Top Banner
PROJECT / TRAINING REPORT ( PROJECT / TRAINING PERIOD MARCHJUNE ) BTPS, NTPC BADARPUR ,NEW DELHI-110044 Submitted In Partial fulfillment of the requirement for the degree of BACHELOR OF TECHNOLOGY (B.TECH) UNDER THE GUIDANCE OF Internal Suprvisor : External Supervisor: Dinesh Jhakar Brahm Shanker H.O.D ME DEPT. (ACME) TRAINER (BTPS) SUBMITTED BY VIKAS SINGH ROLL NO. : 12BTME47 APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING MAHARSHI DAYANAND UNIVERSITY, (ROHTAK-124001)
62

Vikas

Mar 21, 2017

Download

Education

Anand Kumar
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Vikas

PROJECT / TRAINING REPORT

( PROJECT / TRAINING PERIOD MARCH– JUNE )

BTPS, NTPC BADARPUR ,NEW DELHI-110044

Submitted In Partial fulfillment of the requirement for the degree of

BACHELOR OF TECHNOLOGY (B.TECH)

UNDER THE GUIDANCE OF

Internal Suprvisor : External Supervisor:

Dinesh Jhakar Brahm Shanker

H.O.D ME DEPT. (ACME) TRAINER (BTPS)

SUBMITTED BY

VIKAS SINGH

ROLL NO. : 12BTME47

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING

MAHARSHI DAYANAND UNIVERSITY, (ROHTAK-124001)

Page 2: Vikas

ABSTRACT

India’s largest power company, NTPC was set up in 1975 to accelerate power development

in India. NTPC is emerging as a diversified power major with presence in the entire value

chain of the power generation business. Apart from power generation, which is the mainstay

of the company, NTPC has already ventured into consultancy, power trading, ash utilization

and coal mining. NTPC ranked 34 in the 2010 Forbes Global 2000 ranking of the World’s

biggest companies. NTPC became a Maharatna company in May, 2010, one of the only four

companies to be awarded this status.

BADARPUR THERMAL POWER STATION was established on 1973 and it was the part

of Central Government. On 01/04/1978 is was given as No Loss No Profit Plant of NTPC.

Since then operating performance of NTPC has been considerably above the national

average. The availability factor for coal stations has increased from 85.03 % in 1997-98 to

90.09 % in 2006-07, which compares favorably with international standards. The PLF has

increased from 75.2% in1997-98 to 89.4% during the year 2006-07 which is the highest since

the inception of NTPC. Badarpur thermal power station started with a single 95 mw unit.

There were 2 more units (95 MW each) installed in next 2 consecutive years. Now it has total five

units with total capacity of 720 MW. Ownership of BTPS was transferred to NTPC with effect from

01.06.2006 through GOIs Gazette Notification . The power is supplied to a 220 KV network

that is a part of the northern grid. The ten circuits through which the power is evacuated from

the plant are:

1. Mehrauli 2. Okhla

3. Ballabgarh 4. Indraprastha

5. UP (Noida) 6. Jaipur

Page 3: Vikas

ACKNOWLEDGEMENT

It has been a great honor and privilege to undergo training at NTPC Limited, Badarpur,

DELHI, India. I am very grateful to Mr. A K SINGH (DGM HR) & Mr. BRAHM

SHANKER (SUPERVISOR) for giving their valuable time and constructive guidance

in preparing the internship report for Internship. It would not have been possible to

complete this report in short period of time without their kind encouragement and

valuable guidance.

I am also thankful to PROF. DINESH JAKHAR, H.O.D., Department of Mechanical

Engineering, ACME, for his constant support and encouragement.

I would also like to render heartiest thanks to my brother & sister who’s ever helping nature

and support has helped me complete this present work

VIKAS SINGH

ROLL NO. - 12BTME47

8th

Semester, B. Tech

Page 4: Vikas

TABLE OF CONTENTS

LIST OF FIGURES

CHAPTER 1

1.1 COMPANY AND PROFILE 1

1.2 VISSION AND MISSION 1

1.3 POWER GENERATION IN INDIA 1

1.4 EVOLUTION 3

1.5 NTPC HEADQUARTERS 4

1.6 NTPC PLANTS 5

1.8 FUTURE GOALS 7

1.9 ENVIRONMENTAL MANAGEMENT 7

CHAPTER 2

2.1 ABOUT BADARPUR THERMAL POWER STATION 8

2.2 FROM COAL TO ELECRICITY PROCESS 11

2.3 MAIN GENERATOR 13

2.4 MAIN TURBINE DATA 14

CHAPTER 3

3.1 OPERATION 19

3.2 COAL HANDLING PLANT (C.H.P.) & NEW COAL HANDLING PLANT

(N.C.H.P) 34

3.3 GENERATOR AND AUXILIARIES 40

Page 5: Vikas

3.4 TRANSFORMER 47

3.5 INSTRUMENT SEEN 51

3.6 POLLUTION CONTROL SYSTEM 51

3.7 CONTROL AND MONITORING MECHANISM 54

3.8 SOLUTION TO THE PROBLEM 54

REFERENCES

Page 6: Vikas

LIST OF FIGURES

Figure 1: Total Power Generation

Figure 2: Top View BTPS

Figure 3: Flow Chart Of Coal To Electricity

Figure 4: Components Of A Coal Fired Thermal Plant

Figure 5: Strategies Of Ntpc

Figure 6: Parts Of Powerplant

Figure7: External View Of Boiler

Figure8: External View Of Id, Pa & Fd Fans

Figure 9: Coal Cycle

Figure 10: Wagon Trippler

Figure 11: Conveyor

Figure 12: Crushers

Figure 13: Cross-Sectional View Of A Generator

Figure 14: A 95 Mw Generator

Figure 15: Transformer

Page 7: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 1

CHAPTER-1 COMPANY PROFILE

NTPC Limited is the largest thermal power generating company of India. A public sector

company, it was incorporated in the year 1975 to accelerate power development in the

country as a wholly owned company of the Government of India. At present, Government

of India holds 89.5% of the total equity shares of the company and FIIs, Domestic Banks,

Public and others hold the balance 10.5%. Within a span of 31 years, NTPC has emerged

as a truly national power company, with power generating facilities in all the major

regions of the country.

VISION AND MISSION

Vision

“To be the world’s largest and best power producer, powering India’s growth.”

Mission

“Develop and provide reliable power, related products and services at competitive prices,

integrating multiple energy sources with innovative and eco-friendly technologies and

contribute to society.”

POWER GENERATION IN INDIA

NTPC’s core business is engineering, construction and operation of power generating

plants. It also provides consultancy in the area of power plant constructions and power

generation to companies in India and abroad. As on date the installed capacity of NTPC is

27,904 MW through its 15 coal based (22,895 MW), 7 gas based (3,955 MW) and 4 Joint

Venture Projects (1,054 MW). NTPC acquired 50% equity of the SAIL Power Supply

Page 8: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 2

Corporation Ltd. (SPSCL). This JV Company operates the captive power plants of

Durgapur (120 MW), Rourkela (120 MW) and Bhilai (74 MW). NTPC also has 28.33%

stake in Ratnagiri Gas & Power Private Limited (RGPPL) a joint venture company

between NTPC, GAIL, Indian Financial Institutions and Maharashtra SEB Co Ltd.

Figure 1: TOTAL POWER GENERATION

NTPC has set new benchmarks for the power industry both in the area of power plant

construction and operations. Its providing power at the cheapest average tariff in the

country..

NTPC is committed to the environment, generating power at minimal environmental cost

and preserving the ecology in the vicinity of the plants. NTPC has undertaken massive a

forestation in the vicinity of its plants. Plantations have increased forest area and reduced

barren land. The massive a forestation by NTPC in and around its Ramagundam Power

station (2600 MW) have contributed reducing the temperature in the areas by about 3°c.

Page 9: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 3

NTPC has also taken proactive steps for ash utilization. In 1991, it set up Ash Utilization

Division

A "Centre for Power Efficiency and Environment Protection (CENPEEP)" has been

established in NTPC with the assistance of United States Agency for International

Development (USAID). Cenpeep is efficiency oriented, eco-friendly and eco-nurturing

initiative - a symbol of NTPC's concern towards environmental protection and continued

commitment to sustainable power development in India.

EVOLUTION

NTPC was set up in 1975 in 100% by the ownership of Government

of India. In the last 30 years NTPC has grown into the largest power

utility in India.

