Visit to ESP At Aqiu Huarui China
22

Visit to ESP At Aqiu Huarui China

Feb 13, 2017

Download

Documents

M Abid Latif
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Visit to ESP At Aqiu Huarui China

Visit to ESP At Aqiu Huarui China

Page 2: Visit to ESP At Aqiu Huarui China
Page 3: Visit to ESP At Aqiu Huarui China

Manufacturing Status • Jobs Completed so far (70%) :- 1. Steel Support2. High pressure electrical heating equipment3. Walk ladder platform 4. Ash Hopper Barge5. Ash Hopper 6. Mudsill7. Export Head8. Outer and Inlet roof9. Shell10. Import air distribution board11. Inport head

• Jobs Left Incomplete so far (30%)1. External thermal Insultation 2. Outlet Roof3. Cathode System4. Anode System

Page 4: Visit to ESP At Aqiu Huarui China
Page 5: Visit to ESP At Aqiu Huarui China
Page 6: Visit to ESP At Aqiu Huarui China
Page 7: Visit to ESP At Aqiu Huarui China
Page 8: Visit to ESP At Aqiu Huarui China
Page 9: Visit to ESP At Aqiu Huarui China
Page 10: Visit to ESP At Aqiu Huarui China
Page 11: Visit to ESP At Aqiu Huarui China
Page 12: Visit to ESP At Aqiu Huarui China
Page 13: Visit to ESP At Aqiu Huarui China
Page 14: Visit to ESP At Aqiu Huarui China
Page 15: Visit to ESP At Aqiu Huarui China
Page 16: Visit to ESP At Aqiu Huarui China
Page 17: Visit to ESP At Aqiu Huarui China
Page 18: Visit to ESP At Aqiu Huarui China
Page 19: Visit to ESP At Aqiu Huarui China
Page 20: Visit to ESP At Aqiu Huarui China
Page 21: Visit to ESP At Aqiu Huarui China
Page 22: Visit to ESP At Aqiu Huarui China

Thanks