VIGO, 28 – LEIXOES, 29 junio de 2007
The role of TEN-T on the new Transport Infrastructure
[TEN-T 2007-2013]
Jose AnselmoTEN Transport Project Management
DG TREN
VIGO, 28 – LEIXOES, 29 junio de 2007
The Trans-European Network (TEN) is guided by the:
• TEN Regulation: Regulation (EC) No 680/2007 of the European Parliament and of the Council of 20 June 2007 laying down general rules for the granting of Community financial aid in the field of the trans-European transport and energy networks
• TEN-T Guidelines: Decision 1692/96/EC on Community guidelines for the development of the trans-European transport network (as last amended by Decision 884/2004/EC)
VIGO, 28 – LEIXOES, 29 junio de 2007
State of Play
TEN Regulation (Regulation (EC) No 680/2007) :
• Council Common Position adopted on 22 March
• European Parliament voted on the 23rd of May 2007
• Published in the Official Journal and entry into force expected early July
VIGO, 28 – LEIXOES, 29 junio de 2007
Key New Elements
• Higher level of funding for cross-border sections
• New funding possibilities for PPP projects• Stronger and clearer basis for
concentration of funding• Multi-annual commitments
VIGO, 28 – LEIXOES, 29 junio de 2007
Eligibility
• “Projects of common interest”• Compliance of applications with
Community law• Commitment to make a financial contribution• Cross-border section criteria• Member State agreement
VIGO, 28 – LEIXOES, 29 junio de 2007
Project Selection Criteria I
• Priority projects
• Bottlenecks
• Joint submissions, especially for cross-border sections
• Continuity and capacity optimisation
• Service quality (including interoperability)
VIGO, 28 – LEIXOES, 29 junio de 2007
Project Selection Criteria II
• Traffic management systems in all modes
• Modal balance, especially inland waterways
• Single market
VIGO, 28 – LEIXOES, 29 junio de 2007
Project Selection Criteria III
Decision takes into account:• Project maturity• “Additionality” of EU funding• Financial soundness• Socio-economic effects• Environmental consequences• Financial obstacles• Project complexity, e.g. crossing natural barriers
VIGO, 28 – LEIXOES, 29 junio de 2007
Types of Aid
• Grants for studies and works• Grants for works under availability payment
schemes NEW• Interest rate rebates• Loan Guarantee Instrument NEW• Risk capital participation• Project activities of joint undertakings
VIGO, 28 – LEIXOES, 29 junio de 2007
Maximum Volume of Aid I
• For studies, 50% of eligible cost
• For works:– For priority projects, 20%– For cross-border sections on priority projects,
30%– For other projects, 10%
VIGO, 28 – LEIXOES, 29 junio de 2007
• For ERTMS:– For trackside equipment, 50% for studies and
works– For on-board equipment,
• 50% of development and manufacture costs of prototypes for retrofitting, subject to dual certification
• 50% of cost of series equipment for installation, with a ceiling on aid per traction unit
• For traffic management, 20%
VIGO, 28 – LEIXOES, 29 junio de 2007
Other Funding
• EIB funding is compatible with funding under the TEN-T programme
• Commission to ensure non-cumulation of other EU funds with TEN-T funds
VIGO, 28 – LEIXOES, 29 junio de 2007
Work Programmes
• 80-85% of budget goes to Multi-Annual Work Programme (MWP)
• MWP covers priority projects and traffic management systems
• Annual Work Programme (AWP) funds projects of common interest not included in the MWP
• Mid-term review (and possible revision) of MWP
VIGO, 28 – LEIXOES, 29 junio de 2007
Calls for Proposals
• First calls: May 25-July 20 2007– MWP 2007-2013:
• Priority Projects• SESAR• ITS Road• ERTMS
– AWP 2007
VIGO, 28 – LEIXOES, 29 junio de 2007
Other Issues I
• Commission decision• Annual instalments, pluri-annual commitments,
multi-annual indicative commitments• Project-related expenditure/eligibility date• Progressive payments• Availability payments• Community law and Community policies
VIGO, 28 – LEIXOES, 29 junio de 2007
• Cancellation or suspension conditions• Audits• Financing Committee• EP “droit de regard”• Evaluation• Reporting and publicity• TEN-T Executive Agency
VIGO, 28 – LEIXOES, 29 junio de 2007
The Budget 2007-2013
• €8 013 million for TEN-T projects– 2007: €831 M– 2008: €950 M– 2009: €1 029 M– 2010: €1 062 M– 2011: €1 242 M– 2012: €1 357 M– 2013: €1 541 M
VIGO, 28 – LEIXOES, 29 junio de 2007
Budget ressources
• Multi-annual Work Programme– Field n°1 « Priority Projects »: 6,81105 billion €– Field n°2 « SESAR »: 350 million €– Field n°3 « ITS Road »: 300 million €– Field n°4 « ERTMS »: 500 million €
• Annual Work Programme 2007: 112.607.450€
VIGO, 28 – LEIXOES, 29 junio de 2007
Budget ressources• Multi-annual Work Programme (cont.)
– Field n° 5 « RIS (River Information Services) »:
50 million €– Field n° 6 « MOS » PP21 Motorways of the Sea:
310 million €
VIGO, 28 – LEIXOES, 29 junio de 2007
2007-13 Several Calls• Multi-annual Work Programme
– Field n°1 « Priority Projects »: 1 Call in 2007– Field n°2 « SESAR »: 1 Call in 2007– Field n°3 « ITS Road »: 3 Calls in - 2007, 2009,
and 2011– Field n°4 « ERTMS »: 2 Calls - in 2007 and
2008
VIGO, 28 – LEIXOES, 29 junio de 2007
2007-13 Several Calls• Multi-annual Work Programme (cont.)
– Field n° 5 « RIS (River Information Services) »: 3 Calls = in 2007 (Dec.), 2009 and 2010
– Field n° 6 « MOS » PP21 Motorways of the Sea: 6 Calls from 2007(Dec.) to 2012 (one every year)