COMPLIANCE REPORT FOR COMMERCIAL PROJECT LOCATED IN REVENUE ESTATE OF VILLAGE BAJGHERA, SECTOR-114, GURGAON, HARYANA BY M/s CHINTELS INFRACON (A) HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE REF. LETTER NO. SEIAA/HR/2013/149 DATED 28.05.2013 Sl. No. Conditions Status of Compliance PART A - SPECIFIC CONDITIONS: Construction Phase:- 1. “Consent for Establishment” shall be obtained from Haryana State Pollution Control Board Under Air and Water act and a copy shall be submitted to the SEIAA, Haryana before the start of any construction work at site. Agreed. “Consent to Establishment” has been obtained from the Haryana State Pollution Control Board under Air and Water act. Copy of CTE is enclosed as Annexure –I. 2. A first aid room as proposed in the project report will be provided in both during construction and operation phase of the project. Agreed. First aid room has been provided during construction phase and same will also be managed during operational phase. 3. Adequate drinking water and sanitary facilities should be provided for construction workers at the site. Provision Agreed. An adequate drinking water facility and community toilet has been provided for construction
44
Embed
nromoef.gov.innromoef.gov.in/SMPR/22092015/42.docx · Web viewThe DG sets are installed within factory made enclosure which conforms to the permissible air emission and noise standards
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
COMPLIANCE REPORT FOR COMMERCIAL PROJECT LOCATED IN REVENUE
ESTATE OF VILLAGE BAJGHERA, SECTOR-114, GURGAON, HARYANA BY
M/s CHINTELS INFRACON
(A) HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE REF. LETTER NO. SEIAA/HR/2013/149 DATED 28.05.2013
Sl. No. Conditions Status of Compliance
PART A - SPECIFIC CONDITIONS: Construction Phase:-
1. “Consent for Establishment” shall be obtained
from Haryana State Pollution Control Board
Under Air and Water act and a copy shall be
submitted to the SEIAA, Haryana before the
start of any construction work at site.
Agreed. “Consent to Establishment” has
been obtained from the Haryana State
Pollution Control Board under Air and
Water act. Copy of CTE is enclosed as
Annexure –I.
2. A first aid room as proposed in the project
report will be provided in both during
construction and operation phase of the
project.
Agreed. First aid room has been
provided during construction phase and
same will also be managed during
operational phase.
3. Adequate drinking water and sanitary facilities
should be provided for construction workers at
the site. Provision should be made for mobile
toilets. Open defecation by the labors is
strictly prohibited. The safe disposal of waste
water and solid wastes generated during the
construction phase should be ensured.
Agreed. An adequate drinking water
facility and community toilet has been
provided for construction workers at the
site. Open defecation by the labors has
been strictly prohibited. The wastewater
generated during construction phase is
being sent to septic tanks.
Left over cement and mortars, cement
concrete blocks, aggregate, sand and
other inorganic material will be recycled
and reused as granular subbase (GSB)
layer of pavement.
4. All the top soil excavated during construction
activities should be stored for use in
horticulture/landscape development within the
project site.
Agreed, The top soil excavated during
construction activities is being stored
and will be utilized in horticulture/
landscape developments within the
project site. The remaining excavated
soil had been utilized in re-filling of
foundation, road works, rising of site
level etc.
5. The project proponent shall ensure that the
building material required during construction
phase is properly stored with in the project
area and disposal of construction waste should
not create any adverse effect on the
neighboring communities and should be
disposed of after taking necessary precautions
for general safety and health aspects of people,
only in approved sites with the approval of
competent authority.
Agreed, The building material required
during construction phase have been
properly stored within the project area
and disposal of construction waste does
not create any adverse effects on the
neighboring communities and is being
disposed off by taking the necessary
precautions for general safety and health
aspects of people, only in approved sites
with the approval of competent
authority.
6. Construction spoils, including bituminous
material and other hazardous materials, must
not be allowed to contaminate watercourses
and the dump sites for such material must be
secured so that they should not leach into the
ground water and any hazardous waste
generated during construction phase, should be
disposed off as per applicable rules and norms
with necessary approval of the Haryana State
Pollution Control Board.
Agreed, Construction spoils including
bituminous material and other hazardous
materials will not being allowed to
contaminate water courses and the dump
sites for such material will be secured so
that they should not leach into the
ground water. Materials will be disposed
off as per applicable rules and norms
with necessary approval of the Haryana
State Pollution Control Board.
7. The diesel generator sets to be used during
construction phase should be low sulphur
Agreed. During construction phase, DG
sets has been used for office lighting and
diesel type and should conform to
Environment (Protection) Rules prescribed for
air and noise emission standards.
site lightning. DG sets has been enclosed
with acoustic enclosure. They are running
on low sulphur diesel only with the
provision of air and noise emission
standards as per EPA Rules, 1986.
