining down” or “refilling” plumbing systems will only be payable when

Page 51: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

51

expressly required by an order or instruction from the Contract Administrator for example in emergencies.

7.2 The Contractor’s attention is drawn to the fact that “draining down” and “refilling” systems is given as a fixed rate item within this schedule of rates.

8. MEASUREMENT The measurement expression (per installation) shall mean the total aggregate quantity of work carried out to each individual installation of plumbing equipment, tanks, sanitary ware of the like, which shall be used to determine the band and hence the rate used. Should the total quantity of work per installation in an order exceed in any item the highest band shown in the rates, the rate in the highest band shall be deemed to apply. The expression (per elevation) shall mean the total aggregate quantity of work undertaken on each individual building elevation whish shall be used to determine the band and hence the rate used.

Page 52: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

52

Prefix No. PC06000 SOR No.

Description

Unit

Rate £

Rate p (Pence)

PLUMBING AND SANITARY INSTALLATION Renewals to sanitary installation Renew the following sanitary fittings including isolate water supply, easing stopcock where necessary, remove existing and supply and fix new fittings, taps, traps etc. to match existing and make all connections to existing supply and waste pipes including replacing all pipework as necessary, lift and refix coverings, pipe casings, panelling or the like, reinstate wall tiling and mastic pointing and make good to other finishing’s and all work disturbed. NOTE: The following items are applicable to the renewal of complete sanitary fittings and include for all associated items and costs. No further payment will be made for additional items from the following “repair” sections.

001

Take out existing WC cistern (any size or pattern) supply and fix new rubberiod H.D./Dudley Dauntless black or equivalent WC cistern (high or low level) complete including flush pipe, copper pipe and fittings, fixing to brickwork, making all joints and connections, making good and test on completion.

Item

002

Ditto, all as item 001 but also replace existing overflow with new 22mm nominal diameter plastic overflow, including cutting holes and making food.

Item

003

Remove WC cistern from wall (high or low level) refix cistern board including plugging and screwing to brickwork or the like, reconnect cistern remake joints and connections and make good.

Item

004 Remove existing diaphragm (any pattern) from WC cistern and fit new diaphragm including testing on completion.

Item

005 Remove existing WC cistern siphon unit, supply and fit siphon to match existing and test.

Item

006

Remove existing, supply and fit new WC cistern high or low level concealed or exposed (any make or type) complete with ball valve, handle or chain concealed chain and pulley mechanism, flush pipe, cone connectors as necessary.

007

Overhaul WC cistern ball valve (any size or pattern) including cleaning adjusting and fitting new washer and test on completion.

Item

008

Remove existing ball valve from WC cistern and supply and fit new 15mm diameter brass Portsmouth Pattern ball valve to the appropriate British Standard and plastic ball.

Item

009 Ditto, as item 008 but 22mm diameter. Item

010

Disconnect and remove existing WC pan (any pattern), supply and fix new Ideal Standard or equivalent pan and matching seat to the appropriate British Standard including fixing pan with brass screws to timber or concrete base (as applicable) and remake all connections including cone and jointing to outlet with multi-kwik connector (complete operation).

Item

011

Remove WC seat and fit new back plastic WC seat with chrome metal C.W.S.S.P. hinges and fitting as approved by the CA and to the appropriate British Standard.

Item

012 Ditto, as item 011 but white plastic seat. Item

013 Supply and fit “Colani” toilet seat for the disabled as stocked by Nicholls and Clarke or similar seat as approved by CA.

Item

014 Supply and fit black WC seat with Rossett hinges for back to wall Item

Page 53: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

53

pans.

015 Supply and fit WX seat with Rossett hinges from back to wall pans.

Item

016 Tighten loose seat to pan any size or pattern. Item

017 Remove defective WC flush pipe and cone complete, supply and fix new white plastic flush pipe and cone to match existing.

Item

018 Refix flush pipe any size and pattern to cistern wall and pan. Item

019 Remove existing flush pipe cone fit new and test. Item

020

Remove existing WC pan (any type), remake pan to soil joint using multi-kwik or similar connector, refix existing WC pan and remake flush pipe joints with new cone.

Item

021 Screw down loose WC pan with brass screws including necessary provision of screws.

Item

022

Remove existing fire clay bowl urinal. Supply and fit new fire clay urinal (any size) Armitage shanks or equal approved including all fixings, fittings connections and the like to existing.

Item

023

Remove existing urinal flushing cistern complete. Supply and fix new flushing cistern including all necessary fixings, fitting, connections and the like to exiting.

Item

024

Supply and fit new standard water saver unit with pir connected to mains supply and to existing flushing cistern. (All as manufactured by Water Savers, 21 Cantley Lane, Norwich, NR4 6TA).

Item

025

Ditto, as item 024 but water saver unit to have inbuilt counter. (All as manufactured by Water Savers, 21 Cantley Lane, Norwich, NR4 6TA).

Item

026 Ditto as item 024 but with remote PIR. (All as manufactured by Water Savers, 21 Cantley Lane, Norwich, NR4 6TA).

Item

027

Supply and fit new water saver unit battery operated with remote PIR. (All as manufactured by Water Savers, 21 Cantley Lane, Norwich, NR4 6TA).

Item

028

Supply and fit new water saver unit battery operated with remote PIR. (All as manufactured by Water Savers, 21 Cantley Lane, Norwich, NR4 6TA).

Item

029 Take down, clean and service water saver flushing unit. Refix test and leave in proper working order.

Item

030 Supply and fit new cistermiser including fixings, fittings and connection to existing.

Item

031 Ditto, as item 030 but petcock. Item

032 Replace existing urinal pipe or sparge pipe in same material and include all connections to existing cistern as necessary.

Lm

033 Ditto, as item 032 but spreaders to urinal pipes. Lm

034

Wash Basins Remove existing wash hand basin (any size or pattern), supply and fit new 560mm x 405mm (average) white vitreous china basin to the appropriate British Standard on and including new CI brackets and 35mm slotted waste fitting, new black plastic plug and CP chain, rewashering and overhauling existing waste pipe and hot and cold water supplies including all pipework and joints. (Complete operation).

Item

035

Ditto, as item 034 but supply and fix new pair Pegler or equivalent 15mm chromium plated (on brass) percussion taps to the appropriate British Standard, new Osma or equivalent 38mm diameter UPVC waste pipe (average) 2m long trap and renew 3m (average) length of 15mm diameter copper pipework to hot and hold supplies including all fittings and joints and make good around to receive decorations (complete operation).

Item

036

Ditto, all as item 035 above but remove existing insert basin (any size and type) and supply and fit Armitage shanks planet basin,

Item

Page 54: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

54

sealed to existing worktop complete with waste and overflow fittings, plug and chain, trap, pair of chromium plated Preglers 15mm percussion taps (complete operation).

037

Ditto, all as item 035 but Armitage shanks hand rinse basin complete including preparing and making good to wall (complete operation).

Item

038

Ditto, all as item 035 but stainless steel wash hand basin (Nichols and Clarke S21035.01, S21035.11 or similar approved) complete with wall or floor brackets, waste and overflow fittings, plug and chain, trap and pair of chromium plated Peglers 15mm percussion taps (completed operation).

Item

039 Ditto, all as item 038 but inset wash hand basin size to suit existing hole in worktop.

Item

Major repairs to sanitary installation Major repair to wash hand basin, or stainless steel sink in addition to items listed below. Allow for gaining access (i.e. access panels) and reinstating after the work (refixing panels, new dow corning sealant) as necessary.

040

Remove existing waste pipe from wash basin and fit new 35mm diameter Osma or equivalent waste pipe and trap including all necessary joints, breaking out and making good.

Item

041

Remove wash basin (any size or type) supply and fit new basin brackets as required, refix existing basin making all connections and making good.

Item

042 Remove existing trap to wash basin and fit new Osma or equivalent plastic trap.

Item

043

Clear blockage in wash hand basin (any type) including dismantling and reconnecting waste trap and pipes as required. Test and leave in working order.

Item

044 Remove existing chromed dome grating to urinal outlet, supply and fit new to match existing.

Item

045 Refix existing domed grating to urinal outlet. Item

046 Fabricate and fit new aluminium grating for urinal outlet. Item

047

Minor repairs to sanitary installation Minor repair to sanitary fitting including any of the following; renew chain and handle to high level cistern, renew lever to high level cistern, renew extended flush handle to concealed cistern. Tighten and/or screw down sanitary fitting and leave secure test on completion including removing/refixing access panels as necessary.

Item

048

Copper Pipes and Associated Fittings Turn off, drain down as required, remove existing pipework (copper, galvanised, or iron) inclusive of fittings and fixings. Supply and fix new 15mm diameter copper pipes to the appropriate British Standard including all bends, fittings and fixings using compression fittings only, include all holes and making good and test on completion. Isolated lengths up to 1m.

Item

049 Ditto, as item 048 but lengths over 1m – 10m (per public convenience).

Lm

050 Ditto, as item 048 but lengths over 10m – 20m (per public convenience).

Lm

051 Ditto, all as item 048 but using 22mm diameter pipe and fittings, isolated lengths up to 1m.

Item

052 Ditto, as item 051 but lengths over 1m – 10m (per public convenience).

Lm

053 Ditto, as item 051 but lengths over 10m – 20m (per public convenience).

Lm

054 Ditto, as item 048 but using 28mm diameter pipe and fittings, isolated lengths up to 1m.

Item

Page 55: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

55

055 Ditto, as item 054 but lengths over 1m – 10m (per public convenience).

Lm

056 Ditto, as item 054 but lengths over 10m – 20m (per item public convenience).

Lm

057 Ditto, all as item 048 but s/s sparge pipe and fittings, isolated lengths up to 1m.

Item

058 Ditto, as item 049 but s/steel sparge pipe including spreaders and clips lengths 1 – 5m.

Lm

059 Ditto, as item 048 but s/steel sparge pipe distribution feed from flushing cistern to sparge and spreaders.

Item

060 Descale and service speader to allow even distribution of flush. Item

061 Refix existing pipework to walls or the like using existing fittings; any diameter of pipe, lengths up to 5m.

Lm

062 Refix existing pipework to walls using new fittings and fixings as required; any diameter or pipe, lengths up to 5m.

Lm

063 Blank off pipe, any size, any material. Item

064

Remove defective service valve to appliance including drain down. Supply and fix new valve including all necessary adjustments to associated pipework. Refull and test (complete operation).

Item

064A

Remove defective service vale to appliance including drain down. Supply and fix new ¼ inch turn valve including all necessary adjustments to associated pipework. Refill and test (complete operation).

Item

065

Remove existing and supply and fix new 15mm diameter gun-metal combined draw off stopcock to existing pipework, including draining down as required. Refill and test completion.

Item

066 Ditto, as item 065 but to 22mm diameter. Item

067

Remove existing stopcock from pipework and fit new 15mm diameter fun-metal stopcock to the appropriate British Standard. Copper to copper or copper to lead, including wiping joint if required. Including draining down as required. Refill and test on completion.

Item

068 Ditto, as item 067 but fit new 22mm diameter gunmetal stopcock.

Item

069 Ditto, all as item 067 but fit new 28mm diameter gunmetal stopcock.

Item

070

Remove existing gate valve from pipework and fit new 15mm diameter gun-metal gate valve to the appropriate British Standard. Including draining down as required. Refull and test on completion.

Item

071 Ditto, all as item 070 but 22mm gate valve. Item

072

Supply and fit new gun-metal gate valve 22mm or 28mm diameter including turn off and draining down as required. Refill and test on completion.

Item

073

Supply and fit new brass (Peglers 832 or equivalent) draw off cock 15mm diameter including removing existing, turning off water and draining down as required. Refill and test on completion.

Item

074

Supply and fix new brass safety valve 15mm diameter including removing existing turning off water supply and draining down system if required. Refill and test on completion.

Item

075 Ditto as item 074 but 22mm diameter. Item

076

Supply and fix new brass (Peglers 833 or equivelanet) drain off cock 22mm, diameter including removing existing turning off water and draining down if required. Refill and test on completion.

Item

077

Remove existing tap any type, supply and fix new (hot or cold) chromium plated Peglers percussion tap or equivalent to the

Item

Page 56: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

56

appropriate British Standard and test on completion. Including copper pipe for connection (complete operation).

078 Ditto, all as item 077 but 1 pair. Item

079 Ditto, all as item 077 but new Peglers cleaners sink tap. Item

080 Ditto, all as item 079 but 1 pair. Item

081 Ditto, all as item 077 but new Peglers ¼ turn easy action disabled lever tap.

Item

082 Ditto, all as item 081 but 1 pair. Item

083

Overhaul hot or cold tap, stopcock, gland or the like (any pattern or size) including cleaning, replace washer, re-pack, including tightening tap fitting to basin, draining down and refilling as necessary and test on completion.

Item

084

Overhaul gate valve gland (any pattern or size) including cleaning, adjusting and fitting, new washer, draining down and refilling as necessary and test on completion.

Item

085 Ditto, as item 084 but on mixer valves. Item

086

Remove existing mixer valve (any type) and supply and fix new valve to match existing including all fixings fitting and connection to existing (complete operation).

Item

087

Drain down and remove sprung compression joint to copper pipe, any diameter, clean joint ends and replace with new olives. Refill and test on completion.

Item

088

Hot Water Cylinders Replace direct cylinder (any size). Supply and fit replacement Hercfal double feed direct cylinder manufactured to appropriate B.S. Each cylinder to be BSS 1566 Part 1 Grade 3, and have the kite mark stamped into the metal (with 25 year guarantee). Each cylinder to be supplied with factory applied Herculag performed foam insulation. Including new reconnecting valve, new drain off cock and reconnecting existing immersion heaters, allow for renewing average 1m of copper pipe on all supply and feed pipes and fittings. Include for draining down, refilling and test upon completion.

Item

089 Ditto, as item 088 but including new immersion heaters, cable and all connections.

Item

090

Ditto, all as item 088 but small non standard direct hot water cylinder to the appropriate British Standard, grade 3 (kite marked with 25 year guarantee), including new immersion heater and cables.

Item

091 Remove existing immersion heater from existing cylinder replace same to new cylinder and joint (electrical work included).

Item

092

Remove existing immersion heater supply and fit new 3kw titanium sheathed immersion heater to the appropriate British Standard complete with thermostat including drain down as required (electrical work included). Length 280mm (11”).

