OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
1 of 1
PART IV
SECTION 3
DESCRIPTION OF WORKS AND SPECIFICATIONS
DESIGN CRITERIA
FOR
9 WELL PLATFORMS PROJECT
OFFSHORE DESIGN OIL AND NATURAL GAS CORPORATION LIMITED
MUMBAI REGION, MUMBAI INDIA
ISSUED FOR BID 45 0
PREPARED BY
APPROVEDBY
REMARKS NO. OF PAGES
DATE REV.
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
2 of 2
SECTION - 3
TABLE OF CONTENTS SUB-SECTION TITLE 3.0 DESIGN CRITERIA
3.1 GENERAL
3.2 PROCESS
3.3 PIPING
3.4 STRUCTURAL
3.5 ELECTRICAL
3.6 INSTRUMENTATION
3.7 MECHANICAL, SAFETY &
LIFE SAVING QUIPEMENT
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
3 of 3
PART-IV
SECTION 3.1
DESIGN CRITERIA
GENERAL
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
4 of 4
3.0 DESIGN CRITERIA
3.1 GENERAL
This bid document include design parameters, P & IDs,
electrical schematics, specifications and drawings for piping and
submarine pipelines, mechanical, electrical, instrumentation and
equipment items to convey the concept of ZB, RS-1, RS-2, RS-3,
RS-5, RS-7, RS-4, RS-8 and RS-11 well platform facilities.,
The final design of the facilities is the ultimate
responsibility of the Contractor. In doing this, the Contractor is
expected to follow the guidelines of the preliminary design as
presented herein for the works to be performed to ensure that its
intent is fulfilled. The Contractor shall also ensure that his
final design complies fully with the design philosophy and criteria
as furnished herein.
3.1.1 Objectives
The Contractors design must be done in a manner to assure that
the
following objectives will be met -
- Provide a safe and well protected facility that meets the
requirement as detailed herein and consistent with industry
accepted and good engineering practices.
- Provide facility that complies with the design parameters
and
International Codes and Standards but incorporating changes/
revisions which are not adequately covered and reflected,
considering that bid document is solely based on functional
specifications .
- Install the most appropriate equipment that will allow
optimum operation of the facility for the given design
conditions which will require a minimum of supervisory, operating
and maintenance personnel.
- Provide maximum protection to prevent environmental
pollution.
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
5 of 5
- Provide optimum use of platform space yet allow sufficient
space for operation and maintenance functions, and future
expansions.
- Provide shutdown system dedicated to a failsafe design.
- Provide convenient and safe escape route through pathway,
walkway, ladders, staircases etc.
3.1.2 Basic Environmental Conditions
3.1.2.1 The wind, tidal, wave and current parameters are defined
in report by
A.H.Glenn & Associates (relevant parameters based on this
report are included in Appendix 3.2.1). The complete report will be
given to the contractor to be used in his final design.
3.1.2.2 The minimum seabed temperature is 22.8 C (73 F).
3.1.2.3 The ambient temperature varies from a minimum of 16 C
(60 F) to a maximum of 40 C (104 F).
3.1.3 Deck Equipment Layouts
For new well platforms, Contractor shall develop deck equipment
layout keeping in view operational, maintenance and future
expansion requirement. Besides, safety and environment protection
conforming to international standards shall be adhered to.
Contractor shall ensure that all the facilities are adequately
covered to prevent damage due to dropped objects. Further,
Contractor shall ensure that the facilities (including space for
future facilities) on cellar deck shall be covered with main deck.
Deck equipment layouts contained in layout drawings represent the
desired layouts of facilities to be installed on the existing
platforms. However, Contractor is encouraged to offer alternate /
optimum deck equipment layout which will result in the optimum use
of deck space. Effects of suggested layouts on the overall
structural components shall be taken into consideration by
Contractor and shall be subject to review and approval by the
Company.
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
6 of 6
3.1.4 Noise and Vibration
The Contractor shall follow Part II, Section 5.9 of the document
-
"Offshore Installation Guidance on Design and Construction",
Department of Energy, U.K. (Latest Edition) in general and the
following specifically
- Recommended noise limits for specific work areas. - Vibration
limits for human exposure. - Guidelines to minimize noise and
vibration problems.
3.1.5 Material of Construction
The Contractor shall note that in this bid document, wherever
NACE
Carbon Steel or Carbon Steel with MR-01-75 is specified, it
shall mean NACE Carbon Steel meeting the requirement of NACE
MR-01-75 specification. This requirement shall be applicable to
risers and submarine pipelines, piping components, vessels,
instruments and other related facilities. The Contractor shall
clearly specify this requirement while procuring the necessary
equipment / piping.
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
7 of 7
PART-IV
SECTION 3.2
DESIGN CRITERIA
PROCESS
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
8 of 8
3.2 PROCESS
This section of the bid document outlines design criteria
for
Process and utility systems on ZB, RS-1, RS-2, RS-3, RS-5, RS-7,
RS-11 RS-4 and RS-8 well platforms.
In addition to above contractor shall supply loose material for
the following
- Well/string hook-up (9 well platforms) in well head area for
well fluid, lift gas system and water injection. The respective
hook-up material required for well head area shall also be handed
over as loose supply material.
= - ONE NO. MPFM as per detail mention in instrumentation
specification no 3209. The details of loose supply material are
indicated in clause 2.5 of Basic Bid Work.