8. The diesel required for operating DG sets shall
be stored in underground tanks and if required,
clearance from Chief Controller of Explosives
shall be taken.
Agreed. The diesel required for
operating DG set has been stored in
HDPE Drums and log books has been
maintained adequately.
9. Ambient noise levels should conform to
residential standards both during day and
night. Incremental pollution loads on the
ambient air and noise quality should be closely
monitored during construction phase.
Adequate measures should be taken to reduce
ambient air and noise level during construction
phase, so as to conform to the stipulated
residential standards.
Agreed, ambient noise levels conform
to standards both during day and night.
The silent type DG set with acoustic
enclosures has been installed at project
site and office.
Low sulphur fuel is being used
Exhaust is conforming to the
provisions of Environment
(Protection) Rules prescribed for air
and noise emission standards.
All vehicles entering to the site were
with valid PUC certificate.
All machinery used at the site is new
and periodic maintenance of the
machinery insured.
Results of the environmental
monitoring carried out at the site are
enclosed as Annexure – II
Shelter belt will be provided to reduce
the noise level within the site.
10. Fly ash should be used as building material in
the construction as per the provisions of Fly
Block work bricks are used as building
material. As the bricks contain low
Ash Notification of September, 1999 and
amended as on 27th August, 2003
density that makes it low in Thermal
Conductivity, these bricks act as thermal
Insulators which resist the building for
being heating.
11. Storm water control and its re-use as per
CGWB and BIS standards for various
applications should be ensured.
Agreed. Storm water control and its
reuse will be maintained as per Central
Ground Water Board and BIS standards
for various applications.
12. Water demand during construction should be
reduced by use of premixed concrete, curing
agents and other best practices referred.
Water demand during construction has
been reduced by the practice of using
premixed concrete, curing agents and
other best practices.
13. In view of severe constrains in water supply
augmentation in the region and sustainability
of water resources, the developer will submit
the NOC from CGWA specifying water
extraction quantities and assurance from
HUDA / utility provider indicating source of
water supply and quantity of water with details
of intended use of water potable and non-
potable. Assurance is required for both
construction and operation stages separately. It
shall be submitted to the SEIAA/ R.O. MoEF,
Chandigarh before the start of construction.
Agreed. Ground water will not be
extracted for the purpose of construction
as well as for operation phase of the
project. Water is being supplied by
HUDA during construction and same
will be during Operational phase.
Application has been filled to HUDA for
water supply during construction &
operational phase, the copy of same is
enclosed as Annexure- III (a) & (b).
14. Roof should meet prescriptive requirement as
per Energy Conservation Building Code by
using appropriate thermal insulation material
to fulfill requirement.
Agreed. Roof will be thermal insulated
as per the Energy Conservation Building
Code.
15. Opaque wall should meet prescriptive
requirement as per Energy Conservation
Building Code which is proposed to be
Agreed. Opaque wall will be thermal
insulated as per the Energy Conservation
Building Code.
mandatory for all air conditioned spaces while
it is inspirational for non-air-conditioned
spaces by use of appropriate thermal insulation
material to fulfill requirement.
16. The approval of the competent authority shall
be obtained for structural safety of the
building on account of earthquake, adequacy
of firefighting equipment, etc. as per National
Building Code including protection measures
from lightening etc. If any forestland is
involved in the proposed site, clearance under
Forest Conservation Act shall be taken from
the competent Authority.
Agreed. The approval of competent
authority will be taken for structural
safety of the building due to earthquake,
adequacy of firefighting equipment etc.
as per National Building Code including
protection measures from lightening etc.
Project site does not fall in Forest land
area. NOC Application has been filled to
DC for Aravalli clearance; copy of the
same is enclosed as Annexure-IV.
17. Overexploited groundwater and impending
severe shortage of water supply in the region
requires the developer to redraw the water and
energy conservation plan. Developer shall
submit details of good practices that have been
included in the project to reduce the overall
footprint of the proposed development
including a detailed water balance along with
source and quantities of potable and non
potable water requirement (including water
requirement during construction phase)
incorporating water efficiency / Saving
measures as well as water reuse/ recycling
within 3 months to the SEIAA, Haryana and
R.O. MoEF, GOI Chandigarh before the start
of construction.
Agreed, No ground water extraction will
take place. However, treated water for
construction is being supplied by
HUDA. To reduce the demand in
operation phase, treated water from STP
will be used for horticulture, flushing,
cooling, rest will be used in nearby
construction site. As well as efficient
fixtures will be used to minimize the
water demand for domestic purpose.
18. The project proponent shall construct 03 Nos. Agreed. 03 rain water harvesting pits
rain water harvesting pits for recharging the
ground water within the project premises. Rain
Water harvesting pits shall be designed to
make provisions for silting chamber and
removal of floating matter before entering
harvesting pit, peak rain fall intensity of
45mm/hr must be kept in mind while
redesigning RWH pit. Maintenance budget
and persons responsible for maintenance must
be provided. Care shall also be taken that
contaminated water do not enter any RWH pit.
will be provided for recharging the
ground water within the project
premises. To remove silt and floating
matter, desilting chamber will be
proposed with rain water harvesting pits.