In 1997, Government of India granted NTPC status of ‘Navratna’

being one of the nine jewels of India, enhancing the powers to the

Board of directors.

NTPC became a listed company with majority Government

ownership of 89.5%. NTPC becomes third largest by market

capitalisation of listed companies.

The company rechristened as NTPC Limited in line with its

changing business portfolio and transforms itself from a thermal

power utility to an integrated power utility.

National Thermal Power Corporation is the largest power

generation company in India. Forbes Global 2000 for 2008 ranked

it 411th

the world.

National Thermal Power Corporation is the largest power

generation company in India. Forbes Global 2000 for 2008 ranked

it 317th

in the world.

1975

1997

2004

2005

2008

2009

Page 10: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 4

NTPC has also set up a plan to achieve a target of 50,000 MW

generation capacities.

NTPC has embarked on plans to become a 75,000 MW company

by 2017.

NTPC is the largest power utility in India, accounting for about 20% of India’s installed

capacity.

NTPC HEADQUARTERS

NTPC Limited is divided in 8 Headquarters

S. NO. HEADQUARTERS CITY

1. NCR HQ DELHI

2. ER HEADQUARTER-1 BHUBANESHWAR

3. ER HEADQUARTER-2 PATNA

4. NRHQ LUCKNOW

5. SR HEADQUARTER HYDERABAD

6. WR-1 HEADQUARTER MUMBAI

7. HYDRO HEADQUARTER DELHI

8. WR-2 HEADQUARTER RAIPUR

2012

2017

TABLE:1

Page 11: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 5

NTPC PLANTS

1.Thermal-Coal based

S. NO. CITY STATE INSTALLED

CAPACITY(MW)

1. SINGRAULI UTTAR PRADESH 2000

2. KORBA CHATTISGHAR 2600

3. RAMAGUNDAM ANDHRA PRADESH 2600

4. FARAKKA WEST BENGAL 2100

5. VINDHYACHAL MADHYA PRADESH 3260

6. RIHAND UTTAR PRADESH 2500

7. KAHALGAON BIHAR 2300

8. DADRI UTTAR PRADESH 1820

9. TALCHER ORISSA 3000

10. UNCHAHAR UTTAR PRADESH 1050

11. TALCHER ORISSA 460

12. SIMHADRI ANDHRA PRADESH 1500

13. TANDA UTTAR PRADESH 440

14. BADARPUR DELHI 705

15. SIPAT CHHATTISGHAR 2320

16. SIPAT CHHATTISGHAR 1980

17. BONGAIGAON ASSAM 750

18. MOUDA MAHARASHTRA 1000(2*500MW)

19. RIHAND UTTAR PRADESH 2*500MW

20. BARH BIHAR 3300(5*660)

TOTAL 31495MW

TABLE:2

Page 12: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 6

2. COAL BASED (Owned by JVs)

S.NO. NAME OF THE

JV

CITY STATE INSTALLED

CAPACITY(MW)

1. NSPCL DURGAPUR WEST BENGAL 120

2. NSPCL ROURKELA ORISSA 120

3. NSPCL BHILAI CHHATTISGHAR 574

4. NPGC AURANGABAD BIHAR 1980

5. M.T.P.S. KANTI BIHAR 110

6. BRBCL NABINAGAR BIHAR 1000

TOTAL 3904MW

TABLE:3

1. GAS Based

S.NO. CITY STATE INSTALLED

CAPACITY(MW)

1. ANTA RAJSTHAN 419

2. AURAIYA UTTAR PRADESH 652

3. KAWAS GUJARAT 645

4. DADRI UTTAR PRADESH 817

5. JHANOR GUJARAT 648

6. KAYAMKULAM KERALA 350

7. FARIDABAD HARYANA 430

TOTAL 3995MW

TABLE:4

Page 13: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 7

NTPC HYDEL

The company has also stepped up its hydroelectric power (hydel) projects

implementation. Currently the company is mainly interested in the North-east India

wherein the Ministry of Power in India has projected a hydel power feasibility of 3000

MW.Loharinag Pala Hydro Power Project by NTPC Ltd: In Loharinag Pala Hydro Power

Project with a capacity of 600 MW (150 MW x 4 Units). The main package has been

awarded. The present executives' strength is 100+. The project is located on river

Bhagirathi (a tributory of the Ganges) in Uttarkashi district of Uttarakhand state. This is

the first project downstream from the origin of the Ganges at Gangotri.Tapovan

Vishnugad 520MW Hydro Power Project by NTPC Ltd: In Joshimath town.#Lata

Tapovan 130MW Hydro Power Project by NTPC Ltd: is further upstream to Joshimath

(under environmental revision) Koldam Hydro Power Project 800 MW in Himachal

Pradesh .

FUTURE GOALS

The company has also set a serious goal of having 50000 MW of installed capacity by

2012 and 75000 MW by 2017. NTPC will invest about Rs 20,000 crore to set up a 3,900-

megawatt (MW) coal-based power project in Madhya Pradesh. Company will also start

coal production from its captive mine in Jharkhand in 2011–12, for which the company

will be investing about 18 billion. ALSTOM would be a part of its 660-MW supercritical

projects for Solapur II and Mouda II in Maharashtra.ALSTOM would execute turnkey

station control and instrumentation (C&I) for this project.

ENVIRONMET MANAGEMENT, OCCUPATIONAL

HEALTH and SAFETY SYSTEMS

NTPC has actively gone for adoption of best international practices on environment,

occupational health and safety areas. The organization has pursued the Environmental

Management System (EMS) ISO 14001 and the Occupational Health and Safety

Assessment System OHSAS 18001 at its different establishments. As a result of pursuing

these practices, all NTPC power stations have been certified for ISO 14001 & OHSAS

18001 by reputed national and international Certifying Agencies.

Page 14: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 8

CHAPTER 2

ABOUT BADARPUR THERMAL POWER STATION

Figure 2: Top View BTPS

Badarpur Thermal Power Station is located at Badarpur area in NCT Delhi. The power

plant is one of the coal based power plants of NTPC. The National Power Training

Institute (NPTI) for North India Region under Ministry of Power, Government of India

was established at Badarpur in 1974, within the Badarpur Thermal power plant (BTPS)

complex.It is situated in south east corner of Delhi on Mathura Road near Faridabad. It

was the first central sector power plant conceived in India, in 1965. It was originally

conceived to provide power to neighbouring states of Haryana, Punjab, Jammu and

Kashmir,U.P., Rajasthan, and Delhi.But since year 1987 Delhi has become its sole

beneficiary.

Page 15: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 9

The power is supplied to a 220 KV network that is a part of the northern grid. The ten

circuits through which the power is evacuated from the plant are:

1. Mehrauli 2. Okhla

3. Ballabgarh 4. Indraprastha

5. UP (Noida) 6. Jaipur

Page 16: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 10

Badarpur is situated only 20 km away from Delhi. The plant is located on the left side of

the National Highway (Delhi-Mathura Road) and it comprises of 430 hectares (678 acres)

bordered by the Agra Canal from East and by Mathura-Delhi Road from West. However,

the area for ash disposal is done in the Delhi Municipal limit and is maintained with the

help of Delhi Development Authority.

Basic Steps of Electricity Generation

a) Coal to steam

b) Steam to mechanical power

c) Mechanical power to electrical power

No of plants

Capacity (MW)

NTPC Owned

1. Coal 16 31,855

2. Gas / Liquid Fuel 7 3,955

Total 23 35,810

Owned by Joint Ventures

3. Coal & Gas 7 5364

Grand Total 30 41,174

Page 17: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 11

FROM COAL TO ELECTRICITY PROCESS

Figure 3: FLOW CHART of COAL TO ELECTRICITY

Coal to Steam

Coal from the coal wagons is unloaded in the coal handling plant. This Coal is

transported up to the raw coal bunkers with the help of belt conveyors. Coal is

transported to Bowl mills by Coal Feeders. The coal is pulverized in the Bowl Mill,

where it is ground to powder form. The mill consists of a round metallic table on

which coal particles fall. This table is rotated with the help of a motor. There are

three large steel rollers, which are spaced 120 apart. When there is no coal, these

rollers do not rotate but when the coal is fed to the table it pack up between roller

and the table and ths forces the rollers to rotate. Coal is crushed by the crushing

action between the rollers and the rotating table. This crushed coal is taken away to

the furnace through coal pipes with the help of hot and cold air mixture from P.A. Fan.