Item

093 Ditto, as item 092 but length 350 (14”). Item

094 Ditto, as item 092 but length 687mm (27”). Item

095 Ditto, as item 092 but length 762mm (30”). Item

096

Cold Water Supply Cisterns Disconnect and remove existing storage cistern complete (any type) supply and fit new 227 litre Flextank Polyolefin or equivalent cold water storage cistern type PC50 to the appropriate British Standard (Kite marked) with Bylaw 30 kit and lid complete to platform including lagging set, as required, 15mm diameter Portsmouth pattern ball valve and silencer, drilling cistern and fixing plastic washer and backing plate 22mm diameter PVC over flow pipe 4.00m (average) long and fittings with weeping end and frost guard and 22mm diameter tapping for overflow and cold water supply and connecting to copper

Item

Page 57: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

57

supply and feed pipes allowing for renewing 1m length copper pipe to each including all fun metal couplings connectors and compression fittings only and joint to existing pipework.

097

Ditto, as item 096 but supply and fit new 18 litre Flextank Polyolefin or equivalent cold water header tank type PC4 to the appropriate British Standard (kite marked ) and ditto.

Item

098

Gain access and turn off cold water supply overhaul, clean, adjust and grease supply cistern ball valve, reassemble turn on water supply and test ball valve.

Item

099

Ditto, as item 098 but remove existing ball valve and fit new 15mm Portsmouth pattern brass ball valve and plastic ball to the appropriate British Standard and test.

Item

100 Ditto, as item 099 but supply and fit new 22mm ball valve. Item

101

Supply and fit new mains storage tank lid to existing tank any make or pattern and to include all appropriate fittings to meet water company requirements.

Item

102

Rainwater Installations Guttering Remove and dispose of existing gutter and brackets (any size or pattern) fit new brackets and 100mm diameter PVC gutter including all necessary angles outlets stop ends or other fittings, joints in the running length and jointing to existing (complete operation).

- Isolated lengths not exceeding 1m.

Item

103 Ditto, as item 102 but lengths over 1m – 5m (per elevation). Item

104 Ditto, as item 102 but lengths over 5m – 10m (per elevation). Item

105 Ditto, as item 102 but lengths over 10m – 15 m (per elevation). Item

106 Ditto, as item 102 but 125mm diameter PVC gutter, isolated lengths not exceeding 1m.

Item

107 Ditto, as item 106 but lengths over 1m – 5m (per elevation). Item

108 Ditto, as item 106 but lengths over 5m – 10m (per elevation). Item

109 Remove existing stop end clean off and fit new 100mm diameter PVC stop end.

Item

110 Ditto, as item 109 but 100mm diameter PVC stop end outlet. Item

111 Remove existing 90º bend clean off and fit new 100mm diameter PVC bend.

Item

112 Remove existing running outlet clean off and fit new 100mm diameter PVC running outlet.

Item

113 Remove gutter and existing bracket fit new PVC bracket to timber fascia and replace gutter.

Item

114 Break joint in existing bracket fit new PVC clean off remake joint and test.

Item

115 Clear and clean gutter system (any size or pattern) – per public convenience block, dispose of spoil and test, lengths 0 – 5m.

Item

116 Ditto, as item 115 but lengths over 5m. Lm

117

Down Pipes Remove existing down pipe system complete to public convenience fit new 60mm nominal diameter PVC pipe (average 3m) including 1 no. shoe. Pipe brackets at 1.80m centres plugged and screwed to brickwork or Blockwork and all joints in the running length (complete operation).

Item

118

Remove existing defective down pipe and replace with new UPVC down pipe including all fixings and fittings (complete operation).

Lm

119

Remove defective pipe bracket and fix new PVC bracket to 60mm nominal diameter down pipe including plugging and screwing to brickwork or the like.

Item

120

Remove defective shoe or benc or swan neck and fix new PVC show, or bend or swan neck to 60mm nominal diameter down

Item

Page 58: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

58

pipe including all joints.

121 Locate blockage in existing gully, hopper or down pipe (any size or pattern), clean out dispose of spoil and test.

Item

122 Refix existing rainwater down pipe clip any type or size. Item

123

Underground Services Locate and turn off water supply, cut out (pre-exposed) defective pipe in trench, repair with length of 15mm diameter soft copper tubing to the appropriate British Standard and joint with compression fittings (only) to existing and test. Isolated lengths not exceeding 3m.

Item

124 Ditto, as item 123 but 22mm diameter, isolated lengths not exceeding 3m.

Item

125

Locate and turn off water supply, cut out and remove existing (pre-exposed) defective pipe in trench, repair including laying 15mm diameter HD polythene tube to the appropriate British Standard and make all joints and connections in accordance with the manufacturer’s instructions using soft copper inserts and turn on water and test. Lengths up to 5m.

Item

126 Ditto, as item 125 but lengths over 5m. Lm

127

Soil and Vent Pipes Excavate at base of soil pipe, remake joint and reinstate concrete and cement fillet with cement mortar (1:3).

Item

128

Excavate by hand not exceeding 0.75m deep from existing ground level including breaking plain surface concrete to expose leak in 100m diameter soil and vent pipe, cut out defective pipe not exceeding 1.00m in length, replace with length 100mm diameter UPVC soil and vent pipe to the appropriate British Standard with 2 no. connectors, test and backfill with excavated material well rammed and reinstate concrete (completion operation).

Item

129

Remove defective soil pipe external or internal (any diameter or material) complete and replace with average 5m length of “Osma” or equivalent 100mm nominal diameter UPVC soil and vent pipe including all necessary joints in the running length, fitting with barrel pipe clips at 1.80m centres, plugged and screwed to brickwork supplying and fixing all necessary fittings and connections to wastes and make good and test (complete operation).

Item

130

Cut out length PVC soil pipe, supply and fit sleeved connector and renew average 1.00m length PVC soil pipe to existing boss, including all “P” and “S” trap conversion connectors, all fixings and make good.

Item

131

Cut out existing WC pan arm or bend, supply and fit new “multi-kwik” or similar pan connector and extension piece to existing WC pan (complete operation).

Item

132

UPVC Urinal Waste and Fittings Remove existing defective urinal waste pipe or the like up to 50mm diameter. Supply and fix new UPVC waste pipe including all fixings and clips to any background including jointing to existing (complete operation).

Lm

133 Ditto, as item 132 but defective urinal trap. Item

134 Ditto, as item 132 but defective urinal waste bend. Item

135

Water Heaters Disconnect and remove existing water heater (any type or size) disconnect electric supply and leave safe.

Item

136 Reconnect existing or new water heater fill and test (complete operation).

Item

137 Supply and fit new water heater size type and capacity to match existing connecting to existing fittings (complete operation).

Item

Page 59: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

59

138 Insulation Remove existing as required and supply and fix new 80mm thick fibre glass cylinder jacket (any size).

Item

139 Remove existing as required and supply and fix purpose made insulation sets for Flextank cistern type PC4 or equivalent.

Item

140 Ditto, as item 139 but Flextank cistern type PC50 or equivalent. Item

141

Supply and fix preformed AF/Armaflex or equivalent pipe insulation to pipes not exceeding 35mm diameter. Isolated lengths not exceeding 1m.

Item

142 Ditto, as item 141 but lengths over 1m – 5m (per public convenience).

Lm

143 Ditto, as item 141 but lengths over 5m – 10m (per public convenience).

Lm

144

Sundries Provide a plumber for attendance or inspection of the works as requested or instructed by C.A. (per ¼ hour).

Item

145 Ditto, as item 144 but for each subsequent 15 minute period. Item

146 Overhaul low level WC cistern handle or cistern link repair or replace as necessary clean and adjust and test on completion.

Item

147

Ditto, as item 146 but to concealed cistern chain and pulley mechanism including all necessary removal and re-fixing of chasing.

Item

148 Renew as required extended cistern lever for concealed or boxed in cisterns.

Item

149

Remove existing push button flushing mechanism and fit Armitage shanks palm button flushing mechanism for concealed cistern.

Item

Draining Down and Refilling This item to be read in conjunction with items for closure and opening up to public conveniences in Section 5 and 7.

150

Turn off water supply and main stop cock by water meter, drain down complete plumbing system including all tanks, pipework and the like, shut off all valves as necessary and leave in safe and secure state for closure of public conveniences. Per public convenience.

Item

151 Ditto, as item 150 but leaving stop cock by water meter turned on.

Item

152

Turn on water supply at main stop cock by meter, refill plumbing system, open valves as necessary, test, vent and leave public convenience in working order. Report any defects directly to the C.A. Per public convenience.

Item

153 Ditto, as item 152 but excluding need to turn on at main stop cock by meter.

Item

154

Remove existing WC pan (any pattern) and supply and fix new Armitage Shanks’ back to wall pan including matching seat and all fixings, fittings and connections to existing system (complete operation).

Item

155

Remove existing fireclay slab urinal supply and fix new to match existing including back slab divider, and end piece as necessary complete with all fixing, fittings and connections to existing (complete operation).

Lm

156

Remove existing main storage tank any size any type and replace with new 100/120 gallon tank complete with Bylaw 30 kit including all fixings and connections to existing (complete operation).

Item

157

Remove existing gutter (any size or type) and replace with new to match existing including all fixings, fittings and connections to existing (complete operation).

Lm

158 Record main inlet water meter reading at any unit in the district Item

Page 60: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

60

and supply to C.A.

159

Record main inlet water meter reading at any unit in the district at the same time as undertaking reactive or routine repair and maintenance work and supply to C.A.

Item

160

Set up portaloo on site connection to all services as required including providing water and drainage pipes as necessary testing all fittings and making ready for use.

Item

161 As above but including fitting security boarding around skirt of portaloo to protect service connections.

Item

162

Flush out water tanks on portaloo mobile toilet service all ball valves, taps flushing cisterns, soil pipes water pipes and traps and leave ready for use at Council depot.

Item

163 Carry out minor repairs to flush pipes i.e. fix to pan.

164 Remove old gutter joint and replace with new joint and test.

165 Supply and fix new palm push flush system to existing concealed flush system including all cutting of walls.

Page 61: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

61

DESCRIPTION OF WORKS AND

SCHEDULE OF RATES

SECTION 7

ELECTRICAL INSTALLATIONS

Page 62: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

62

ELECTRICAL INSTALLATIONS

1. GENERALLY 1.1 The scope of the work contained within this section is generally of a repairing nature

that may be encountered during reactive maintenance.

1.2 The Contractor’s attention is particularly drawn to the fact that no detailed electrical layout drawings will be generally be issued and that where applicable the rates shall be deemed to include for designing electrical layouts or systems.

1.3 Notwithstanding anything contained within this schedule all Electrical work shall comply with the “IEE Wiring Regulations for Electrical Installations” as current at the date of installation as issued by the Institution of Electrical Engineers Regulations issued under the Electricity Acts of the Byelaws of the electric supply and/or transmission company, and all rates shall be deemed to include for this provision. The rates are also deemed to include for giving all notices demandable under such Acts or Byelaws and for liaising where necessary with the electricity supply and/or transmission company.

1.4 All labour or sub-contractors employed on any electrical work shall be approved members of the N.I.C.E.I.C., and the Contractor shall provide evidence of such membership to the satisfaction of the Contract Administrator.

1.5 For the purpose of this specification the definitions contained within the above denied I.E.E. regulations current at the date of tender shall apply and the Contractor it to note that generally no description of workmanship is given within these preambles but that the I.E.E. Regulations shall be deemed to be the method and level of workmanship required for all electrical work and that disputes arising with regard to inadequate workmanship will be settled by strict reference to these regulations.

1.6 All apparatus and wiring shall be suitable for use with 240 volt 50HZ single phase alternating current.

1.7 All wiring is to be executed in a neat and efficient manner properly set out with minimum length of cable runs connected to the closest appropriate supply.

1.8 The Contractor shall be responsible, and the rates are deemed to include for making all arrangements with the electricity supply and/or transmission company for the disconnection of old wiring and connection of new wiring into meters and for the connection of earth leads or the like to the neutral block. The Contractor shall ensure that no work is carried out to the electricity supply and/or transmission company’s equipment or seals broken without their necessary written permission. On completion of any work the Contractor shall check that all connections have been made by the electricity supply company and confirm this in writing to the Contract Administrator.

1.9 No additions or alterations, temporary or permanent shall be made to an existing installation, unless and until it has been ascertained that the ratings and the condition of any existing equipment (including that of the supply authority) which will have to carry any additional load is adequate for the purposes which it is required and is adequately earthed.

1.10 The rates for all electrical operations where applicable are deemed to include for the following:- 1) Assembling and jointing together the component parts of composite units and

providing any necessary jointing materials.

2) All patterns, moulds, templates or the like.

Page 63: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

63

3) The provision of all appropriate fixings. 4) Fixing to whatever background may be encountered with the correct fastenings

and any necessary drilling to include:-

(a) Building board which shall be deemed to include hardboard, fibre cement sheet, plaster board, fibreboard and similar materials which do not grip wood-screws.

(b) Timber which shall be deemed to include softwood, hardwood, block board, plywood and similar materials which will grip wood-screws when a lead-hole has been drilled.

(c) Metal-faced or composition-faced timber which shall be deemed to include

faced block board, faced plywood and similar materials which will grip wood-screws when a lead-hole and a shank clearance hole have been drilled.

(d) Brickwork, concrete or stonework which shall be deemed to include

reinforced concrete block work and similar materials which required plugging irrespective of any plaster, glazed tiles, composition or other finish (excluding glass) to the surface.

(e) Perforated metal which shall be deemed to include slotted steel, cable-trays

and similar material which does not require drilling. 5) Working on internal or external locations.

6) All temporary work, removing same and making good after including lifting and

replacing floorboards or the like. 7) All “builders work in connection” (with regard to the nature of the work) including

marking the position of all holes, mortices, chases or the like, bedding and pointing components or units of equipment, cutting and pinning ends of support for equipment, ancillaries, all fittings, all trunking or the like, all holes, notches, mortices, chases, or the like, cutting floorboards, notching joists and all making good in connection therewith.

8) Testing of all work on completion to the satisfaction of the Contract Administrator

an providing a copy of the appropriate test certificate for the Health and Safety File.