General Requirements
The description, sizes, specifications, drawings furnished in
this bid document for various facilities on ZB, RS-1, RS-2, RS-3,
RS-5, RS-7, RS-11, RS-4 and RS-8 well platforms, are indicative
& minimum requirements to be provided by the Contractor. Also,
it is the Contractor's responsibility under this contract to
perform all necessary process simulations, using preferably
PROVISION or HYSIM software, and design calculations considering
adequate margins when specifying equipment. Any deviation shall
require companys approval . Contractor shall prepare process design
basis for ZB, RS-1, RS-2, RS-3 RS-5, RS-7, RS-11, RS-4 and RS-8
well platforms, (based on the design criteria indicated in this
section. On its review and approval, for ZB. RS-1,RS-2, RS-3 ,RS-5,
RS-7, RS-11, RS-4 and RS-8 well platforms, the Contractor shall
carry out simulation for different cases indicated in this criteria
and develop detailed Process Flow Diagrams In case, simulation
results show higher rates for some applications, same (higher
rates) shall be used for design
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
9 of 9
within the scope of this tender. The design of process and
associated utility systems for ZB, RS-1, RS-2, RS-3, RS-5, RS-7,
RS-11, RS-4 and RS-8 well Platforms shall be suitable for these
rates. Contractor shall also develop detailed Piping and
Instrumentation Diagrams and SAFE charts, incorporating all
suppliers information..
For ZB, RS-1, RS-2, RS-3, RS-5, RS-7, RS-11, RS-4 and RS-8
well
platforms, the routing / distribution of various utilities
(namely Vent/ CD/ OHD/ ODD headers, instrument gas, utility gas,
fire water etc.) shown in the bid P & IDs are indicative. The
Contractor shall complete these as per final engineering
requirements.
Placed below, is the list of sizing calculations/ documents/
drawings which shall be submitted by Contractor, for review and
approval
- Process Design Basis - Process Simulation Report - PFDs -
P&IDs (1st submission & subsequent revisions) - Process
Calculation Report
NOTE Contractor shall necessarily include sizing
calculations
in respect of process/ utility piping, equipment/ vessels,
safety/ relief valves, control valves, choke valves, orifice plates
etc, in above report. However, the sizing of test separator, valves
and orifice plates shall be preliminary & subject to review and
approval of calculations received from vendors/ suppliers.
- SAFE charts - Cause & Effect Diagram - Process Data Sheets
for Instruments - Process Data Sheets for Equipments - Line List -
Equipment List - Pressure & Temperature Profiles (for
pipelines) - Fire Water Hydraulic calculations ( RS-7,ZB ) - Vent
Dispersion Calculations Contractor to note that based upon review
and approval of aforesaid calculations/ documents/ drawings only,
P&IDs shall be Approved For Construction (AFC).
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
10 of 10
On ZB, RS-1, RS-2, RS-3, RS-5, RS-7, RS-11, RS-4 and RS-8
well
platforms. space provision shall be kept for installation of
future facilities as shown in P & IDs, layouts and elsewhere in
the bid document. It shall be ensured that these future facilities
can be installed and operated with ease. Engineering shall be done
to take care of future facilities. The built-up of future
facilities requirement in local and main shutdown panels are in
firm scope of supply of the Contractor. Adequate care shall be
exercised when developing the existing platforms modification
requirement with special emphasis towards safety, operability and
hook up with the existing system with minimum shutdown time
requirements. It shall be ensured that modifications to be
implemented, do not affect the safety and operability of the
systems at the existing platforms.
The following sections outline the design criteria for ZB,
RS-1,
RS-2, RS-3 RS-5, RS-7, RS-11, RS-4 and RS-8 well platforms.
Also, the size of topside piping, riser and pipeline from barrel to
barrel to be maintained same to ensure smooth piggability.
Documentation
The Contractor shall submit all documentation as per the
requirements given elsewhere in the bid document. In addition,
Contractor shall prepare 8 Nos. process packages and submit to the
Company & their Consultants, within one month of approval of
all these documents. The process package shall consist of the
following documents: - Design basis (with approved deviations, if
any) - AFC P & IDs/ Suppliers P & IDs ) - AFC Equipment
Layouts ) (A0 & A3 size & bound ) together) - PFDs &
Material Balance ) - Data Sheets for Equipments - Data Sheets for
Instruments - SAFE Charts - Logic Diagram - Line List - Equipment
List - All process / sizing calculations
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
11 of 11
3.2.1 WELL PLATFORM FACILITIES
This sub-section of the bid document defines the design criteria
for the process and utility systems required on ZB, RS-1, RS-2,
RS-3, RS-5, RS-7, RS-11, RS-4 and RS-8 well platforms. Design of
these new platforms shall be done as per the data given in this
sub-section. All the process, utility, safety and instrumentation
systems must meet the requirement of API-RP-14C Recommended
Practice for Analysis, Design, Installation and Testing of Basic
surface safety systems on offshore production platforms- Latest
Edition.
The complete platform system design shall be based on unmanned
operation requiring minimum attention for routine maintenance and
check-ups.