Care will be taken that contaminated
water will not be entered in any of RWH
pits. RWH plan with showing the storm
water line and RWH pit is enclosed as
Annexure-V.
19. The Project Proponent shall provide minimum
one Hydraulic ladder of sufficient length for
escape of people in case of fire.
Maximum height of the building will be
59.70 m. Maximum height upto which
hydraulic ladder can be provided is 12 m
so, permanent ladder will be provided
instead of hydraulic ladder.
20. The project proponent shall submit assurance
from the DHBVN for supply of 1672 kVA of
power supply before the start of construction.
In no case project will be operational solely on
generators without any power supply from any
external power utility.
Agreed. Application has been filed to
HVPNL for supply of electricity; copy
of the same is enclosed as Annexure-
VI.
21. Detail calculation of power load and ultimate
power load of the project shall be submitted to
DHBVN under intimation to SEIAA, Haryana
before the start of construction provision shall
be made for electrical infrastructure in the
licensed area.
Agreed. Detail calculation of power load
and ultimate power load of the project
has been submitted to HVPNL,
Application has been filled to HVPNL;
copy of the same is enclosed as
Annexure-VI.
22. The project proponent shall obtain NOC from
nearest fire station before the start of
construction.
Agreed. Fire NOC will be obtained from
the nearest fire station.
23. The Project proponent shall not raise any
construction in the natural land depression/
Nallah/ Water course and shall ensure that the
natural flow from the Nallah/ Water course is
not obstructed.
Agreed, the project site does not contain
any natural land depression nallah/ water
course as well as no natural flow will be
obstructed by the project.
24. The project proponent shall keep the plinth
level of the building blocks sufficiently above
the level of the approach road to the Group
Housing Project as per prescribed bye laws.
Levels of the other areas in the Group Housing
Projects shall also be kept suitably so as to
avoid flooding.
Agreed, The plinth level of the building
block will be above the level of the
approach road as per the prescribed bye
laws. Levels will be suitably maintained
to avoid flooding.
25. Construction shall be carried out so that
density of population does not exceed as
approved by Director General Town and
Country Department Haryana.
Agreed, population density will be as per
the approved Building plan by Director
General Town and Country Department,
Haryana.
26. The Project proponent shall submit an
affidavit with the declaration that ground
water will not be used for construction and
only treated water should be used for
construction.
Agreed, Ground water will not be used
for the construction activity. No ground
water is being extracted during
construction phase; affidavit for the
same has already been submitted.
27. The project proponent shall not cut any
existing tree and project landscaping plan
should be modified to include those trees in
green area.
There is no need to cut the trees. Only
small bushes clearing were required
during the construction activity.
28. The project proponent shall provide helipad
facility as required under NBC norms and
shall seek permission of helipad from AAI
accordingly.
Agreed. Maximum height of the
building will be 59.70 m. So, there is no
need to provide Helipad facility
29. The project proponent shall ensure that ECBC
norms for composite climate zone are met. In
Agreed, ECBC norms for composite
climate zone, water heating, pumping,
Particular building envelope, HVAC service
water heating, pumping, lighting and electrical
infrastructure must meet ECBC norms.
lighting and electrical infrastructure
have been followed.
30. The PP shall provide 3 meter high barricade
around the project area, dust screen for every
floor above the ground, proper sprinkling and
covering of stored material to restrict dust and
air pollution during construction.
Agreed, 3 meter high barricade around
the project area and dust screen has been
installed during construction.
31. The project proponent shall construct a
sedimentation basin in lower level of project
site to trap pollutants and other waste during
rain.
Agreed. Sedimentation basin has been
constructed to trap pollutants and other
waste during rain.
32. The project proponent shall provide proper
Rasta of proper width and proper strength for
each project before the start of construction.
Agreed. Proper Rasta of proper width
and proper strength has been provided.
33. The window wall ratio of the construction
project should not exceed 40%.
Agreed. The window wall ratio of the
construction project will not be exceeded
40%.
34. The project proponent shall keep the plinth
level of the building above the HFL of the said
Najafgarh Jheel/drain attained in the last 100
years.
Agreed, plinth level of the building has
been kept higher than the HFL of the
Najafgarh Jheel/drain i.e. 213.575 m
attained in the last 100 years.
35. The project proponent shall obtain NOC from
HUDA as well as Irrigation Department before
the start of construction, regarding possible
adverse effect of project proposal on the said
Najafgarh Jheel.
Agreed. The application will be filled to
HUDA as well as irrigation department
regarding possible adverse effect of
project on the said Najafgarh Jheel.
36. The project proponent shall provide all the
safety measures for the workers during
construction phase of high rise building.
Agreed. Safety measures for the workers
during construction phase are being
provided.
