Page 1: Visual Project Management webinar handout

Why Engineering Projects are Late( and How to Prevent Them from Being So)

Visual Project Managementhttp://pinnacle-strategies.com

1

Page 2: Visual Project Management webinar handout

2

What are these people doing?

Page 3: Visual Project Management webinar handout

3

About Projects

• It’s hard to get a project team to work together

• Projects will be better if our resources are fully utilized

• Start the project sooner, you’ll finish it sooner

• Planning is the key to project success

Page 4: Visual Project Management webinar handout

4

Why Are Projects Late?

Page 5: Visual Project Management webinar handout

You are the new Director of Engineering - What is the status of the project work?

5

Page 6: Visual Project Management webinar handout

6

Project Teams Cannot See

Where are we?

Where is the path?

Page 7: Visual Project Management webinar handout

7

Three Keys

ALIGNMENT

CONTROL WIP

COLLABORATION

Page 8: Visual Project Management webinar handout

8

Project teams don’t work together.

• Is this collaboration?– Protecting reputations– Defending original delivery promises– Giving “reasons” for why

things haven’t quite worked out

– Focus on the past, not the future

Page 9: Visual Project Management webinar handout

9

Project Team Members have Different Goals

• Resource utilization?• Earned hours?• Budget compliance?• Get promoted?• Avoid punishment?

Page 10: Visual Project Management webinar handout

10

It Doesn’t Have to be Lose-Lose

• Resource utilization?

• Earned hours?• Budget

compliance?• Get

promoted?• Avoid

punishment?

Page 11: Visual Project Management webinar handout

11

PROJECT MANAGEMENT MYTHOLOGY

Page 12: Visual Project Management webinar handout

12

The prevailing notion is that to finish early, one should start early.

Page 13: Visual Project Management webinar handout

13

Everyone Starts Early

Here’s the project manager

Page 14: Visual Project Management webinar handout

14

Too much work creates confusion about priorities.

Page 15: Visual Project Management webinar handout

15

Confusion Breeds Multitasking

Page 16: Visual Project Management webinar handout

16

Multitasking Adds Excess Time

Day 42

Task 1 Task 2 Task 3

12 days 12 days 12 days

Task 2 Task 3 Task 1 Task 2 Task 3

7 days 7 days 7 days 7 days 7 days 7 days

Day 28

Setu

p

Setu

p

Setu

p

Setu

p

Task 1

Setu

p

Setu

p

Setu

p

Setu

p

Setu

p

Day 35

Page 17: Visual Project Management webinar handout

17

Collaboration Summary

• Lack of view of path forward– Conflicting priorities

among members– Shifting priorities from

managers– What is the most

important thing now?

• Conflicting objectives• Defensive posture

among team members

Page 18: Visual Project Management webinar handout

18

Too Much WIP Summary

• Haystack Syndrome blocks effective management

• Lost capacity increases costs and delays– Tasks out of sequence– Rework due to

incomplete information– Multitasking

Page 19: Visual Project Management webinar handout

Conventional Approach to Projects

19

Make a Good Plan

Execute the Plan Success

Page 20: Visual Project Management webinar handout

20

Project Failures are Commonplace

“A staggering 39% of projects with budgets over $10 million USD failed.”

Standish Group Research Exchange

Page 21: Visual Project Management webinar handout

To Be Successful

• Get control of the work• Focus on execution behaviors • Use the team (or structure) that already exists

to make room for proper planning

21

Get Control

Execute Well

Release Capacity Success

Page 22: Visual Project Management webinar handout

22

Foundation of Execution Maturity

Page 23: Visual Project Management webinar handout

23

HOW TO PREVENT PROJECTS FROM BEING LATE

3 Keys

Page 24: Visual Project Management webinar handout

24

Improve Visibility

1. Improve Teamwork and Collaboration during execution

Page 25: Visual Project Management webinar handout

25

Align the Team

2. Establish a common goal for the team

Page 26: Visual Project Management webinar handout

26

Manage the Flow

3. Control the amount of work in the system

Page 27: Visual Project Management webinar handout

27

COLLABORATION IN EXECUTIONThe First Step

Page 28: Visual Project Management webinar handout

28

Collaboration During Execution

• Provide visibility• Focus on the future– Stop blaming and get moving

• Focus on the right things• Bust the bottlenecks• Establish common goals• Solving the team’s problems

Page 29: Visual Project Management webinar handout

29

Make it Visible – Like This…

Page 30: Visual Project Management webinar handout

30

Or…Like This….

Page 31: Visual Project Management webinar handout

31

Engage The Team – Focus on the Future

Page 32: Visual Project Management webinar handout

32

Standup Meeting

• 10 minutes• Analysis• Assignment

of Action• Adjourn

Page 33: Visual Project Management webinar handout

33

Person to Person Accountability

Team members know who has the ball and their scope of action.

Page 34: Visual Project Management webinar handout

34

Focus on the Right Things

Project X

Project YY

Project XX

Project Z

Project Y

Estimate Select Engineering Procurement

Good Flow

Gap in Flow

Gap in Flow

Bottleneck

Bottleneck & Gap

Page 35: Visual Project Management webinar handout

35

Accelerate Flow

Project X

Project YY

Project XX

Project Z

Project Y

Estimate Select Engineering Procurement

Stopped!