Page 18: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 12

P.A. Fan takes atmospheric air, a part of which is sent to Air-Preheaters for heating

while a part goes directly to the mill for temperature control. Atmospheric air from F.D.

Fan is heated in the air heaters and sent to the furnace as combustion air.

Water from the boiler feed pump passes through economizer and reaches the boiler

drum. Water from the drum passes through down comers and goes to the bottom ring

header. Water from the bottom ring header is divided to all the four sides of the

furnace. Due to heat and density difference, the water rises up in the water wall tubes.

Water is partly converted to steam as it rises up in the furnace. This steam and water

mixture is again taken to thee boiler drum where the steam is separated from water.

water follows the same path while the steam is sent to superheaters for superheating.

The superheaters are located inside the furnace and the steam is superheated (540 oC)

and finally it goes to the turbine.Flue gases from the furnace are extracted by induced

draft fan, which maintains balance draft in the furnace (-5 to –10 mm of wcl) with

forced draft fan. These flue gases emit their heat energy to various super heaters in the

pent house and finally pass through air-preheaters and goes to electrostatic precipitators

where the ash particles are extracted. Electrostatic Precipitator consists of metal

plates, which are electrically charged. Ash particles are attracted on to these

plates, so that they do not pass through the chimney to pollute t he atmosphere.

Regular mechanical hammer blows cause the accumulation of ash to fall to the bottom

of the precipitator where they are collected in a hopper for disposal.

Page 19: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 13

Steam to Mechanical Power

From the boiler, a steam pipe conveys steam to the turbine through a stop valve

(which can be used to shut-off the steam in case of emergency) and through control

valves that automatically regulate the supply of steam to the turbine. Stop valve and

control valves are located in a steam chest and a governor, driven from the main

turbine shaft, operates the control valves to regulate the amount of steam used. (This

depends upon the speed of the turbine and the amount of electricity required from the

generator).

Steam from the control valves enters the high pressure cylinder of the turbine, where it

passes through a ring of stationary blades fixed to the cylinder wall. These act as

nozzles and direct the steam into a second ring of moving blades mounted on a disc

secured to the turbine shaft. The second ring turns the shafts as a result of the force of

steam. The stationary and moving blades together constitute a „stage‟ of turbine and in

practice many stages are necessary, so that the cylinder contains a number of rings of

stationary blades with rings of moving blades arranged between them. The steam passes

through each stage in turn until it reaches the end of the high-pressure cylinder and in

its passage some of its heat energy is changed into mechanical energy.

The steam leaving the high pressure cylinder goes back to the boiler for reheating and

returns by a further pipe to the intermediate pressure cylinder. Here it passes through

another series of stationary and moving blades.

Finally, the steam is taken to the low-pressure cylinders, each of which enters at the

centre flowing outwards in opposite directions through the rows of turbine blades

through an arrangement called the „double flow‟- to the extremities of the cylinder. As

the steam gives up its heat energy to drive the turbine, its temperature and pressure

fall and it expands. Because of this expansion the blades are much larger and longer

towards the low pressure ends of the turbine.

Page 20: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 14

Mechanical Power to Electrical Power

As the blades of turbine rotate, the shaft of the generator, which is coupled to tha

of t he turbine, also rotates. It results in rotation of the coil of the generator, which

causes induced electricity to be produced.

Basic Power Plant Cycle

Figure 4: COMPONENTS OF A COAL FIRED THERMAL PLANT

The thermal (steam) power plant uses a dual (vapour+ liquid) phase cycle. It is a close

cycle to enable the working fluid (water) to be used again and again. The cycle used

is Rankine Cycle modified to include superheating of steam, regenerative feed water

heating and reheating of steam. On large turbines, it becomes economical to increase

the cycle efficiency by using reheat, which is a way of partially overcoming

temperature limitations. By returning partially expanded steam, to a reheat, the

average temperature at which the heat is added, is increased and, by expanding this

reheated steam to the remaining stages of the turbine, the exhaust wetness is

considerably less than it would otherwise be conversely, if the maximum tolerable

wetness is allowed, the initial pressure of the steam can be appreciably increased.

Bleed Steam Extraction: For regenerative system, nos. of non-regulated extractions is

taken from HP, IP turbine. Regenerative heating of the boiler feed water is widely

used in modern power plants; the effect being to increase the average temperature

at which heat is added to the cycle, thus improving the cycle efficiency.

Page 21: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 15

On large turbines, it becomes economical to increase the cycle efficiency by using

reheat, which is a way of partially overcoming temperature limitations. By returning

partially expanded steam, to a reheat, the average temperature at which the heat is

added, is increased and, by expanding this reheated steam to the remaining stages of

the turbine, the exhaust wetness is considerably less than it would otherwise be

conversely, if the maximum tolerable wetness is allowed, the initial pressure of the steam

can be appreciably increased.

Bleed Steam Extraction: For regenerative system, nos. of non-regulated extractions is

taken from HP, IP turbine. Regenerative heating of the boiler feed water is widely used

in modern power plants; the effect being to increase the average temperature at which

heat is added to the cycle, thus improving the cycle efficiency.

TABLE: 6

MAIN TURBINE DATA

Rated output of Turbine 210 MW

Rated speed of turbine 3000 rpm

Rated pressure of steam before emergency 130 kg/cm^2

Stop valve rated live steam temperature 535 o Celsius

Page 22: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 16

Rated steam temperature after reheat at inlet to receptor valve 535 o Celsius

Steam flow at valve wide open condition 670 tons/hour

Rated quantity of circulating water through condenser 27000 cm/hour

1. For cooling water temperature (o Celsius) 24,27,30,33

2. Steam flow required for 210 MW in ton/hour 68,645,652,662

MAIN GENERATOR

Maximum continuous KVA rating 24700KVA

Maximum continuous KW 210000KW

Rated terminal voltage 15750V

Rated Stator current 9050 A

Rated Power Factor 0.85 lag

Excitation current at MCR Condition 2600 A

Slip-ring Voltage at MCR Condition 310 V

Rated Speed 3000 rpm

Rated Frequency 50 Hz

Short circuit ratio 0.49

Direction of rotation viewed Anti Clockwise

Phase Connection Double Star

Number of terminals brought out 9(6 neutral and 3 phases)

Page 23: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 17

STRATEGIES OF NTPC

Figure 5: STRATEGIES OF NTPC

Technological Initiatives

a) Introduction of steam generators (boilers) of the size of 800 MW.

b) Integrated Gasification Combined Cycle (IGCC) Technology.

c) Launch of Energy Technology Centre -A new initiative for development of technologies

with focus on fundamental R&D.

d) The company sets aside up to 0.5% of the profits for R&D.

e) Roadmap developed for adopting µClean Development. Mechanism to help get / earn

Page 24: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 18

µCertified Emission Reduction.

Corporate Social Responsibility

As a responsible corporate citizen NTPC has taken up number of CSR initiatives.

a) NTPC Foundation formed to address Social issues at national level

b) NTPC has framed Corporate Social Responsibility Guidelines committing up to0.5% of

net profit annually for Community Welfare.

c) The welfare of project affected persons and the local population around

NTPC projects are taken care of through well drawn Rehabilitation and Resettlement policies.

d) The company has also taken up distributed generation for remote rural areas.

Partnering government in various initiatives

a) Consultant role to modernize and improvise several plants across the country.

b) Disseminate technologies to other players in the sector.

c) Consultant role ³Partnership in Excellence´ Programme for improvement of PLF of 15

Power Stations of SEBs.

d) Rural Electrification work under Rajiv Gandhi Garmin Vidyutikaran.

Page 25: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 19

CHAPTER 3

OPERATION OF POWER PLANT/ (PROJECT)

BASIC PRINCIPLE

As per FARADAY‟s Law-“Whenever the amount of magnetic flux linked with a circuit

changes, an EMF is produced in the circuit. Generator works on the principle of

producing electricity. To change the flux in the generator turbine is moved in a great

speed with steam.” To produce steam, water is heated in the boilers by burning the coal.

In a Badarpur Thermal PowerStation, steam is produced and used to spin a turbine that

operates a generator. Water is heated, turns into steam and spins a steam turbine which

drives an electrical generator. After it passes through the turbine, the steam is condensed

in a condenser; this is known as a Rankine cycle.