37. The project proponent shall use better U-Value Agreed.
glass.
38. The project proponent shall obtain NOC from
AAI before the start of construction.
Agreed. NOC from AAI has been
obtained and is enclosed as Annexure-
VII.
39. The project proponent shall not restrict the
village Rasta and shall provide Rasta of proper
width
Agreed. The PP will not restrict the
village Rasta and also has been provided
Rasta of proper width.
PART A- SPECIFIC CONDITIONS : Operation Phase
a) “Consent to operate” shall be obtained from
Haryana State Pollution Control Board under
Air and water Act and a copy shall be
submitted to the SEIAA. Haryana.
Agreed. “Consent to operate” will be
obtained from Haryana State Pollution
Control Board under Air and water Act.
b) The Sewage Treatment Plant (STP) shall be
installed for the treatment of the sewage to be
prescribed standards including odour and
treated effluent will be recycled to achieve
zero exit discharge. The installation of STP
should be certified by an independent expert
and a report in this regard should be submitted
to the SEIAA, Haryana before the project is
commissioned for operation. Tertiary
treatment of waste water is mandatory.
Discharge of treated sewage shall conform to
the norms and standards of HSPCB,
Panchkula.
Agreed, The Sewage Treatment Plant
(STP) will be installed for the treatment
of the sewage to the prescribed standards
including odour and treated effluent will
be recycled and used for flushing,
cooling, and rest will be used in nearby
construction site. Report of installation
of STP will be submitted to the SEIAA,
Haryana before the project is
commissioned for operation. Discharge
of effluent will be conforming to the
norms and standards of HSPCB,
Panchkula.
c) Separation of the grey and black water should
be done by the use of dual plumbing line.
Treatment of 100% grey water by
decentralized treatment should be done
ensuring that the recirculated water should
have BOD maximum upto 10 ppm and the
Agreed, grey and black water will be
separated by the use of dual plumbing
line. Agreed, recycled water will be used
for flushing, gardening, cooling and rest
will be used for nearby construction site.
Dual plumbing plan is enclosed as
recycled water will be used for flushing,
gardening and DG set cooling and running of
fountain in the water body to achieve zero exit
discharge.
Annexure-VIII.
d) For disinfection of the treated waste water
ultra violet radiation or ozonization process
should be used.
Agreed, for disinfection of the treated
wastewater, ultra violet radiation process
will be used.
e) The solid waste generated should be properly
collected and segregated. Bio degradable
waste shall be decomposed at site and dry/
inert solid waste should be disposed off to
approved sites for land filling after recovering
recyclable material.
Agreed. The solid waste generated will
be properly collected and segregated.
Bio-degradable waste will be
decomposed at site by composting and
used as manure, dry/inert solid waste
will be disposed off in MSW disposal
site. Solid waste management plan is
enclosed as Annexure – IX.
f) Diesel Power generating sets proposed as
source of backup power for lifts, common area
illumination and for domestic use should be of
enclosed type and conform to rules made
under the Environment (Protection) Act, 1986.
The location of the DG sets should be in the
basement as promised by the project
proponent with appropriate stack height i.e.
above the roof level as per the CPCB norms.
The diesel used for DG sets should be of low
sulphur contents (maximum upto 0.25%)
Agreed. The location of DG sets will be
in basement and conform to rules made
under the Environment (Protection) Act,
1986. The diesel used for DG sets will
be of low sulphur contents (maximum
up to 0.25%).
g) Ambient Noise Level should be controlled to
ensure that it does not exceed the prescribed
standards both within and at the boundary of
the proposed residential complex.
Agreed. The Ambient noise level will be
controlled that it does not exceed the
prescribed standards both within and at
the boundary of the project.
h) The project proponent should maintain at least Agreed. The project proponent is
38.35% as green cover area for tree plantation
especially all around the periphery of the
project and on the road sides preferably with
local species so as to provide protection
against particulates and noise. The 10% open
spaces inside the plot should be preferably
landscaped and covered with vegetation/grass,
Herbs& shrubs Only local available plant
species shall be used.
maintaining at least 38.35% as green
cover area for tree plantation especially
all around the periphery of the project
and on the road sides preferably with
local species so as to provide protection
against particulates and noise. The open
spaces inside the plot will be preferably
landscape and covered with
vegetation/glass. Landscape Plan is
attached as Annexure-X.
i) The project proponent shall strive to minimize
water in irrigation of landscape by minimizing
grass area, using native variety, xeriscaping
and mulching, utilizing efficient irrigation
system, scheduling irrigation only after
checking evapo-transpiration data.
Agreed. The PP will minimize water in
irrigation of landscape by minimizing
grass area, using native variety,
xeriscaping and mulching, utilizing
efficient irrigation system, scheduling
irrigation only after checking evapo-
transpiration data.
j) Rain water harvesting for roof runoff and
surface runoff, as per plan submitted should be
implemented. Before recharging the surface
runoff, pre-treatment through sedimentation
tanks must be done to remove suspended
matter, oil and grease. The bore well for rain
water recharging shall be kept at least 5 m
above the highest ground water table. Care
shall be taken that contaminated water do not
enter any RWH pit.
