Top Banner
COMPLIANCE REPORT FOR COMMERCIAL PROJECT LOCATED IN REVENUE ESTATE OF VILLAGE BAJGHERA, SECTOR-114, GURGAON, HARYANA BY M/s CHINTELS INFRACON (A) HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE REF. LETTER NO. SEIAA/HR/2013/149 DATED 28.05.2013 Sl. No. Conditions Status of Compliance PART A - SPECIFIC CONDITIONS: Construction Phase:- 1. “Consent for Establishment” shall be obtained from Haryana State Pollution Control Board Under Air and Water act and a copy shall be submitted to the SEIAA, Haryana before the start of any construction work at site. Agreed. “Consent to Establishment” has been obtained from the Haryana State Pollution Control Board under Air and Water act. Copy of CTE is enclosed as Annexure –I. 2. A first aid room as proposed in the project report will be provided in both during construction and operation phase of the project. Agreed. First aid room has been provided during construction phase and same will also be managed during operational phase. 3. Adequate drinking water and sanitary facilities should be provided for construction workers at the site. Provision Agreed. An adequate drinking water facility and community toilet has been provided for construction
44

nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

May 01, 2018

Download

Documents

ngohanh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

COMPLIANCE REPORT FOR COMMERCIAL PROJECT LOCATED IN REVENUE

ESTATE OF VILLAGE BAJGHERA, SECTOR-114, GURGAON, HARYANA BY

M/s CHINTELS INFRACON

(A) HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE REF. LETTER NO. SEIAA/HR/2013/149 DATED 28.05.2013

Sl. No. Conditions Status of Compliance

PART A - SPECIFIC CONDITIONS: Construction Phase:-

1. “Consent for Establishment” shall be obtained

from Haryana State Pollution Control Board

Under Air and Water act and a copy shall be

submitted to the SEIAA, Haryana before the

start of any construction work at site.

Agreed. “Consent to Establishment” has

been obtained from the Haryana State

Pollution Control Board under Air and

Water act. Copy of CTE is enclosed as

Annexure –I.

2. A first aid room as proposed in the project

report will be provided in both during

construction and operation phase of the

project.

Agreed. First aid room has been

provided during construction phase and

same will also be managed during

operational phase.

3. Adequate drinking water and sanitary facilities

should be provided for construction workers at

the site. Provision should be made for mobile

toilets. Open defecation by the labors is

strictly prohibited. The safe disposal of waste

water and solid wastes generated during the

construction phase should be ensured.

Agreed. An adequate drinking water

facility and community toilet has been

provided for construction workers at the

site. Open defecation by the labors has

been strictly prohibited. The wastewater

generated during construction phase is

being sent to septic tanks.

Left over cement and mortars, cement

concrete blocks, aggregate, sand and

other inorganic material will be recycled

and reused as granular subbase (GSB)

layer of pavement.

Page 2: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

4. All the top soil excavated during construction

activities should be stored for use in

horticulture/landscape development within the

project site.

Agreed, The top soil excavated during

construction activities is being stored

and will be utilized in horticulture/

landscape developments within the

project site. The remaining excavated

soil had been utilized in re-filling of

foundation, road works, rising of site

level etc.

5. The project proponent shall ensure that the

building material required during construction

phase is properly stored with in the project

area and disposal of construction waste should

not create any adverse effect on the

neighboring communities and should be

disposed of after taking necessary precautions

for general safety and health aspects of people,

only in approved sites with the approval of

competent authority.

Agreed, The building material required

during construction phase have been

properly stored within the project area

and disposal of construction waste does

not create any adverse effects on the

neighboring communities and is being

disposed off by taking the necessary

precautions for general safety and health

aspects of people, only in approved sites

with the approval of competent

authority.

6. Construction spoils, including bituminous

material and other hazardous materials, must

not be allowed to contaminate watercourses

and the dump sites for such material must be

secured so that they should not leach into the

ground water and any hazardous waste

generated during construction phase, should be

disposed off as per applicable rules and norms

with necessary approval of the Haryana State

Pollution Control Board.

Agreed, Construction spoils including

bituminous material and other hazardous

materials will not being allowed to

contaminate water courses and the dump

sites for such material will be secured so

that they should not leach into the

ground water. Materials will be disposed

off as per applicable rules and norms

with necessary approval of the Haryana

State Pollution Control Board.

7. The diesel generator sets to be used during

construction phase should be low sulphur

Agreed. During construction phase, DG

sets has been used for office lighting and

Page 3: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

diesel type and should conform to

Environment (Protection) Rules prescribed for

air and noise emission standards.

site lightning. DG sets has been enclosed

with acoustic enclosure. They are running

on low sulphur diesel only with the

provision of air and noise emission

standards as per EPA Rules, 1986.

8. The diesel required for operating DG sets shall

be stored in underground tanks and if required,

clearance from Chief Controller of Explosives

shall be taken.

Agreed. The diesel required for

operating DG set has been stored in

HDPE Drums and log books has been

maintained adequately.

