INTRODUCTIONThese Specifications are standard for all contracts awarded by the Commonwealth Transportation Board. The requirements stated herein may be revised or amended from time to time but only to the extent permitted under the special provisions and special provision copied notes included in the specific contract. Reference (date and title) will be made to these Specifications on plans and contract documents. Copies may be obtained from the Office of the Contract Engineer at 1401 East Broad Street, Richmond, Virginia 23219.

C. F. Gee Acting Chief Engineer

iii

TABLE OF CONTENTSINTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . TABLE OF CONTENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii v

LIST OF TABLES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xxv DIVISION I . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . GENERAL PROVISIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 101DEFINITIONS OF ABBREVIATIONS, ACRONYMS, AND TERMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101.01Abbreviations and Acronyms. . . . . . . . . . . . . . . . . . . . . . . . . . 101.02Terms. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 102BIDDING REQUIREMENTS AND CONDITIONS . . 102.01Prequalification of Bidders. . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.02Content of Proposal. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.03Interpretation of Quantities in Proposal. . . . . . . . . . . . . . . . . . . 102.04Examination of Site of Work and Proposal. . . . . . . . . . . . . . . . 102.05Preparation of Bid. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.06Irregular Bids. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.07Proposal Guaranty. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.08Disqualification of Bidder. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.09Delivery of Bid. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.10Withdrawal of Bid. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.11Combination or Conditional Proposals. . . . . . . . . . . . . . . . . . . 102.12Public Opening of Bids. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.13Material Guaranty. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.14Use of Debarred Suppliers. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 103AWARD AND EXECUTION OF CONTRACTS . . . . . 103.01Consideration of Bids. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103.02Award of Contract. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103.03Cancellation of Award. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103.04Return of Proposal Guaranty. . . . . . . . . . . . . . . . . . . . . . . . . . . 103.05Requirements of Contract Bond. . . . . . . . . . . . . . . . . . . . . . . . 103.06Contract Documents. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103.07Execution and Approval of Contract. . . . . . . . . . . . . . . . . . . . . 103.08Failure To Furnish Bonds or Certificate of Insurance. . . . . . . . SECTION 104SCOPE OF WORK . . . . . . . . . . . . . . . . . . . . . . . . . . . . 104.01Intent of Contract. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 104.02Alteration of Quantities or Character of Work. . . . . . . . . . . . . . 104.03Differing Site Conditions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 104.04Maintenance During Construction. . . . . . . . . . . . . . . . . . . . . . . v 1 1

3 3 5 14 14 16 16 17 17 18 19 19 20 21 21 21 21 21 22 22 22 22 22 23 23 26 26 26 26 27 29 30

104.05Removing and Disposing of Structures and Obstructions. . . . . 104.06Cleanup. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 105CONTROL OF WORK . . . . . . . . . . . . . . . . . . . . . . . . . 105.01Authority of Engineer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105.02Plans and Working Drawings. . . . . . . . . . . . . . . . . . . . . . . . . . 105.03Conformity with Plans and Specifications. . . . . . . . . . . . . . . . . 105.04Furnishing and Erecting Precast Structures. . . . . . . . . . . . . . . . 105.05Coordination of Plans, Standard Drawings, Specifications, Supplemental Specifications, Special Provisions, and Special Provision Copied Notes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105.06Cooperation of Contractor. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105.07Cooperation With Regard to Utilities. . . . . . . . . . . . . . . . . . . . 105.08Cooperation among Contractors. . . . . . . . . . . . . . . . . . . . . . . . 105.09Holidays. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105.10Construction Stakes, Lines, and Grades. . . . . . . . . . . . . . . . . . . 105.11Authority and Duties of Inspector. . . . . . . . . . . . . . . . . . . . . . . 105.12Inspection of Work. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105.13Removal of Unacceptable and Unauthorized Work. . . . . . . . . . 105.14Size and Weight Limitations. . . . . . . . . . . . . . . . . . . . . . . . . . . 105.15Acceptance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105.16Submission and Disposition of Claims. . . . . . . . . . . . . . . . . . . SECTION 106CONTROL OF MATERIAL . . . . . . . . . . . . . . . . . . . . 106.01Source of Supply and Quality Requirements. . . . . . . . . . . . . . . 106.02Material Inspection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106.03Local Material Sources (Pits and Quarries). . . . . . . . . . . . . . . . 106.04Disposal Areas. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106.05Rights for and Use of Materials Found on Project. . . . . . . . . . . 106.06Samples, Tests, and Cited Specifications. . . . . . . . . . . . . . . . . . 106.07Plant Inspection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106.08Storing Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106.09Handling Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106.10Unacceptable Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106.11Material Furnished by the Department. . . . . . . . . . . . . . . . . . . SECTION 107LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107.01Laws To Be Observed. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107.02Permits, Certificates, and Licenses. . . . . . . . . . . . . . . . . . . . . . 107.03Patented Devices, Materials, and Processes. . . . . . . . . . . . . . . . 107.04Restoration of Work Performed by Others. . . . . . . . . . . . . . . . . 107.05FederalAid Provisions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107.06Sanitary Provisions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107.07Public Convenience and Safety. . . . . . . . . . . . . . . . . . . . . . . . . 107.08RailwayHighway Provisions. . . . . . . . . . . . . . . . . . . . . . . . . . 107.09Construction Over or Adjacent to Navigable Waters. . . . . . . . . 107.10Barricades and Warning Signs. . . . . . . . . . . . . . . . . . . . . . . . . . vi