The process and utility systems required on each platform are
discussed in greater detail in the following clauses -
3.2.1.1 NAME OF PLATFORMS : ZB, RS-1, RS-2, RS-3 RS-5, RS-7,
RS-11, RS-4 and RS-8 (Total 9)
3.2.1.2 DESIGN LIFE : 25 years
3.2.1.3 PLATFORM LOCATION :
LOCATION WGS-84 EVEREST-1830 Bombay High Datum
(EVEREST 1830) 732625mE 732603.358mE 732778.358mE
UTM 2145375mN 2145123.510mN
2145128.510mN
19 23 20.77 19 23 18.255N
19 2318.345NZB GEOGRAPHIC
AL 7112 53.939 71 12 54.264E
71 13 00.263E
750413mE 750391.263mE 750566.263mE
UTM 2147021mN 2146769.469mN
2146774.469mNRS1 (FJ1)
GEOGRAPHICAL
1924 6.566 19 24 04.054N
19 24 04.138N
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
12 of 12
71 23 4.079 71 23 04.482E
71 23 10.481E
736875mE 736853.337mE 737028.337mE
UTM 2146625mN 2146373.496mN
2146378.496mN
19 23 59.616
19 23 57.104N
19 23 57.192NRS2 (P02) GEOGRAPHIC
AL 71 15 20.098
71 15 20.442E
71 15 26.441E
744934.789mE 744913.079mE 745088.079mE
UTM 2145186.803mN 2144935.292mN
2144940.292mN
19 23 9.378 19 23 06.862N
19 23 06.947NRS3 (P06) GEOGRAPHIC
AL 71 19 55.555
71 19 55.934E
71 20 01.932E
2136 875 mN 2136 623.512
mN 2136 628.512
mNUTM
758 375 mE 758 353.201 mE
758 528.201 mE
19o 18 33.141 N
19o 18 30.601 N
19o 18 30.683 N
RS7 (P-17)
GEOGRAPHICAL 71o 27
31.883 E71o 27 32.320
E 71o 27 38.315 E
2148 625 mN 2148 373.473 mN
2148 378.473 mN
UTM 743 625 mE 743 603.303
mE 743 778.303 mE
19o 25 01.719 N
19o 24 59.212 N
19o 24 59.298 N
RS-4 (P-04)
GEOGRAPHICAL 71o 19
12.272 E71o 19 12.646
E 71o 19 18.645 E
2138 500 mN 2138 248.537
mN 2138 253.537
mNRS-11 ( FJ-7)
UTM 739 125 mE 739 103.310
mE 739 278.31 mN
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
13 of 13
19o 19 34.522 N
19o 19 31.989 N
19o 19 32.076 N
GEOGRAPHICAL 71o 16
33.515 E71o 16 33.868
E 71o 16 39.864 E
2135 375 mN 2135 123.548
mN 2135 128.548
mNUTM
742 625 mE 742 603.285 mE
742 778.285 mE
19o 17 51.427 N
19o 17 48.885 N
19o 17 48.972 N
RS-8 (FJ-2)
GEOGRAPHICAL 71o 18
31.943 E71o 18 32.310
E 71o 18 38.305 E
2151 875 mN 2151 623.466
mN 2151 628.466
mNUTM
737 125 mE 737 103.345 mE
737 278.345 mE
19o 26 50.180 N
19o 26 47.683 N
19o 26 47.771 N
RS-5 ( P-01)
GEOGRAPHICAL 71o 15
31.022 E71o 15 31.368
E 71o 15 37.368 E
3.2.1.4 DESTINATION OF WELL FLUID : BHN (from RS-5)
SA/BHS (from RS-1,RS-3, RS-4)
SH Complex (from RS-7)
ID (from RS-8 )
IC (from ZB,RS-2, RS-11)
3.2.1.5 FIELD MAP : REFER DRAWING VOLUME - IV
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
14 of 14
3.2.1.6 PLATFORM CAPACITY (STOCK TANK CONDITION)
Platformwise, production rates for ZB, RS-1, RS-2, RS-3,
RS-5,
RS-7, RS-11, RS-4 and RS-8 well platforms are placed below
:-
ZB PLATFORM MAX.OIL/ GAS/ MAX.WATER MAX.
CASE CASE LIQUID
OIL, BOPD 13667 997 1 1734
WATER, 3778 16615 7765 BWPD LIQUID, 17445 17612 19499
BLPD TOTAL GAS 0.746 0.462 0.677
MMSCMD
RS-1 PLATFORM MAX.OIL/ MAX.WATER MAX.
CASE CASE LIQ/GAS
OIL, BOPD 3791 1202 4927
WATER, 4210 9560 6543
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
15 of 15
BWPD LIQUID, 8001 10762 11471
BLPD TOTAL GAS 0.228 0.305 0.402 MMSCMD
RS-2 PLATFORM MAX.OIL/ GAS/ MAX.WATER MAX.
CASE CASE LIQUID
OIL, BOPD 3019 807 2421
WATER, 12579 14999 13501
BWPD LIQUID, 15598 15805 15922 BLPD TOTAL GAS 0.320 0.282 0.302
MMSCMD RS-3 PLATFORM MAX.OIL/ GAS/ MAX.WATER MAX.
CASE CASE LIQUID
OIL, BOPD 4032 2909 3185
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
16 of 16
WATER, 10944 12082 12125 BWPD LIQUID, 14976 14991 15310 BLPD
TOTAL GAS 0.516 0.476 0.486 MMSCMD
RS-4 PLATFORM MAX.OIL/ GAS/ MAX.WATER LIQUID CASE CASE
OIL, BOPD 3951 743
WATER, 6096 7975
BWPD LIQUID, 10047 8718
BLPD TOTAL GAS 0.406 0.30 MMSCMD
RS-5 PLATFORM MAX.OIL/GAS MAX.WATER . LIQUID CASE CASE
OIL, BOPD 5865 1641 WATER, 6734 9446 BWPD
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
17 of 17
LIQUID, 12599 11088 BLPD TOTAL GAS 0.594 0.508 MMSCMD
RS-7 PLATFORM MAX.OIL/ GAS MAX.WATER
LIQUID CASE CASE
OIL, BOPD 2201 780
WATER, 702 1030 BWPD LIQUID, 2904 1810 BLPD TOTAL GAS, 0.383
0.374 MMSCMD
RS-8 PLATFORM MAX.OIL/GAS MAX.WATER
. LIQUID CASE CASE
OIL, BOPD 2527 478 WATER, 6871 7671 BWPD LIQUID, 9398 8149 BLPD
TOTAL GAS, 0.253 0.221 MMSCMD
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
18 of 18
RS-11 PLATFORM MAX.OIL MAX.WATER MAX. LIQUID/
. CASE CASE GAS
CASE OIL, BOPD 3908 857 3616
WATER, 4928 9152 7684 BWPD LIQUID, 8836 10009 11300 BLPD TOTAL
GAS, 0.427 0.362 0.431 MMSCMD Additionally, surge factor of 25% on
max. well fluid flow rates and
swell factor of min. 15% on oil flow rates shall be considered
for the design of topside facilities.