9. Ambient noise levels should conform to

residential standards both during day and

night. Incremental pollution loads on the

ambient air and noise quality should be closely

monitored during construction phase.

Adequate measures should be taken to reduce

ambient air and noise level during construction

phase, so as to conform to the stipulated

residential standards.

Agreed, ambient noise levels conform

to standards both during day and night.

The silent type DG set with acoustic

enclosures has been installed at project

site and office.

Low sulphur fuel is being used

Exhaust is conforming to the

provisions of Environment

(Protection) Rules prescribed for air

and noise emission standards.

All vehicles entering to the site were

with valid PUC certificate.

All machinery used at the site is new

and periodic maintenance of the

machinery insured.

Results of the environmental

monitoring carried out at the site are

enclosed as Annexure – II

Shelter belt will be provided to reduce

the noise level within the site.

10. Fly ash should be used as building material in

the construction as per the provisions of Fly

Block work bricks are used as building

material. As the bricks contain low

Page 4: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

Ash Notification of September, 1999 and

amended as on 27th August, 2003

density that makes it low in Thermal

Conductivity, these bricks act as thermal

Insulators which resist the building for

being heating.

11. Storm water control and its re-use as per

CGWB and BIS standards for various

applications should be ensured.

Agreed. Storm water control and its

reuse will be maintained as per Central

Ground Water Board and BIS standards

for various applications.

12. Water demand during construction should be

reduced by use of premixed concrete, curing

agents and other best practices referred.

Water demand during construction has

been reduced by the practice of using

premixed concrete, curing agents and

other best practices.

13. In view of severe constrains in water supply

augmentation in the region and sustainability

of water resources, the developer will submit

the NOC from CGWA specifying water

extraction quantities and assurance from

HUDA / utility provider indicating source of

water supply and quantity of water with details

of intended use of water potable and non-

potable. Assurance is required for both

construction and operation stages separately. It

shall be submitted to the SEIAA/ R.O. MoEF,

Chandigarh before the start of construction.

Agreed. Ground water will not be

extracted for the purpose of construction

as well as for operation phase of the

project. Water is being supplied by

HUDA during construction and same

will be during Operational phase.

Application has been filled to HUDA for

water supply during construction &

operational phase, the copy of same is

enclosed as Annexure- III (a) & (b).

14. Roof should meet prescriptive requirement as

per Energy Conservation Building Code by

using appropriate thermal insulation material

to fulfill requirement.

Agreed. Roof will be thermal insulated

as per the Energy Conservation Building

Code.

15. Opaque wall should meet prescriptive

requirement as per Energy Conservation

Building Code which is proposed to be

Agreed. Opaque wall will be thermal

insulated as per the Energy Conservation

Building Code.

Page 5: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

mandatory for all air conditioned spaces while

it is inspirational for non-air-conditioned

spaces by use of appropriate thermal insulation

material to fulfill requirement.

16. The approval of the competent authority shall

be obtained for structural safety of the

building on account of earthquake, adequacy

of firefighting equipment, etc. as per National

Building Code including protection measures

from lightening etc. If any forestland is

involved in the proposed site, clearance under

Forest Conservation Act shall be taken from

the competent Authority.

Agreed. The approval of competent

authority will be taken for structural

safety of the building due to earthquake,

adequacy of firefighting equipment etc.

as per National Building Code including

protection measures from lightening etc.

Project site does not fall in Forest land

area. NOC Application has been filled to

DC for Aravalli clearance; copy of the

same is enclosed as Annexure-IV.

17. Overexploited groundwater and impending

severe shortage of water supply in the region

requires the developer to redraw the water and

energy conservation plan. Developer shall

submit details of good practices that have been

included in the project to reduce the overall

footprint of the proposed development

including a detailed water balance along with

source and quantities of potable and non

potable water requirement (including water

requirement during construction phase)

incorporating water efficiency / Saving

measures as well as water reuse/ recycling

within 3 months to the SEIAA, Haryana and

R.O. MoEF, GOI Chandigarh before the start

of construction.

Agreed, No ground water extraction will

take place. However, treated water for

construction is being supplied by

HUDA. To reduce the demand in

operation phase, treated water from STP

will be used for horticulture, flushing,

cooling, rest will be used in nearby

construction site. As well as efficient

fixtures will be used to minimize the

water demand for domestic purpose.

18. The project proponent shall construct 03 Nos. Agreed. 03 rain water harvesting pits

Page 6: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

rain water harvesting pits for recharging the

ground water within the project premises. Rain

Water harvesting pits shall be designed to

make provisions for silting chamber and

removal of floating matter before entering

harvesting pit, peak rain fall intensity of

45mm/hr must be kept in mind while

redesigning RWH pit. Maintenance budget

and persons responsible for maintenance must

be provided. Care shall also be taken that

contaminated water do not enter any RWH pit.

will be provided for recharging the

ground water within the project

premises. To remove silt and floating

matter, desilting chamber will be

proposed with rain water harvesting pits.

