  • Bored PilePT. Indonesia Pondasi Raya

  • Bored PileSurveying

  • Bored PileSurveyingMobilisasiSet up of equipment

  • Bored PileSurveyingSet up of equipmentPlacement equipmentProvide concrete/steel plate platform if required

  • Bored PileSurveyingSet up of equipmentPlacement equipmentPrimary boringContinue boringCheck and adjust verticality from 2 directions

  • Bored PileSurveyingSet up of equipmentPlacement equipmentPrimary boringContinue boringReplace Auger with bucket

  • Bored PileSurveyingSet up of equipmentPlacement equipmentPrimary boringContinue boringInserting casing

  • Bored PileSurveyingSet up of equipmentPlacement equipmentPrimary boringContinue boringInserting casingContinue boring

  • Bored PileSurveyingSet up of equipmentPlacement equipmentPrimary boringContinue boringInserting casingContinue boringTerminated boringCheck required depthCheck soil tipe

  • Bored PileSurveyingSet up of equipmentPlacement equipmentPrimary boringContinue boringInserting casingContinue boringTerminated boringCleaning bore hole

  • Bored PileSurveyingSet up of equipmentPlacement equipmentPrimary boringContinue boringInserting casingContinue boringTerminated boringCleaning bore holeSteel cage installationConnect with lifting bars

  • Bored PileSurveyingSet up of equipmentPlacement equipmentPrimary boringContinue boringInserting casingContinue boringTerminated boringCleaning bore holeSteel cage installationTremie pipe installation

  • Bored PileSurveyingSet up of equipmentPlacement equipmentPrimary boringContinue boringInserting casingContinue boringTerminated boringCleaning bore holeSteel cage installationTremie pipe installationConcretingTremie pipe length reducedaccording to concreting progressToe of tremie pipe always minimum 1.5m below top of concrete.

  • Bored PileSurveyingSet up of equipmentPlacement equipmentPrimary boringContinue boringInserting casingContinue boringTerminated boringCleaning bore holeSteel cage installationTremie pipe installationConcretingWithdraw tremie