1.11 The contractor is to note that the work in this section where applicable is to be read in

conjunction with the relevant section of “plumbing” and the rates shall be deemed to allow for the liaison between “plumbers work” and “electrician’s work” in relation to any order or instruction issued by the Contract Administrator.

1.12 Where items are described as removed, the rates are deemed to include for removal of the fittings and, if the existing wiring is not to be re-used – if surface fixed it shall be removed, together with any trunking or the like and, if embedded, cut off and left in with the outlet made good.

1.13 Other fittings removed by the Contractor during the course of works shall be

reinstalled and connected and the Contractor is deemed to have included for this in his Schedule of Rates.

2. MAINS DISTRIBUTION AND EARTHING

2.1 Consumer units are all to be insulated to the appropriate British Standard and are to

be fitted with Miniature Circuit breakers, double pole main switch, and residual current

Page 64: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

64

circuit breakers complying with the appropriate British Standard MCB ways to be as follows:- 6A rating - for lighting circuits 32A rating - for power circuits 20A rating - for water heater circuits

2.2 Switch fuses are to be insulated and shall comply with the appropriate British Standard.

2.3 Residual current circuit breakers shall be current operated double pole completed with terminal covers to comply with the appropriate British Standard.

2.4 Earth clamps shall be “Tenby EC15” adjustable clamps or other approved to the appropriate British Standard and shall be visible and easily accessible.

2.5 Earthing and bonding of services shall be carried out strictly in accordance with the IEE Regulations current at the date of installation, and the rates shall be deemed to include for making all necessary arrangements with the electricity supply and/or transmission company for connections of the main earth leads to the service cables where applicable.

3. CABLES AND WIRING 3.1 The installation and system of wiring shall be carried out in PVC covered cable

concealed under floorboards and roof spaces or the like whenever possible. Existing conduit where chased may be used when possible. All new wiring work unless otherwise instructed shall be “surfaced fixed” and shall be concealed in trunking. Wherever possible drops are to be concealed in cupboards, corners of rooms or abutting architraves and are to be inconspicuous as possible. Horizontal runs are to be immediately above skirting’s.

3.2 Trunking shall be white mini-trunking to the appropriate British Standard and shall be fixed accordance with the manufacture’s instruction and of a suitable size to suit the number of cables to be housed.

3.3 The rates shall include for trunking which shall be deemed to include for plugging and screwing to walls at 900mm centres or as required and all necessary angles, “T” junctions and other fittings where applicable complete with clip-on lids.

3.4 Socket outlets are to be wired on a ring main system.

3.5 All cables shall conform B.A.S.E.C. standards and shall be 240 Volt P.V.C. sheathed to the appropriate British Standard. Flexible cables shall conform to the appropriate British Standard and the following is a list of cables to be used:- Lighting circuits 1.5mm² Socket outlets 2.5mm² Immersion heater outlets 2.5mm² Heater control outlet 2.5mm² Flexible cables (excluding immersion heaters) 0.75mm² Flexible cables to immersion heaters 2.5mm² Earthing runs 10mm² Circulator pump 0.75mm² Main earthing lead 16mm²

3.6 Cables shall run 150mm clear non electrical services where possible. Vertical runs

shall be directly above or beneath the outlet or switch being served and joints in

Page 65: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

65

cables shall be the minimum necessary and shall be made with junction boxes complying with the appropriate British Standard.

3.7 Where cables pass through joists or the like they shall be run at right angles to the

joists which shall be holed in accordance with the appropriate Code of Practice. Joists shall not be notched.

3.8 Avoidance of heating pipes

3.9 All cables shall be spaced at least 230mm from any pipes intended to carry hot water. The electrical Contractor shall be responsible for checking the runs of any such pipes before commencing wiring.

3.10 Looping Wiring shall be carried out upon the “looping in” principle. All joints shall be made at main switches, distribution boards, sealing boxes, socket outlets, lighting outlets and switch boxes only. No joints shall be made boxes, nor will any through joints allowed.

4. STANDARD ELECTRICAL FITTINGS AND ACCESSORIES 4.1 Unless otherwise specified within this schedule, all electrical fittings and accessories

are to be to the approved British Standard and are to be of a manufacturer approved in advance with the Contract Administrator so as to provide consistency of fittings used for the duration of the contract.

4.2 Unless otherwise directed by the Contract Administrator the mounting heights for all fittings shall be fixed in the position that the existing fitting has been removed or as follows:- Item Height above floor Measured To Consumer Unit To existing position Lighting Switches 1400 mm Centre Extractor Fans 2025 mm Centre

SSO 250 mm Bottom Earth Bonding Cable To suit pipes to be bonded - Outlets

4.3 Fluorescent fittings shall be to the appropriate British Standard or equal pattern

fittings with matching white tubes and starters (where applicable) fixed in accordance with the manufacturer’s instructions.

4.4 Bulkhead fittings shall be 28/16W2D to BS fixed in accordance with the manufacturer’s instructions.

4.5 Extractor fans shall be “Airflow” or equal wall or window fans pull-cord switches fixed in accordance with the manufacturer’s instructions.

4.6 Smoke detectors shall be mains operated and equipment shall be to the appropriate section of BS. Replacement equipment shall be of the same type and manufacture as that removed.

5. TESTING

5.1 Each electrical operation of work shall be tested on completion of the work for function and to the requirements of the IEE Regulations and the rates shall be

Page 66: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

66

deemed to include for this provision, including recording and completing all notices, and for providing to the Contract Administrator on each occasion for the Health and Safety File and for the cost of all power consumed. Repeated test shall be at the Contractor’s own expense.

5.2 All operatives employed on any work shall have in their possession at all times sufficient test equipment to undertake the required testing and reporting accordance with the regulation to either the “minor works” “periodic” or “electrical installation report” standards as appropriate to the nature of the work.

5.3 The results of all test on electrical equipment are to be recorded and supplied to the Contract Administrator and the rates shall include for the cost thereof.

5.4 Notwithstanding 5.3 above, however, where applicable as soon as an installation is complete and ready for connection the Contractor shall complete a “Notice of Completion” and where P.M.E applies an “Earthing Declaration” and any other notices required which shall be submitted to the supply company.

5.5 Notwithstanding 5.3 above also where applicable a completion certificate conforming to the I.E.E. regulations and provided by the N.I.C.E.I.C shall be completed, signed by a competent and authorised person and sent to the contract administration for retention.

Page 67: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

67

Prefix No. PC07000 SOR No.

Description

Unit

Rate £

Rate p (pence)

ELECTRICAL INSTALLATIONS Information The Contractor is to note that all materials within this section are to be as fully specified in the preceding preambles.

001

Mains Distribution Disconnect existing ELCB/RCCB remove, prepare for, supply and install residual current circuit breaker including all labours and test.

Item

002

Prepare for, supply and install copper earth rod with connecting cap including average 10m length cable to consumer unit all labours and test.

Item

003 Prepare for, supply and install 10mm² metre tails average 1m long and test.

Item

004 Ditto, as item 003 but 16mm² Item

005

Disconnect and remove defective consumer unit (any type) prepare for (including re-fixing backing plate) and supply and fit new 4 way all-insulated consumer unit and test excluding MCB’s.

Item

006 Ditto, as item 005 but 6 way consumer unit. Item

007 Ditto, as item 005 but 8 way consumer unit. Item

008 Ditto, as item 005 but 10 way consumer unit. Item

009 Ditto, as item 005 but 12 way consumer unit. Item

010 Prepare for, supply and install 20A insulated switch fuse and test.

Item

011 Disconnect and remove defective MCB and replace with new 6 amp rating MCB.

Item

012 Ditto, as item 011 but 16 amp MCB. Item

013 Ditto, as item 011 but 20 amp MCB. Item

014 Ditto, as item 011 but 32 amp MCB. Item

015 Ditto, as item 011 but 45 amp MCB. Item

016 Supply and fix new 6 amp rating MCB. Item

017 Ditto, as item 016 but 16 amp MCB. Item

018 Ditto, as item 016 but 20 amp MCB. Item

019 Ditto, as item 016 but 32 amp MCB. Item

020 Ditto, as item 016 but 45 amp MCB. Item

021 Ditto, as item 016 but blank shield. Item

022 Disconnect and remove defective HRC cartridge fuse holder and replace with new 6 amp fuse holder and fuse and test.

Item

023 Ditto, as item 022 but 16 amp fuse. Item

024 Ditto, as item 022 but 20 amp fuse. Item

025 Ditto, as item 022 but 32 amp fuse. Item

026 Ditto, as item 022 but 45 amp fuse. Item

027 Earthing Refix bonding clamps where removed by other trades.

Item

028

Prepare for, supply and fix new earth bonding to sink unit and cross bond water supply pipes including clips and average 2m length cable and test.

Item

029

Remove existing earth bonding, supply and fix new earth cross bonding to gas and water services for P.M.E., including clips and average 10m length cable and test.

Item

030

Power Installation Prepare for, supply and install 1-gang 13 amp switched socket outlet surface wired including cable all necessary trunking to match existing all labours and test.

Item

031 Ditto, as item 030 but 2-gang switch socket outlet. Item

Page 68: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

68

032 Ditto, as item 030 but 1-gang metal switch socket outlet. Item

033 Ditto, as item 030 but 2-gang metal switched socket outlets. Item

034

Remove defective socket outlet supply and fit new 13 amp 1-gang switched socket outlet complete with surface box including all labours and test.

Item

035 Ditto, as item 034 but 2-gang switched socket outlet and box. Item

036 Ditto, as item 034 but 1-gang metal switch socket outlet. Item

037 Ditto, as item 034 but 2 gang metal switch socket outlet. Item

038 Remove defective socket outlet plate supply and fix new 13 amp 1-gang switched socket outlet.

Item

039 Ditto, as item 038 but 2-gang switched socket outlet. Item

040 Ditto, as item 038 but 1 gang metal switch socket outlet. Item

041 Ditto, as item 038 but 2 gang metal switch socket outlet. Item

042

Remove defective fused spur outlet and supply and fix new fused spur outlet in plastic or metal suit existing appliance including all labours and test.

Item

043 Ditto, as item 042 but switched. Item

044

Remove defective spur outlet, supply and fix new fused spur outlet in plastic or metal to suit existing flex outlet and pilot lamp including all labours and test.

Item

045 Ditto, as item 044 but replace average 1m length of flex in heat resisting cable.

Item

046 Remove defective flex from outlet to appliance, supply and fix new 2.25mm² heat resisting cable average length 1m and test.

Item

047 Remove defective cartridge plug fuse and supply and fix new 3 amp cartridge fuse and test.

Item

048 Ditto, as item 047 but 5 amp fuse and test. Item

049 Ditto, as item 047 but 13 amp fuse and test. Item

050 Remove defective external weatherproof MK Masterseal socket outlet and replace including new circuit isolator.

Item

051

Provide new fitting outlet, surface or flush mounted fitting and box, in plastic or metal to suit existing surface mounted cable in mini trunking, wiring connection to existing circuits as spur or direct from the consumer unit as necessary.

Item

052 Remove defective single faceplate (any type) and blank off connections including supply and fix new faceplate blank.

Item

053

Provide new outlet surface mounted fitting and box in plastic or metal to suit existing with surface mounted cable in metal conduit, wiring connection to existing circuits as spur or direct from consumer unit as necessary (average 3m run).

Item

054 Supply and fit plastic counduit for lighting or power cable including junctions and clips.

Lm

055

Lighting Installation Rewire length of faulty or damaged cable between fittings and junction boxes or provide and make new connections within the run of the existing cable as necessary. Surface mounted cable fixed in cable trays or trunking. Twin and multicore mineral insulated copper sheathed cables with copper conductors and PVC outer sheath: light duty 600v. three core cable total cross sectional area not exceeding 2.50mm² including all connections or PVC covered flat twin and earth cable as appropriate (average 5m length).

Item

056

Minor repairs to the following luminaires at any level including remake faulty connections, renewing wiring, MCB, fixing fitting to any background as necessary, single fluorescent fitting.

Item

057 Ditto, as item 056 but double fluorescent fitting. Item

058 Ditto, as item 056 but vandal proof fitting. Item

059 Ditto, as item 056 but bulkhead fitting. Item

Replace lamps to light fitting, provide and fix all bulbs, tubes and

Page 69: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

69

060 starters of correct type and rating, at any level, to the following light fittings (Note: these items are for replacing lamps and starters only and will not be paid in addition to the above items of minor repair). Single fluorescent fitting.

Item

061 Ditto, as item 060 but 12 in or single tube. Item

062 Ditto, as item 060 but 16w 2D low energy tube. Item

063 Ditto, as item 060 but 28w 2D low energy tube. Item

064 Ditto, as item 060 but bulkhead fitting. Item

065 Ditto, as item 060 but PL11w low energy tube. Item

066 Remove defective ceiling rose and fitting (any type) supply and fix new set including rose, lamp holder and flex.

Item

067

Remove defective lamp holder and flex supply and fit new lamp holder and flex to existing rose including repairing existing and test.

Item

068 Remove defective batten holder (any type) supply and fix new including re-fixing bulb and test.

Item

069

Renew the following luminaire, and the like at any level, including removing existing fitting and supply and fit new fitting, renewing wiring and lamps, connect to conduit systems including replacement conduit as necessary. New fittings to match existing (complete). 4ft fluorescent fitting, single tube.

Item

070 Ditto, as item 069 but 6ft fluorescent fitting single tube. Item

071 Ditto, as item 069 but 8ft fluorescent fitting single tube. Item

072 Ditto as item 069 but waterproof fluorescent 28w prismatic unit. Item

073 Ditto, as item 069 but 4ft anti corrosive fluorescent fitting. Item

074 Ditto, as item 069 but 6ft anti corrosive fluorescent fitting. Item

075 Ditto, as item 069 but bulkhead light fitting. Item

076 Ditto as item 069 but external vandal resistant bulkhead fitting complete protective wire cage or similar.

Item

077 Renew existing light switch with MK Masterseal water proof light switch.

Item

078

Replace existing tube (any size or type) with Osram Delux ® le lamps or equivalent low energy light including all necessary alteration and adaptation to existing fitting and lamp holder. Single fluorescent fitting.