Care will be taken that contaminated

water will not be entered in any of RWH

pits. RWH plan with showing the storm

water line and RWH pit is enclosed as

Annexure-V.

19. The Project Proponent shall provide minimum

one Hydraulic ladder of sufficient length for

escape of people in case of fire.

Maximum height of the building will be

59.70 m. Maximum height upto which

hydraulic ladder can be provided is 12 m

so, permanent ladder will be provided

instead of hydraulic ladder.

20. The project proponent shall submit assurance

from the DHBVN for supply of 1672 kVA of

power supply before the start of construction.

In no case project will be operational solely on

generators without any power supply from any

external power utility.

Agreed. Application has been filed to

HVPNL for supply of electricity; copy

of the same is enclosed as Annexure-

VI.

21. Detail calculation of power load and ultimate

power load of the project shall be submitted to

DHBVN under intimation to SEIAA, Haryana

before the start of construction provision shall

be made for electrical infrastructure in the

licensed area.

Agreed. Detail calculation of power load

and ultimate power load of the project

has been submitted to HVPNL,

Application has been filled to HVPNL;

copy of the same is enclosed as

Annexure-VI.

22. The project proponent shall obtain NOC from

nearest fire station before the start of

construction.

Agreed. Fire NOC will be obtained from

the nearest fire station.

Page 7: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

23. The Project proponent shall not raise any

construction in the natural land depression/

Nallah/ Water course and shall ensure that the

natural flow from the Nallah/ Water course is

not obstructed.

Agreed, the project site does not contain

any natural land depression nallah/ water

course as well as no natural flow will be

obstructed by the project.

24. The project proponent shall keep the plinth

level of the building blocks sufficiently above

the level of the approach road to the Group

Housing Project as per prescribed bye laws.

Levels of the other areas in the Group Housing

Projects shall also be kept suitably so as to

avoid flooding.

Agreed, The plinth level of the building

block will be above the level of the

approach road as per the prescribed bye

laws. Levels will be suitably maintained

to avoid flooding.

25. Construction shall be carried out so that

density of population does not exceed as

approved by Director General Town and

Country Department Haryana.

Agreed, population density will be as per

the approved Building plan by Director

General Town and Country Department,

Haryana.

26. The Project proponent shall submit an

affidavit with the declaration that ground

water will not be used for construction and

only treated water should be used for

construction.

Agreed, Ground water will not be used

for the construction activity. No ground

water is being extracted during

construction phase; affidavit for the

same has already been submitted.

27. The project proponent shall not cut any

existing tree and project landscaping plan

should be modified to include those trees in

green area.

There is no need to cut the trees. Only

small bushes clearing were required

during the construction activity.

28. The project proponent shall provide helipad

facility as required under NBC norms and

shall seek permission of helipad from AAI

accordingly.

Agreed. Maximum height of the

building will be 59.70 m. So, there is no

need to provide Helipad facility

29. The project proponent shall ensure that ECBC

norms for composite climate zone are met. In

Agreed, ECBC norms for composite

climate zone, water heating, pumping,

Page 8: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

Particular building envelope, HVAC service

water heating, pumping, lighting and electrical

infrastructure must meet ECBC norms.

lighting and electrical infrastructure

have been followed.

30. The PP shall provide 3 meter high barricade

around the project area, dust screen for every

floor above the ground, proper sprinkling and

covering of stored material to restrict dust and

air pollution during construction.

Agreed, 3 meter high barricade around

the project area and dust screen has been

installed during construction.

31. The project proponent shall construct a

sedimentation basin in lower level of project

site to trap pollutants and other waste during

rain.

Agreed. Sedimentation basin has been

constructed to trap pollutants and other

waste during rain.

32. The project proponent shall provide proper

Rasta of proper width and proper strength for

each project before the start of construction.

Agreed. Proper Rasta of proper width

and proper strength has been provided.

33. The window wall ratio of the construction

project should not exceed 40%.

Agreed. The window wall ratio of the

construction project will not be exceeded

40%.

34. The project proponent shall keep the plinth

level of the building above the HFL of the said

Najafgarh Jheel/drain attained in the last 100

years.

Agreed, plinth level of the building has

been kept higher than the HFL of the

Najafgarh Jheel/drain i.e. 213.575 m

attained in the last 100 years.

35. The project proponent shall obtain NOC from

HUDA as well as Irrigation Department before

the start of construction, regarding possible

adverse effect of project proposal on the said

Najafgarh Jheel.

Agreed. The application will be filled to

HUDA as well as irrigation department

regarding possible adverse effect of

project on the said Najafgarh Jheel.

36. The project proponent shall provide all the

safety measures for the workers during

construction phase of high rise building.

Agreed. Safety measures for the workers

during construction phase are being

provided.

37. The project proponent shall use better U-Value Agreed.

Page 9: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

glass.

38. The project proponent shall obtain NOC from

AAI before the start of construction.

Agreed. NOC from AAI has been

obtained and is enclosed as Annexure-

VII.