Page 36: Visual Project Management webinar handout

36

Functional Synchronization

Portfolio ManagementIndividual Project

Procurement

Page 37: Visual Project Management webinar handout

37

ALIGN THE TEAM The Second Step

Page 38: Visual Project Management webinar handout

38

Establish Common Goals

Performance Management:The process by which organizations align their resources, systems and employees to strategic objectives and priorities

Page 39: Visual Project Management webinar handout

Completing Projects is Behavior

How to create the right behavior to drive the project in the right direction?

39

Page 40: Visual Project Management webinar handout

Behavior is a Function of Consequences

• You have everything you need to understand people– What is the behavior?– What are the consequences of that behavior?

40

Page 41: Visual Project Management webinar handout

41

“Show me how you measure me, I’ll show you how I’ll behave”

("If you measure me in an irrational way, don't complain about irrational behavior.")

Eli Goldratt

Page 42: Visual Project Management webinar handout

42

“People do what they do because of what happens to them when they do it”

Aubrey Daniels

Page 43: Visual Project Management webinar handout

43

What do we want our people to do?

Move the project to completion (as fast as possible)

Page 44: Visual Project Management webinar handout

Measurements Help Drive Consequences

• Health function– Should I do something?

• Diagnostic function– What should I do?

• Managers use measurements to determine when and on what to act

44

Page 45: Visual Project Management webinar handout

45

Different Behaviors at Different Levels

Increase Throughput

Decrease WIP

Release on Time

Decrease Cycle Time

Reduce Work Blockages

Reduce Rework

Prioritize Projects

Page 46: Visual Project Management webinar handout

46

Metrics in Vertical Alignment

Increase Throughput

Decrease WIP

Release on Time

Decrease Cycle Time

Reduce Work Blockages

Reduce Rework

Prioritize Projects

TP

WIP Target % CT TP

Days in WIP Rework Days by Reason

Page 47: Visual Project Management webinar handout

47

Metrics Driving the Right Behavior

More Projects Completed

Should I act?

Escalation of Work Stoppages

Where to act?

Getting More Done in Less Time

Should I act?

Page 48: Visual Project Management webinar handout

48

Leadership Reinforcement

Throughput Report

Trend Analysis

Escalation Summary

Escalation Pareto Analysis

Leadership Action

Page 49: Visual Project Management webinar handout

49

Gaining Collaboration Summary

• Make the process and the work visible• Agreement on way forward• Person to person accountability• Common Goals– Metrics to reinforce the right behavior– Horizontal and vertical alignment

Page 50: Visual Project Management webinar handout

50

MANAGE THE FLOWThe Third Step

Page 51: Visual Project Management webinar handout

51

The Objective of the System?

Flow

Page 52: Visual Project Management webinar handout

52

Control the work in the system

The Constraint sets the rate for the entire system.

Page 53: Visual Project Management webinar handout

53

To Increase the Rate, Eliminate the Bottlenecks

• Create process momentum during execution• Focused effort to solve problems

Page 54: Visual Project Management webinar handout

54

MOVING AHEADImplementation

Page 55: Visual Project Management webinar handout

55

Going Visual

1. What is your execution maturity?2. Map the project process3. Define the team4. Build a draft of the board– Refine board

5. Begin standup meetings– Refine process

6. Implement measures & controls– Refine process

Page 56: Visual Project Management webinar handout

56

Foundation of Execution Maturity

• The Project Team:– Works together – Has a common goal– Controls the WIP

Page 57: Visual Project Management webinar handout

57

Map the Project Process

Page 58: Visual Project Management webinar handout

58

Define the Team

Page 59: Visual Project Management webinar handout

59

Build the First Board

Page 60: Visual Project Management webinar handout

60

Begin Standup Meetings

Page 61: Visual Project Management webinar handout

61

Implement Measures and Controls

Page 62: Visual Project Management webinar handout

62

Why does project performance suffer?

Lack of Collaboration

Too Much Work in Process

Page 63: Visual Project Management webinar handout

63

3 Steps to Deliver More Projects On Time

1. Visual Execution to facilitate collaboration2. Common Purpose / Alignment on the team3. Control the amount of work in the system to

maximize flow

We’re not driving cars, we’re managing traffic

Page 64: Visual Project Management webinar handout

64

ViewPoint Execution Maturity

ViewPoint Visual

Single Priority System

Control WIP

Measurement Alignment

Collaboration

ViewPoint Electronic

Remote Collaboration

Measurement Automation

Buffer Management

Resource loading

Date promising

ViewPoint EasyChain

Probabilistic Planning

Resource Management

“What if” capability

Page 65: Visual Project Management webinar handout

ViewPointtm Visual Results

• 433% increase in effective capacity• 326% increase in units shipped• Lead-time reduced from 31 to 8 days• Revenue increased $4MM/month

65

Page 66: Visual Project Management webinar handout

66

Practical Ideas for Improving Project Execution

• Start projects as late as possible• Cut the number of projects in the portfolio by

half (don’t start a new one until you finish one)• One person decides work priorities• Don’t start a task unless you can finish it

completely

Page 67: Visual Project Management webinar handout

67

Next…