Item

079 Ditto, as item 078 but to 6ft single fluorescent fitting. Item

080 Ditto, as item 078 but 8ft single fluorescent fitting. Item

081 Ditto, as item 078 but to bulkhead fitting. Item

082

Circuits Prepare for supply and install 1-gang, 1-way lighting point surface wired 10m length of cable switch plate, surface box, ceiling rose, lamp holder and flex, all necessary trunking to match existing and test.

Item

083 Ditto, as item 082 but metal switch plate. Item

084

Remove defective 1-gang surface mounted lighting switch and box either in plastic or metal supply and fix new switch plate and box to match existing complete test.

Item

085 Ditto, as item 084 but 2-gang. Item

086 Ditto, as item 0874 but 2-way 1-gang. Item

087

Remove defective 1-gang switch plate only surface or flush fixed either in plastic or metal. Supply and fix new 1-gang switch plate to match and test.

Item

088 Ditto, as item 087 but 2-gang. Item

089 Remove defective plastic pull switch and cord supply and fit new to match.

Item

090

Ditto, as item 084 but 3-gang 1-way lighting switch and box either in metal or plastic to match existing. Supply and fix new plate and box to match existing.

Item

091 Ditto, as item 084 but 3-gang 1-way, main entrance metal switch Item

Page 70: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

70

plate.

092

Water heaters Prepare for, supply and surface fix immersion heater circuit complete from consumer unit to hot water cylinder with and including average 15m length of cable, switched spur outlet with pilot lamp and average 1m length of heat resisting flex, connect to immersion heater all labours and test.

Item

093

Remove defective spur outlet and flex complete, supply and fit new 20 amp D.P. fused spur outlet with pilot lamp including average 2m length of heat resisting flex, connect to appliance and test.

Item

094

Major repair to immersion including any or all of the following: Test heater, renew/adjust thermostat, renew heatproof flexible cable, test and leave in working order.

Item

095

Replace immersion heater 3kw with integral thermostat and including wiring to adjacent point in suitable sized heat resisting flex test and leave in working order.

Item

096

Major repair to water heater including any or all of the following: Test heater/spur, refix and remake faulty connections, replace fuse, renew neon indicator, adjust thermostat.

Item

097 Disconnect existing circulating pump (any type) and leave safe. Item

098

Reconnect only circulating pump (existing or supplied elsewhere – see “plumbing”) to outlet including 2m average length of flex and test.

Item

099 Remove defective time switch, supply and fix new Smiths timber switch to existing wiring and test.

Item

100

Remove defective hand dryer (any size or type) supply and fit new sensor type hand-dryer as existing or as approved by CA including all necessary fixings, fittings, connections and cables to existing system (complete operation).

Item

101 Carry out repair/overhaul to electric hand-dryer (any size or type) refit and leave in working order.

Item

102 Remove defective heater element to hand dryer, any type, supply and fit new, test and leave in working order.

Item

103

Ventilators Remove defective (if necessary) supply and fix new 150mm Vent-Axia window or wall mounted extractor fan including hole through glass or wall, fused spur outlet from existing ring main and all connections (average 3m length).

Item

104

Ditto, as item 103 but ceiling mounted extractor fan including hole through ceiling, fused spur outlet from existing ring main and all connections.

Item

105 Prepare for supply and fix 5 amp jointing box and test. Item

106 Ditto, as item 105 but 30 amp. Item

107 Refix only existing trunking to backing including plugging and screwing.

Item

108

Carry out periodic test of the electrical installation and submit a NICEIC current edition completion and inspection certificate to C.A. (per public convenience, ladies, gents and disabled).

Item

109 Provide an electrician for attendance or inspection of works as requested or instructed by the C.A. (per ¼ hour).

Item

110

Ditto, as item 109 but for each subsequent 15 minute period. Public Convenience Closure/Opening This item to be read in conjunction with similar items in Section 5 and 6.

Item

111 Isolated mains electrical supply to convenience and leave all electrics safe for period of closure. – Per public convenience.

Item

112 Ditto, as item 111 but reconnecting, testing and leaving in Item

Page 71: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

71

working order electrics to public convenience (report faults to C.A.).

113

Wire and fix supply to water saver Circuit wired in 1-5mm²/twin earth concealed in trunking with fuse rating of 6MCB at consumer unit and 3 amp at appliance.

Item

114 Ditto, as item 113 but with remote sensor. Item

115 Supply and renew battery to water saver unit. Item

116 Supply and renew battery to air freshener dispenser. Item

117 Record electric supply meter reading at any unit in the district and supply to C.A.

Item

118

Record electric supply meter reading at any unit in the district at the same time as undertaking reactive route repair and maintenance work and supply to C.A.

Item

119 Supply and fit mini photocell to new or existing external lighting. Item

Page 72: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

72

DESCRIPTION OF WORKS AND

SCHEDULE OF RATES

SECTION 8

FLOOR, WALL AND CEILING FINISHINGS

Page 73: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

73

FLOOR, WALL AND CEILING FINISHINGS

1. GENERALLY 1.1 The Contractor is to note that it is envisaged that the work in this section will often

occur as a consequence of other repair operations and as such the rates shall be deemed to include for the liaison between trades where applicable.

1.2 In addition to the specific requirements of this section of preambles, the Contractors it to note that where applicable the provisions contained within the “Concrete Work Preambles” shall equally apply.

1.3 All rates for all work within this section where applicable are deemed to include for the following:- (1) Work to walls, ceilings or floors in compartments not exceeding 4.00m² on plan or

work that would normally give rise to a premium on measured rates including, but not limited to, work not exceeding 300mm wide and work to soffits exceeding 3.50m high.

(2) Work and labour carried out over hand. (3) Work to existing surfaces and preparation thereto, and work on bases of differing

natures. (4) Temporary rules, templates, support work or the like. (5) Fair joints to flush edges of existing finishes and preparation thereto and

junctions between straight and curved work. (6) Making good and labours on finishing’s including pointing around steel joists, w.c.

pedestals, angles, trunking, ducting, floor springs, ventilators, pipes, tubes and the like.

(7) Working finishing’s into recessed covers, shaped inserts and the like. (8) Curved or straight work.

2. TILES 2.1 The Contractors attention is particularly drawn to the unit of measurement of small

quantities of tiles within this section which is per No. of tiles which has been chosen to reflect the patching and isolated nature of the work. The Contractors attention is also drawn to the “general preamble” section relating to the m² measurement of tiling.

2.2 Glazed wall tiles shall conform to the appropriate British Standard. However, the Contractor is to note that the rates for replacing tiles are deemed to include for the extra over cost of providing and fixing cushion edge tiles where necessary.

2.3 The rates for all wall tiling are deemed to include for setting the tiles square to match the existing pattern with straight even joints, and for fixing with an approved waterproof wall tiling adhesive to BS and pointing in white cement grout on completion.

2.4 The Contractor is also to note that the rates for all wall tiling are deemed to include all cutting to angles, boundaries and junctions or the like.

2.5 The glazed wall tiles included within this schedule are plain “white” and the Contractor is to note that where tiles of a differing colour or pattern are encountered during any repair work which would prevent the use of standard white replacement tiles he shall

Page 74: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

74

inform he Contract Administrator prior to the commencement of any work, to receive his instructions. The fixing of any coloured or patterned tiles without the prior instructions of the Contract Administrator will be deemed to be carried out at no greater cost to the Council than the rates included for white tiles within this schedule or at the Contractors own expense.

2.6 Clay floor quarry tiles shall conform to the appropriate British standard and shall be square edge colour to match existing unless otherwise directed by the Contract Administrator. Coving tiles shall be to match existing.

2.7 The tiles shall be fixed with an approved quarry tile adhesive grouted with an approved grout applied strictly in accordance with the manufactures instructions.

2.8 The rates for quarry tiles are deemed to include for providing a cork expansion joint where necessary and for levelling and setting the tiles square to match the existing pattern where applicable. The rates for quarry tiles are also deemed to include for all cutting to angles, boundaries and junctions shall be 3mm.

3. PLASTERBOARD 3.1 All plasterboard shall be British Gypsum or equivalent, approved and conform to the

appropriate British Standard and be provided with a suitable face ready to received decoration. The board shall be fixed strictly in accordance with the manufacturer’s instructions (“The White Book”) avoiding continuous cross joints and fixed at not more than 200mm centres to joists, bearers, studs or the like with galvanised drywall plasterboard screws, kept 12mm from the edge of boards (or as otherwise described). Gaps between boards shall be 3mm.

3.2 All plasterboard shall have scrimmed joints as described in the Painting and Decorating Preambles.

3.3 The contractor is to note that the rates for all items of plasterboard are deemed to include where applicable for cutting around edges of opening, abutments to toher finishing’s, intersections, internal and external angles, forming corners and cutting to the profile of openings and the like.

4. PLASTER 4.1 All plaster specified shall conform to the appropriate British Standard as applicable

and shall be used strictly in accordance with the manufacturer’s instructions.

4.2 All plastering work is to be carried out generally in accordance with the appropriate Code of Practise BS.

4.3 The rates for all plastering are deemed in include for working behind pipes or the like and all necessary temporary rules. In addition, the rates for plastering on concrete surfaces are to include for hacking on brick for keyed surfaces or for raking out joints 15mm deep to form an adequate key.

4.4 Notwithstanding 4.3 above, all surfaces to be plastered, rendered or the like are to be cleaned down with stiff or wire brushes and clean water and left free from dust, loose material, grease or other deleterious matter prior to any work commencing.

4.5 Sand for plastering shall conform to the appropriate British Standard. Water shall be clean mains water free from deleterious matter. Cement is to be described in the “Concrete Preambles”.

4.6 Render coats shall consists of one part cement to three parts sand by volume and shall be spread by a trowel and struck off level. When the render coat has begun to dry and harden it should be combed with evenly distributed wavy horizontal combings

Page 75: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

75

the indentations of which should be 20mm apart and 5mm deep to corm a key and all rates shall be deemed to include for this provision.

4.7 Single coat work on Gypsum wallboard shall be Thistle board finishing plaster to a not less than 4mm thickness from the face of the lath.

4.8 Expanded metal lathing shall be galvanised and conform to the appropriate British standard 24 gauge plain expanded type and fixed with galvanised staples., the rates for all lathing are to be included for well lapping and wiring together at joints.

5. SUNDRIES 5.1 P.V.A. bonding agent shall be an approved P.V.A. adhesive and sealer, diluted and

applied strictly in accordance with the manufacturer’s instructions.

5.2 “Synthaprufe” or equivalent water proofer shall be applied strictly in accordance with the manufacturer’s instructions.

5.3 Floor tiles shall be similar to Marley Econoflex vinyl floor tiles series 4 size 300mm x 300mm x 2mm to the appropriate British Standard laid with the tile manufacture’s approved bitumen floor tile adhesive. Tiles shall be laid as recommended in BS.

5.4 Latex levelling screed will only be laid when specifically directed by the Contract Administrator and the rate for floor tiles shall be deemed to include for making good to the screed or sub-base.

5.5 Tiling in public toilets should be carried out in accordance with B.S. “tiling in wet conditions” and allow for 2mm spacing between tiles and silicone expansion joint at the end of walls. Adhesive and grout must be cementicious.

6. MEASUREMENT The measurement expression (per area) shall mean the total aggregates quantity of the work carried out in a single toilet area, which shall be used to determine the band and hence the rate used. Should the total quantity of work per area in an order exceed in any item in the highest band shown in the rates, the rate in the highest band shall be deemed to apply. Toilet area shall mean per ladies or gents toilet block.

7. SCOPE OF WORK The Contractor should note that work above the highest quantity shown in any band in this section of the schedule will be deemed not the be reactive maintenance work and as such would not normally be ordered under the scope of this contract, except at the discretion of the Contract Administrator. (The Contractor may however be required to provide a quotation for such larger scale work on an individual order basis and the value of such work will be treated as a variation order).

Page 76: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

76

Prefix No. PC08000 SOR No.

Description

Unit

Rate £

Rate p (pence)

001

FINISHINGS Internal Work Walls Remove defective wall tiles or the like, make good surface of wall, supply and fix new glazed ceramic tiles to match existing bedded in Richafix or the equivalent adhesive including all cutting and grouting in white cement grout (complete operation) in areas up to 10 no. tiles (per toilet area).

Item

002 Ditto, as item 001 but areas 11 – 15 no. tiles (per toilet area). No.

003 Ditto, as item 001 but areas 16 – 25 no. tiles (per toilet area). No.

004 Ditto, as item 001 but areas 26 – 35 no. tiles (per toilet area). No.

005 Ditto, as item 001 but areas 36 no. tiles (per toilet area). m²

006

Prepare and apply white “Dow-Corning” or similar master joint at junction of fitting and walls or the like. Isolated lengths not exceeding 1.00m (per toilet area).

Item

007 Ditto, as item 006 but lengths over 1m – 10m (per toilet area). Lm

008

Supply and fix 12.5mm thick “Gyproc” or similar square edge wallboard to the appropriate British Standard to timber grounds or base with galvanised jiggered shank plasterboard nails at 200mm centres including all labours. Areas up to 2.50m² (per toilet area).

Item

009 Ditto, as item 008 but areas over 2.50m² - 5.00m² (per toilet area).

010 Ditto, as item 008 but areas over 5.00m² - 20m² (per toilet area).

011

Prepare surface of wall for plaster including chipping wall if necessary to form key. Apply P.V.A. bonding agent to wall and render in cement mortar (3:1) and one coat Siraphite or similar wall finish (average 15mm overall thickness) trowelled smooth to receive decorations including all labours (complete operation). Areas up to 0.25m² (per toilet area).

012 Ditto, as item 011 but areas 0.25m² - 0.50m² (per toilet area). Item

013 Ditto, as item 011 but areas 0.50m² - 1.00m² (per toilet area). Item

014 Ditto, as item 011 but areas 1.00m² - 5.00m² (per toilet area). m²

015 Ditto, as item 011 but areas 5.00m² - 20.00m² (per toilet area). m²

016

Hack off existing setting plaster coat and other wall finishing’s, prepare wall surface and apply average 5mm thick Siraphite or similar setting coat trowelled smooth to receive decorations including all labours (complete operation). Areas up to 0.25m² (per toilet area).