3.2.1.7 WELL DATA
3.2.1.7.1 WELL CONFIGURATION
ZB WELL PLATFORM
No. of Wells to be drilled : 12 (twelve) nos. No. of Producers :
11 (eleven) nos. (single completion) No .of injector : One no.
(Single completion)
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
19 of 19
No.of free slots : Nill
RS-1 WELL PLATFORM
No. of Wells to be drilled : 6 (six) nos. No. of Producers : 6
(six) nos. (5 nos. single completion & 1 nos. duel
completion)
No .of free slots : Nil
RS-2 WELL PLATFORM
No. of Wells to be drilled : 5 (five) nos. No. of Producers :
5(five nos single completion) No .of free slots : 1 (one ) nos.
RS-3 WELL PLATFORM
No. of Wells to be drilled : 6 (six) nos. No. of Producers : 6
(4 nos. single completion& 2 nos. Duel completion) No .of free
slots : Nil
RS-5 WELL PLATFORM
No. of Wells to be drilled : 6 (six) nos. No. of Producers : 6
(six) nos. 4 nos. (single completion) 2 nos. (Duel completion) No
.of free slots : 3 (three ) nos.
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
20 of 20
RS-7 WELL PLATFORM
No. of Wells to be drilled : 7 (seven) nos. No. of Producers : 5
(five) nos. 5 nos. (single completion )
No. of water injector : 2 (two) nos. 2 nos. (single completion)
No. of free slots : .
RS-11 WELL PLATFORM
No. of Wells to be drilled : 5 (five) nos. No. of Producers : 5
(five) nos. 2 nos. (single completion) 3 nos.(Duel completion) No.
of free slot(s) : 4 (four) nos. RS-4 WELL PLATFORM
No. of Wells to be drilled : 5 (five) nos. No. of Producers : 5
(five) nos. 4 nos.( single completion) one(dual ompletion wells)
No. of free slots : 1 (one)
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
21 of 21
RS-8 WELL PLATFORM
No. of Wells to be drilled : 4 (four) nos. No. of Producers : 4
(four) nos. 3 nos. single completion 1 no. dual completion No. of
free slots : 2 (two ) 3.2.1.7.2 PRODUCER WELL CAPACITY PER STRING
(STOCK
TANK CONDITION) FOR ZB, RS-1, RS-2, RS-3, RS-5, RS-11, RS-4,
RS-8 PLATFORM
LIQUID (BLPD) : 4000
OIL PERCENTAGE : UPTO 100 (OF TOTAL LIQUID) WATER PERCENTAGE :
UPTO 94
(OF TOTAL LIQUID) GLR (SM/M) : 250
3.2.1.7.3 PRODUCER WELL CAPACITY PER STRING (STOCK TANK
CONDITION) FOR RS-7 PLATFORM
LIQUID (BLPD) : 4000
OIL PERCENTAGE : UPTO 100 (OF TOTAL LIQUID) WATER PERCENTAGE :
UPTO 75
(OF TOTAL LIQUID) GLR (SM/M) : 1150
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
22 of 22
3.2.1.7.4 WELL FLUID CHARACTERISTICS : As per ANNEXURE-1
3.2.1.8 WELL HEAD CONDITIONS AFTER CHOKE
Pressure, kg/cm (g) : 15-21
Temp. degree C : 60 - 93
3.2.1.9 BASIS FOR DESIGN OF TOPSIDE FACILITIES (WELL FLUID)
All topside facilities shall be designed for a design pressure
and
design temperature of 93.7 kg/cm(g) and 104 degree Centigrade,
respectively, unless indicated otherwise.
3.2.1.10 CHEMICAL INJECTION SYSTEM
Oil Corrosion Inhibitor (OCI) injection shall be carried out
using
associated gas pressure and max. possible gravity head. For
separating associated gas from well fluid, a pipe separator shall
be installed. Contractor shall ensure that the pipe separator size
shall be adequate to fulfill gas requirement of OCI storage vessel
and IUG System.
3.2.1.10.1 OIL CORROSION INHIBITOR SYSTEM
Service : Production / test header and departing
well fluid pipeline Associated gas source : Pipe Separator
Chemical : COREXIT-7730 or equivalent Dosage rate : 60 ppm (wt)
of max. well fluid flow rate @ 30 ppm (wt) of max flow at each,
prod/
test header and departing well fluid pipeline
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
23 of 23
Storage capacity : 15 days Dilutant : Nil
Mode of Injection : Associated gas pressure and gravity head
3.2.1.10.2 BACTERICIDE AND OXYGEN SCAVENGER
No permanent facilities shall be provided for injecting the
above
chemicals. Bactericide and oxygen scavenger shall be injected
through the connection provided for this purpose into the departing
well fluid line using portable pump. Provision for hooking up of
portable pump to the well fluid departing line shall be
provided.
3.2.1.11 WELL TESTING
Platform shall be provided with adequate facilities for well
testing
which shall include the following:
3.2.1.11.1 PRODUCTION MANIFOLD The wellhead producer well
strings (flow arms) shall be connected to
test and production headers. 3.2.1.11.2 TWO-PHASE TEST SEPARATOR
& CORIOLIS BASE MASS FLOW METER
Well/strings testing facility shall include two-phase test
separator complete with shut-down panel, safety and control system
etc. along with coriolis based mass flow meters (latest generation)
in its gas & liquid outlet piping to measure gas, oil &
water flow rates produced from selected individual wells/strings
.