39. The project proponent shall not restrict the

village Rasta and shall provide Rasta of proper

width

Agreed. The PP will not restrict the

village Rasta and also has been provided

Rasta of proper width.

PART A- SPECIFIC CONDITIONS : Operation Phase

a) “Consent to operate” shall be obtained from

Haryana State Pollution Control Board under

Air and water Act and a copy shall be

submitted to the SEIAA. Haryana.

Agreed. “Consent to operate” will be

obtained from Haryana State Pollution

Control Board under Air and water Act.

b) The Sewage Treatment Plant (STP) shall be

installed for the treatment of the sewage to be

prescribed standards including odour and

treated effluent will be recycled to achieve

zero exit discharge. The installation of STP

should be certified by an independent expert

and a report in this regard should be submitted

to the SEIAA, Haryana before the project is

commissioned for operation. Tertiary

treatment of waste water is mandatory.

Discharge of treated sewage shall conform to

the norms and standards of HSPCB,

Panchkula.

Agreed, The Sewage Treatment Plant

(STP) will be installed for the treatment

of the sewage to the prescribed standards

including odour and treated effluent will

be recycled and used for flushing,

cooling, and rest will be used in nearby

construction site. Report of installation

of STP will be submitted to the SEIAA,

Haryana before the project is

commissioned for operation. Discharge

of effluent will be conforming to the

norms and standards of HSPCB,

Panchkula.

c) Separation of the grey and black water should

be done by the use of dual plumbing line.

Treatment of 100% grey water by

decentralized treatment should be done

ensuring that the recirculated water should

have BOD maximum upto 10 ppm and the

Agreed, grey and black water will be

separated by the use of dual plumbing

line. Agreed, recycled water will be used

for flushing, gardening, cooling and rest

will be used for nearby construction site.

Dual plumbing plan is enclosed as

Page 10: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

recycled water will be used for flushing,

gardening and DG set cooling and running of

fountain in the water body to achieve zero exit

discharge.

Annexure-VIII.

d) For disinfection of the treated waste water

ultra violet radiation or ozonization process

should be used.

Agreed, for disinfection of the treated

wastewater, ultra violet radiation process

will be used.

e) The solid waste generated should be properly

collected and segregated. Bio degradable

waste shall be decomposed at site and dry/

inert solid waste should be disposed off to

approved sites for land filling after recovering

recyclable material.

Agreed. The solid waste generated will

be properly collected and segregated.

Bio-degradable waste will be

decomposed at site by composting and

used as manure, dry/inert solid waste

will be disposed off in MSW disposal

site. Solid waste management plan is

enclosed as Annexure – IX.

f) Diesel Power generating sets proposed as

source of backup power for lifts, common area

illumination and for domestic use should be of

enclosed type and conform to rules made

under the Environment (Protection) Act, 1986.

The location of the DG sets should be in the

basement as promised by the project

proponent with appropriate stack height i.e.

above the roof level as per the CPCB norms.

The diesel used for DG sets should be of low

sulphur contents (maximum upto 0.25%)

Agreed. The location of DG sets will be

in basement and conform to rules made

under the Environment (Protection) Act,

1986. The diesel used for DG sets will

be of low sulphur contents (maximum

up to 0.25%).

g) Ambient Noise Level should be controlled to

ensure that it does not exceed the prescribed

standards both within and at the boundary of

the proposed residential complex.

Agreed. The Ambient noise level will be

controlled that it does not exceed the

prescribed standards both within and at

the boundary of the project.

h) The project proponent should maintain at least Agreed. The project proponent is

Page 11: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

38.35% as green cover area for tree plantation

especially all around the periphery of the

project and on the road sides preferably with

local species so as to provide protection

against particulates and noise. The 10% open

spaces inside the plot should be preferably

landscaped and covered with vegetation/grass,

Herbs& shrubs Only local available plant

species shall be used.

maintaining at least 38.35% as green

cover area for tree plantation especially

all around the periphery of the project

and on the road sides preferably with

local species so as to provide protection

against particulates and noise. The open

spaces inside the plot will be preferably

landscape and covered with

vegetation/glass. Landscape Plan is

attached as Annexure-X.

i) The project proponent shall strive to minimize

water in irrigation of landscape by minimizing

grass area, using native variety, xeriscaping

and mulching, utilizing efficient irrigation

system, scheduling irrigation only after

checking evapo-transpiration data.

Agreed. The PP will minimize water in

irrigation of landscape by minimizing

grass area, using native variety,

xeriscaping and mulching, utilizing

efficient irrigation system, scheduling

irrigation only after checking evapo-

transpiration data.

j) Rain water harvesting for roof runoff and

surface runoff, as per plan submitted should be

implemented. Before recharging the surface

runoff, pre-treatment through sedimentation

tanks must be done to remove suspended

matter, oil and grease. The bore well for rain

water recharging shall be kept at least 5 m

above the highest ground water table. Care

shall be taken that contaminated water do not

enter any RWH pit.