33 34 34 34 35 37 37

38 38 39 40 41 42 44 44 45 46 46 47 49 49 50 50 53 55 55 56 57 57 58 58

58 58 59 60 61 61 61 61 62 75 75

107.11Use of Explosives. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107.12Protecting and Restoring Property and Landscape. . . . . . . . . . . 107.13Responsibility for Damage Claims. . . . . . . . . . . . . . . . . . . . . . 107.14Environmental Stipulations. . . . . . . . . . . . . . . . . . . . . . . . . . . . 107.15Opening Sections of Projects to Traffic. . . . . . . . . . . . . . . . . . . 107.16Contractors Responsibility for Work. . . . . . . . . . . . . . . . . . . . . 107.17Contractors Responsibility for Utility Property and Services. . 107.18Furnishing Right of Way. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107.19Personal Liability of Public Officials. . . . . . . . . . . . . . . . . . . . 107.20No Waiver of Legal Rights. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 108PROSECUTION AND PROGRESS OF WORK . . . . . 108.01Subcontracting. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108.02Notice to Proceed. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108.03Prosecution of Work. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108.04Critical Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108.05Limitation of Operations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108.06Gratuities. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108.07Character of Workers, Work Methods, and Equipment. . . . . . . . 108.08Progress Schedule. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108.09Determination and Extension of Contract Time Limit. . . . . . . . 108.10Suspension of Work Ordered by the Engineer. . . . . . . . . . . . . . 108.11Failure To Complete on Time. . . . . . . . . . . . . . . . . . . . . . . . . . 108.12Liquidated Damages. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108.13Default of Contract. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108.14Termination of Contract. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108.15Termination of Contractors Responsibilities. . . . . . . . . . . . . . . SECTION 109MEASUREMENT AND PAYMENT . . . . . . . . . . . . . . . 109.01Measurement of Quantities. . . . . . . . . . . . . . . . . . . . . . . . . . . . 109.02Plan Quantities. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109.03Scope of Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109.04Compensation for Altered Quantities. . . . . . . . . . . . . . . . . . . . . 109.05Extra and Force Account Work. . . . . . . . . . . . . . . . . . . . . . . . . 109.06Eliminated Items. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109.07Partial Payments. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109.08Payment for Material on Hand. . . . . . . . . . . . . . . . . . . . . . . . . 109.09Final Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109.10Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 110MISCELLANEOUS PROVISIONS . . . . . . . . . . . . . . . 110.01Common Carrier Rates. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110.02Labor and Wages. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110.03Equal Employment Opportunity. . . . . . . . . . . . . . . . . . . . . . . . 110.04Use of Minority Business Enterprises (MBEs). . . . . . . . . . . . . 110.05Construction Safety and Health Standards. . . . . . . . . . . . . . . . . 110.06Bulletin Boards and Posting Official Notices. . . . . . . . . . . . . . 110.07Certification of Nonsegregated Facilities. . . . . . . . . . . . . . . . . . vii

76 76 76 77 81 82 82 83 83 84 84 84 84 85 85 85 85 86 87 87 89 89 90 90 91 92 92 92 97 97 98 99 101 102 104 106 107 107 107 108 109 114 117 118 118

DIVISION II . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . MATERIALS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 200GENERAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 200.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 200.02Conformance with Specifications. . . . . . . . . . . . . . . . . . . . . . . 200.03General Sampling and Testing Procedures. . . . . . . . . . . . . . . . . 200.04Acceptance Procedures for Aggregates. . . . . . . . . . . . . . . . . . . 200.05Handling and Storing Aggregates. . . . . . . . . . . . . . . . . . . . . . . 200.06Technician and Batcher Certification. . . . . . . . . . . . . . . . . . . . SECTION 201MINERAL FILLER . . . . . . . . . . . . . . . . . . . . . . . . . . . 201.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 201.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 202FINE AGGREGATE . . . . . . . . . . . . . . . . . . . . . . . . . . . 202.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202.03Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 203COARSE AGGREGATE . . . . . . . . . . . . . . . . . . . . . . . . 203.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 203.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 203.03Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 204STONE FOR MASONRY, RIPRAP, POROUS BACKFILL, AND GABIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 204.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 204.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 205CRUSHER RUN AGGREGATE . . . . . . . . . . . . . . . . . . 205.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 205.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 205.03Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 206LIGHTWEIGHT AGGREGATE . . . . . . . . . . . . . . . . . 206.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 206.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 207SELECT MATERIAL . . . . . . . . . . . . . . . . . . . . . . . . . . 207.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207.03JobMix Formula for Select Material, Type I. . . . . . . . . . . . . . 207.04Mixing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207.05Acceptance of Select Material, Type I. . . . . . . . . . . . . . . . . . . . 207.06Referee System for Select Material, Type I. . . . . . . . . . . . . . . . 207.07Payment Adjustment System for Select Material, Type I. . . . . . viii