Quantity : One
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
24 of 24
Capacity : As described in Clause 3.2.1.7.2 (producer well
string capacity)
Type : 2- phase, Horizontal Separator
Surge factor : 25% on maximum well fluid
flow
Swell factor : 15% minimum
Liquid Residence Time : 3 minutes (min.) on maximum liquid flow
including surge and swell
Design Basis : International Codes & Standards
Operating Pressure, Kg(Cmg) : 15-21
Operating Temperature, C : 60-93
Design Pressure, Kg(Cmg) : 47.0
Design Temperature C : 104.0
Max. Liquid Level : Centre line of horizontal vessel (including
surge)
Liquid carryover in gas : Max. 13.4 Litres/ MMSCM of gas. Liquid
particle size should not be more than 10 micron
Minimum nozzle size for the vessel shall be fixed by vendor
depending upon requirement for glass flake filled vinyl ester
lining. The system shall be designed for the following components
in gas phase - CO2 : 3% H2S : 230 ppm
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
25 of 25
Water : Saturated Mol. Wt. : 21-24
Testing facilities shall conform to API-RP-14C and other
international standards.
Contractor shall have complete responsibility for process
guarantee
of test separator and coriolis based mass flow meters and their
integration with other facilities on ZB, RS-1, RS-2, RS-3, RS-5,
RS-7, RS-11, RS-4 and RS-8 well platforms for well testing
requirement and not limited to design criteria, specification, data
sheet etc. included in bid document.
Further, the specifications in respect of two-phase test
separator and water cut meter, though, included in the bid
document, yet Contractor shall have the liberty to suggest
modifications in the same and put-up for companys approval, to
achieve the intent of scope of work. Contractor shall also develop
specification for coriolis based mass flow meter (for gas outlet)
and submit to Company for review and approval.
3.2.1.12 CRUDE CONDENSATE VESSEL
3.2.1.12.1 PURPOSE : To collect liquid from Closed Drain
Headers (CDH) and Open Hydrocarbon Drain (OHD) Headers
3.2.1.12.2 HOLD-UP : 2 M (Minimum)
3.2.1.12.3. LIQUID DISPOSAL : To departing well fluid pipeline
based upon blow-case design & utilizing lift gas/ instrument
& utility gas for blow down of liquid into the departing
pipeline
Contractor shall review the blow-case design indicated in bid P
& IDs and incorporate necessary changes for automatic blow down
(without any manual intervention) of crude/ condensate into well
fluid pipeline, within the scope of this tender. Further,
Contractor
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
26 of 26
shall demonstrate that the final blow-case design adopted shall
remain operational under all operating conditions and meet safety
requirements.
3.2.1.14 SAFETY AND RELIEF SYSTEM
Platform Safety Relief System including ESD & FSD shall
be
designed as per API-RP-14C. All vents shall be discharged to a
relief (vent) header which shall be connected to a vent boom
located at a safe distance from platform. Vent boom shall be at
such an angle, height and distance from the main deck so that H2S
and HC gas concentration, on the platforms shall remain within
acceptable limits for personnel safety under worst conditions.
Contractor shall carry out dispersion analysis considering all
production scenario and worst environmental conditions based on
which the vent boom extension / elevation shall be decided.
3.2.1.15 FIRE AND GAS DETECTION & FIRE SUPPRESSION
Various fire and gas detection and fire suppression facilities
shall be
provided to ensure safe operation of the platform. These shall
include:-
- Fixed HC Gas Detection, Alarm and Shutdown System - Portable
HC Gas Detectors (2 nos. for each platform) - Portable CO2 &
DCP Fire Extinguisher
- ESD and FSD provisions Relevant codes e.g. API-RP-14C &
NFPA shall be followed. (A list
of codes is attached as APPENDIX 3.2.1).
3.2.1.15.1 Dry Chemical System
Dry chemical system shall comprise of a minimum 3 no. skids
of
350 lb. each, one each on cellar deck, main deck and
helideck.
3.2.1.16 DIESEL STORAGE
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
27 of 27
Diesel shall be stored in the deck crane pedestal. The size
shall be sufficient to cater for 48 hrs. continuous operation of
the deck crane.
3.2.1.17 LAUNCHERS/ RECEIVERS
PLATFORM LAUNCHERS/ RECEIVERS
ZB i) 16 WF launcher (to ICD)
ii) 6 LG Receiver (from IB) iii) 6 WI Receiver (from IQ) iv) 2
Nos.12 Launcher/Receiver (Space only)
RS-1 i) 10 WF launcher (to SA)
ii) 6 LG Receiver (from SC1) iii) 2 Nos.12 Launcher/Receiver
(Space only)
RS-2 i) 12 WF launcher (to ICD)
ii) 6 LG Receiver (from NM) iii) 2 Nos. 12 Launcher/Receiver
(Space only)
RS-3 i) 12 WF launcher (to BHS)
ii) 6 LG Receiver (from SA/BHS) iii) 2 Nos. 12 Launcher &
Receiver (Space only)
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
28 of 28
RS-5 i) 12 WF launcher (to BHN)
ii) 6 LG Receiver (from NM) iii) 2 Nos.12 Launcher/ Receiver
(Space only)
RS-4 i) 12 WF launcher (to BHS)
ii) 6 LG Receiver (from SB) iii) 2 Nos.12 Launcher/Receiver
(Space only)
RS-8 i)10 WF launcher (to ID)
ii) 4 LG Receiver (from ID) iii) 2 Nos.12 Launcher/Receiver
(Space only)
RS-7 i) 12 WF launcher (to SH Complex)
ii) 6 LG Receiver (from SH
Complex)
iii) 6 Receiver for water injection (from ED)
iv) 2 Nos. 12 Launcher/ Receiver (Space only)
RS-11 i) 12 WF launcher (to ICD)
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
29 of 29
ii) 4 LG Receiver (from ICP) iii) 2 Nos. 12 Launcher &
Receiver (Space only)
3.2.1.18 INSTRUMENT AND UTILITY GAS SYSTEM
Lift gas will be used as the primary source of Instrument and
Utility
Gas. During start-up and failure of lift gas, associated gas
separated from well fluid in pipe separator shall be used for
meeting instrument and utility requirements. The instrument and
utility gas system shall primarily consist of utility gas cooler/
air cooled finned pipe heat exchanger, pressure reduction system,
filter separator, instrument gas receiver and hairpin type double
pipe heat exchanger alongwith piping, safety and instrumentation
items.