Rainwater harvesting as per plan for roof
run-off and surface run-off will be
implemented. Suspended matter, oil and
grease will be removed by treatment
before recharging with surface run-off.
The bore well for recharge will be kept
at least 5 m above the highest ground
water table. Rain water Harvesting Plan
is enclosed as Annexure-V.
k) The ground water level and its quality should
be monitored regularly in consultation with
Central Ground Water Authority.
Agreed. Ground water level and its
quality will be monitored regularly in
consultation with Central Ground Water
Authority, if required.
l) There should be no traffic congestion near the
entry and exist points from the roads adjoining
the proposed project site. Parking should be
fully internalized and no public space should
be utilized.
Agreed. Parking will be completely
internalized and no public space will be
utilized. Care will be taken to ensure that
there will be no traffic congestion at the
entry and exit points. Traffic circulation
plan is enclosed as Annexure-XI.
m) A report on the energy conservation measures
conforming to energy conservation norms
finalize by Bureau of Energy Efficiency
should be prepared incorporating details about
building materials & technology; R & U
factors etc. and submit to the SEIAA, Haryana
in three months’ time.
Agreed. Report on energy conservation
measure conforming to energy
conservation norms finalized by BEE
which will include details of building
materials and technology, R & U factors
etc. will be submitted to the SEIAA,
Haryana within three months’ time.
n) Energy conservation measures like installation
of CFLs/TFLs for lighting the areas outside
the building should be integral part of the
project design and should be in place before
project commissioning. Used CFLs and TFLs
should be properly collected and disposed
off/sent for recycling as per the prevailing
guidelines/rules of the regulatory authority to
avoid mercury contamination. Use of solar
panels must be adapted to the maximum extent
possible for energy conservation.
Agreed. CFL light will be used in
common areas like lift, corridors,
staircase and service areas. CFLs will be
properly collected and disposed off/sent
for recycling as per the prevailing
guidelines/rules of the regulatory
authority to avoid mercury
contamination. Use of solar panels will
be adapted to the maximum extent
possible for energy conservation.
o) The project proponent shall use zero ozone
depleting potential material in insulation,
refrigeration, air-conditioning. PP shall also
provide Halon free fire suppression system.
Agreed. The PP will use zero ozone
depleting potential material in insulation,
refrigeration, air-conditioning and also
provide Halon free fire suppression
system.
p) The solid waste generated should be properly
collected and segregated as per the
Agreed, The solid waste generated will
be collected and segregated as per the
requirement of the MSW Rules, 2000 and as
amended from time to time. The bio-
degradable waste should be composted by
vermicomposting at the site earmarked within
the project area and dry/inert solid waste
should be disposed off to the approved sites
for land filling after recovering recyclable
material.
requirement of the MSW Rules, 2000.
The bio-degradable waste will be
composted at the site earmarked within
the project area and dry/inert solid waste
will be disposed off to the approved sites
for land filling after recovering
recyclable material. Solid waste
management plan is enclosed as
Annexure IX.
q) The provision of the solar water heating
system shall be as per norms specified by
HAREDA and shall be made operational in
each building block.
Agreed. Provision of the solar water
heating system will be as per norms
specified by HAREDA and will be made
operational in open spaces and signage.
r) The traffic plan and the parking plan proposed
by the PP should be adhered to meticulously
with further scope of additional parking for
future requirement. There should be no traffic
congestion near the entry and exit points from
the roads adjoining the proposed project site.
Parking should be fully internalized and no
public space should be used.
Agreed. The traffic plan and the parking
plan will be adhered with further scope
of additional parking for future
requirement. Parking will be fully
internalized and no public space will be
used. Traffic circulation plan is enclosed
as Annexure-XI.
s) The project shall be operationalized only once
HUDA will provide domestic water supply
system in the area.
Agreed. Project will be operationalized
once HUDA will provide domestic water
supply system in the area.
t) Operation and maintenance of STP, solid
waste management and electrical
infrastructure shall be ensured even after the
completion of sell.
Agreed. Operation and maintenance of
STP, solid waste management and
electrical infrastructure will be
maintained by the Environment
Management Cell.
u) Different type of wastes should be disposed
off as per provisions of municipal solid waste,
Agreed. Municipal solid waste will be
disposed as per the Municipal Solid
biomedical waste, hazardous waste, e waste,
batteries & plastic rules made under
Environment Protection Act, 1986.
Particularly E-waste and Battery waste shall
be disposed of as per existing E-waste
Management Rules 2011 and Batteries
Management Rules 2001. The project
proponent should maintain a collection center
for E-waste and it should be disposed of to
only registered and authorized
dismantler/recycler.