121 121 123 123 123 123 124 125 125 126 126 126 126 126 126 127 129 129 129 131

132 132 132 133 133 133 133 134 134 134 134 134 135 136 136 137 138 138

SECTION 208SUBBASE AND AGGREGATE BASE MATERIAL . . 208.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208.03Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208.04JobMix Formula. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208.05Mixing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208.06Acceptance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208.07Referee System. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208.08Payment Adjustment System. . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 209OPEN GRADED SHOULDER MATERIAL . . . . . . . . 209.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 209.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 209.03Mixing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 210ASPHALT MATERIALS . . . . . . . . . . . . . . . . . . . . . . . 210.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 210.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 210.03Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 210.04Payment Adjustment System. . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 211ASPHALT CONCRETE . . . . . . . . . . . . . . . . . . . . . . . . 211.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.03JobMix Formula. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.04Asphalt Concrete Mixtures. . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.05Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.06Tests. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.07Plant Inspection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.08Acceptance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.09Adjustment System. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.10Referee System. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.11Handling and Storing Aggregates. . . . . . . . . . . . . . . . . . . . . . . 211.12Asphalt Concrete Mixing Plant. . . . . . . . . . . . . . . . . . . . . . . . . 211.13Preparation of Mixture. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.14Storage System. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.15Initial Production. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 212JOINT MATERIALS . . . . . . . . . . . . . . . . . . . . . . . . . . 212.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 213DAMPPROOFING AND WATERPROOFING MATERIALS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 213.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 213.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ix

138 138 139 139 140 140 141 142 142 144 144 144 144 145 145 145 145 146 146 146 147 150 157 158 159 160 160 163 164 165 165 169 170 170 170 170 171

179 179 179

SECTION 214HYDRAULIC CEMENT . . . . . . . . . . . . . . . . . . . . . . . . 214.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 214.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 215HYDRAULIC CEMENT CONCRETE ADMIXTURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 215.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 215.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 215.03Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 216WATER FOR USE WITH CEMENT OR LIME . . . . . 216.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 216.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 217HYDRAULIC CEMENT CONCRETE . . . . . . . . . . . . 217.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 217.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 217.03Handling and Storing Materials. . . . . . . . . . . . . . . . . . . . . . . . . 217.04Measurement of Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 217.05Equipment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 217.06Classification of Concrete Mixtures. . . . . . . . . . . . . . . . . . . . . 217.07Proportioning Concrete Mixtures. . . . . . . . . . . . . . . . . . . . . . . 217.08Acceptance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 217.09Mixing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 217.10Placement Limitations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 218HYDRAULIC CEMENT MORTAR AND GROUT . . . 218.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 218.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 218.03Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 219RIGHTOFWAY MONUMENTS . . . . . . . . . . . . . . . . 219.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 219.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 220CONCRETE CURING MATERIALS . . . . . . . . . . . . . 220.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 220.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 221GUARDRAIL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 221.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 221.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 222MASONRY UNITS . . . . . . . . . . . . . . . . . . . . . . . . . . . . 222.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 222.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

180 180 180

180 180 180 181 182 182 182 182 182 182 185 185 187 189 189 192 193 196 197 197 197 197 198 198 198 199 199 199 200 200 200 202 202 202

x

SECTION 223STEEL REINFORCEMENT . . . . . . . . . . . . . . . . . . . . 223.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 223.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 224CASTINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 224.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 224.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 224.03Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 225STEEL FORGINGS AND STEEL SHAFTING . . . . . . 225.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 225.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 226STRUCTURAL STEEL . . . . . . . . . . . . . . . . . . . . . . . . 226.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 226.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 227STEEL GRID FLOORING . . . . . . . . . . . . . . . . . . . . . . 227.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 227.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 227.03Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 228STEEL PILES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 228.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 228.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 229ALUMINUM ALLOY . . . . . . . . . . . . . . . . . . . . . . . . . . 229.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 229.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 230BRONZE AND COPPER ALLOY . . . . . . . . . . . . . . . . 230.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 230.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 231PAINT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 231.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 231.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 231.03Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 232PIPE AND PIPE ARCHES . . . . . . . . . . . . . . . . . . . . . . 232.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 233GALVANIZING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 233.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 233.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 233.03Repair of Galvanized Surfaces. . . . . . . . . . . . . . . . . . . . . . . . .

203 203 203 205 205 205 205 205 205 206 206 206 206 210 210 211 211 211 211 211 212 212 212 213 213 214 214 214 214 215 221 221 221 229 229 229 229

xi

SECTION 234GLASS BEADS FOR REFLECTORIZING TRAFFIC MARKINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 234.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 234.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 235RETROREFLECTORS . . . . . . . . . . . . . . . . . . . . . . . . 235.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 235.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 236WOOD PRODUCTS . . . . . . . . . . . . . . . . . . . . . . . . . . . 236.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 236.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 237BEDDING MATERIAL AND BEARING PADS . . . . . 237.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 237.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 238ELECTRICAL AND SIGNAL COMPONENTS . . . . . 238.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 238.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 239SODIUM CHLORIDE AND CALCIUM CHLORIDE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 239.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 239.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 240LIME . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 240.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 240.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 241FLY ASH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 241.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 241.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 242FENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 242.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 242.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 243EPOXYRESIN SYSTEMS . . . . . . . . . . . . . . . . . . . . . 243.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 243.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 243.03Handling and Storing Materials. . . . . . . . . . . . . . . . . . . . . . . . . 243.04Acceptance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 244ROADSIDE DEVELOPMENT MATERIALS . . . . . . . 244.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 244.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