Rainwater harvesting as per plan for roof

run-off and surface run-off will be

implemented. Suspended matter, oil and

grease will be removed by treatment

before recharging with surface run-off.

The bore well for recharge will be kept

at least 5 m above the highest ground

water table. Rain water Harvesting Plan

is enclosed as Annexure-V.

k) The ground water level and its quality should

be monitored regularly in consultation with

Central Ground Water Authority.

Agreed. Ground water level and its

quality will be monitored regularly in

consultation with Central Ground Water

Authority, if required.

Page 12: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

l) There should be no traffic congestion near the

entry and exist points from the roads adjoining

the proposed project site. Parking should be

fully internalized and no public space should

be utilized.

Agreed. Parking will be completely

internalized and no public space will be

utilized. Care will be taken to ensure that

there will be no traffic congestion at the

entry and exit points. Traffic circulation

plan is enclosed as Annexure-XI.

m) A report on the energy conservation measures

conforming to energy conservation norms

finalize by Bureau of Energy Efficiency

should be prepared incorporating details about

building materials & technology; R & U

factors etc. and submit to the SEIAA, Haryana

in three months’ time.

Agreed. Report on energy conservation

measure conforming to energy

conservation norms finalized by BEE

which will include details of building

materials and technology, R & U factors

etc. will be submitted to the SEIAA,

Haryana within three months’ time.

n) Energy conservation measures like installation

of CFLs/TFLs for lighting the areas outside

the building should be integral part of the

project design and should be in place before

project commissioning. Used CFLs and TFLs

should be properly collected and disposed

off/sent for recycling as per the prevailing

guidelines/rules of the regulatory authority to

avoid mercury contamination. Use of solar

panels must be adapted to the maximum extent

possible for energy conservation.

Agreed. CFL light will be used in

common areas like lift, corridors,

staircase and service areas. CFLs will be

properly collected and disposed off/sent

for recycling as per the prevailing

guidelines/rules of the regulatory

authority to avoid mercury

contamination. Use of solar panels will

be adapted to the maximum extent

possible for energy conservation.

o) The project proponent shall use zero ozone

depleting potential material in insulation,

refrigeration, air-conditioning. PP shall also

provide Halon free fire suppression system.

Agreed. The PP will use zero ozone

depleting potential material in insulation,

refrigeration, air-conditioning and also

provide Halon free fire suppression

system.

p) The solid waste generated should be properly

collected and segregated as per the

Agreed, The solid waste generated will

be collected and segregated as per the

Page 13: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

requirement of the MSW Rules, 2000 and as

amended from time to time. The bio-

degradable waste should be composted by

vermicomposting at the site earmarked within

the project area and dry/inert solid waste

should be disposed off to the approved sites

for land filling after recovering recyclable

material.

requirement of the MSW Rules, 2000.

The bio-degradable waste will be

composted at the site earmarked within

the project area and dry/inert solid waste

will be disposed off to the approved sites

for land filling after recovering

recyclable material. Solid waste

management plan is enclosed as

Annexure IX.

q) The provision of the solar water heating

system shall be as per norms specified by

HAREDA and shall be made operational in

each building block.

Agreed. Provision of the solar water

heating system will be as per norms

specified by HAREDA and will be made

operational in open spaces and signage.

r) The traffic plan and the parking plan proposed

by the PP should be adhered to meticulously

with further scope of additional parking for

future requirement. There should be no traffic

congestion near the entry and exit points from

the roads adjoining the proposed project site.

Parking should be fully internalized and no

public space should be used.

Agreed. The traffic plan and the parking

plan will be adhered with further scope

of additional parking for future

requirement. Parking will be fully

internalized and no public space will be

used. Traffic circulation plan is enclosed

as Annexure-XI.

s) The project shall be operationalized only once

HUDA will provide domestic water supply

system in the area.

Agreed. Project will be operationalized

once HUDA will provide domestic water

supply system in the area.

t) Operation and maintenance of STP, solid

waste management and electrical

infrastructure shall be ensured even after the

completion of sell.

Agreed. Operation and maintenance of

STP, solid waste management and

electrical infrastructure will be

maintained by the Environment

Management Cell.

u) Different type of wastes should be disposed

off as per provisions of municipal solid waste,

Agreed. Municipal solid waste will be

disposed as per the Municipal Solid

Page 14: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

biomedical waste, hazardous waste, e waste,

batteries & plastic rules made under

Environment Protection Act, 1986.

Particularly E-waste and Battery waste shall

be disposed of as per existing E-waste

Management Rules 2011 and Batteries

Management Rules 2001. The project

proponent should maintain a collection center

for E-waste and it should be disposed of to

only registered and authorized

dismantler/recycler.

