Visit to ESP At Aqiu Huarui China
Visit to ESP At Aqiu Huarui China
Manufacturing Status • Jobs Completed so far (70%) :- 1. Steel Support2. High pressure electrical heating equipment3. Walk ladder platform 4. Ash Hopper Barge5. Ash Hopper 6. Mudsill7. Export Head8. Outer and Inlet roof9. Shell10. Import air distribution board11. Inport head
• Jobs Left Incomplete so far (30%)1. External thermal Insultation 2. Outlet Roof3. Cathode System4. Anode System
Thanks