The electricity generated at the plant is sent to consumers through high-voltage power

lines The Badarpur Thermal Power Plant has Steam Turbine-Driven Generators which

has a collective capacity of 705MW. The fuel being used is Coal which is supplied from

the Jharia Coal Field in Jharkhand. Water supply is given from the Agra Canal.

THERMAL POWER PLANT

A Thermal Power Station comprises all of the equipment and a subsystem required to

produce electricity by using a steam generating boiler fired with fossil fuels or biofuels to

drive an electrical generator. Some prefer to use the term ENERGY CENTER because such

facilities convert forms of energy, like nuclear energy, gravitational potential energy or heat

energy (derived from the combustion of fuel) into electrical energy. However, POWER

Page 26: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 20

PLANT is the most common term in the united state; While POWER STATION prevails in

many Commonwealth countries and especially in the United Kingdom.

Such power stations are most usually constructed on a very large scale and designed for

continuous operation.

Figure 6: parts of powerplant

Typical elements of a coal fired thermal power station

1. cooling tower

Page 27: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 21

2. Cooling water pump

3. Three -phase transmission line

4. Step up transformer

5. Electrical Generator

6. Low pressure turbine

7. Boiler feed water pump

8. Surface condenser

9. Intermediate pressure steam turbine

10. Steam control valve

11. High pressure steam turbine

12. Deaerator

13.Feed water heater

14. Coal conveyor

15. Coal hopper

16. Coal pulverizer

17. Boiler drum

18. Bottom ash hoper

19. Super heater

20. Forced draught (draft) fan

21. Reheater

22. Combustion air intake

Page 28: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 22

23. Economizer

24. Air preheater

25. Precipitator

26. Induced draught (draft) fan

27. Fuel gas stack

The description of some of the components written above is described as follows:

1. Cooling towers

Cooling Towers are evaporative coolers used for cooling water or other working medium to

near the ambivalent web-bulb air temperature. Cooling towers use evaporation of water to

reject heat from processes such as cooling the circulating water used in oil refineries,

Chemical plants, power plants and building cooling, for example. The tower vary in size

from small roof-top units to very large hyperboloid structures that can be up to 200 meters

tall and 100 meters in diameter, or rectangular structure that can be over 40 meters tall and 80

meters long. Smaller towers are normally factory built, while larger ones are constructed on

site.

The primary use of large, industrial cooling tower system is to remove the heat absorbed in

the circulating cooling water systems used in power plants, petroleum refineries,

petrochemical and chemical plants, natural gas processing plants and other industrial

facilities. The absorbed heat is rejected to the atmosphere by the evaporation of some of the

cooling water in mechanical forced-draft or induced draft towers or in natural draft

hyperbolic shaped cooling towers as seen at most nuclear power plants.

2. Cooling Water Pump

it pumps the water from the cooling tower which goes to the condenser

3. Three phase transmission line

Page 29: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 23

Three phase electric power is a common method of electric power transmission. It is a type

of polyphase system mainly used to power motors and many other devices. A Three phase

system uses less conductor material to transmit electric power than equivalent single phase,

two phase, or direct current system at the same voltage. In a three phase system, three circuits

reach their instantaneous peak values at different times. Taking one conductor as the

reference, the other two current are delayed in time by one-third and two-third of one cycle

of the electrical current. This delay between “phases” has the effect of giving constant power

transfer over each cycle of the current and also makes it possible to produce a rotating

magnetic field in an electric motor.

At the power station, an electric generator converts mechanical power into a set of electric

currents, one from each electromagnetic coil or winding of the generator. The current are

sinusoidal functions of time, all at the same frequency but offset in time to give different

phases. In a three phase system the phases are spaced equally, giving a phase separation of

one-third one cycle. Generators output at a voltage that ranges from hundreds of volts to

30,000 volts. At the power station, transformers: step-up” this voltage to one more suitable

for transmission.

4. Unit transformer (3-phase)

At the power station, transformers step-up this voltage to one more suitable for

transmission. After numerous further conversions in the transmission and distribution

network the power is finally transformed to the standard mains voltage (i.e. the

“household” voltage). The power may already have been split into single phase at this

point or it may still be three phase. Where the step-down is 3 phase, the output of this

transformer is usually star connected with the standard mains voltage being the phase-

neutral voltage. Another system commonly seen in North America is to have a delta

connected secondary with a center tap on one of the windings supplying the ground and

neutral. This allows for 240 V three phase as well as three different single phase voltages(

120 Vbetween two of the phases and neutral , 208 V between the third phase ( or wild leg)

and neutral and 240 V between any two phase) to be available from the same supply.

5. Electrical generator

Page 30: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 24

An Electrical generator is a device that converts kinetic energy to electrical energy, generally

using electromagnetic induction. The task of converting the electrical energy into mechanical

energy is accomplished by using a motor. The source of mechanical energy may be a

reciprocating or turbine steam engine, , water falling through the turbine are made in a

variety of sizes ranging from small 1 hp (0.75 kW) units (rare) used as mechanical drives for

pumps, compressors and other shaft driven equipment , to 2,000,000 hp(1,500,000 kW)

turbines used to generate electricity. There are several classifications for modern steam

turbines.

Steam turbines are used in all of our major coal fired power stations to drive the generators or

alternators, which produce electricity. The turbines themselves are driven by steam generated

in ‘Boilers’ or ‘steam generators’ as they are sometimes called.

Electrical power stations use large steam turbines driving electric generators to produce most

(about 86%) of the world’s electricity. These centralized stations are of two types: fossil fuel

power plants and nuclear power plants. The turbines used for electric power generation are

most often directly coupled to their-generators .As the generators must rotate at constant

synchronous speeds according to the frequency of the electric power system, the most

common speeds are 3000 r/min for 50 Hz systems, and 3600 r/min for 60 Hz systems. Most

large nuclear sets rotate at half those speeds, and have a 4-pole generator rather than the more

common 2-pole one.

Energy in the steam after it leaves the boiler is converted into rotational energy as it passes

through the turbine. The turbine normally consists of several stage with each stages

consisting of a stationary blade (or nozzle) and a rotating blade. Stationary blades convert the

potential energy of the steam into kinetic energy into forces, caused by pressure drop, which

results in the rotation of the turbine shaft. The turbine shaft is connected to a generator,

which produces the electrical energy.

6. Low Pressure Turbine

Energy in the steam after it leaves the boiler is converted into rotational energy as it

passes through the turbine. The turbine normally consists of several stages with each

stages consisting of a stationary blade (or nozzle) and a rotating blade. Stationary blades

Page 31: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 25

convert the potential energy of the steam into kinetic energy and direct the flow onto the

rotating blades. The rotating blades convert the kinetic energy into impulse and reaction

forces, caused by pressure drop, which results in the rotation of the turbine shaft. The

turbine shaft is connected to a generator, which produces the electrical energy.

Low Pressure Turbine (LPT) consists of 4x2 stages. After passing through Intermediate

Pressure Turbine steam is passed through LPT which is made up of two parts- LPC

REAR & LPC FRONT. As water gets cooler here it gathers into a HOTWELL placed in

lower parts of turbine.

7. Condensation Extraction Pump

A Boiler feed water pump is a specific type of pump used to pump water into a steam

boiler. The water may be freshly supplied or returning condensation of the steam

produced by the boiler. These pumps are normally high pressure units that use suction

from a condensate return system and can be of the centrifugal pump type or positive

displacement type.

Construction and operation:

Feed water pumps range in size up to many horsepower and the electric motor is usually

separated from the pump body by some form of mechanical coupling. Large industrial

condensate pumps may also serve as the feed water pump. In either case, to force the

water into the boiler, the pump must generate sufficient pressure to overcome the steam

pressure developed by the boiler. This is usually accomplished through the use of a

centrifugal pump. Feed water pumps usually run intermittently and are controlled by a

float switch or other similar level-sensing device energizing the pump when it detects a

lowered liquid level in the boiler. Some pumps contain a two-stage switch. As liquid

lowers to the trigger point of the first stage, the pump is activated. If the liquid continues

to drop, (perhaps because the pump has failed, its supply has been cut off or exhausted, or

its discharge is blocked) the second stage will be triggered. This stage may switch off the

boiler equipment (preventing the boiler from running dry and overheating), trigger an

alarm, or both.