Wastes (Management and Handling)

Rules, 2000. Biomedical waste will not

be generated by the project. Hazardous

wastes will be handled as per the

Hazardous Waste (Management and

Handling) Rules, 2000. E-waste will be

taken care as per E waste (management

and Handling) Rules, 2011 and Plastic

waste will be handled as per the Plastic

waste (Management and Handling)

Rules, 2011.

v) Standards for discharge of environment

pollutants as enshrined in various schedule of

rule 3 of Environment Protection Rule 1986

shall be strictly complied with.

Agreed. All the required standard

discharge will be followed for discharge

of environment pollutants as enshrined

in various schedule of rule 3 of

Environment Protection Rules, 1986.

w) The project proponent shall make provision

for guard pond and other provisions for safety

against failure in the operation of wastewater

treatment facilities. The project proponent

shall also identify acceptable outfall for treated

effluent.

Agreed, guard pond and safety against

failure in the operation of wastewater

treatment facilities will be provided. The

project proponent will also identify

acceptable outfall for treated effluent.

x) The project proponent shall ensure that the

emission standards of noise and air with in the

CPCB prescribed limits. Noise and Emission

level of DG sets greater than 800 Kva shall be

as per as CPCB latest standards for high

capacity DG sets.

Agreed. Noise and Air Emission will be

as per as CPCB latest standards.

y) The project proponent should strive to

maintain the power factor between 0.98 to 1.0

in order to conserve energy.

Agreed. Power factor will be maintained

between 0.98 to 1.0 in order to conserve

energy.

Page 15: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

PART-B GENERAL CONDITIONS

I The Project proponent shall ensure the

commitments made in Form-1, Form-1A,

EIA/EMP and other documents submitted to

the SEIAA for the protection of environment

and proposed environmental safeguards are

complied with in letter and spirit.

Agreed. All safeguards mentioned in the

Application are implemented during the

construction phase and will be

implemented to the maximum possible

extent.

II Six monthly compliance reports should be

submitted to the Haryana State Pollution

Control Board and Regional Office, MOEF,

GOI, Northern Region, Chandigarh and a copy

to the Regulatory Authority of Haryana.

Agreed. Six monthly compliance reports

are being submitted to Haryana State

Pollution Control Board and Regional

Office, MOEF, GOI, Northern Region,

Chandigarh and a copy to the Regulatory

Authority of Haryana.

Acknowledgement copies of previously

submitted compliance report are

attached as Annexure-XII.

III The SEIAA, Haryana reserves the right to add

additional safeguard measure subsequently, if

found necessary. Environmental Clearance

granted will be revoked if it is found that false

information has been given for getting

approval of this project. SEIAA reserves the

right to revoke the clearance if conditions

stipulated are not implemented to the

satisfaction of SEIAA/MoEF.

Agreed, The SEIAA Haryana reserves

the right to add additional safeguard

measure subsequently, if found

necessary.

IV The Project proponent will not violate any

judicial orders/ pronouncements issued by the

Hon’ble Supreme Court/High Courts.

Agreed. There will be no violation of

any judicial order/ pronouncements

issued by the Hon’ble Supreme

Court/High Courts.

V All other statutory clearances such as the

approvals for storage of diesel from Chief

Agreed, all the required applicable

clearance will be obtained from the

Page 16: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

Controller of Explosives, Fire Department,

Civil Aviation Department, Forest

Conservation Act, 1980 and Wildlife

(Protection) Act, 1972, PLPA, 1900, Forest

Act, 1927 etc. shall be obtained, as applicable

by project proponents from the respective

authorities prior to construction of the project

respective authority. AAI NOC and

Aravalli NOC are enclosed as

Annexure- VII & IV respectively.

VI The project proponent should inform the

public that the project has been accorded

Environment Clearance by the SEIAA and

copies of the clearance letter are available with

the State Pollution Control Board & SEIAA.

This should be advertised within 7 days from

the date of issue of the clearance letter at least

in two local newspaper that are widely

circulated in the region and the copy of the

same should be forwarded to SEIAA,

Haryana. A copy of Environment Clearance

Conditions shall also be put on project

proponent web site for public awareness.

Agreed, Advertisement has been given

in the local newspaper informing to

public that Environment clearance has

been obtained.

VII Any appeal against this Environment

Clearance shall lie with the National Green

Tribunal, if preferred, within a period of 30

days as prescribed under Section 16 of the

National Green Tribunal Act, 2010.

Not applicable.

VIII The project proponent shall put in place

Corporate Environment Policy as mentioned

in MoEF, GOI OM No. J-11013/41/2006-IA II

(I) dated 26.4.2012 within 3 month periods.

Agreed, Corporate Environment

Responsibility as mentioned in MOEF,

GOI OM No. J-11013/41/2006-IA II (I)

dated 26.4.2012 will be justified.

That the safe and hygienic working

conditions have been provided for the

Page 17: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

workers during construction.

That the drinking water and sanitary

facilities of the type of mobile sulabh

shauchalayas has been provided during

construction phase.

First aid facilities will be maintained at

readily accessible place where necessary

appliances including sterilized cotton,

wool, etc. have been available.

Routine inspection, cleaning and

maintenance of the site has been

occurred.