229 229 229 230 230 230 232 232 232 234 234 234 238 238 238

245 245 245 246 246 246 247 247 247 247 247 247 252 252 252 255 256 257 257 257

xii

SECTION 245GEOSYNTHETICS . . . . . . . . . . . . . . . . . . . . . . . . . . . . 245.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 245.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 245.03Testing and Documentation. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 246PAVEMENT MARKING . . . . . . . . . . . . . . . . . . . . . . . . 246.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 246.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 247REFLECTIVE SHEETING . . . . . . . . . . . . . . . . . . . . . 247.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 247.02Detail Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 247.03Warranty Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . DIVISION III . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ROADWAY CONSTRUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 301CLEARING AND GRUBBING . . . . . . . . . . . . . . . . . . 301.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 301.02Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 301.03Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 302DRAINAGE STRUCTURES . . . . . . . . . . . . . . . . . . . . . 302.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 302.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 302.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 302.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 303EARTHWORK . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 303.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 303.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 303.03Erosion and Siltation Control. . . . . . . . . . . . . . . . . . . . . . . . . . 303.04Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 303.05Tolerances. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 303.06Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 304CONSTRUCTING DENSITY CONTROL STRIPS . . 304.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 304.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 304.03Equipment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 304.04Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 304.05Tolerances. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 304.06Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 305SUBGRADE AND SHOULDERS . . . . . . . . . . . . . . . . . 305.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

264 264 264 264 266 266 266 277 277 278 285 287 287 289 289 289 290 291 291 291 292 301 305 305 305 306 308 318 319 327 327 327 327 328 328 329 329 329

xiii

305.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 305.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 305.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 306LIME STABILIZATION . . . . . . . . . . . . . . . . . . . . . . . . 306.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 306.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 306.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 306.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 307HYDRAULIC CEMENT STABILIZATION . . . . . . . . 307.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 307.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 307.03Field Laboratory. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 307.04Weather Limitations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 307.05Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 307.06Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 308SUBBASE COURSE . . . . . . . . . . . . . . . . . . . . . . . . . . . 308.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 308.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 308.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 308.04Tolerances. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 308.05Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 309AGGREGATE BASE COURSE . . . . . . . . . . . . . . . . . . 309.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 309.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 309.03Equipment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 309.04Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 309.05Density Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 309.06Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 310TACK COAT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 310.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 310.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 310.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 310.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 311PRIME COAT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 311.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 311.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 311.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 311.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 312SEAL COAT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xiv

329 330 333 335 335 335 335 338 338 338 339 339 339 339 344 345 345 345 345 346 347 348 348 348 348 348 349 349 350 350 350 350 352 352 352 352 352 353 354 354 354

312.03Equipment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.04Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.05Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 313STABILIZED OPEN-GRADED MATERIAL . . . . . . . 313.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 313.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 313.03Proportioning. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 313.04Equipment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 313.05Acceptance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 313.06Placing Limitations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 313.07Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 313.08Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 314PENETRATION SURFACE COURSES . . . . . . . . . . . . 314.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 314.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 314.03Weather Limitations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 314.04Equipment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 314.05Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 314.06Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 315ASPHALT CONCRETE PAVEMENT . . . . . . . . . . . . . 315.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 315.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 315.03Equipment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 315.04Placement Limitations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 315.05Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 315.06Pavement Samples. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 315.07Pavement Tolerances. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 315.08Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 316HYDRAULIC CEMENT CONCRETE PAVEMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 316.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 316.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 316.03Equipment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 316.04Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 316.05Tolerances. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 316.06Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . DIVISION IV . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . BRIDGES AND STRUCTURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 401STRUCTURE EXCAVATION . . . . . . . . . . . . . . . . . . . . 401.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 401.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xv

354 354 356 356 356 356 357 358 358 359 360 361 361 361 362 362 362 363 364 365 365 365 365 366 367 376 376 378

378 378 379 379 381 393 394 397 397 399 399 399

401.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 401.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 402SHEET PILES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 402.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 402.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 402.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 402.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 403BEARING PILES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 403.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 403.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 403.03Pile Types. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 403.04Determination of Pile Lengths. . . . . . . . . . . . . . . . . . . . . . . . . 403.05Order List. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 403.06Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 403.07Determination of Bearing Capacities. . . . . . . . . . . . . . . . . . . . . 403.08Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 404HYDRAULIC CEMENT CONCRETE OPERATIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 404.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 404.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 404.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 404.04Bridge Deck Construction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 404.05Expansion and Fixed Joints. . . . . . . . . . . . . . . . . . . . . . . . . . . . 404.06Bridge Seat Bearing Areas. . . . . . . . . . . . . . . . . . . . . . . . . . . . 404.07Finishing Concrete Surfaces. . . . . . . . . . . . . . . . . . . . . . . . . . . 404.08Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 405PRESTRESSED CONCRETE . . . . . . . . . . . . . . . . . . . 405.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 405.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 405.03Plant Review. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 405.04Concrete Controls. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 405.05Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 405.06Tolerances. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 405.07Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 406REINFORCING STEEL . . . . . . . . . . . . . . . . . . . . . . . . 406.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 406.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 406.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 406.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 407STEEL STRUCTURES . . . . . . . . . . . . . . . . . . . . . . . . . 407.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 407.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xvi