Page 32: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 26

8. Condenser

The steam coming out from the Low Pressure Turbine (a little above its boiling pump) is

brought into thermal contact with cold water (pumped in from the cooling tower) in the

condenser, where it condenses rapidly back into water, creating near Vacuum-like

conditions inside the condenser chest.

9. Intermediate Pressure Turbine

Intermediate Pressure Turbine (IPT) consists of 11 stages. When the steam has been passed

through HPT it enters into IPT. IPT has two ends named as FRONT & REAR.

Steam enters through front end and leaves from Rear end.

10. Steam Governor Valve

Steam locomotives and the steam engines used on ships and stationary applications such

as power plants also required feed water pumps. In this situation, though, the pump was

often powered using a small steam engine that ran using the steam produced by the boiler

a means had to be provided, of course, to put the initial charge of water into the boiler

(before steam power was available to operate the steam-powered feed water pump).The

pump was often a positive displacement pump that had steam valves and cylinders at one

end and feed water cylinders at the other end; no crankshaft was required. In thermal

plants, the primary purpose of surface condenser is to condense the exhaust steam from a

steam turbine to obtain maximum efficiency and also to convert the turbine exhaust

steam into pure water so that it may be reused in the steam generator or boiler as boiler

feed water. By condensing the exhaust steam of a turbine at a pressure below atmospheric

pressure, the steam pressure drop between the inlet and exhaust of the turbine is

increased, which increases the amount heat available for conversion to mechanical

power.

11.High Pressure Turbine

Steam coming from Boiler directly feeds into HPT at a temperature of 540°C and at a

pressure of 136 kg/cm2. Here it passes through 12 different stages due to which its

Page 33: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 27

temperature goes down to 329°C and pressure as 27 kg/cm2. This line is also called as

CRH – COLD REHEAT LINE. It is now passed to a REHEATER where its temperature

rises to 540°C and called as HRH-HOT REHEATED LINE.

12. Deaerator

A Deaerator is a device for air removal and used to remove dissolved gases (an alternate

would be the use of water treatment chemicals) from boiler feed water to make it non-

corrosive. A dearator typically includes a vertical domed deaeration section as the

deaeration boiler feed water tank. A Steam generating boiler requires that the circulating

steam, condensate, and feed water should be devoid of dissolved gases, particularly

corrosive ones and dissolved or suspended solids. The gases will give rise to corrosion of

the metal. The solids will deposit on the heating surfaces giving rise to localized heating

and tube ruptures due to overheating. Under some conditions it may give rise to stress

corrosion cracking. Deaerator level and pressure must be controlled by adjusting control

valves the level by regulating condensate flow and the pressure by regulating steam flow.

13. Feed water heater

A Feed water heater is a power plant component used to pre-heat water delivered to a

steam generating boiler. Preheating the feed water reduces the irreversibility involved in

steam generation and therefore improves the thermodynamic efficiency of the system.

This reduces plant operating costs and also helps to avoid thermal shock to the boiler

metal when the feed water is introduced back into the steam cycle. In a steam power

(usually modelled as a modified Rankine cycle), feed water heaters allow the feed water

to be brought up to the saturation temperature very gradually. This minimizes the

inevitable irreversibility associated with heat transfer to the working fluid (water).

14. Coal conveyor

Coal conveyors are belts which are used to transfer coal from its storage place to Coal

Hopper. A belt conveyor consists of two pulleys, with a continuous loop of material- the

conveyor Belt – that rotates about them. The pulleys are powered, moving the belt and

Page 34: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 28

the material on the belt forward.Conveyor belts are extensively used to transport industrial

and agricultural material, such as grain, coal, ores etc.

15. Coal Hopper

Coal Hoppers are the places which are used to feed coal to Fuel Mill. It also has the

arrangement of entering Hot Air at 200°C inside it which solves our two purposes:-

1. If our Coal has moisture content then it dries it so that a proper combustion takes place.

2. It raises the temperature of coal so that its temperature is more near to its Ignite

Temperature so that combustion is easy

16. Pulverized Fuel Mill

A pulveriser is a device for grinding coal for combustion in a furnace in a fossil fuel

power plant.

17. Boiler feed water pump

A Boiler feed water pump is a specific type of pump used to pump water into a steam

boiler. The water may be freshly supplied or retuning condensation of the steam produced

by the boiler. These pumps are normally high pressure units that use suction from a

condensate return system and can be of the centrifugal pump type or positive displacement

type.

Page 35: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 29

Figure7: EXTERNAL VIEW OF BOILER

Construction and operation:

Feed water pumps range in size up to many horsepower and the electric motor is usually

separated from the pump body by some form of mechanical coupling. Large industrial

condensate pumps may also serve as the feed water pump. In either case, to force the

water into the boiler; the pump must generate sufficient pressure to overcome the steam

pressure developed by the boiler. This is usually accomplished through the use of a

centrifugal pump.

Feed water pumps usually run intermittently and are controlled by a float switch or other

similar level-sensing device energizing the pump when it detects a lowered liquid level in

the boiler is substantially increased. Some pumps contain a two-stage switch. As liquid

lowers to the trigger point of the first stage, the pump is activated. I f the liquid continues to

drop (perhaps because the pump has failed, its supply has been cut off or exhausted, or its

discharge is blocked); the second stage will be triggered.

18. Ash Hopper

A steam drum is used in the company of a mud-drum/feed water drum which is located at

a lower level.So that it acts as a sump for the sludge or sediments which have a tendency to

Page 36: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 30

accumulate at the bottom.

19. Super Heater

A Super heater is a device in a steam engine that heats the steam generated by the boiler

again increasing its thermal energy. Super heaters increase the efficiency of the steam

engine, and were widely adopted. Steam which has been superheated is logically known

as superheated steam; non- superheated steam is called saturated steam or wet steam.

Super heaters were applied to steam locomotives in quantity from the early 20th century,

to most steam vehicles, and also stationary steam engines including power stations.

20. Force Draught Fan

External fans are provided to give sufficient air for combustion. The forced draught fan

takes air from the atmosphere and, warms it in the air preheater for better combustion,

injects it via the air nozzles on the furnace wall.

21. Reheater

Reheater is a heater which is used to raise the temperature of steam which has fallen from

the intermediate pressure turbine.

22. Air Intake

Air is taken from the environment by an air intake tower which is fed to the fuel.

23. Economizers

Economizer, or in the UK economizer, are mechanical devices intended to reduce energy

consumption, or to perform another useful function like preheating a fluid. The term

economizer is used for other purposes as well-Boiler, power plant, heating, ventilating

and air-conditioning. In boilers, economizer are heat exchange devices that heat fluids ,

usually water, up to but not normally beyond the boiling point of the fluid. Economizers

are so named because they can make use of the enthalpy and improving the boiler‟s

efficiency. They are devices fitted to a boiler which save energy by using the exhaust

gases from the boiler to preheat the cold water used to fill it (the feed water). Modern day

Page 37: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 31

boilers, such as those in cold fired power stations, are still fitted with economizer which

is decedents of Green‟s original design. In this context there are turbines before it is

pumped to the boilers. A common application of economizer in steam power plants is to

capture the waste heat from boiler stack gases (flue gas) and transfer thus it to the boiler

feed water thus lowering the needed energy input , in turn reducing the firing rates to

accomplish the rated boiler output . Economizer lower stack temperatures which may

cause condensation of acidic combustion gases and serious equipment corrosion damage

if care is not taken in their design and material selection.

24. Air Preheater

Air preheater is a general term to describe any device designed to heat air before another

process (for example, combustion in a boiler). The purpose of the air preheater is to

recover the heat from the boiler flue gas which increases the thermal efficiency of the

boiler by reducing the useful heat lost in the flue gas. As a consequence, the flue gases

are also sent to the flue gas stack (or chimney) at a lower temperature allowing simplified

design of the ducting and the flue gas stack. It also allows control over the temperature of

gases leaving the stack.

25. Precipitator

An Electrostatic precipitator (ESP) or electrostatic air cleaner is a particulate device that

removes particles from a flowing gas (such As air) using the force of an induced electrostatic

charge. Electrostatic precipitators are highly efficient filtration devices, and can easily

remove fine particulate matter such as dust and smoke from the air steam.

ESP’s o ti ue to e e elle t de i es for o trol of a i dustrial parti ulate e issio s,

including smoke from electricity-generating utilities (coal and oil fired), salt cake collection

from black liquor boilers in pump mills, and catalyst collection from fluidized bed catalytic

crackers from several hundred thousand ACFM in the largest coal-fired boiler application.