Item

017 Ditto, as item 016 but areas 0.25m² - 0.50m² (per toilet area). Item

018 Ditto, as item 016 but areas 0.50m² - 1.00m² (per toilet area). Item

019 Ditto, as item 016 but areas 1.00m² - 5.00m² (per toilet area). m²

020 Ditto, as item 016 but areas 5.00m² - 20.00m² (per toilet area). m²

021

Prepare wall and apply average 5mm thick Sirapite or similar setting coat to rendered walls trowelled smooth to receive decorations including all labours (complete operation). Areas up to 0.25m² (per toilet area).

Item

022 Ditto, as item 021 but areas over 0.25m² - 0.50m² (per toilet area).

Item

023 Ditto, as item 021 but areas over 0.50m² - 1.00m² (per toilet area).

Item

024 Ditto, as item 021 but areas over 1.00m² - 5.00m² (per toilet area).

Page 77: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

77

025 Ditto, as item 021 but areas over 5.00m² - 20.00m² (per toilet area).

026

Hack off defective rendering to expose base (any material) prepare wall including raking out joints and apply one coat of P.V.A bonding agent and re-render with one coat cement and sand (1:3) and one coat Sirapite or similar wall finish average 15mm thick surface overall trowelled smooth to receive decorations including all labours, (complete operation). Areas up to 0.25m² - 0.50m² (per toilet area).

Item

027 Ditto, as item 026 but areas over 0.25m² - 0.50m² (per toilet area).

Item

028 Ditto, as item 026 but areas over 0.50m² - 1.00m² (per toilet area).

Item

029 Ditto, as item 026 but areas over 1.00m² - 5.00m² (per toilet area).

030 Ditto, as item 021 but areas over 5.00m² - 20.00m² (per toilet area).

031

Ceilings Supply and fix 12.5mm thick square edge “Gyproc” or similar plasterboard to existing ceiling joists over existing ceiling finish with 3mm joints fixed with 50mm average length galvanised wire nails at 200mm centres including all labours (complete operation). Ares up to 200m² (per toilet area).

032 Ditto, as item 032 but areas over 2.00m² - 5.00m² (per toilet area).

033 Ditto, as item 032 but areas over 5.00m² - 10.00m² (per toilet area).

034 Ditto, as item 032 but areas over 10.00m² - 20.00m² (per toilet area).

035

Cut out defective area of plasterboard ceiling and patch repair ceiling including cutting back clean edges to suitable grounds, battens or joists and skim coat smooth to receive decorations (complete operation). Areas up to 0.25m² (per toilet area).

Item

036 Ditto, as item 035 but areas over 0.25m² - 0.50m² (per toilet area).

Item

037 Ditto, as item 035 but areas over 0.50m² - 1.00m² (per toilet area).

Item

038 Ditto, as item 035 but areas over 1.00m² - 5.00m² (per toilet area).

Item

039

Prepare ceiling and apply plaster skim coat average 5mm think including scrimming all joints trowelled smooth to receive decorations including all labours (complete operation). Areas up to 0.25m² (per toilet area).

Item

040 Ditto, as item 039 but areas over 0.25m² - 0.50m² (per toilet area).

Item

041 Ditto, as item 039 but areas over 0.50m² - 1.00m² (per toilet area).

Item

042 Ditto, as item 039 but areas over 1.00m² - 5.00m² (per toilet area).

043

Plastering, Finishes Replace covings and cornices to ceiling including hack down existing coving, prepare surfaces and provide new moulded plaster coving 127mm deep including all adhesive, tapes, fillers. Allow for forming all internal/external angles, cutting around obstructions and decorating to match adjoining areas. Lengths totalling but not exceeding 5m per toilet area.

Item

044 Ditto, as item 043 but lengths exceeding 5m in total per toilet area.

Lm

Page 78: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

78

045

Cut out defective fire resistant boarding and renew with 6mm thick supalux fire resistant boarding, sanded with butt joints. Including all cutting back, replacement of grounds and making good of adjoining surfaces ready to receive decorations (complete operation). Areas to 1m² (per toilet area).

Item

046 - Area exceeding 1m² (per toilet area). m²

047

Floors Hack up existing composite floor screed and clear away prepare base and apply one coat of approved bonding agent, supply and lay “Sealofloor” (Sealocrete Limited” screed or equivalent 12mm thick mixed in accordance with the manufacturer’s instructions with 2.5m parts granite chippings (6mm to dust) by volume and trowelled smooth including all labours. Areas up to 1.00m² (per toilet area).

Item

048 Ditto, as item 047 but areas over 1.00m² - 5.00m² (per toilet area).

049 Ditto, as item 047 but areas over 5.00m² - 10.00m² (per toilet area).

050 Ditto, as item 047 but areas over 10.00m² - 20.00m² (per toilet area).

051

Hack off existing floor tiles or the like and clear away prepare base, supply and fix new quarry tiles, colour size to match existing tiles to be fixed with appropriate adhesive and grout including expansion joints at perimeter as necessary, including all labours (complete operation). Areas up to 5 no. tiles (per toilet area).

Item

052 Ditto, as item 051 but areas 6 – 10 no. tiles (per toilet area). No.

053 Ditto, as item 051 but areas 11 – 20 no. tiles (per toilet area). No.

054 Ditto, as item 051 but areas 21 no. tiles (per toilet area). m²

055

Hack off existing cover tiles and clear away, prepare base and supply and fix new cove tiles colour and size to match existing. Tiles to be fixed with appropriate adhesive and grout including all labours (complete operation). 1 – 5 tiles per toilet area.

Item

056 Ditto, as item 055 but over 5 tiles per toilet area. Lm

057 Lay 3mm thick (average) latex levelling screed to existing concrete floor.

058

Break up and remove composite floor screed, seal and lay cement mortar (1:3) screed (average 50mm thick) trowelled smooth including all labours (complete operation). Areas up to 1m² (per toilet area).

Item

059 Ditto, as item 058 but areas over 1.00m² - 5.00m² (per toilet area).

060 Ditto, as item 059 but areas 5.00m² - 10.00m² (per toilet area). m²

061 Ditto, as item 059 but areas over 10.00m² - 20.00m² (per toilet area).

062

Sundries Cut out crack in plaster or the like not exceeding 100mm wide form dovetail key, make good with cement mortar (1:3) and Siraphite or similar finish coat, trowelled smooth to receive decorations including all labours (complete operation). Lengths up to 2m (per toilet area).

Item

063 Ditto, as item 062 but lengths 2 – 5m (per toilet area). Lm

064 Ditto, as item 062 but lengths 5 – 10m (per toilet area). Lm

065

Cut out crack in plaster or the like not exceeding 50mm wide, around door or window frames, form dovetailed key, make good with cement mortar (1:3) and Siraphite or similar finish coat, trowelled smooth to receive decorations including all labours (complete operation).

Lm

Page 79: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

79

066

Cut out crack in plaster or the like not exceeding 50mm, wide around pipe any size, form dovetailed key, make good with cement mortar (1:3) and Siraphite or similar finish coat, trowelled smooth to receive decorations including all labours (complete operation). Areas up to 0.25m²

067

Cut out defective plaster or the like around basin or the like make good with cement mortar (1:3) and Siraphite or similar finish coat, trowelled smooth to receive decorations including all labours (complete operation). Average 1m².

Item

068

Prepare wall and form external angle in cement mortar (1:3) and Siraphite or similar finish plaster up to 200mm firth including all labours (complete operation).

Lm

069

External Work Hack off defective rendering to expose base (any material) prepare wall including raking out joints and apply one coat of Blue Circle or similar stabilising solution and re-render with one coat cement and sand (1:3) average 15mm thick finish to match existing including all labours. Areas up to 0.25m² (per wall elevation).

Item

070 Ditto, as item 069 but areas over 0.25m² - 0.50m² (per wall elevation).

Item

071 Ditto, as item 069 but areas over 0.50m² - 1.00m² (per wall elevation).

Item

072 Ditto, as item 069 but areas over 1.00m² - 5.00m² (per wall elevation).

Item

073

Pebble dash previously prepared wall where necessary to match existing or new work. Areas up to 1m² (per wall elevation).

Item

074 Ditto, as item 073 but areas exceeding 1m² (per wall elevation).

075 Galvanised metal lath fixed to any surface ready to receive new render. Areas up to 1m² (per wall elevation).

Item

076 Ditto, as item 075 but areas exceeding 1m² (per wall elevation).

Page 80: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

80

DESCRIPTION OF WORKS AND

SCHEDULE OF RATES

SECTION 9

GLAZING

Page 81: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

81

GLAZING

1. GENERALLY 1.1 The Contractor is to note that where glass is to be removed it shall be carried out so

as to cause the minimum amount of damage to surrounding frames, adjoining glass or the like, which shall be adequately protected. Damage arising from failure to observe this clause shall be made good at the Contractor’s own expense to the satisfaction of the Contract Administrator.

1.2 Material resembling glass have been included in this section and shall be deemed to be “glazing” for the purpose of this contract.

1.3 All rates contained within the “glazing” section of the schedule are deemed to include for the cost of working at whatever height or location may be ordered and for some provision, erection and removal of all necessary scaffolding, towers, platforms, ladders, roofing ladders or the like that may be required to execute the works up to second storey eaves level and associated roofs.

1.4 Where applicable the rates for glazing are deemed to include for the removal of existing glass, pre-measurement, all cutting, preparation, cleaning and knotting or priming rebates, bedding and fixing, finishing and cleaning on completion to remove all broken glass fragments however small.

1.5 Wherever possible glass shall be cut to size on an approved glass cutting table at other relevant clauses contained in this schedule, the Contractor is to ensure that at all times whilst glazing work is in progress, members of the public are properly protected and kept informed of situations where a danger may arise. At the cessation of all work howsoever caused the Contractor is to completely clear all working areas of fragments of glass however small, by means of an industrial vacuum cleaner if required and leave safe to the satisfaction of the Contract Administrator.

2. GLASS OR THE LIKE 2.1 All glass shall be the best of its respective kind free from bubbles, air holes and other

defects and shall conform where applicable to the appropriate British Standards. Toughened and laminated glass shall be to BS and permanently marked as such in an approved manner.

2.2 The minimum thickness of glass to be fixed in windows and doors shall be 6mm toughened or laminated. In all cases panes of glass or the like are to be in one piece and are to be cut and fitted with due allowance for expansion. The unit of measurement of glass is “per pane”.

2.3 Where applicable the rates for wired or other pattern glass are deemed to include for alignment of wires or patterns to adjacent panes.

3. GLAZING 3.1 All glazing shall be carried out strictly in accordance with the appropriate Code of

Practise for the Glazing of Buildings BS 6262.

3.2 Wherever possible all orders for re-glazing shall be completed in one operation without the necessity to “board up”. For the avoidance of doubt, the term “one operation” and the Contractor’s rates for glazing shall be deemed to include provision for any necessary site visits to pre-measure glass and for collecting materials from the Contractor’s depot/store or a glass supplier and thereafter returning to site to complete the order within a timescale that is reasonable, (in the opinion of the Contract Administrator whose decision shall be final and binding), having regard to

Page 82: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

82

the nature of the breakage or repair and the safety and welfare of the public and/or the security of the premises.

3.3 Where an order is specifically issued to “make safe” broken glass or where in the opinion of the operative on arriving at the location to which an order refers, the breakage or repair is such so as to immediately threaten the safety or welfare of the public and/or the security of the premises, or for reasons beyond the control of the Contractor the repair cannot be completed in one operation as defined above, the broken glass shall be made safe and the pane or opening as appropriate boarded up. The boarding shall be securely fixed and shall be the minimum necessary to secure the premises. Operatives responding to orders to “make safe” glazing shall at all times have sufficient materials available to “board up” on the first occasion that they visit the location to which an order refers.

3.4 If in the opinion of the Contract Administrator the Contractor is “band up” a glazed area that ought to have been re-glazed in one operation as defined above; which for the avoid of doubt shall specifically include boarding up necessitated by the Contractor’s failure to maintain adequate stocks or supplies of glass or glazing materials or for any other matter reasonably within the Contractor’s control; the Council will not reimburse the Contractor for the cost of boarding up which shall be deemed to have been undertaken for the Contractor’s convenience and at his own expense.

3.5 Putty for glazing to timber shall be linseed oil putty to the appropriate British Standard.

3.6 Putty for glazing to metal shall be “Arbo NP90” or similar and rates shall be deemed to include for priming rebates with one coat of NP 90 or similar primer in accordance with the manufacturer’s instructions prior to fixing.

3.7 Mastic for glass fixed with beads is to be an approved non-hardening mastic.

3.8 All putties are to be the full length of rebates, neatly and cleanly finished with a weathered face, and back putties are to be neatly trimmed to 3mm above the height of the face putty.

3.9 Glass fixed in timber frames is to be well bedded in putty, back puttied and sprigged in as required. Glass in metal frames is to be pinned or clipped.

3.10 Where described as fixed with beads, rates are deemed to include for providing wrought softwood beads, fixed with either pins or brass screws and cups as described.

3.11 Before fixing new glazed, timber rebates shall be cleaned, primed and painted to match existing.

3.12 Where macralon is specified the rates quoted include similar materials (e.g. lexan clear polycarbonate sheet). Although marcralon is to be used unless specified otherwise.

3.13 Clean all glass on completion and replace all cracked and broken glass.

4. SCOPE OF THE WORK The Contractor should note that glazing in any material or building element not included in this section of the schedule of rates will be deemed not to be reactive maintenance work and as such would not normally be ordered under the scope of this contract, except at the discretion of the Contract Administrator. (The Contractor may, however, be required to

Page 83: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

83

provide a quotation for such work on an individual order basis and such work will be treated as a variation order).

Page 84: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

84

Prefix No. PC09000 SOR No.

Description

Unit

Rate £

Rate p (pence)

001

GLAZING Georgian Wired Cast Glass Hack out defective glass, putty and beads apply one coat of knotting to rebate as required cut and fix 7mm thick Georgian Wired Cast Glass to timber with and including screwed beads and approved non setting compound. Oanes up to 0.50m² (price per pane).

Item

002 Ditto, as item 001 but panes over 0.50m² but not exceeding 1.00m² in area (price per pane).

Item

003 Ditto, as item 001 but panes over 1.00m² but not exceeding 2.00m² in area (price per pane).

Item

004

Hack out defective glass and back putties apply one coat of primer to rebates as required cut and fix 7mm thick Georgian Wired Cast Glass to metal with putty including for measurement and all labours. Panes up to 0.50m² (price per pane).