399 403 404 404 405 405 406 406 406 406 406 411 412 412 417 422

423 423 424 424 443 444 445 446 448 449 449 449 450 451 451 459 461 462 462 462 462 465 466 466 466

407.03Working Drawings. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 407.04Fabrication Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 407.05Handling, Storing, and Shipping Materials. . . . . . . . . . . . . . . . 407.06Erection Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 407.07Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 408BEARING DEVICES AND ANCHORS . . . . . . . . . . . . 408.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 408.02Materials and Fabrication. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 408.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 408.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 409STEEL GRID FLOORS . . . . . . . . . . . . . . . . . . . . . . . . 409.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 409.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 409.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 409.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 410RAILINGS AND PARAPETS . . . . . . . . . . . . . . . . . . . . 410.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 410.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 410.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 410.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 411PROTECTIVE COATING OF METAL IN STRUCTURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 411.01Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 411.02Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 411.03Certifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 411.04General Surface Preparation and Application Standards . . . . . . 411.05Existing Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 411.06New Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 411.07Galvanized Surfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 411.08Environmental Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 411.09Health and Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 411.10Measurement and Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 412WIDENING, REPAIRING, AND RECONSTRUCTING EXISTING STRUCTURES . . . . . . . . . . . . 412.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 412.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 412.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 412.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 413DISMANTLING AND REMOVING EXISTING STRUCTURES OR REMOVING PORTIONS OF EXISTING STRUCTURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 413.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xvii

466 467 475 476 484 486 486 486 486 507 507 507 507 508 509 509 509 509 510 512

513 513 513 514 514 520 521 523 523 527 528

529 529 529 530 540

542 542

413.02Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 413.03Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 414RIPRAP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 414.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 414.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 414.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 414.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 415CONCRETE SLOPE PROTECTION . . . . . . . . . . . . . 415.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 415.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 415.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 415.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 416WATERPROOFING . . . . . . . . . . . . . . . . . . . . . . . . . . . 416.01Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 416.02Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 416.03Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 416.04Measurement and Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 417DAMPPROOFING . . . . . . . . . . . . . . . . . . . . . . . . . . . 417.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 417.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 417.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 417.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 418TIMBER STRUCTURES . . . . . . . . . . . . . . . . . . . . . . . 418.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 418.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 418.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 418.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 419BRIDGE CONDUIT SYSTEMS AND LIGHTING SYSTEMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 419.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 419.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 419.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 419.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 420PREFORMED ELASTOMERIC JOINT SEALER . . . 420.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 420.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 420.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 420.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 421ELASTOMERIC EXPANSION DAMS . . . . . . . . . . . . 421.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xviii

543 544 545 545 545 545 550 551 551 551 552 553 553 553 554 554 559 560 560 560 560 560 561 561 562 562 565

566 566 566 566 566 567 567 567 567 568 568 568

421.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 421.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 421.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 422NAVIGATION LIGHTS . . . . . . . . . . . . . . . . . . . . . . . . 422.01Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 422.02Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 422.03Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 422.04Measurement and payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . DIVISION V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . INCIDENTAL CONSTRUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 501UNDERDRAINS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 501.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 501.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 501.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 501.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 502INCIDENTAL CONCRETE ITEMS . . . . . . . . . . . . . . 502.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 502.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 502.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 502.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 503RIGHTOFWAY MONUMENTS . . . . . . . . . . . . . . . . 503.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 503.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 503.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 503.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 504SIDEWALKS, STEPS, AND HANDRAILS . . . . . . . . . 504.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 504.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 504.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 504.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 505GUARDRAIL AND STEEL MEDIAN BARRIERS . . . 505.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 505.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 505.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 505.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 506RETAINING WALLS . . . . . . . . . . . . . . . . . . . . . . . . . . 506.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 506.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 506.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 506.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . xix

568 568 569 570 570 570 570 571 573 573 575 575 575 575 576 576 576 576 577 583 586 586 586 586 586 586 586 586 587 589 590 590 591 591 593 595 595 595 595 597

SECTION 507FENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 507.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 507.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 507.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 507.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 508DEMOLITION OF PAVEMENT AND OBSCURING ROADWAY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 508.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 508.02Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 508.03Measurement and Payment. . . . . .. . . . . . . . . . . . . . . . . . . . . . . SECTION 509PATCHING HYDRAULIC CEMENT CONCRETE PAVEMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 509.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 509.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 509.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 509.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 510RELOCATING OR MODIFYING EXISTING MISCELLANEOUS ITEMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 510.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 510.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 510.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 510.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 511ALLAYING DUST . . . . . . . . . . . . . . . . . . . . . . . . . . . . 511.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 511.02Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 511.03Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 512MAINTAINING TRAFFIC . . . . . . . . . . . . . . . . . . . . . . 512.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 512.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 512.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 512.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 513MOBILIZATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 513.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 513.02Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 514FIELD OFFICE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 514.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 514.02Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 514.03Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 515PLANING PAVEMENT . . . . . . . . . . . . . . . . . . . . . . . . 515.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xx