IX The fund ear marked for environment

protection measures should be kept in separate

account and should not be diverted for other

purposes and year wise expenditure shall be

reported to the SEIAA/ RO MoEF GoI under

rules prescribed for Environment Audit.

Agreed, The fund earmarked for

environment protection measures will be

kept in separate account and will not be

diverted for other purposes and year

wise expenditure will be reported to the

SEIAA/ RO MoEF GoI under rules

prescribed for Environment Audit.

X The project proponent shall obtain NOC under

Aravali notification from CEC of hon’ble

supreme court regarding coverage under

Aravali notification.

Agreed. Aravali clearance from Deputy

Commissioner, Gurgaon is enclosed as

Annexure-IV.

(B) COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE

MANUAL 2010 OF MOEF

SI.

No.Points as per EIA Guidance Manual Status of Compliance

A. Air Environment

Page 18: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

SI.

No.Points as per EIA Guidance Manual Status of Compliance

1. Wind erosion is a serious problem in areas where the

ground is virtually bare and devoid of vegetation.

Vegetation methods are found to be most effective

in the form of windbreaks and shelterbelts.

Barricade around the project area is being

provided to restrict dust and air pollution

during construction phase.

2. Sprinkling of water and fine spray from nozzles to

suppress the dust.

Water sprinkling is being carried out

regularly through tanker water at site for

dust suppression.

3. On-Road-Inspection should be done for black smoke

generating machinery.

All the machineries deployed at site are of

highest standard and of reputed make and

comply with emission & noise standards.

Inspections and maintenance of

construction machineries and vehicles are

carried out periodically.

4. Promotion of use of cleaner fuel should be done. Ultra low sulphur diesel (ULSD) (sulphur

content less than 0.05%) is being used for

running of DG sets, vehicles and

construction machineries.

Page 19: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

SI.

No.Points as per EIA Guidance Manual Status of Compliance

5. All DG sets should comply emission norms notified

by MoEF.

The DG sets are installed within factory

made enclosure which conforms to the

permissible air emission and noise

standards notified by MOEF. DG sets are

new and certified by manufacturers. DG

sets has stack height which complies with

emission norms notified by MoEF.

Monitoring of emissions of DG sets is also

being carried out periodically. While,

during operation phase, adequate stack

height will be provided as per CPCB

guidelines.

6. Vehicles having pollution under control certificate

may be allowed to ply.

It is ensured that all the vehicles used for

construction activities are having valid

Pollution under Control (PUC)

certificates. The vehicles without valid

Pollution under Check (PUC) certificate

are not permitted at project site.

7. Use of covering sheet to prevent dust dispersion at

buildings and infrastructure sites, which are being

constructed.

Exposed areas are covered with tarpaulin

sheets to prevent soil erosion due to the

wind.

8. Use of covering sheets should be done for trucks to

prevent dust dispersion from the trucks,

implemented by district offices.

The trucks carrying construction materials

and debris are suitably covered by

tarpaulin and plastic sheets. The trucks

carrying construction materials & debris

without cover are not permitted to enter or

leave the project site.

Page 20: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

SI.

No.Points as per EIA Guidance Manual Status of Compliance

9. Paving is a more permanent solution to dust control,

suitable for longer duration projects. High cost is the

major drawback to paving.

During construction, access roads have

been covered with gravels to prevent dust

emission.

(At the completion stage of the project, all

permanent internal roads & walkway will

be paved and greeneries will be

developed)

10. Reducing the speed of a vehicle to 20 kmph can

reduce emissions by a large extent. Speed bumps are

commonly used to ensure speed reduction. In cases

where speed reduction cannot effectively reduce

fugitive dust, it may be necessary to divert traffic to

nearby paved areas.

Speed of the vehicles is restricted by

erecting speed bumps at regular intervals

at project site and proper signage is

provided for guided vehicular movement

and speed restrictions.

11. Material storages/ warehouses-Care should be taken

to keep all material storages adequately covered and

contained so that they are not exposed to situations

where winds on site could lead to dust/ particulate

emissions. Fabrics and plastics for covering piles of

soils and debris is an effective means to reduce

fugitive dust.

No construction materials like cement,

sand and aggregates are stored at site.

Ready-mixed concrete is being used for

concrete work at project site which is

being transported from the off-site

batching plant. At the off-site batching

plant, the construction materials are

properly stored in covered storage yard

with proper shades and covers.

B. Noise Environment

Page 21: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

SI.

No.Points as per EIA Guidance Manual Status of Compliance

1. Setting up the barriers: National Building Code 2005

suggests that design solutions such as barrier blocks

should be used to reduce external LA10 noise levels

to at least 60-70dB(A) at any point 1.0 m from any

inward looking façade.

The project site is located in residential

area earmarked by the local development

authority. The site is enclosed with high

barricade wall around the project

boundary, which is more than the

prescribed height of 3 m.

The DG sets are installed within factory

made acoustic enclosure which conforms

to the permissible noise standards notified

by MOEF. DG sets are new and certified

by manufacturers.