.
3.2.1.18.1 Purpose
The system shall be provided to cater to the requirement of
instrumentation, blowing down crude / condensate to departing well
fluid pipeline and pneumatic supply to OCI transfer pump.
3.2.1.18.2 Operation and Philosophy
The pipe separator shall be operated continuously for OCI
Injection system and also, as fall back arrangement for inst./
utility gas.
3.2.1.18.3 Gas Conditioning System
Inlet Gas Conditions
Pressure, kg/cmg - Normal/minimum/Design : 8/7.5/10.6
Temperature, Deg. C - Normal/minimum/Design : 60/40/75
3.2.1.18.4 The Gas Conditioning System (including Instrument Gas
System and
Utility Gas System) and Instrument Gas System shall be designed
for minimum 80 NM/hr. and 25 NM/hr., respectively. However, the
Contractor shall consider higher of the utility gas requirement
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
30 of 30
(OCI transfer pump and blow down requirement for crude/
condenste vessel) plus Instrument Gas Requirement (Max.) for
deciding the total capacity of Gas Conditioning System.
Gas conditioning system consists of the following equipment
-
ITEM CAPACITY NUMBER TYPE
i) Utility Gas To meet the requirement One Finned Pipe Cooler
Cooler/ Air of inst. & utility gas (*)_ Cooled Finned Pipe Heat
Exchanger
(*) Shall be manifolded with multiple smaller bore pipes having
extended surfaces.
ii) IG/UG Filter To meet the requirement One -
Separator of inst.& utility gas
iii) Hairpin type To meet the requirement One Based on heat
double pipe of instrument gas transfer from
prod. heat exchanger header to inst.
gas 3.2.1.18.5 HAIRPIN TYPE DOUBLE PIPE HEAT EXCHANGER
The Instrument / Utility gas downstream of filter separator
remain
saturated and not having required dew point for proper
functioning of the instruments as well as OCI transfer pump.
In view of above, a hairpin type double pipe heat exchanger
is
envisaged downstream of instrument gas receiver. It is
anticipated that the Instrument / Utility gas will get heat from
the well fluid flowing in the production header.
The design of hairpin type double pipe heat exchanger shall be
based
on providing 10 degree superheat to Instrument / Utility gas.
This
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
31 of 31
heat exchanger may preferably be kept in the scope of Instrument
/ Utility gas System vendor who shall demonstrate and provide all
necessary back-up calculations to prove that the system being
supplied is capable enough to fulfill the design criteria and also,
even after pressure reduction, the instrument gas shall remain
condensate free for smooth operation of instruments.
3.2.1.18.6 INSTRUMENT GAS RECEIVER Number : One Capacity : 15
minutes requirement between
normal and minimum pressure Pressure, kg/cm(g)
Normal/min./Design : 7.5/5.5/10.6 Temperature, deg. C
Normal/Min./Design : 55/30/10
3.2.1.19 WATER INJECTION FACILITIES FOR ZB
Water injection facilities shall be provided on ZB well platform
only, as per following details:-
Source of injection water : IQ well platform No. of wells on
water injection : 3 nos. (*) (all single completion)
Injection Pressure (at well head) : 95.0 kg/cm2g
* Well ZB#JH is an injector well. ZB#CH & #EH shall be
converted from producer to injector subsequently.
Departing and arrival pressure and temperature for IQ - ZB
water
injection pipeline are given below
Sl.No. Pipeline Departing Arrival
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
32 of 32
Pres.,kg/cm2g Temp.,deg c Pres.,kg/cm2g Temp.,deg c IQ ZB 1
IQ-ZB
103.0 28 96.0 28 Injection Water shall be hooked up with fire
water header after
pressure reduction and serve as source of water for fire
suppression in case of FSD on ZB well platform.
Water injection facilities shall be designed for the following
flow
rates
SM3/day Sl.No. Max. Nor. Min.
1 ZB Platform - Wellwise 1600 1000 500 - Total 3000 2400 500
3.2.1.20 WATER INECTION FOR RS-7
Water injection facilitiesbe provided on RS-7 well platform , as
per following details:-
Source of injection water : ED well Platform No. of wells on
water injection : 2 nos. (*) (all single completion)
Injection Pressure (at well head) : 95.0 kg/cm2g Departing and
arrival pressure and temperature for ED- RS-7 water
injection pipeline are given below
Departing Arrival Sl.No. Pipeline Pres.,kg/cm2g Temp.,deg c
Pres.,kg/cm2g Temp.,deg c
1 ED-RS-7 ED RS-7
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
33 of 33
133.14 27.47 133 36.98 Injection Water shall be hooked up with
fire water header after
pressure reduction and serve as source of water for fire
suppression in case of FSD on RS-7 well platform.
Water injection facilities shall be designed for the following
flow
rates
SM3/day Sl.No. Max. Nor. Min.
1 RS-7 Platform - RS-7 BH 1000 750 350 RS-7 CH 400 250 150 Total
1400 1000 500
3.2.1.21 BASIS FOR DESIGN OF TOPSIDE FACILTIES (INJECTION
WATER) All topside facilities shall be designed for a design
pressure and
design temperature of 151.6 kg/cm (g) and 55 deg Centigrade,
respectively.