598 598 598 598 600

601 601 601 602

603 603 603 604 606

606 606 606 607 607 607 607 607 608 608 608 608 609 626 630 630 630 631 631 631 634 634 634

515.02Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 515.03Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 516DEMOLITION OF BUILDINGS AND CLEARING PARCELS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 516.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 516.02Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 516.03Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 517UTILITY COORDINATOR . . . . . . . . . . . . . . . . . . . . . 517.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 517.02Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 517.03Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 518TRAINEES ON CONSTRUCTION PROJECTS . . . . . 518.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 518.02Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 518.03Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 519SOUND BARRIER WALLS . . . . . . . . . . . . . . . . . . . . . 519.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 519.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 519.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 519.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 520WATER AND SANITARY SEWER FACILITIES . . . . 520.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 520.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 520.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 520.04Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 520.05Disinfecting Water Mains. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 520.06Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . DIVISION VI . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ROADSIDE DEVELOPMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 601SELECTIVE TREE REMOVAL, TRIMMING, AND CLEANUP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 601.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 601.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 601.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 601.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 602TOPSOIL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 602.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 602.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 602.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 602.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . xxi

634 635

635 635 635 637 637 637 637 638 639 639 639 641 641 641 641 644 646 646 646 646 648 654 657 658 661 661

663 663 663 663 664 664 664 664 664 665

SECTION 603SEEDING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 603.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 603.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 603.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 603.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 604SODDING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 604.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 604.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 604.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 604.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 605PLANTING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 605.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 605.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 605.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 605.04Care of Plants. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 605.05Establishment Period. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 605.06Guarantee. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 605.07Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 606SOIL RETENTION COVERINGS . . . . . . . . . . . . . . . . 606.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 606.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 606.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 606.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 607HERBICIDE SPRAYING . . . . . . . . . . . . . . . . . . . . . . . 607.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 607.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 607.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 607.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 608MOWING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 608.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 608.02Equipment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 608.03Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 609TREE WELLS AND TREE WALLS . . . . . . . . . . . . . . . 609.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 609.02Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 609.03Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 610GABIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 610.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 610.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 610.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 610.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . xxii

665 665 665 665 667 668 668 668 668 669 669 669 670 670 673 674 675 675 676 676 676 676 677 677 677 677 677 678 678 678 678 678 678 678 679 679 679 679 679 680 681

DIVISION VII . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . TRAFFIC CONTROL DEVICES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 700GENERAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 700.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 700.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 700.03Working Drawings. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 700.04Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 700.05Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 701TRAFFIC SIGNS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 701.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 701.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 701.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 701.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 702DELINEATORS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 702.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 702.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 702.03General Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 702.04Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 702.05Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 703TRAFFIC SIGNALS . . . . . . . . . . . . . . . . . . . . . . . . . . . 703.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 703.02Equipment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 703.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 703.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 704PAVEMENT MARKINGS AND MARKERS . . . . . . . . 704.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 704.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 704.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 704.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . . SECTION 705LIGHTING SYSTEMS . . . . . . . . . . . . . . . . . . . . . . . . . 705.01Description. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 705.02Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 705.03Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 705.04Measurement and Payment. . . . . . . . . . . . . . . . . . . . . . . . . . . .

683 683 685 685 685 687 687 694 696 696 696 697 702 702 702 703 703 703 704 705 705 705 724 730 732 732 732 733 740 740 740 740 741 742

xxiii

xxiv

LIST OF TABLESI1Schedule of Liquidated Damages . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II1Fine Aggregate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II2Soundness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II3Sizes of Open Graded Coarse Aggregates . . . . . . . . . . . . . . . . . . . . . . II4Soundness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II5Abrasion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II6Design Range: Select Material, Type I . . . . . . . . . . . . . . . . . . . . . . . . . II7Process (P) and Range (R) Tolerance: Select Material, Type I . . . . . . . II8Atterberg Limits: Select Material, Type I . . . . . . . . . . . . . . . . . . . . . . . II9Design Range for Dense Graded Aggregates . . . . . . . . . . . . . . . . . . . . II10Process Tolerances for Each Laboratory Sieve (%) . . . . . . . . . . . . . . II11Atterberg Limits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II12Standard Deviation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II12AAggregate Properties . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II13Asphalt Concrete Mixtures Design Range . . . . . . . . . . . . . . . . . . . II13AMinimum and Maximum Boundaries of Restricted Gradation . . . . II14Mixture Design Criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II14ARecommended Performance Grade of Asphalt . . . . . . . . . . . . . . . . II15Process Tolerance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II16Standard Deviation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II17Requirements for Hydraulic Cement Concrete . . . . . . . . . . . . . . . . . . II18(Deleted) II19Requirements: Component A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II20(Deleted) II21Requirements: Mixed Epoxy Systems . . . . . . . . . . . . . . . . . . . . . . . . II22Fine Aggregate (Silica Sand) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II23(Deleted) III1Limited Asphalt Application Temperature . . . . . . . . . . . . . . . . . . . . . III2Asphalt Concrete Paving Limitations . . . . . . . . . . . . . . . . . . . . . . . . . III3Density Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III4Payment Schedule for Lot Densities . . . . . . . . . . . . . . . . . . . . . . . . . . IV1Pile Tolerance Criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV2(Deleted) IV3Bolt Tension . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV4Nut Rotation From Snug Tight Condition . . . . . . . . . . . . . . . . . . . . . IV5(Deleted) IV6Coating Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . VII1Pavement Markings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 128 129 130 131 132 135 135 136 139 139 140 143 148 152 153 154 157 162 164 191 252 253 256