C. Water Environment

1. Curing water should be sprayed on concrete

structures; free flow of water should not be allowed

for curing.

Curing compounds are being used for

curing. No water is being used for curing.

2. After liberal curing on the first day, all concrete

structures should be painted with curing chemical to

save water. This will stop daily water curing hence

save water.

Curing compounds are being used to save

water for curing. No water is being used

for curing.

3. Concrete structures should be covered with thick

cloth/gunny bags and then water should be sprayed

on them. This would avoid water rebound and will

ensure sustained and complete curing.

Curing compounds are being used for

curing. No water is being used for curing.

4. Ponds should be made using cement and sand mortar

to avoid water flowing away from the flat surface

while curing

No water is being used for curing hence

ponds are not proposed in the site.

Page 22: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

SI.

No.Points as per EIA Guidance Manual Status of Compliance

5. Water ponding should be done on all sunken slabs;

this would also highlight the importance of having

an impervious formwork.

No water is being used for curing.

3.0 Compliance to NGT Order dated 10.04.2015 related to Construction

SI.

No

.

NGT Order dated 10.04.2015 Status of Compliance

1. Every builder or owner shall put tarpaulin on

scaffolding around the area of construction and

the building. No person including builder,

owner can be permitted to store any

construction material particularly sand on any

part of the street, roads in any colony.

Tarpaulin covers are provided around the area

of construction, wherever required. No

construction materials such as cement, sand and

aggregates are stored at site. Ready-mixed

concrete is being used for concrete work at

project site which is being transported from the

off-site batching plant. At the off-site batching

plant, the construction materials are properly

stored in covered storage yard with proper

shades and covers.

2. The construction material of any kind that is

stored in the site will be fully covered in all

respects so that it does not disperse in the Air

in any form.

Tarpaulin covers are provided around the area

of construction, wherever required. No

construction materials such as cement, sand and

aggregates are stored at site. Ready-mixed

concrete is being used for concrete work at

project site which is being transported from the

off-site batching plant. At the off-site batching

plant the construction materials are properly

stored in covered storage yard with proper

shades and covers.

Page 23: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

SI.

No

.

NGT Order dated 10.04.2015 Status of Compliance

3. All the construction material and debris shall

be carried in the trucks or other vehicles which

are fully covered and protected so as to ensure

that the construction debris or the construction

material does not get dispersed into the air or

atmosphere, in any form whatsoever.

The trucks carrying construction materials and

debris are suitably covered by tarpaulin and

plastic sheets. The trucks carrying construction

materials & debris without cover are not

permitted to enter or leave the project site.

4. The dust emissions from the construction site

should be completely controlled and all

precautions taken in that behalf.

All necessary precautions are adopted to

control the dust emissions. Water sprinkling at

site is carried out through tanker water

regularly at site for dust suppression.

5. The vehicles carrying construction material

and construction debris of any kind should be

cleaned before it is permitted to ply on the road

after unloading of such material.

The vehicles carrying construction material and

construction debris is being cleaned before it is

permitted to ply on the road after unloading of

such material.

6. Every worker working on the construction site

and involved in loading, unloading and

carriage of construction material and

construction debris shall be provided with

mask to prevent inhalation of dust particles.

All safety measures are taken. All construction

workers are being provided with personal

protective equipment (PPE) by the contractors

as required under the health & safety norms.

Workers handling the fine materials wear mask

to prevent inhalation of dust particles.

7. Every owner and or builder shall be under

obligation to provide all medical help,

investigation and treatment to the workers

involved in the construction of building and

carry of construction material and debris

relatable to dust emission.

Full-fledged first aid facility is provided at the

construction site and regular medical check-ups

by Doctor are conducted for construction

workers. Logbook is being maintained with

medical treatment details of the workers.

Page 24: nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards

SI.

No

.

NGT Order dated 10.04.2015 Status of Compliance

8. It shall be the responsibility of every builder to

transport construction material and debris

waste to construction site, dumping site or any

other place in accordance with rules and in

terms of this order.

Construction material and debris waste is being

to construction site, dumping site or any other

place in accordance with rules and in terms of

this order.

9. All to take appropriate measures and to ensure

that the terms and conditions of the earlier

order and these orders should strictly comply

with by fixing sprinklers, creations of green air

barriers.

Regular sprinkling of water is being carried out

at site through tanker.

10. Compulsory use of wet jet in grinding and

stone cutting.

Structural work is under progress at site. All

necessary precautions will be taken in the stone

cutting and grinding area which will be done at

later stage of construction.

11. Wind breaking walls around construction site. The site is enclosed with high barricade wall

around the project boundary which acts as a

wind breaker.

12. All the builders who are building commercial,

residential complexes which are covered under

the EIA Notification of 2006 shall provide

green belt around the building that they

construct. All Authorities shall ensure that such

green belts are in existence prior to issuance of

occupancy certificate.

Green area will be developed at the end of

construction stage as per approved building

plan.