The original parallel plate-Weighted wire design (described above) has evolved as more

efficient ( and robust) discharge electrode designs were developed, today focusing on rigid

Page 38: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 32

discharge electrodes to which many sharpened spikes are attached , maximizing corona

production. Transformer –rectifier systems apply voltages of 50-100 Kilovolts at relatively

high current densities. Modern controls minimize sparking and prevent arcing, avoiding

damage to the components. Automatic rapping systems and hopper evacuation systems

remove the collected parti ulate atter hile o li e allo i g ESP’s to sta i operatio for

years at a time.

26. Induced Draught Fan

The induced draft fan assists the FD fan by drawing out combustible gases from the

furnace, maintaining a slightly negative pressure in the furnace to avoid backfiring

through any opening. At the furnace outlet and before the furnace gases are handled by

the ID fan, fine dust carried by the outlet gases is removed to avoid atmospheric

pollution. This is an environmental limitation prescribed by law, which additionally

minimizes erosion of the ID fan.

Figure8: EXTERNAL VIEW OF ID, PA & FD FANS

Page 39: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 33

27. Fuel gas stack

A Fuel gas stack is a type of chimney, a vertical pipe, channel or similar structure through

which combustion product gases called fuel gases are exhausted to the outside air. Fuel gases

are produced when coal, oil, natural gas, wood or any other large combustion device. Fuel

gas is usually composed of carbon dioxide (CO2) and water vapor as well as nitrogen and

excess oxygen remaining from the intake combustion air. It also contains a small percentage

of pollutants such as particulates matter, carbon mono oxide, nitrogen oxides and sulfur

oxides. The flue gas stacks are often quite tall, up to 400 meters (1300 feet) or more, so as to

disperse the exhaust pollutants over a greater aria and thereby reduce the concentration of the

pollutants to the levels required by governmental environmental policies and regulations.

When the fuel gases exhausted from stoves, ovens, fireplaces or other small sources within

residential abodes, restaurants , hotels or other stacks are referred to as chimneys.

Page 40: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 34

COAL HANDLING PLANT (C.H.P) & NEW COAL HANDLING

PLANT (N.C.H.P)

The old coal handling plant caters to the need of units 2,3,4,5 and 1 whereas the latter

supplies coal to units 4 and V.O.C.H.P. supplies coal to second and third stages in the advent

coal to usable form to (crushed) form its raw form and send it to bunkers, from where it is

send to furnace.

Figure 9: COAL CYCLE

Page 41: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 35

Major Components

1.Wagon Tippler: - Wagons from the coal yard come to the tippler and are emptied here.

The process is performed by a slip –ring motor of rating: 55 KW, 415V, 1480 RPM. This

motor turns the wagon by 135 degrees and coal falls directly on the conveyor through

vibrators. Tippler has raised lower system which enables is to switch off motor when

required till is wagon back to its original position. It is titled by weight balancing principle.

The motor lowers the hanging balancing weights, which in turn tilts the conveyor. Estimate

of the weight of the conveyor is made through hydraulic weighing machine.

Motor Specification

1. (i) H.P 75 HP

2. (ii) Voltage 415, 3 phase

3. (iii) Speed 1480 rpm

4. (iv) Frequency 50 Hz

5. (v) Current rating 102 A

Figure 10: WAGON TRIPPLER

Page 42: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 36

2.Conveyor: - There are 14 conveyors in the plant. They are numbered so that their function

can be easily demarcated. Conveyors are made of rubber and more with a speed of 250-

300m/min. Motors employed for conveyors has a capacity of 150 HP. Conveyors have a

capacity of carrying coal at the rate of 400 tons per hour. Few conveyors are double belt, this

is done for imp. Conveyors so that if a belt develops any problem the process is not stalled.

The conveyor belt has a switch after every 25-30 m on both sides so stop the belt in case of

emergency. The conveyors are 1m wide, 3 cm thick and made of chemically treated

vulcanized rubber. The max angular elevation of conveyor is designed such as never to

exceed half of the angle of response and comes out to be around 20 degrees.

Conveyors:-

10A, 10B

11A, 11B

12A, 12B

13A, 13B

14A, 14B

15A, 15B

16A, 16B

17A, 17B

18A, 18B

Page 43: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 37

FIGURE 11: CONVEYOR

3. Metal Separators: - As the belt takes coal to the crusher, No metal pieces should go along

with coal. To achieve this objective, we use metal separators. When coal is dropped to the

crusher hoots, the separator drops metal pieces ahead of coal. It has a magnet and a belt

and the belt is moving, the pieces are thrown away. The capacity of this device is around 50

kg. .The CHP is supposed to transfer 600 tons of coal/hr, but practically only 300-400 tons

coal is transfer.

4. Crusher: - Both the plants use TATA crushers powered by BHEL. Motors. The crusher is of

ring type and motor ratings are 400 HP, 606 KV. Crusher is designed to crush the pieces to

20 mm size i.e. practically considered as the optimum size of transfer via conveyor.

Page 44: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 38

FIGURE 12: CRUSHERS

5. Rotatory Breaker: - OCHP employs mesh type of filters and allows particles of 20mm size

to go directly to RC bunker, larger particles are sent to crushes. This leads to frequent

clogging. NCHP uses a technique that crushes the larger of harder substance like metal

impurities easing the load on the magnetic separators.

6. Rotary components

(a) ID Fans: - Located between electrostatic precipitator and chimney.

Type-radical

Speed-1490 rpm

Rating-300 KW

Voltage-6.6 KV

Lubrication-by oil

Page 45: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 39

(b) FD Fans: - Designed to handle secondary air for boiler. 2 in number and provide ignition

of coal.

Type-axial

Speed-990 rpm

Rating-440 KW

Voltage-6.6 KV

(c)Primary Air Fans: - Designed for handling the atmospheric air up to 50 degrees Celsius, 2

in numberAnd they transfer the powered coal to burners to firing.

Type-Double suction radial

Rating-300 KW

Voltage-6.6 KV

Lubrication-by oil

Type of operation-continuous

7. Coal feed to plant:

Feeder motor specification

(i) Horse power 15 HP

(ii) Voltage 415V, 3 phase

(iii) Speed 1480 rpm

Page 46: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 40

Generator and Auxiliaries

Generator Fundamentals

The transformation of mechanical energy into electrical energy is carried out by the

Generator. This Chapter seeks to provide basic understanding about the working principles

and development of Generator.

Figure 13: CROSS-SECTIONAL VIEW OF A GENERATOR

Working Principle

The A.C. Generator or alternator is based upon the principle of electromagnetic induction

and consists generally of a stationary part called stator and a rotating part called rotor. The

stator housed the armature windings. The rotor houses the field windings. D.C. voltage is

applied to the field windings through slip rings. When the rotor is rotated, the lines of

magnetic flux (i.e. magnetic field) cut through the stator windings. This induces an

electromagnetic force (EMF) in the stator windings. The magnitude of this EMF is given by

the following expression.

E = 4.44 /O FN volts

Page 47: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 41

0 = Stre gth of ag eti field i We er’s.

F = Frequency in cycles per second or Hertz.

N = Number of turns in a coil of stator winding

F = Frequency = P*n/120

Where P = Number of poles

n = revolutions per second of rotor.

From the expression it is clear that for the same frequency, number of poles increases with

decrease in speed and vice versa. Therefore, low speed hydro turbine drives generators

have 14 to 20 poles were as high speed steam turbine driven generators have generally 2

poles.

Figure 14: A 95 MW GENERATOR

Generator component

This deals with the two main components of the Generator viz. Rotor, its winding &

balancing and stator, its frame, core & windings.

Page 48: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 42

Rotor

The electrical rotor is the most difficult part of the generator to design. It revolves in most

modern generators at a speed of 3,000 revolutions per minute. The problem of

guaranteeing the dynamic strength and operating stability of such a rotor is complicated by

the fact that a massive non-uniform shaft subjected to a multiplicity of differential stresses

must operate in oil lubricated sleeve bearings supported by a structure mounted on

foundations all of which possess complex dynamic be behavior peculiar to them. It is also an

electromagnet and to give it the necessary magnetic strength

The windings must carry a fairly high current. The passage of the current through the

windings generates heat but the temperature must not be allowed to become so high,

otherwise difficulties will be experienced with insulation. To keep the temperature down,

the cross section of the conductor could not be increased but this would introduce another

problems. In order to make room for the large conductors, body and this would cause

mechanical weakness. The problem is really to get the maximum amount of copper into the

windings without reducing the mechanical strength. With good design and great care in

construction this can be achieved. The rotor is a cast steel ingot, and it is further forged and

machined. Very often a hole is bored through the centre of the rotor axially from one end of

the other for inspection. Slots are then machined for windings and ventilation.