Item

005 Ditto, as item 004 but panes over 0.50m² but not exceeding 1.00m² in area (price per pane).

Item

006 Ditto, as item 004 but panes over 1.00m² but not exceeding 2.00m² in area (price per pane).

Item

007

Georgian Wired Polished Glass Hack out defective glass, putty and beads apply one coat of knotting to rebate as required cut and fix 7mm thick Georgian Wired Polished glass to timber with and including beads to match existing fixed with brass cups and screws and approved non setting compound. Panes up to 0.50m² in are (price per pane).

Item

008 Ditto, as item 007 but panes over 0.50m² but not exceeding 1.00m² in area (price per pane).

Item

009 Ditto, as item 007 but panes over 1.00m² but not exceeding 2.00m² in area (price per pane).

Item

010

Hack out defective glass and back putties apply one coat of primer to rebates as required cut and fix 7mm thick Georgian Wired Polished Glass to metal with putty include for measurement and all labours. Panes up to 0.50m² (price per pane).

Item

011 Ditto, as item 010 but panes over 0.50m² but not exceeding 1.00m² in area (price per pane).

Item

012 Ditto, as item 010 but panes over 1.00m²but not exceeding 2.00m² in area (price per pane).

Item

013

Macralon Sheeting Ditto, all as item 001 but cut and fix 6mm clear polycarbonate sheet (Macralon) and glazing with beads. Panes up to 0.50m² in area (price per pane).

Item

014 Ditto, as item 013 but panes over 0.50m² but not exceeding 1.00m² in area (price per pane).

Item

015 Ditto, as item 013 but panes over 1.00m² but not exceeding 2.00m² in area (price per pane).

Item

016

Ditto, as item 004 but cut and fix 6mm frosted polycarbonate sheet (Macralon) and glazed putty to metal or wood. Panes up to 0.50m² in area (price per pane).

Item

017 Ditto, as item 016 but panes over 0.50m² but not exceeding 1.00m² in area (price per pane).

Item

018 Ditto, as item 016 but panes over 1.00m² but not exceeding 2.00m² in area (price per pane).

Item

Page 85: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

85

019

Ditto, as item 001 but cut and fix 3mm Meshlite plastic and screwing to back beads and fixing with screwed beads. Panes up to 0.50m² in area (price per pane).

Item

020 Ditto, as item 019 but panes over 0.50m² but not exceeding 1.00m² in area (price per pane).

Item

021 Ditto, as item 019 but panes over 1.00m² but not exceeding 2.00m² in area (price per pane).

Item

022

Ditto, all as item 004 but cut and fix 3mm Meshlite plastic and glazing with putty to metal. Panes up to 0.50m² in area (price per pane).

Item

023 Ditto, as item 022 but panes over 0.50m² but not exceeding 1.00m² in area (price per pane).

Item

024 Ditto, as item 022 but panes over 1.00m² but not exceeding 2.00m² in area (price per pane).

Item

025

Glass to roofs etc. To include for re-glazing, hacking out old putty or glazing compound, remove clips/springs/beads, hack out glass and prepare opening to receive new glass, new glass as described together with making good to decorations. Roof panels not exceeding 0.50m² area.

Item

026 Ditto, as item 025 but roof panel exceeding 0.5m² and not exceeding 1m² total area.

Item

027 Ditto, as item 025 but roof panel exceeding 1m². m²

028

Extra over any specilaised glazing for glazing to skylight including all access ladders etc. in small panes (up to 0.5m²)

Item

029 Ditto, as item 028 but medium panes (up to 1m²). Item

030 Ditto, as item 028 but large panes. m²

031

Ventilators and Associated Work Remove existing defective ventilator and supply and fix new “Ventamatic Ventilator” or similar with cord operated shutter and storm guard, average size 160mm diameter.

Item

032

Cut hole in existing or new glass for ventilator average size 160mm diameter and supply and fix new “Ventamatic Ventilator” or similar with cord and operated shutter and storm guard.

Item

033

Sundries Hack out defective face putty to timber frames apply one coat of knotting to exposed rebates and re-putty (per frame).

Lm

034 Hack out defective face putty metal frames clean out rebates and re-putty (per frame).

Lm

035

Hack out defective glass (any type) and putty, beads or back putties as appropriate. Apply knotting or primer to rebate (as required) and cut and fix glazing as specified by C.A. including all beads and or putties as required. Panes 0 – 0.50m² in area (price per pane).

Item

036 Ditto, as item 035 but panes 0.50 – 1.00m² area (price per pane).

Item

037 Ditto, as item 035 but panes over 1.00m² in area. m²

038

Supply and fix clear Lexan or similar to cover information signs and the like. Signs to be fixed with anti-vandal screws. Signs up to 0.25m²

Item

039 Ditto, as item 038 but signs up to 0.25m – 0.50m² Item

040 Ditto, as item 038 but signs 0.50 – 1.00m² Item

041 Refit existing Polycarbonate sheeting.

Page 86: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

86

DESCRIPTION OF WORKS AND SCHEDULE OF RATES

SECTION 10 PAINTING AND DECORATING

Page 87: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

87

PAINTING AND DECORATING

1. GENERALLY

1.1 The Contractor is to note that the work within this section will often occur as a

consequence of other repair operations and as such the rates shall be deemed to

include for the liaison between trades where applicable.

1.2 All rates contained within this section of the schedule are deemed to include for the

cost of working at whatever height or location may be ordered and for the provision,

erection and removal of all necessary scaffolding, towers, platforms, ladders or the

like that may be required to execute the works.

1.3 All rates contained within this section of the schedule for internal work, (i.e. work

within a building structure), are deemed to include for the cost of all necessary

ladders, step ladders, tressles, boards or the like necessary to undertake the work in

accordance with health and safety regulations.

1.4 The Contractor’s attention is particularly drawn to the fact that in anticipation of the

varying degrees of surface preparation that are likely to be encountered on surfaces

of an identical nature, generally all painting and the like has been divided into

separate operations of preparatory work and separate operations for each individual

coat of paint. As a consequence an order from the Contract Administrator to carry out

painting or the like will state:

a) The item(s) to be painted and their location.

b) The particular preparatory operation required.

c) Details of all coats required, including their respective colours.

No painting whatsoever is to be carried out (unless otherwise described as part of an operation of work elsewhere within this schedule – for example, priming timber) unless the prior approval of the Contract Administrator has been received.

1.5 Where the term “girth” is used it shall be deemed to mean the total girth of all adjoining like items to be painted. Where applicable wok has been divided into surfaces not exceeding 300mm girth and surfaces over 300mm girth.

1.6 “Surfaces” shall be deemed to mean and shall be measure as the area covered and

where applicable allowances made to measurement (unless otherwise stated herein) for the extra girth of edges, mouldings, panels, sinking’s, corrugations, flutings, carvings, enrichments and the like.

1.7 The Contractor is to note that internal operations of painting on woodwork shall be

deemed to include for working on all items of joinery, frames, linings, skirting’s, dado rails, wall mouldings, capping’s, margins, doors and other timer surfaces excluding windows or associated work and that cutting in edges on flush surfaces and work to butts and fastenings shall be deemed to be included where applicable.

1.8 For the purposes of this Contract glazed doors shall be deemed to be as flush doors

and the surface area shall be measured each size over all glass and the additional surface area of painting measured over glazing shall be deemed to cover the additional cost of cutting in next to glass and working over glazing beads or the like irrespective of the pane size.

Page 88: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

88

1.9 Windows or glazed screens shall be measured each side (i.e. internally and externally) as an overall superficial area, over frames, linings, mullions, transoms, sills and glass (irrespective of pane size. Cutting in next to glass or weather stripping and work on glazing beads, butts and fastenings shall be deemed to be included. Work on edges of opening casements shall be deemed to be included within the rate for external painting to windows.

1.10 Work on gutters, downpipes or the like externally shall be deemed to be measured as

the surfaces to be painted defined by girth (see Clause 1.5 above). Work to brackets, fittings and the like shall be deemed to be included within the girth measurement. The Contractor is to note that no distinction is made between previously painted timber or metal surfaces in work externally.

1.11 Work to pipes or the like shall be classified and measured by girth (see Clause 1.5

above) and the rates shall be deemed to include for work to all fittings, joints, clips, brackets or the like.

1.12 Where the Contractor is instructed to execute decoration work on a member, surface

or item that is found to be, or he considers being, unsound or unfitting to receive decoration without prior repair work, he shall inform the Contract Administrator immediately and await his instructions.

1.13 Where applicable all ironmongery or the like shall be removed throughout any

decorating work and subsequently re-fixed and all rates shall be deemed to include for this provision. (Face plates to cylinder locks) or the like are not to be painted).

1.14 Work on each side of close-type fencings and gates (grouped together) shall be

measured net overall. Each side of ornamental railings, gates, louvered window openings and the like shall be measured overall regardless of voids.

1.15 Notwithstanding any of the relevant clauses contained within these documents

appertaining to the cleaning of work ore removal of debris, on completion or at each cessation of the work the Contractor is to clean all glass and the like of paint spots or runs to the satisfaction of the Contract Administrator. In addition, the Contractor is to remove from site all empty tins or the like a surplus paint which under no circumstances shall be poured into drainage systems.

1.16 The Contractor’s attention is particularly drawn to the need to adequately protect the

surrounding environment during painting and decorating work and at all times to erect adequate signs and to inform the public of surfaces that are “wet”. The Contractor shall allow in his rates for the protection of all fittings, the provisions of dust sheets and the removal and replacement of all items to facilitate decorating work.

2. PAINTING AND DECORATING

2.1 The whole of the paint or the like materials in this contract shall be to the appropriate British Standard and where applicable all materials are to be obtained from either ICI –Dulux, Crown Decorative Products Ltd or other approved supplier and shall be used strictly in accordance with the manufacturer’s instructions. Low odour, water based paint shall be used on all internal surfaces.

2.2 The colour of all paint or the like to be used shall be as specified on each particular

order from the Contract Administrator (see Clause 1.4 above) and will be selected from the appropriate British Standard Trade Colours range (and shall be used with the appropriate recommended tint of undercoat where applicable).

Page 89: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

89

2.3 All painting is to be executed in an approved manner by brush or roller to the appropriate sections of the BS. Spray painting will not be permitted without the approval of the Contract Administrator.

2.4 All woodwork is to be well rubbed down with fine abrasive paper before each coat or as otherwise described. All surfaces are to be clean dry and free from moisture, oil or grease and precautions shall be taken to prevent dust settling on any finished work. Painting shall not be carried out in the vicinity of other trade operations which might cause dust or otherwise damage the work. All work shall be touched up on completion as required by the Contract Administrator at no extra cost.

2.5 No painting on exterior work shall be executed in wet, damp, frosty or foggy weather (or upon surfaces that are not thoroughly dry or clean).

2.6 Each coat is to be completed over the whole of the work before the next coat is proceeded with including any additional stopping and rubbing down that may be necessary and at least 24 hours shall elapse between the finishing of one coat and the commencement of the next. Where two undercoats are required by an order, the Contractor shall use either a dark or light grey for the first coats (to suit the final tint) and the second coat shall be as recommended by the manufacturer (see Clause 2.2 above)

2.7 Knotting shall be best quality patent knotting to BS and primer shall conform to the British Standard appropriate to the surface of the next and to reject any work that is unsatisfactory for whatever reason which shall be removed and put right at the Contractor’s own expense.

2.8 blank

2.9 All paint shall be thoroughly mixed and stirred before use and stored so as to

minimise exposure to extremes of temperature. All paint used shall be delivered to each location of work in the manufacturer’s original container which must be properly resealed after opening. Where kettles are used they must be properly cleaned out before and after use and before changing the type or colour of paint. Paint shall not be thinned prior to use other than in strict accordance with the manufacturer’s instructions.

2.10 Existing paintwork next to glass shall be cut back to sight lines using a sharp blade or the like. Where burning off of existing paint is required it shall be carried out so as to avoid total scorching or damage to glass which shall be made good at the Contractor’s expense. Any paint removers used shall be approved by the Contract Administrator prior to use. After paint has been removed the surface must be smothered and properly dusted off, all knots coated with shellac and allowed to dry hard before the application of wood primer. When the primer is hard all cracks, shakes, holes or the like shall be made good with stopping as described in Clause 2.7 above.

2.11 All rubbing down is to be carried out using waterproof abrasive papers of suitable grades. Any existing paint which curls or lifts before or after priming, undercoating or glossing must be cut back, rubbed down and the coat re-applied until a completely sound and even surface is achieved to the satisfaction of the Contract Administrator all at the Contractor’s own expense.

2.12 Where applicable, all painting is to include the edge of doors, underside of splashboards, sills, drips, weather moulds, grooves and the like and any such omission shall be made good at the Contractor’s expense to the satisfaction of the Contract Administrator. Windows and doors are not to be painted in the “closed” position.

Page 90: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

90

2.13 All woodwork from which paint is not removed shall be thoroughly cleaned down with a solvent to remove dirt, grease or wax polish. The surface shall then be rubbed down with a light grade abrasive paper, dusted off and any cracks made good as described in Clause 2.7. Minor areas of poorly adhering or defective paint shall be removed by carefully scraping back to firm edge. This edge shall then be well rubbed down and if necessary the exposed area primed. Defective, cracked or uneven putties to glazing shall be hacked out, rebates prepared and primed as required and the putties made good prior to any painting being carried out. Putties must be allowed to form a hard skin before painting.

2.14 All metal surfaces shall be cleaned down to remove all dirt, grease and the like and all loose or defective paint shall be removed by scrapping back to a firm edge. All rust shall be removed with a wire brush, chipped or scraped as necessary and bare metal shall be primed with an appropriate primer.

2.15 All external walls are to be prepared strictly in accordance with the current Code of Practice and minor repairs affected with cement and sand (1:3) or as otherwise directed by the Contract Administrator.

2.16 All surfaces or internal walls or ceilings are to be brushed down to remove loose or flaking material and thoroughly washed with sugar soap solution to remove all dirt and other deposits and left to dry. Minor wall or ceiling imperfections shall be made good with a flexible preparatory filler approved by the Contract Administrator and rubbed smooth and the rates shall be deemed to include for this provision.