Wastes (Management and Handling)
Rules, 2000. Biomedical waste will not
be generated by the project. Hazardous
wastes will be handled as per the
Hazardous Waste (Management and
Handling) Rules, 2000. E-waste will be
taken care as per E waste (management
and Handling) Rules, 2011 and Plastic
waste will be handled as per the Plastic
waste (Management and Handling)
Rules, 2011.
v) Standards for discharge of environment
pollutants as enshrined in various schedule of
rule 3 of Environment Protection Rule 1986
shall be strictly complied with.
Agreed. All the required standard
discharge will be followed for discharge
of environment pollutants as enshrined
in various schedule of rule 3 of
Environment Protection Rules, 1986.
w) The project proponent shall make provision
for guard pond and other provisions for safety
against failure in the operation of wastewater
treatment facilities. The project proponent
shall also identify acceptable outfall for treated
effluent.
Agreed, guard pond and safety against
failure in the operation of wastewater
treatment facilities will be provided. The
project proponent will also identify
acceptable outfall for treated effluent.
x) The project proponent shall ensure that the
emission standards of noise and air with in the
CPCB prescribed limits. Noise and Emission
level of DG sets greater than 800 Kva shall be
as per as CPCB latest standards for high
capacity DG sets.
Agreed. Noise and Air Emission will be
as per as CPCB latest standards.
y) The project proponent should strive to
maintain the power factor between 0.98 to 1.0
in order to conserve energy.
Agreed. Power factor will be maintained
between 0.98 to 1.0 in order to conserve
energy.
PART-B GENERAL CONDITIONS
I The Project proponent shall ensure the
commitments made in Form-1, Form-1A,
EIA/EMP and other documents submitted to
the SEIAA for the protection of environment
and proposed environmental safeguards are
complied with in letter and spirit.
Agreed. All safeguards mentioned in the
Application are implemented during the
construction phase and will be
implemented to the maximum possible
extent.
II Six monthly compliance reports should be
submitted to the Haryana State Pollution
Control Board and Regional Office, MOEF,
GOI, Northern Region, Chandigarh and a copy
to the Regulatory Authority of Haryana.
Agreed. Six monthly compliance reports
are being submitted to Haryana State
Pollution Control Board and Regional
Office, MOEF, GOI, Northern Region,
Chandigarh and a copy to the Regulatory
Authority of Haryana.
Acknowledgement copies of previously
submitted compliance report are
attached as Annexure-XII.
III The SEIAA, Haryana reserves the right to add
additional safeguard measure subsequently, if
found necessary. Environmental Clearance
granted will be revoked if it is found that false
information has been given for getting
approval of this project. SEIAA reserves the
right to revoke the clearance if conditions
stipulated are not implemented to the
satisfaction of SEIAA/MoEF.
Agreed, The SEIAA Haryana reserves
the right to add additional safeguard
measure subsequently, if found
necessary.
IV The Project proponent will not violate any
judicial orders/ pronouncements issued by the
Hon’ble Supreme Court/High Courts.
Agreed. There will be no violation of
any judicial order/ pronouncements
issued by the Hon’ble Supreme
Court/High Courts.
V All other statutory clearances such as the
approvals for storage of diesel from Chief
Agreed, all the required applicable
clearance will be obtained from the
Controller of Explosives, Fire Department,
Civil Aviation Department, Forest
Conservation Act, 1980 and Wildlife
(Protection) Act, 1972, PLPA, 1900, Forest
Act, 1927 etc. shall be obtained, as applicable
by project proponents from the respective
authorities prior to construction of the project
respective authority. AAI NOC and
Aravalli NOC are enclosed as
Annexure- VII & IV respectively.
VI The project proponent should inform the
public that the project has been accorded
Environment Clearance by the SEIAA and
copies of the clearance letter are available with
the State Pollution Control Board & SEIAA.
This should be advertised within 7 days from
the date of issue of the clearance letter at least
in two local newspaper that are widely
circulated in the region and the copy of the
same should be forwarded to SEIAA,
Haryana. A copy of Environment Clearance
Conditions shall also be put on project
proponent web site for public awareness.
Agreed, Advertisement has been given
in the local newspaper informing to
public that Environment clearance has
been obtained.
VII Any appeal against this Environment
Clearance shall lie with the National Green
Tribunal, if preferred, within a period of 30
days as prescribed under Section 16 of the
National Green Tribunal Act, 2010.
Not applicable.
VIII The project proponent shall put in place
Corporate Environment Policy as mentioned
in MoEF, GOI OM No. J-11013/41/2006-IA II
(I) dated 26.4.2012 within 3 month periods.
Agreed, Corporate Environment
Responsibility as mentioned in MOEF,
GOI OM No. J-11013/41/2006-IA II (I)
dated 26.4.2012 will be justified.
That the safe and hygienic working
conditions have been provided for the
workers during construction.