3.2.1.22 LIFT GAS FACILITIES FOR ZB,RS-1,RS-2,RS-3
Lift gas facilities shall be provided as per following
details:
Source Lift gas facilities : IB platform (for ZB) SC1 platform
(for RS1) NM platform (for RS2) SA/BHS platform (for RS3) No. of
producer wells on gas lift :
- 11 nos. (all single compl.) on ZB platform - 6 nos. (5 nos.
single compl. & one dual compl.) on RS1 platform - 5 nos. (all
single compl.) on RS2 platform
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
34 of 34
- 6 nos. (4 nos. single compl. & 2 nos. dual compl.) on RS3
platform
Injection Pressure (at well head) : 80.0 kg/cm2g Departing and
arrival pressure and temperature for lift gas pipelines
are given below
Departing Arrival Sl.No. Pipeline Pres.,kg/cm2g Temp.,deg c
Pres.,kg/cm2g Temp.,deg c
IB ZB 1 IB-ZB 88.0 27 83.0 25
SC1 RS1 2 SC1-RS1 86.7 29 84.8 28
NM RS2 3 NM-RS2 85.0 28 83.8 26
SA RS3 4 BHS-RS3 87.1 36 85.3 27
Lift gas facilities shall be designed for the following flow
rates
MMSCMD Sl.No. Max. Nor. Min.
1 ZB Platform - Wellwise 0.06 0.03 - 0.045 0.01 - Total 0.506
0.405 0.02 2 RS1 Platform - Wellwise 0.075 0.03 0.06 0.01 - Total
0.300 0.240 0.02 3 RS2 Platform - Wellwise 0.06 0.03 0.045 0.01 -
Total 0.338 0.270 0.02 4 RS3 Platform - Wellwise 0.1125 0.045 0.090
0.01 - Total 0.413 0.330 0.02
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
35 of 35
Lift gas pipelines shall be designed for a design pressure and
design temperature of 105.0 kg/cmg and 75 deg. centigrade,
respectively.
Lift Gas composition : As per
ANNEXURE-2 Lift gas facilities shall include Lift Gas Manifold,
lift gas flow arm
piping, instrumentation, safety system and etc.
3.2.1.23 LIFT IES FOR RS-5,RS-7,RS-11,RS-4,RS-8 ` Lift gas
facilities shall be provided as per following details:
Source : NM Platform for RS-5 : SH Complex for RS-7 : IC complex
for RS-11 : SB Platform for RS-4 : ID Platform for RS-8 No. of
producer wells on gas lift :
- 6 nos. ( 4 nos.single compl & 2 nos. dual compl..) on RS-5
platform
- 5 nos. (5 nos. single compl. ) on RS-7 platform - 5 nos. (2
nos. single compl& 3 nos. dual compl..) on RS-11
platform - 5 nos. (4 nos. single compl. & 1 no. dual compl.)
on RS-4
platform - 4 nos. (3 nos. single compl. & 1 no. dual compl.)
RS-8 platform
Injection Pressure (at well heads) : 80.0 kg/cm2g
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
36 of 36
Departing and arrival pressure and temperature for lift gas
pipelines are given below
Departing Arrival Sl.No. Pipeline Pres.,kg/cm2g Temp.,deg c
Pres.,kg/cm2g Temp.,deg c
NM RS-5 1 NM RS-5 - - 84.47 30.00
SHP RS-7 2 SHP-RS-7 95.0 58 94.09 21.32
IC RS-11 3 IC-RS-11 89.0 55 87.10 29.80
SB RS-43 4 SB-RS-4 83.0 24 83.013 22.72
ID RS-8 5. ID- RS-8 84.4 24 81.55 27.30
Lift gas facilities shall be designed for the following flow
rates
MMSCMD Sl.No. Max. Nor. Min.
1 RS-5 Platform - Wellwise 0.075 0.03 - 0.06 0.01 - Total 0.60
0.36 0.02 2 RS-7 Platform - Wellwise 0.075 0.03 0.06 0.01 - Total
0.325 0.225 0.02 3 RS-11 Platform - Wellwise 0.06 0.03 0.045 0.01 -
Total 0.48 0.30 0.02 4 RS4 Platform - Wellwise 0.105 0.045 0.090
0.01 - Total 0.63 0.405 0.02 5 RS-8 Platform - Wellwise 0.06
0.03-0.06 0.01 - Total 0.30 0.225 0.02
Lift gas pipelines shall be designed for a design pressure and
design
temperature of 105.0 kg/cmg and 75 deg. centigrade,
respectively.
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
37 of 37
Lift Gas composition : As per
ANNEXURE-2 Lift gas facilities shall include KO Drum, lift gas
manifold, lift gas
flow arm piping, instrumentation, safety system and etc.
3.2.1.24 KO Drum
3 KO Drum is proposed to be installed downstream of scrapper tee
for removal of liquid condensed in lift gas pipeline. Contractor
shall size KO Drum considering separation of 15 lb/ MMSCF liquid.
However, size of KO Drum shall be maintained same on all 5 nos.
well platforms. The P&ID and process data sheets are placed
elsewhere in the bid document. Bidder shall review the P&ID and
process data sheets and suggest necessary changes for automatic
drainage (no manual drainage envisaged) of liquid into well fluid
pipeline, within the scope of this tender.
3.2.1.25 BASIS FOR DESIGN OF TOPSIDE FACILTIIES (LIFT GAS)
All topside facilities shall be designed for a design pressure
and
design temperature of 105.0 kg/cm (g) and 75 deg Centigrade,
respectively.