2.17 Where wall or ceiling surfaces are found to be damp or infected with mould growth

the Contractor shall notify the Contract Administrator and await his instructions.

2.18 All paint, emulsion or the like shall be applied evenly over the whole surface to give a

hard solid film, free from hairs, dirt, brush marks, sags, runs, drips or any other imperfections.

2.19 On no account are decorating products to be tipped down gullies, manholes, sinks,

basins, water closets or the like. All waste shall be disposed off-site at a licensed tip.

3. TEXTURED CEILING COATINGS

3.1 Textured ceiling coatings shall be Artex or equal and shall be applied strictly in accordance with the manufacturer’s instructions in the following manner to:- Rendered Surfaces – One light caulking coat as necessary and one finished

coat mixed to the correct consistency and laid on and (unless otherwise instructed) stippled by hand as the work proceeds to the approval of the Contract Administrator.

Plasterboard Surfaces – All joints are to be filled with plastic compound 350mm wide and covered with damp Krapt scrim 63mm wide pressed home. Caulk all nail heads and differences in board levels and joints previously scrimmed and apply one finishing as described above.

4. MEASUREMENT

4.1 The measurement expression (per area) shall mean the total aggregate quantity of

work carried out in a single toilet which shall be used to determine the band and hence the m² rated used. Should the total quantity of work per toilet in an order

Page 91: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

91

exceed in any item the highest band shown in the rates, the m² rate in the highest band shall be deemed to apply. (This clause shall not apply to complete toilet re-decoration as Items 080-090 inclusive).

Page 92: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

92

Prefix No. PC0100000 SOR No.

Description Unit Rate £ p

001

PAINTING AND DECORATING Internal Work Walls Prepare and wash down walls or the like with sugar soap to remove dirt and deposits, rinse off with clean water and leave ready to receive decorations including all labours. Areas up to 5.00 m² (per toilet area).

Item

002 Ditto, as item 001 but areas over 5.00 m² (per toilet area). m²

003

Prepare and scrape walls to remove all loose and flaking material, wash with sugar soap solution to remove dirt and deposits, rinse off with clean water and leave ready to receive decorations including all labours. Areas up to 5.00 m² (per toilet area)

Item

004 Ditto, as item 003 but areas over 5.00 m² (per toilet area). m²

005 Prepare and apply on coat ‘Crown Stabilising Primer’ or similar and leave walls ready to receive decoration including all labours. Areas up to 5.00 m² (per toilet area).

Item

006 Ditto, as item 005 but areas over 5.00 m² (per toilet area). m²

007 Prepare and apply one coats of masonry paint to walls or the like any type of surface including all labours. Areas up to 5.00 m² (per toilet area).

Item

008 Ditto, as item 007 but areas over 5.00 m² (per toilet area). m²

009 Prepare and apply one coat of eggshell paint to walls or the like any type of surface including all labours. Areas up to 5.00 m² (per toilet area).

Item

010 Ditto, as item 009 but areas over 5.00 m² (per toilet area). m²

011 Prepare and apply one coat of gloss paint to walls or the like any type of surface including all labours. Areas up to 5.00 m² (per toilet area).

Item

012 Ditto, as item 011 but areas over 5.00 m² (per toilet area). m²

013

Ceilings Prepare and wash off ceilings with sugar soap to remove dirt and deposits, rinse off with clean water and leave ready to receive decorations including all labours. Areas up to 5.00 m² (per toilet area).

Item

014

Ditto as item 013 but areas over 5.00 m² (per toilet area).

Page 93: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

93

015

Prepare and scrape ceilings to remove all loose and flaking material, wash with sugar soap solution to remove dirt and deposits, rinse off with clean water and leave ready to receive decorations including all labours. Areas up to 5.00 m² (per toilet area).

Item

016 Ditto as item 015 but areas over 5.00 m² (per toilet area). m²

017 Prepare and apply one coat ‘Crown Stabilising Primer’ or similar to ceilings and leave ready to receive decoration including all labours. Areas up to 5.00 m² (per toilet area).

Item

018 Ditto as item 017 but areas over 5.00 m² (per toilet area). m²

019 Prepare and apply one coat of eggshell paint to ceilings or the like any type of surface including all labours. Areas up to 5.00 m² (per toilet area).

Item

020 Ditto as item 019 but areas over 5.00 m² (per toilet area). m²

021 Prepare and apply one coat of gloss paint to ceilings or the like any type of surface including all labours. Areas up to 5.00 m² (per toilet area).

Item

022 Ditto as item 021 but areas over 5.00 m² (per toilet area). m²

023 Prepare and apply one coat of emulsion paint to plastered ceilings or the like any type of surface including all labours. Areas up to 5.00 m² (per toilet area).

Item

024 Ditto as item 023 but areas over 5.00 m² (per toilet area). m²

025 Prepare and apply one coat of masonry paint to artexed ceilings or the like any type of surface including all labours.

026 Ditto as item 025 but areas over 5.00 m² (per toilet area). m²

027

Plastic Ceiling Coatings Prepare and apply asbestos free artex or similar plastic compound to plaster board ceilings, including taping all joints in accordance with the manufacturer’s instructions and working to a selected pattern or to match existing and edging with a 25mm brush including all labours (complete operation). Areas up to 5.00 m² (per toilet area).

Item

028 Ditto as item 027 but areas over 5.00 m² (per toilet area). m²

029

Prepare and apply asbestos free artex or similar plastic compound to plastered ceilings, including working to a selected pattern or to match existing and edging with a 25mm brush including all labours (complete operation). Areas up to 5.00 m² (per toilet area).

Item

030 Ditto as item 029 but areas over 5.00 m² (per toilet area). m²

Page 94: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

94

031

Woodwork Prepare new woodwork ready to receive decorations including knot, stop up , rub down, prime and leave ready to receive further decorations including all labours (girth not exceeding 300mm)

Lm

032

Prepare new woodwork ready to receive decorations including knot, stop up, prime and leave ready to receive further decorations including all labours (girth exceeding 300mm)

033 Remove defective paintwork (burn off or the like) and prepare to receive decorations including all labours (girth not exceeding 300mm).

Lm

034 Remove defective paintwork (burn off or the like) and prepare to receive decorations including all labours (girth exceeding 300mm).

035

Prepare previously painted woodwork including wipe down, stop up, scrape off to remove all loose and flaking material, rub down, dust off and leave ready to receive decorations including all labours (girth not exceeding 300mm).

Lm

036

Prepare previously painted woodwork including wipe down, stop up, scrape off to remove, all loose and flaking material rub down, dust off and leave ready to receive decorations including all labours (girth exceeding 300mm).

037 Prepare and apply one coat of undercoat to woodwork or the like and leave ready to receive further decorations including all labours (girth not exceeding 300mm).

Lm

038 Prepare and apply one coat of undercoat to woodwork or the like and leave ready to receive further decorations including all labours (girth exceeding 300mm).

039 Prepare and apply one coat of gloss paint to woodwork or the including all labours (girth not exceeding 300mm).

Lm

040 Prepare and apply one coat of gloss paint to woodwork or the like including all labours (girth exceeding 300mm).

041

Prepare and apply one coat of undercoat point to timber or metal window frame and sashes, including stop up, scrape, rub down, dust off and leave ready to receive further decoration including all labours (measured overall).

042 Ditto, as item 041 but to louvered or part louvered windows. m²

043 Prepare and apply one coat of gloss finishing paint to timber or metal window frames and sashes including all labours (measured overall).

044 Ditto, as item 043 to louvered or part louvered windows. m²

Page 95: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

95

045

Metal Surfaces Prepare and apply one coat of undercoat to pipework or the like and leave ready to receive further decorations including all labours (girth not exceeding 300mm).

Lm

046 Prepare and apply one coat of gloss paint to pipework or the like and leave ready to receive further decorations including all labours (girth not exceeding 300mm).

Lm

047 Prepare and apply one coat of undercoat to ready primed steel general surfaces (exceeding 300mm girth).

048 Prepare and apply one coat of gloss finishing paint to metal surfaces including all labours.

049

Walls Prepare and apply one coat of ‘Crown Stronghold Masonry Paint’ or equivalent to rough cast walls or the like, including all labours. Areas up to 5.00 m² (per elevation).

Item

050 Ditto, as item 049 but areas over 5.00 m² (per elevation). m²

051

EXTERNAL WORK Woodwork Prepare new woodwork ready to receive decorations including knot, stop up, rub down, prime and leave ready to receive further decorations including all labours (girth not exceeding 300m).

Lm

052

Prepare new woodwork ready to receive decorations including knot, stop up, prime and leave ready to receive further decorations including all labours (girth exceeding 300mm).

053 Remove defective paintwork (burn off or the like) and prepare to receive decorations including all labours (girth not exceeding 300mm).

Lm

054 Remove defective paintwork (burn off or the like) and prepare to receive decorations including all labours (girth exceeding 300mm).

055

Prepare previously painted woodwork including wipe down, stop up, scrape off to remove all loose and flaking material, rub down, dust off and leave ready to receive decorations including all labours (girth not exceeding 300mm).

Lm

056

Prepare previously painted woodwork including wipe down, stop up, scrape off to remove all loose and flaking material, rub down, dust off and leave ready to receive decorations including all labours (girth exceeding 300mm).

057 Prepare and apply one coat of undercoat to woodwork or the like and leave ready to receive further decorations including all labours (girth not exceeding 300mm).

Lm

Page 96: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

96

058 Prepare and apply one coat of undercoat to woodwork or the like and leave ready to receive further decorations including all labours (girth exceeding 300mm)

059 Prepare and apply one coat of gloss paint to woodwork or the like including all labours (girth not exceeding 300mm).

Lm

060 Prepare and apply one coat of gloss paint to woodwork or the like including all labours (girth exceeding 300mm).

061

Prepare and apply one coat of undercoat paint to timber or metal window frame and sashes, including stop up, scrap, rub down, dust off and leave ready to receive further decoration including all labours (measured overall).

062 Ditto, as item 060 but to louvered or part louvered windows. m²

063 Prepare and apply one coat of gloss finishing paint to timber or metal window frames and sashes including all labours (measured overall).

064 Ditto, as item 063 but louvered or part louvered windows. m²

065 Prepare and apply 2 coats or ‘Crown’ or similar timber guard wood preservative to general surfaces, including all labours (girth not exceeding 300mm).

Lm

066 Prepare and apply 2 coats or ‘Crown’ or similar timber guard wood preservative to general surfaces, including all labours (girth exceeding 300mm).

067

Metal Surfaces – Externally Prepare and apply one coat of undercoat to pipework or the like and leave ready to receive further decorations including all labours (girth not exceeding 300mm).

Lm

068 Prepare and apply one coat of gloss paint to pipework or the like and leave ready to receive further decorations including all labours (girth not exceeding 300mm).

Lm

069 Prepare and apply one coat of undercoat to ready primed steel general surfaces (exceeding 300mm girth).

070 Prepare and apply one coat of gloss finishing paint to metal surfaces including all labours.

071 Prepare and apply on coat Bitumastic paint to general surfaces (exceeding 300mm girth).

072 Prepare and apply one coat or Bitumastic paint to general surfaces (girth not exceeding 300mm).

Lm

Page 97: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

97

073 Prepare and apply 2 coats of creosote or similar wood preservative to timber surfaces including all labours (girth not exceeding 300mm).

Lm

074 Prepare and apply 2 coats of creosote or similar wood preservative to timber surfaces including all labours (girth exceeding 300mm).

075 Prepare and apply 2 coats of linseed oil to hardwood timber surfaces including stop up and rub down as necessary and all labours (girth not exceeding 300mm).

Lm

076 Prepare and apply 2 coats of linseed oil to hardwood timber surfaces including stop up and rub down as necessary and all labours (girth exceeding 300mm).

077

Walls – Externally Prepare and apply one coat ‘Crown Stronghold Masonry Paint’ or equivalent to rough cast walls or the like, including all labours. Areas up to 5.00 m² (per elevation).

Item

078 Ditto, as item 077 but areas 5.00 m² - 10 m² (per elevation). m²

079 Ditto, as item 077 but areas 10 m² (per elevation). m²

080

Complete re-decoration of toilet areas, ceiling height not exceeding 4.0m Prepare and wash down walls/ceiling or the like with sugar soap. Rinse off with water, prepare for final decorations, including stop up/rub down. Apply 2 full coats of emulsion paint to walls/ceilings or the like including wipe down, stop up, scrape off to remove all loose and flaking material. Apply one full coat of undercoat and one full coat of gloss to woodwork metalwork, windows and the like. Including all labours, complete operation. All surfaces to be left clean ie, floors working surfaces and electrical fittings. Remove all items of rubbish. Note: Cupboards up to 1m² to be taken as this item. Pro rata this item 50% for walls/ceilings only. Floor areas up to 2.50m².

Item

081 Ditto, as item 080 but floor areas 2.50 m² - 5.00 m². Item

082 Ditto, as item 080 but floor areas exc 5.00m² - not exceeding 15.00m².

Item

083 Ditto, as item 080 but floor areas exc 5.00m² - not exceeding 15.00m².

Item

084 Ditto, as item 080 but floor areas exc 5.00m² - not exceeding 15.00m².

Item

085 Ditto, as item 080 but floor areas exc 20.00m² - 25.00m². Item

086 Ditto, as item 080 but floor areas exc 25.00m² - 30.00m². Item

Page 98: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

98

087 Ditto, as item 080 but floor areas exc 30.00m² - 35.00m². Item

088 Ditto, as item 080 but floor areas exc 35.00m² - 40.00m². Item

089 Ditto, as item 080 but floor areas exc 40.00m² - 45.00m². Item

090 Ditto, as item 080 but floor areas exc 45.00m² - 50.00m². Item

NB

These items will normal apply for areas which have been vandalised or damaged by fire. The programmed redecoration of toilet units may be subject to one off estimates for any specific unit

Page 99: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

99

DESCRIPTION OF WORKS AND SCHEDULE OF RATES

SECTION 11 AGREED FIXED PRICE AND DAYWORK RATES

Page 100: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

100

AGREED FIXED PRICE AND DAYWORK RATES

1. LABOUR DAYWORK RATES

1.1 Clause 4.4.2.1 of the J.C.T Standard Form of Measured Term Contract shall apply The

valuation of dayworks in respect of labour shall be hereinafter in this section of the

schedule of rates which shall be inserted in Appendix Item 9(d) of the contract

conditions.