Rotor winding

Silver bearing copper is used for the winding with mica as the insulation between

conductors. A mechanically strong insulator such as micanite is used for lining the slots.

Later designs of windings for large rotor incorporate combination of hollow conductors with

slots or holes arranged to provide for circulation of the cooling gas through the actual

conductors. When rotating at high speed. Centrifugal force tries to lift the windings out of

the slots and they are contained by wedges. The end rings are secured to a turned recess in

the rotor body, by shrinking or screwing and supported at the other end by fittings carried

Page 49: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 43

by the rotor body. The two ends of windings are connected to slip rings, usually made of

forged steel, and mounted on insulated sleeves.

Stator

Stator frame: The stator is the heaviest load to be transported. The major part of this load is

the stator core. This comprises an inner frame and outer frame. The outer frame is a rigid

fabricated structure of welded steel plates, within this shell is a fixed cage of girder built

circular and axial ribs. The ribs divide the yoke in the compartments through which

hydrogen flows into radial ducts in the stator core and circulate through the gas coolers

housed in the frame. The inner cage is usually fixed in to the yoke by an arrangement of

springs to dampen the double frequency vibrations inherent in 2 pole generators. The end

shields of hydrogen cooled generators must be strong enough to carry shaft seals. In large

generators the frame is constructed as two separate parts. The fabricated inner cage is

inserted in the outer frame after the stator core has been constructed and the winding

completed. Stator core: The stator core is built up from a large number of 'punching" or

sections of thin steel plates. The use of cold rolled grain-oriented steel can contribute to

reduction in the weight of stator core for two main reasons:

a) There is an increase in core stacking factor with improvement in lamination cold Rolling

and in cold buildings techniques.

b) The advantage can be taken of the high magnetic permeance of grain-oriented steels of

work the stator core at comparatively high magnetic saturation without fear or excessive

iron loss of two heavy a demand for excitation ampere turns from the generator rotor.

Stator Windings

Each stator conductor must be capable of carrying the rated current without overheating.

The insulation must be sufficient to prevent leakage currents flowing between the phases to

earth. Windings for the stator are made up from copper strips wound with insulated tape

which is impregnated with varnish, dried under vacuum and hot pressed to form a solid

Page 50: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 44

insulation bar. These bars are then place in the stator slots and held in with wedges to form

the complete winding which is connected together at each end of the core forming the end

turns. These end turns are rigidly braced and packed with blocks of insulation material to

withstand the heavy forces which might result from a short circuit or other fault conditions.

The generator terminals are usually arranged below the stator. On recent generators (210

MW) the windings are made up from copper tubes instead of strips through which water is

circulated for cooling purposes. The water is fed to the windings through plastic tubes.

Generator Cooling System

The 200/210 MW Generator is provided with an efficient cooling system to avoid excessive

heating and consequent wear and tear of its main components during operation. This

Chapter deals with the rotor-hydrogen cooling system and stator water cooling system

along with the shaft sealing and bearing cooling systems.

Rotor Cooling System

The rotor is cooled by means of gap pick-up cooling, wherein the hydrogen gas in the air gap

is sucked through the scoops on the rotor wedges and is directed to flow along the

ventilating canals milled on the sides of the rotor coil, to the bottom of the slot where it

takes a turn and comes out on the similar canal milled on the other side of the rotor coil to

the hot zone of the rotor. Due to the rotation of the rotor, a positive suction as well as

discharge is created due to which a certain quantity of gas flows and cools the rotor. This

method of cooling gives uniform distribution of temperature. Also, this method has an

inherent advantage of eliminating the deformation of copper due to varying temperatures.

Hydrogen Cooling System

Hydrogen is used as a cooling medium in large capacity generator in view of its high heat

arr i g apa it a d lo de sit . But i ie of it’s for i g a e plosi e i ture ith

oxygen, proper arrangement for filling, purging and maintaining its purity inside the

Page 51: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 45

generator have to be made. Also, in order to prevent escape of hydrogen from the

generator casing, shaft sealing system is used to provide oil sealing.

The hydrogen cooling system mainly comprises of a gas control stand, a drier, an liquid level

indicator, hydrogen control panel, gas purity measuring and indicating instruments,

The system is capable of performing the following functions:

I. Filling in and purging of hydrogen safely without bringing in contact with air.

II. Maintaining the gas pressure inside the machine at the desired value at all the times.

III. Provide indication to the operator about the condition of the gas inside the machine

i.e. its pressure, temperature and purity.

IV. Continuous circulation of gas inside the machine through a drier in order to remove

any water vapor that may be present in it.

V. Indication of liquid level in the generator and alarm in case of high level.

Stator Cooling System

The stator winding is cooled by distillate.

Turbo generators require water cooling arrangement over and above the usual hydrogen

cooling arrangement. The stator winding is cooled in this system by circulating

demineralised water (DM water) through hollow conductors. The cooling water used for

cooling stator winding calls for the use of very high quality of cooling water. For this

purpose DM water of proper specific resistance is selected. Generator is to be loaded within

a very short period if the specific resistance of the cooling DM water goes beyond certain

preset values. The system is designed to maintain a constant rate of cooling water flow to

the stator winding at a nominal inlet water temperature of 400C.

Page 52: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 46

Rating of 95 MW Generator-

Manufacture by Bharat heavy electrical Limited (BHEL)

Capacity - 117500 KVA

Voltage - 10500V

Speed - 3000 rpm

Hydrogen - 2.5 Kg/cm2

Power factor - 0.85 (lagging)

Stator current - 6475 A

Frequency - 50 Hz

Stator winding connection - 3 phase

Rating of 210 MW Generator-

Manufacture by Bharat heavy electrical Limited (BHEL)

Capacity - 247000 KVA

Voltage (stator) - 15750 V

Current (stator) - 9050 A

Voltage (rotor) - 310 V

Current (rotor) - 2600 V

Speed - 3000 rpm

Power factor - 0.85

Frequency - 50 Hz

Hydrogen - 3.5 Kg/cm2

Stator winding connection - 3 phase star connection

Page 53: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 47

TRANSFORMER

A transformer is a device that transfers electrical energy from one circuit to another by

magnetic coupling without requiring relative motion between its parts. It usually comprises

two or more coupled windings, and in most cases, a core to concentrate magnetic flux. An

alternating voltage applied to one winding creates a time-varying magnetic flux in the core,

which includes a voltage in the other windings. Varying the relative number of turns

between primary and secondary windings determines the ratio of the input and output

voltages, thus transforming the voltage by stepping it up or down between circuits. By

transforming electrical power to a high-voltage, _low-current form and back again, the

transformer greatly reduces energy losses and so enables the economic transmission of

power over long distances. It has thus shape the electricity supply industry, permitting

generation to be located remotely from point of demand.

FIGURE 15: TRANSFORMER

WORKING PRINCIPLE:

It works on FARADAY‟S LAW OF ELECTROMAGNETIC INDUCTION (self

or mutual induction depending on the type of transformer).

Page 54: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 48

MAIN PARTS

CONSERVATOR

It is used generally to conserve the insulating property of the oil from deterioration&

protect the transformer against failure on account of bad quality of oil.

SILICAGEL DEHYDRATING BREATHER

It is used to prevent entry of moisture inside the transformer tank. The breather

consists of silica gel.

GAS OPERATED RALAY

It is a gas actuated relay used for protecting oil immersed transformer against all

types of faults. It indicates presence of gases in case of some minor fault & take

out the transformer out of circuit in case of serious fault.

BUSHING

It is made from highly insulating material to insulate & to bring out the terminals

of the transformer from the container. The bushings are of 3 types:

a). Porcelain bushings used for low voltage transformer

b). Oil filled bushings used for voltage up to 33KV.

c). Condensed type bushings used for voltage above 33KV

OIL GAUGE

Every transformer with an oil guage to indicate the oil level. The oil guage may be

provided with the alarm contacts which gave an alarm the oil level has dropped

beyond permissible height due to oil leak etc.