That the drinking water and sanitary
facilities of the type of mobile sulabh
shauchalayas has been provided during
construction phase.
First aid facilities will be maintained at
readily accessible place where necessary
appliances including sterilized cotton,
wool, etc. have been available.
Routine inspection, cleaning and
maintenance of the site has been
occurred.
IX The fund ear marked for environment
protection measures should be kept in separate
account and should not be diverted for other
purposes and year wise expenditure shall be
reported to the SEIAA/ RO MoEF GoI under
rules prescribed for Environment Audit.
Agreed, The fund earmarked for
environment protection measures will be
kept in separate account and will not be
diverted for other purposes and year
wise expenditure will be reported to the
SEIAA/ RO MoEF GoI under rules
prescribed for Environment Audit.
X The project proponent shall obtain NOC under
Aravali notification from CEC of hon’ble
supreme court regarding coverage under
Aravali notification.
Agreed. Aravali clearance from Deputy
Commissioner, Gurgaon is enclosed as
Annexure-IV.
(B) COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE
MANUAL 2010 OF MOEF
SI.
No.Points as per EIA Guidance Manual Status of Compliance
A. Air Environment
SI.
No.Points as per EIA Guidance Manual Status of Compliance
1. Wind erosion is a serious problem in areas where the
ground is virtually bare and devoid of vegetation.
Vegetation methods are found to be most effective
in the form of windbreaks and shelterbelts.
Barricade around the project area is being
provided to restrict dust and air pollution
during construction phase.
2. Sprinkling of water and fine spray from nozzles to
suppress the dust.
Water sprinkling is being carried out
regularly through tanker water at site for
dust suppression.
3. On-Road-Inspection should be done for black smoke
generating machinery.
All the machineries deployed at site are of
highest standard and of reputed make and
comply with emission & noise standards.
Inspections and maintenance of
construction machineries and vehicles are
carried out periodically.
4. Promotion of use of cleaner fuel should be done. Ultra low sulphur diesel (ULSD) (sulphur
content less than 0.05%) is being used for
running of DG sets, vehicles and
construction machineries.
SI.
No.Points as per EIA Guidance Manual Status of Compliance
5. All DG sets should comply emission norms notified
by MoEF.
The DG sets are installed within factory
made enclosure which conforms to the
permissible air emission and noise
standards notified by MOEF. DG sets are
new and certified by manufacturers. DG
sets has stack height which complies with
emission norms notified by MoEF.
Monitoring of emissions of DG sets is also
being carried out periodically. While,
during operation phase, adequate stack
height will be provided as per CPCB
guidelines.
6. Vehicles having pollution under control certificate
may be allowed to ply.
It is ensured that all the vehicles used for
construction activities are having valid
Pollution under Control (PUC)
certificates. The vehicles without valid
Pollution under Check (PUC) certificate
are not permitted at project site.
7. Use of covering sheet to prevent dust dispersion at
buildings and infrastructure sites, which are being
constructed.
Exposed areas are covered with tarpaulin
sheets to prevent soil erosion due to the
wind.
8. Use of covering sheets should be done for trucks to
prevent dust dispersion from the trucks,
implemented by district offices.
The trucks carrying construction materials
and debris are suitably covered by
tarpaulin and plastic sheets. The trucks
carrying construction materials & debris
without cover are not permitted to enter or
leave the project site.
SI.
No.Points as per EIA Guidance Manual Status of Compliance
9. Paving is a more permanent solution to dust control,
suitable for longer duration projects. High cost is the
major drawback to paving.
During construction, access roads have
been covered with gravels to prevent dust
emission.
(At the completion stage of the project, all
permanent internal roads & walkway will
be paved and greeneries will be
developed)
10. Reducing the speed of a vehicle to 20 kmph can
reduce emissions by a large extent. Speed bumps are
commonly used to ensure speed reduction. In cases
where speed reduction cannot effectively reduce
fugitive dust, it may be necessary to divert traffic to
nearby paved areas.
Speed of the vehicles is restricted by
erecting speed bumps at regular intervals
at project site and proper signage is
provided for guided vehicular movement
and speed restrictions.
11. Material storages/ warehouses-Care should be taken
to keep all material storages adequately covered and
contained so that they are not exposed to situations
where winds on site could lead to dust/ particulate
emissions. Fabrics and plastics for covering piles of
soils and debris is an effective means to reduce
fugitive dust.
No construction materials like cement,
sand and aggregates are stored at site.
Ready-mixed concrete is being used for
concrete work at project site which is
being transported from the off-site
batching plant. At the off-site batching
plant, the construction materials are
properly stored in covered storage yard
with proper shades and covers.
B. Noise Environment
SI.
No.Points as per EIA Guidance Manual Status of Compliance
1. Setting up the barriers: National Building Code 2005
suggests that design solutions such as barrier blocks
should be used to reduce external LA10 noise levels
to at least 60-70dB(A) at any point 1.0 m from any
inward looking façade.