351 368 373 375 416 479 480 517 735

xxv

Division I GENERAL PROVISIONS

101.01

SECTION 101DEFINITIONS OF ABBREVIATIONS, ACRONYMS, AND TERMS101.01Abbreviations and Acronyms. In these specifications and in other contract documents, the following abbreviations and acronyms shall be interpreted as follows: AAR ..................................................................Association of American Railroads AASHTO ............................................American Association of State Highway and Transportation Officials ABS.....................................................Acrylonitrilebutadienestyrene (an elastomer) AC ................................................................................................Alternating current ACI ...............................................................................American Concrete Institute ADT ..............................................................................Annual average daily traffic AED ..................................................................Associated Equipment Distributors AISC .........................................................American Institute of Steel Construction AISI ......................................................................American Iron and Steel Institute ANSI ............................................................American National Standards Institute APA ..........................................................................American Plywood Association API ......................................American Petroleum Institute; American Pipe Institute AREA ..................................................American Railway Engineering Association ASCE .............................................................American Society of Civil Engineers ASME ..................................................American Society of Mechanical Engineers ASTM ..................................................American Society for Testing and Materials AWG .........................................................................................American wire gage AWPA ........................................................American Wood Preservers Association AWS ...............................................................................American Welding Society AWWA ..............................................................American Water Works Association BOCA ..................................................Building Officials and Code Administrators C ...................................................................Celsius, when preceded by degree(s) CBR ......................................................................................California bearing ratio CRSI ................................................................Concrete Reinforcing Steel Institute DBE....................................................................Disadvantaged Business Enterprise DC ........................................................................................................Direct current DHV........................................................................................Design hourly volume EEI.......................................................................................Edison Electric Institute EEO..........................................................................Equal employment opportunity EIA ........................................................................Electronic Industries Association EPA ......................................................................Environmental Protection Agency EPDM ..........................................Ethylenepropylenedienemonomer (an elastomer) F ..............................................................Fahrenheit, when preceded by degree(s) F/A ................................................................................................Filler/asphalt ratio 3

101.01 FHWA ...................................................................Federal Highway Administration FS .....................................Federal Specifications, General Services Administration ICEA ...........................................................Insulated Cable Engineers Association IMSA ....................................................International Municipal Signal Association ITE ..................................................................Institute of Transportation Engineers LCD .........................................................................................Liquid crystal display LPG..........................................................................................Liquid petroleum gas MBE ............................................................................Minority Business Enterprise MEKP .........................................................................Methyl ethyl ketone peroxide MIL .......................................................................................Military specifications MSDS ............................................................................Materials Safety Data Sheet MUTCD .........................................Manual on Uniform Traffic Control Devices for Streets and Highways and the Virginia supplement to same NEC ....................................................................................National Electrical Code NEMA..............................................National Electrical Manufacturers Association NIST ...............................................National Institute of Standards and Technology NRC.......................................................................Nuclear Regulatory Commission PCI..............................................................................Prestressed Concrete Institute PE...........................................................................................................Polyethylene PTL ...............................................................................Plywood Testing Laboratory PVC................................................................................................Polyvinylchloride PVF.................................................................................................Polyvinylfluoride REA..................................................................Rural Electrification Administration SAE .......................................................................Society of Automotive Engineers SPIB ......................................................................Southern Pine Inspection Bureau SSPC .....................................................................Steel Structures Painting Council TAPPI .........................................Technical Association of Pulp and Paper Industry TFE .......................................................................................Polytetrafluoroethylene UL ...........................................................................Underwriters Laboratories, Inc. VAC......................................................................................Volts alternating current VDC.............................................................................................Volts direct current VDOT ...........................................................Virginia Department of Transportation VEP ................................................................................Value engineering proposal VFA .....................................................................................Voids filled with asphalt VMA................................................................................Voids in mineral aggregate VOSH...........................................Virginia Occupational Safety and Health agency VTM ..........................................................Virginia test methods; voids in total mix WBE..............................................................................Women Business Enterprise 4

101.02 101.02Terms. In these specifications and in other contract documents, the following terms and pronouns used in place of them shall be interpreted as follows: A Advertisement, Notice of. A public announcement, as required by law, inviting bids for work to be performed or materials to be furnished that indicates approximate principal quantities, location of work to be performed, character and quantity of materials to be furnished, and time and place for opening bids. Alkali soil. Soil in which total alkali chlorides calculated as sodium chloride are more than 0.10 percent based on total solids. Award. The decision of the Board to accept the bid of the lowest responsive and responsible bidder for the work. The award is subject to the execution and approval of a satisfactory Contract therefor, and such conditions as may be specified or required by law. Award date. The date on which the decision is made by the Board to accept the bid of the lowest responsive and responsible bidder. B Backfill. Material used to replace or the act of replacing material removed during construction; may also denote material placed or the act of placing material adjacent to structures. Balance point. The approximate point, based on estimated shrinkage or swell, where the quantity of earthwork excavation and borrow, if required, is equal to the quantity of embankment material plus any surplus excavation material. Base course. A layer of material of specified thickness on which the intermediate or surface course is placed. Base flood. The flood or tide having a one percent chance of being exceeded in any given year. Bid. The offer of a bidder, submitted on the proposal, to perform the work and furnish the materials and labor at the prices set forth therein; valid only when properly signed and guaranteed. Bidder. Any individual, partnership, corporation, or joint venture that formally submits a bid for the work contemplated, or for any portion thereof, acting directly or through a duly authorized representative. Bids, Invitation for. See Advertisement, Notice of. 5