TAPPINGS

Page 55: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 49

The transformer are usually provided with few tappings on secondary side so

that output voltage can be varied for constant input voltage.

RADIATOR

It increases the surface area of the tank & more heat is thus radiated in less time.

CONSTRUCTIONAL FEATURES

a) 3 phase transformer is constructed in the core type construction

b) For reducing losses a smaller thickness of lamination is used.

c) For the above reason it is also called cold-rolled steel instead hot-rolled steel is

used.

d) High flux densities (1.4 to 1.7 Wb/sq m) are used in the core of power transformer

which carry load throughout.

e)For high voltage winding, disc type coils are used.

CLASSIFICATION

(I) ACCORDING TO THE CORE

a)Core type transformer

b)Shell type transformer

c)Berry type transformer

(II) ACCORDING TO THE PHASES

a)1phase transformer

b)3phase transformer

COOLING OF TRANSFORMERS :

As size of transformer becomes large, the rate of the oil circulating becomes insufficient

to dissipate all the heat produced & artificial means of increasing the circulation by

electric pumps. In very large transformers, special coolers with water circulation may

have to be employed.

Page 56: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 50

TYPES OF COOLING

AIR COOLING

a) Air Natural

b)Air Forced

OIL IMMERSED COOLING

a) Oil Natural Air Cooling

b)Oil Natural Force Cooling

c)Oil Forced Air Natural Cooling

d) Oil Forced Air Forced Cooling

MAIN PARTS OF TRANSFORMER

1.Primary Winding

2.Secondry Winding

3.Oil Level

4.Conservator

5.Breather

6.Drain Cocks

7.Cooling Tubes

8.Transformer Oil

9.Earth Point

10.Explosion Vent

11.Temperature Gauge

12.Secondary Terminal

13.Primary Terminal

14.Buchholz Relay

Rating of transformer

No load voltage (HV) - 229 KV

Page 57: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 51

No load Voltage (LV) -10.5 KV

Line current (HV) -315.2 A

Line current (LV) - 873.2 A

Temp rise - 45 Celsius

Oil quantity - 40180 lit

Weight of oil - 34985 Kg

Total weight - 147725 Kg

Core & winding - 84325 Kg

Phase -3

Frequency - 50 Hz

INSTRUMENTS SEEN

1. MICROMETER

This instrument is used for measuring inside as well as outside diameter of bearing.

2. MEGGAR

This instrument is used for measuring insulation resistance.

3. VIBRATION TESTER

It measures the vibration of the motor. It is measured in three dimensions-axial, vertical and

horizontal.

POLLUTION CONTROL SYSTEMS:

While deciding the appropriate technology for its projects, NTPC integrates many

environmental provisions into the plant design. In order to ensure that NTPC complies

with all the stipulated environment norms, various state-of-the-art pollution control

Page 58: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 52

systems / devices as discussed below have been installed to control air and water

pollution.

Electrostatic Precipitators:

The ash left behind after combustion of coal is arrested in high efficiency Electrostatic

Precipitators (ESPs) and particulate emission is controlled well within the stipulated

norms. The ash collected in the ESPs is disposed to Ash Ponds in slurry form.

Flue Gas Stacks:

Tall Flue Gas Stacks have been provided for wide dispersion of the gaseous emissions

(SOX, NOX etc.) into the atmosphere.

Low-NOX Burners:

In gas based NTPC power stations, NOX emissions are controlled by provision of Low-

NOX Burners (Dry or wet type) and in coal fired stations, by adopting best combustion

practices.

Neutralization Pits:

Neutralization pits have been provided in the Water Treatment Plant (WTP) for pH

correction of the Effluents before discharge into Effluent Treatment Plant (ETP) for

further treatment and use.

Coal Settling Pits / Oil Settling Pits:

In these Pits, coal dust and oil are removed from the effluents emanating from the Coal

Handling Plant (CHP), coal yard and Fuel Oil Handling areas before discharge into ETP.

DE & DS Systems:

Dust Extraction (DE) and Dust Suppression (DS) systems have been installed in all coal

fired power stations in NTPC to contain and extract the fugitive dust released in the Coal

Handling Plant (CHP).

Page 59: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 53

Cooling Towers:

Cooling Towers have been provided for cooling the hot Condenser cooling water in

closed cycle, Condenser Cooling Water (CCW) Systems. This helps in reduction in

thermal pollution and conservation of fresh water.

Ash Dykes & Ash Disposal systems:

Ash ponds have been provided at all coal based stations except Dadri where Dry Ash

Disposal System has been provided. Ash Ponds have been divided into lagoons and

provided with garlanding arrangement for changeover of the ash slurry feed points for

even filling of the pond and for effective settlement of the ash particles.

Ash in slurry form is discharged into the lagoons where ash particles get settled from the

slurry and clear effluent water is discharged from the ash pond. The discharged effluents

conform to standards specified by CPCB and the same is regularly monitored.

At its Dadri Power Station, NTPC has set up a unique system for dry ash collection and

disposal facility with Ash Mound formation. This has been envisaged for the first time in

Asia which has resulted in progressive development of green belt besides far less

requirement of land and less water requirement as compared to the wet ash disposal

system.

Ash Water Recycling System:

Further, in a number of NTPC stations, as a proactive measure, Ash Water Recycling

System (AWRS) has been provided. In the AWRS, the effluent from ash pond is

circulated back to the station for further ash sluicing to the ash pond. This helps in

savings of fresh water requirements for transportation of ash from the plant.

The ash water recycling system has already been installed and is in operation at

Ramagundam, Simhadri, Rihand, Talcher Kaniha, Talcher Thermal, Kahalgaon, Korba

and Vindhyachal. The scheme has helped stations to save huge quantity of fresh water

required as make-up water for disposal of ash.

Liquid Waste Treatment Plants & Management System:

Page 60: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 54

The objective of industrial liquid effluent treatment plant (ETP) is to discharge lesser and

cleaner effluent from the power plants to meet environmental regulations. After primary

treatment at the source of their generation, the effluents are sent to the ETP for further

treatment. The composite liquid effluent treatment plant has been designed to treat all

liquid effluents which originate within the power station e.g. Water Treatment Plant

(WTP), Condensate Polishing Unit (CPU) effluent, Coal Handling Plant (CHP) effluent,

floor washings, service water drains etc. The scheme involves collection of various

effluents and their appropriate treatment centrally and re-circulation of the treated

effluent for various plant uses.

NTPC has implemented such systems in a number of its power stations such as

Ramagundam, Simhadri, Kayamkulam, Singrauli, Rihand, Vindhyachal, Korba, Jhanor

Gandhar, Faridabad, Farakka, Kahalgaon and Talcher Kaniha. These plants have helped

to control quality and quantity of the effluents discharged from the stations.

Sewage Treatment Plants & Facilities:

Sewage Treatment Plants (STPs) sewage treatment facilities have been provided at all

NTPC stations to take care of Sewage Effluent from Plant and township areas. In a

number of NTPC projects modern type STPs with Clarifloculators, Mechanical Agitators,

sludge drying beds, Gas Collection Chambers etc. have been provided to improve the

effluent quality. The effluent quality is monitored regularly and treated effluent

conforming to the prescribed limit is discharged from the station. At several stations

treated effluents of STPs are being used for horticulture purpose.

CONTROL & MONITORING MECHANISMS

SOLUTION TO THE PROBLEMS

There are basically two types of Problems faced in a Power Plant

1. Metallurgical

2. Mechanical

Page 61: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 55

Mechanical Problem can be related to Turbines that is the max speed permissible for a

turbine is3000 rpm so speed should be monitored and maintained at that level.

Metallurgical Problem can be view as the max Inlet Temperature for Turbine is 1060°

C so temperature should be below the limit. Monitoring of all the parameters is necessary

for the safety of both:

1. Employees

2. Machines

So the Parameters to be monitored are

1. Speed

2. Temperature

3. Current

4. Voltage

5. Pressure

6. Eccentricity

7. Flow of Gases

8. Vacuum Pressure

9. Valves

10. Level

11. Vibration

Page 62: Vikas

Industrial Training Report 2016

APPLIED COLLEGE OF MANAGEMENT AND ENGINEERING Page 56

REFERNCES

1.Library of BTPS

2.Supporting Staff

3.Books