1.2 These inclusive hourly rates shall be revised at the date of annual revision of the

contract as detailed in Contract Appendix Item 7. The rate for each “trade” will be

revised by the same annual percentage as the schedule of rates section to which it

relates calculated in accordance with the formula interested in Contract Appendix Item

7. The annual revision for the Labourer’s Daywork Rate shall be as calculated for

“Table 4.4 General Maintenance”.

1.3 The Contractor’s attention is particularly drawn to Clause 4.4 of the Measured Term

Contract. Valuation of an order or part thereof shall not be undertaken at Daywork

Rates without the prior authority of the Contract Administrator whose opinion on the

matter shall be final and binding.

1.4 Unless in the opinion of the Contract Administrator whose decision shall be final and

binding, the nature of the work ordered specifically requires a “craft” operative, the

Contractor will only be reimbursed for “Dayworks” at the Labourer’s rate even if he

chooses to allow a craft operative to undertake the work.

1.5 Where in the opinion of the Contract Administrator an order or part thereof shall be

valued using Labour Daywork Rates, the Contractor shall maintain for inspection but

the Contract Administrator prior to payment a separate “voucher” in respect of every

works, the workmen’s names and their trade designation. The daywork voucher(s) shall

be provided to the Contract Administrator by the Contractor when submitting his invoice

to which the daywork relates.

1.6 The Contract Administrator will specify on each order that in his opinion will be properly

valued by Daywork Rates, the estimated number of hours necessary to undertake the

work. The estimated number of hours shall also be deemed to be the maximum

number of hours that the Contractor is permitted in which to carry out the work and the

hours so specified shall not be exceeded, neither will payment be made for additional

hours, unless the prior approval of the Contract Administrator has been obtained.

1.7 The hourly rates tendered by the Contractor and inserted hereinafter will be deemed to

include for all costs of employing labour including guaranteed minimum weekly

earnings; bonus payments; all other guaranteed payments; differentials or extra

payments for crafts or skills; lost time; payments in respect of holidays and public

holidays; payments in respect of any other Local or National Agreements; Council’s

Contributions to Annual Holiday Credits, National Insurance Contributions, Pension

Schemed, Contributions to death benefit schemes; any other contribution, levy or tax

imposed by statue payable by the Contractor in his capacity as an Council; all costs

involved in complying with the contract conditions; small hand tools; travelling to and

from the location to which an order applies and the Contractor’s depot; together with all

other incidental or associated costs including overheads and profit.

Page 101: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

101

1.8 For the avoidance of doubt the Contractor is to note that Labour Daywork Rates shall

only be applicable to hours worked at the location to which an order applies and the

Contractor shall not claim reimbursement for lost timeor travelling time.

2. OTHERDAYWORKS PROVISIONS

2.1 Clause 4.4.2.3 of the JCT Standard Form of Measured Term Contract shall apply. The

valuation of Dayworks shall be calculated in respect of all items other than labour, i.e.

Materials, Plant, Consumables, Stores, Services and Sub-Contractor’s in accordance

with the Definition of the Prime Cost of Building Works of a Jobbing or Maintenance

Character, Subject to adjustment by Percentages ‘B’ as inserted in Contract Appendix

item 9(e).

2.2 The Contractor shall have submitted on the form of tender for insertion in Contract

Appendix item 9(e) the percentages that he requires to be added in respect of

overheads and profit to all Dayworks other than labour, i.e. Materials, Plant,

Consumables, Stores, Services and Sub-Contractors.

2.3 The percentages submitted by the Contractor, (Percentages ‘B’) shall not be subject to

annual adjustment and shall be fixed for the period of the contract.

Page 102: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

102

Prefix No. PC0100000 SOR No.

Description Unit Rate £ p

LABOUR DAYWORK RATES The following schedule of inclusive hourly rates shall be priced for inserting into the conditions of contract Appendix 9(d)

001 Bricklayers daywork rate Per Hour

002 Carpenters daywork rates Per Hour

003 Painters daywork rate Per Hour

004 Plumbers daywork rate Per Hour

005 Electricians daywork rate Per Hour

006 Labourers daywork rate Per Hour

Page 103: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

103

DESCRIPTION OF WORKS AND SCHEDULE OF RATES

SECTION 12 GENERAL ITEMS

Page 104: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

104

GENERAL ITEMS

1. SAFETY CHECKS

1.1 The authority are committed to ensuring units are maintained in a safe condition and to

this end regime a regular check to be undertaken of all units.

1.2 The person undertaking the check must be competent in all aspects of building work.

1.3 The check to be undertaken utilising the form provided by the CA and any section must

be completed.

1.4 Where any item is found during the course of an inspection that renders the unit either

in part or in full unsafe for use from whatever cause then the contractor is required to

either make the problem safe or exclude the public. Where the building is considered

unsafe the suitable barriers to be erected at a safe distance the CA must be informed

at the earliest opportunity where a unit is closed or is found to be unsafe from whatever

cause. The safety of the public, Contractors Employees, the Councils Employees and

other Contractors’ Employees is paramount.

Page 105: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

105

Prefix No. PC0100000 SOR No.

Description Unit Rate £ p

001 Undertaken safety check on any unit, complete form and submit to C.A.

Item

002 As 001 above but on a routine basis every calendar month to be programmed in with other works.

Item

003 As 002 but every 3 months Item

Page 106: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

106

SCHEDULE 5

FORM OF TENDER AND DRAFT FORMS

Page 107: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

107

FORM OF TENDER

FOR

A TERM MAINTENANCE CONTRACT FOR THE REACTIVE REPAIR AND MAINTENANCE OF COUNCIL OWNED PUBLIC CONVENIENCES WITHIN THE

TENDRING DISTRICT FOR FIVE YEARS DURATION

To: The Chairman and Members of the Tendring District Council I/We the undersigned hereby offer to carry out and complete for a period of 5 years all orders issued for work which is within the scope of and in accordance with the Conditions of Contract and Specification to the satisfaction of the Contract Administrator and at the prices submitted in my/our Schedule of Rates subject only to adjustment in the second and subsequent years of the Contract as detailed in the Conditions of Contract or as hereinafter described. Percentage ‘B’ – Dayworks I/We will require the following percentage to be added in respect of the following for Orders, or for the appropriate part of Orders, carried out under the Contract as daywork (JCT Contract Clause 4.4.2.3). Overheads and profit on Materials ___________________% (to two decimal places) Overheads and profit on Plant, ___________________% (to two decimal places) Consumable Stores and Services Overheads and Profit on Sub-Contractors ____________________% (to two decimal places) I/We will require the following lump sum premium in respect of a guarantee Bond for the first contract year as described in the Conditions of Contract.

£………………………………………… (amount of words………………………………………… …………………………………………………)

The name of the Bondsman will be as follows:- ……………………………………………………………………………………………………………………… ……………………………………………………………………………………………………………………... I/We will if so required enter into a Contract Guarantee Bond with the agreed Bondsman to be jointly and severally bound as defined in the Conditions of Contract for the due performance of the Contract. I/We will when if so required sign and complete the parent company indemnity certificate. I/We agree that unless and until a formal agreement under seal is prepared and executed, this Tender, together with your written acceptance thereof, shall not constitute a binding contract between us. I/We understand that the Council does not bind themselves to accept the lowest or any tender that they may receive. I/We understand that this tender is exclusive of Value Added Tax (VAT). I/We certify that:- (1) This is a bona fide tender, intended to be competitive, and that I/We have not fixed or

adjusted the amount of the tender by or under or in accordance with any agreement or

arrangement with any other person.

(2) I/We have not done and we undertake that we will not do at any time before the date

and hour specified for the return of this Tender any of the following acts:-

Page 108: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

108

(a) Communicate to a person other than the person calling for these tenders the

amount, or approximate amount of the proposed tender or details of my/our

rates submitted herein other than where the disclosure was in confidence for

the sole purpose of obtaining insurance or bond premium quotations required

for the preparation of the tender;

(b) Enter into any agreement or arrangement with any other person that he/she

shall refrain from tendering or as to the amount of any tender to be submitted;

(c) Offer or pay or give or agree to pay or give any sum or money or valuable

consideration directly or indirectly to any person for doing or having done

causing or having caused to be done in relation to any other tender or

proposed tender for the said work any act or things of the sort described

above.

(For the avoidance of doubt it should be noted that the work “person” includes; any persons and anybody or association, corporate or unincorporated; and “any agreement or agreement” includes any such transaction, formal or informal, and whether legally binding or not).

(3) I/We enclose our proposed method statement detailing the information requested by

the Council and as out in the instruction to tenderers

(4) I/We enclose our Health and Safety Method statement detailing the manner in which

I/We intend to meet our statutory and contractual obligations with regard to Health,

Safety and Welfare.

(5) I/We enclose our “generic” Construction Phase Health and Safety plan in accordance

with the Construction (Design and Management) Regulations 1994.

(6) I/We have submitted my/our tender on the basis that T.U.P.E regulations; do

apply*/do not apply*(*delete as applicable) and enclose details in support of out

proposals with regard to T.U.P.E.

Page 109: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

109

I/We agree that the terms of the above declaration will form part of any Contract with you resulting from the acceptance of our Tender and that any breach of this declaration and undertaking will be deemed to be a breach of that Contract entitling you to determine the Contract forthwith or to take advantage of any provision in that Contract entitling you to determine my/our employment under that Contract. Signature: ……………………………………… On behalf of: Full name of Tenderer……………………………………………………………………………………………. Address:………………………………………………………………………………………………………….... ………………………………………………………………………………………………………........ (In the case of a ………………………………………………………………………………………………….. Limited Liability Company ………………………………………………………………………………………. the Registered Office) …………………………………………………………………………………………… Date: …………………………………………. CHECKLIST OF DOCUMENT TO BE RETURNED AT THE TIME OF TENDER

Document Attached (Tick)

Form of Tender – fully completed

Schedule of Rates – fully priced

Method Statement

Health and Safety Method Statement

Construction Phase Health and Safety Plan

Details applicable to T.U.P.E.

Page 110: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

110

DRAFT FORM OF BOND We whose registered office is at (hereinafter called The Contractor) and COMPANY LIMITED whose registered office is at (hereinafter called The Surety) are held and firmly bound to TENDRING DISTRICT COUNCIL (hereinafter called The Council) in the sum of For the payment of which sum the Contractor and Surety bind themselves their successors and assigns jointly and severally by these present Sealed without respective seals and dated this day of ……………. WHEREAS the Contractor by an Agreement made between the Council or the one part and the Contractor of the other part has entered into a Contract (hereinafter called the said Contract) for the completion of the works and services in conformity with the provisions of the said Contract re: NOW THE CONDITIONS of the above-written Bond are such that is the Contractor shall duly perform and observe the terms provisions conditions and stipulations of the said Contract on the Contractor’s part to be performed and observed according to the true purpose, intent and meaning thereof or if on default by the Contractor the Surety shall satisfy and discharge and damages sustained by the Council thereby up to the amount of the above-written Bond then this obligation shall be null and void but otherwise shall remain in full force and effect but no alteration in the terms od the said Contract made by agreement between the Council and the Contractor or in the extent or nature of the works and services to be performed thereunder and no allowance of time by the Council or the Contract Administer under the said Contract nor any forbearance or forgiveness in or respect of any matter or thing concerning the said Contract on the part of the Council or the said Contract Administrator shall in any way we lease the Surety from any liability under the above-written Bond provided always the Surety’s liability hereunder shall cease upon completion of the Contract.

Page 111: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

111

The Common Seal of Was hereunto affixed in the presence of ) ) Director ) ) Secretary ) ) The Common Seal of COMPANY LIMITED Was hereunto affixed in the presence of

) ) Authorised Signatory ) ) Authorised Signatory )

) )

Page 112: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

112

DRAFT

FORM OF PARENT COMPANY IINDEMNITY THIS AGREEMENT is made the day of Two Thousand and ……………. BETWEEN (hereinafter called the “Parent Company”) of the one part and TENDRING DISTRICT COUNCIL of Town Hall, Station Road, Clacton-on-Sea, in the County of Essex (hereinafter called the “Council”) of the other part WHEREAS:- (1) This agreement is supplemental to a contract (hereinafter called “The Contract”)

dated the

………………………………………….two thousand and ………………… made between

(hereinafter called the “Contractor”) of the one part and the Council of the other part whereby the Contractor agreed and undertook to carry out a contract for the Reactive Repair and Maintenance of Council owned Public Conveniences within the Tendring District area a five year duration commencing ………………………. (2) The Parent Company has agreed to indemnify the Council in manner hereinafter

appearing

NOW THE PARENT COMPANY HEREBY AGREES with the Council as follows:- 1. If the Contractor (unless relieved from performance by any Clause of the Contract or

by statue or by the decision of a Tribunal of competent jurisdiction) shall in any

respect fail to execute the Contract or commit any breach of their obligations

thereunder then the Parent Company will indemnify the Council against all losses,

damages, costs and expenses which may be incurred by him with reason of any

default on the part of the Contractor in performing and observing the agreements and

provisions on their part contained in the Contract.

2. IT IS FURTHER AGREED AND DECLARED that in the event of this indemnity

coming into force then the Parent Company will have the option of completing the

Contractor’s obligation itself or of appointing another Contractor to so after

consultation with the Council.

3. If any question or dispute shall arise as to the amount of any such losses, damages,

costs and expenses the amount thereof shall be determined by the Contract

Administrator whose decisions shall be final and who shall be deemed to be acting as

an expert and not as an arbitrator.

4. The Parent Company shall not be discharge or released from this indemnity by any

arrangement made between the Contractor and the Council without the assent of the

Parent Company or by any alteration in the obligations undertaken by the Contractor

or by any forbearance whether as to payment time performance or otherwise.

Page 113: Volume 2 Schedules 4 and 5 GENERAL PREAMBLES AND ... · rate shall remain as tendered and the Contractor is to allow in his pricing of each item for the range of work indicated or

113

IN WITNESS WHEREOF THE Parent Company has caused its Common Seal to be hereunto affixed the day the day and year first before written. THE COMMON SEAL ) ) ) Director ………………………………………………………………………….. Secretary …………………………………………………………………………