101.02 Board. Commonwealth Transportation Board of Virginia. Borrow. Suitable material from sources outside the roadway that is used primarily for embankments. Brackish water. Water in which total alkali chlorides calculated as sodium chloride are more than 0.10 percent based on total solids. Bridge. A structure, including supports, that is erected over a depression or an obstruction, such as water, a highway, or a railway, that has a track or passageway for carrying traffic.

C Calendar day. Any day shown on the calendar. Camber. A vertical curvature induced or fabricated into beams or girders and a deck slab or slab span formwork; a vertical curvature set in the grade line of a pipe culvert to accommodate differential settlement. Channel. A water course or drainage way. Commissioner. Commonwealth Transportation Commissioner. Composite hydrograph. A graph showing the mean daily discharge versus the calendar day, indicating trends in high and low flow for a one year period. Construction area. The area where authorized construction occurs. Construction limits. The intersection of side slopes, including slope rounding, with the original ground, plus slopes for drainage ditches or incidental construction. Contract. The written agreement executed between the Department and the Contractor that sets forth the obligations of the parties thereunder, including, but not limited to, the performance of the work, furnishing of materials and labor, and basis of payment. The Contract also includes these specifications; supplemental specifications; special provisions; special provision copied notes; plans; standard drawings; change orders; and work orders and agreements that are required to complete the construction of the specified work in an acceptable manner, including authorized extensions thereof, all of which constitute one instrument. Oral representations or promises shall not be considered a part of the Contract. Contract Engineer. The Engineers authorized representative for administering the advertisement, receiving bids, and awarding contracts for the Department. Contract item. A specifically described unit of work for which a price is provided in the Contract. 6

101.02 Contract time limit. The number of calendar days or calendar date that specifies the time allowed for completion of the work described in the Contract, including authorized extensions. Contractor. Any individual, partnership, corporation, or joint venture that contracts with the Department to perform the prescribed work. Cul-de-sac. An area at the terminus of a dead-end street or road that is constructed for the purpose of allowing vehicles to turn around. Culvert. A structure that is not classified as a bridge which provides an opening under any roadway. Cut. The portion of a roadway formed by excavating below the surface of the earth. D Day. Unless otherwise stated, a calendar day. Deflection. The vertical movement occurring between the supports of a bridge superstructure or its components (beams, girders, and slabs) that results from their own weight and from dead and live loads. Although all parts of a structure are subject to deflections, usually only those deflections that occur in the superstructure are of significance during construction. Department. Virginia Department of Transportation. Deputy Commissioner. The assistant to the Commissioner who performs such of the Commissioners duties as have been delegated to him by the Commissioner. Design flood. The magnitude of flood that a given structure can convey without exceeding a designated flood level. Disincentive. A monetary deterrent used to discourage the Contractor from exceeding the contract time limit. Disposable material. Material generally found to be unsuitable for roadway construction or material that is surplus. Disposal areas. Areas generally located off the project right of way where unsuitable or surplus material is deposited. Drainage ditch. An artificial depression constructed to carry off surface water. E Earthwork. The work consisting of grubbing, drainage, roadway excavation, embankment excavation, borrowing, grading, placing rock, and preparing subgrades. 7

101.02 Easement (Right of way). A grant of the right to use property for a specific use. Embankment. A structure of soil, soil aggregate, or broken rock between the existing ground and subgrade. Employee. Any person working on the project specified in the Contract who is under the direction or control of or receives compensation from the Contractor or subcontractor. Engineer. The Chief Engineer, who acts directly or through his duly authorized representative. The representative acts within the scope of the particular duties assigned to him or the authority given to him. Equipment. Machinery, tools, and other apparatus, together with the necessary supplies for upkeep and maintenance, that are necessary for acceptable completion of the work. Extra work. An item of work that is not provided for in the Contract as awarded but that is found to be essential to the satisfactory fulfillment of the Contract within its intended scope. F

Falsework. A framework of wood or steel used to support forms for the construction of concrete slab spans or t-beams, or provide temporary support for structural units during the construction or reconstruction of permanent supports. Federal agencies or officers. An agency or officer of the federal government and any agency or officer succeeding in accordance with the law to the powers, duties, jurisdictions, and authority of the agency or officer mentioned. Flood frequency. A statistical average recurrence interval of floods of a given magnitude. Force account work. Prescribed work of a contractual status performed by the Contractor and compensated for as specified in Section 109.05. Formwork. A temporary structure or mold used to retain the plastic or fluid concrete in its designated shape until it hardens. Formwork shall be designed to resist the fluid pressure exerted by plastic concrete and additional fluid pr