The project site is located in residential
area earmarked by the local development
authority. The site is enclosed with high
barricade wall around the project
boundary, which is more than the
prescribed height of 3 m.
The DG sets are installed within factory
made acoustic enclosure which conforms
to the permissible noise standards notified
by MOEF. DG sets are new and certified
by manufacturers.
C. Water Environment
1. Curing water should be sprayed on concrete
structures; free flow of water should not be allowed
for curing.
Curing compounds are being used for
curing. No water is being used for curing.
2. After liberal curing on the first day, all concrete
structures should be painted with curing chemical to
save water. This will stop daily water curing hence
save water.
Curing compounds are being used to save
water for curing. No water is being used
for curing.
3. Concrete structures should be covered with thick
cloth/gunny bags and then water should be sprayed
on them. This would avoid water rebound and will
ensure sustained and complete curing.
Curing compounds are being used for
curing. No water is being used for curing.
4. Ponds should be made using cement and sand mortar
to avoid water flowing away from the flat surface
while curing
No water is being used for curing hence
ponds are not proposed in the site.
SI.
No.Points as per EIA Guidance Manual Status of Compliance
5. Water ponding should be done on all sunken slabs;
this would also highlight the importance of having
an impervious formwork.
No water is being used for curing.
3.0 Compliance to NGT Order dated 10.04.2015 related to Construction
SI.
No
.
NGT Order dated 10.04.2015 Status of Compliance
1. Every builder or owner shall put tarpaulin on
scaffolding around the area of construction and
the building. No person including builder,
owner can be permitted to store any
construction material particularly sand on any
part of the street, roads in any colony.
Tarpaulin covers are provided around the area
of construction, wherever required. No
construction materials such as cement, sand and
aggregates are stored at site. Ready-mixed
concrete is being used for concrete work at
project site which is being transported from the
off-site batching plant. At the off-site batching
plant, the construction materials are properly
stored in covered storage yard with proper
shades and covers.
2. The construction material of any kind that is
stored in the site will be fully covered in all
respects so that it does not disperse in the Air
in any form.
Tarpaulin covers are provided around the area
of construction, wherever required. No
construction materials such as cement, sand and
aggregates are stored at site. Ready-mixed
concrete is being used for concrete work at
project site which is being transported from the
off-site batching plant. At the off-site batching
plant the construction materials are properly
stored in covered storage yard with proper
shades and covers.
SI.
No
.
NGT Order dated 10.04.2015 Status of Compliance
3. All the construction material and debris shall
be carried in the trucks or other vehicles which
are fully covered and protected so as to ensure
that the construction debris or the construction
material does not get dispersed into the air or
atmosphere, in any form whatsoever.
The trucks carrying construction materials and
debris are suitably covered by tarpaulin and
plastic sheets. The trucks carrying construction
materials & debris without cover are not
permitted to enter or leave the project site.
4. The dust emissions from the construction site
should be completely controlled and all
precautions taken in that behalf.
All necessary precautions are adopted to
control the dust emissions. Water sprinkling at
site is carried out through tanker water
regularly at site for dust suppression.
5. The vehicles carrying construction material
and construction debris of any kind should be
cleaned before it is permitted to ply on the road
after unloading of such material.
The vehicles carrying construction material and
construction debris is being cleaned before it is
permitted to ply on the road after unloading of
such material.
6. Every worker working on the construction site
and involved in loading, unloading and
carriage of construction material and
construction debris shall be provided with
mask to prevent inhalation of dust particles.
All safety measures are taken. All construction
workers are being provided with personal
protective equipment (PPE) by the contractors
as required under the health & safety norms.
Workers handling the fine materials wear mask
to prevent inhalation of dust particles.
7. Every owner and or builder shall be under
obligation to provide all medical help,
investigation and treatment to the workers
involved in the construction of building and
carry of construction material and debris
relatable to dust emission.
Full-fledged first aid facility is provided at the
construction site and regular medical check-ups
by Doctor are conducted for construction
workers. Logbook is being maintained with
medical treatment details of the workers.
SI.
No
.
NGT Order dated 10.04.2015 Status of Compliance
8. It shall be the responsibility of every builder to
transport construction material and debris
waste to construction site, dumping site or any
other place in accordance with rules and in
terms of this order.
Construction material and debris waste is being
to construction site, dumping site or any other
place in accordance with rules and in terms of
this order.
9. All to take appropriate measures and to ensure
that the terms and conditions of the earlier
order and these orders should strictly comply
with by fixing sprinklers, creations of green air
barriers.
Regular sprinkling of water is being carried out
at site through tanker.
10. Compulsory use of wet jet in grinding and
stone cutting.
Structural work is under progress at site. All
necessary precautions will be taken in the stone
cutting and grinding area which will be done at
later stage of construction.
11. Wind breaking walls around construction site. The site is enclosed with high barricade wall