3.2.1.26 MATERIAL OF CONSTRUCTION (Topside Facilities)
Material of Corrosion
Construction Allowance
WELL FLUID : CS-NACE 6 MM
LIFT GAS : CS-NACE 6 MM
INJECTION WATER : CS 3 MM
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
38 of 38
3.2.1.27 RTU PARAMETERS
In general, RTU parameters required to be monitored are shown in
P&IDs. However, these are indicative and minimum and Contractor
is required to supplement the same, based on the list placed at
ANNEXURE-4.
.
3.2.1.28 FLOW METER SPECIFICATIONS
Contractor shall develop specifications in respect of coriolis
based mass flow meter (latest generation) and multi beam (online)
ultrasonic flowmeter (latest generation) and submit to company for
review and approval. The observations made by Company shall be duly
considered and incorporated for final approval before placement of
the order for the these items.
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
39 of 39
ANNEXURE-1
(Sheet 1 of 4) WELL FLUID COMPOSITION (TYPICAL) MUMBAI HIGH
FIELD
COMPONENT FOR GOR-703 MOL PERCENT (ON DRY BASIS)* N2 1.16 CO2
3.00 H2S 0.023 C1 69.994 C2 5.866 C3 4.409 IC4 0.879 NC4 1.064 IC5
0.197 NC5 0.169 C6 0.089 CUT-1 2.093 CUT-2 0.639 CUT-3 1.873 CUT-4
1.086 CUT-5 1.174 CUT-6 0.973 CUT-7 0.657 CUT-8 0.968 CUT-9 0.773
CUT-10 0.633 CUT-11 0.401 CUT-12 1.880 ------------- 100.0000
--------------
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
40 of 40
(Sheet 2 of 4)
PSEUDO-CUT DETAILS
CUT ABP (DEG C) SP GR CUT-1 40 0.645 CUT-2 65 0.702 CUT-3 95
0.767 CUT-4 125 0.778 CUT-5 155 0.796 CUT-6 185 0.799 CUT-7 215
0.801 CUT-8 245 0.840 CUT-9 275 0.848 CUT-10 305 0.862 CUT-11 335
0.863 CUT-12 465 0.888 * THIS IS A TYPICAL WELL FLUID
COMPOSITION.
CONTRACTOR SHALL GENERATE THE COMPOSITION OF WELL FLUID FOR
OTHER GORs AND ALSO, FOR LIFT GAS BASED ON INFORMATION FURNISHED IN
THIS DATA SHEET.
CRUDE OIL PROPERTIES API GRAVITY AT 60 degree F : 38-40 B.S.
& W, % VOL. : TRACES POUR POINT, degree C : 27.0 WAX CONTENT, %
WT : 14-15% w/w RVP OF STABILISED CRUDE : 0.7 kg/cmA(Max.)
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
41 of 41
(Sheet 3 of 4)
VISCOSITY : AS PER TABLE BELOW
TYPICAL CRUDE OIL VISCOSITY (CP) DATA AT DIFFERENT
TEMPERATURES
1st Stage Separator Sample
(Collected at 14 kg/cmg & 85C)
2nd Stage Separator Sample (Collected at 3.5 kg/cmg &
85C)
3rd Stage Separator Oil Sample
(Collected at Atmospheric
Temp. & Pressure)
Oil Sample from Storage Tanker (Temp. 18C)
Temp Increas-ing
Temp.
Decreas-ing
Temp.
Reheat-ing
Cooling
Increas-ing
Temp/
Decreas-ing
Temp.
Increas-ing
Temp/
Decreas-ing
Temp.
Increas-ing
Temp/
Decreas-ing
Temp.
24C Ball does not roll
Ball does not roll
Ball does not roll
- - - - - -
26C 4.9827 -do- -do- - Ball does not roll
18.2242*
- - -
28C 3.9370 -do- -do- Ball does not roll
2.7762 - - Ball does not roll
Ball does not roll
29C - 2.8903 -do- 3.5561 - - - - -
30C 3.5936 2.4961 2.4746 3.5136 1.4455 4.5309 Ball does not
roll
5.4875 3.2371
35C 2.8276 2.2177 2.2249 3.0789 1.2244 See Note
4
4.4834 -do- 4.9931 3.0115
40C 2.5279 1.9677 2.0396 2.7728 1.0891 4.2723 2.9075 4.7326
2.8282
50C 2.1858 1.8047 1.7688 2.0455 0.9613 2.6399 2.1525 2.5252
2.1624
80C - - - - - 1.3316 1.2488 - -
* Repeat experiments at 28C showed inconsistent roll
timings.
1) Viscosity of 1st Stage Separator sample was determined at 14
kg/cmg. 2) Viscosity of 2nd Stage Separator sample was determined
at 3.5 kg/cmg.
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
42 of 42
(Sheet 4 of 4)
3) Viscosity of 3rd Stage Separator Oil and Storage tanker oil
sample was determined at atmospheric pressure.
4) Viscosity of 2nd Stage Separator sample with decreasing
Temperature
are not as they are expected to be.
AVERAGE FORMATION WATER ANALYSIS
COMPONENT mg/l Ca++ 290
Mg++ 36
Na+ and K+ as Na+ 9483
Cl- 14200
SO4= 230
CO3= 120
HCO3= 1281
TDS 25640
Salinity AS Nacl 23400
TSS 40
pH 8.3
Sp. Gr.@ 30C 1.018
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
43 of 43
ANNEXURE-2
LIFT GAS COMPOSITION - MUMBAI HIGH FIELD COMPONENT MOL%
N2 1.365 CO2 3.475 C1 81.613 C2 6.505 C3 4.314 IC4 0.706 NC4
0.764 IC5 0.094 NC5 0.068 C6 1.070 H2S 0.026
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
44 of 44
APPENDIX- 3.2.1 List of applicable codes for Fire Suppression
System and design of other well platform facilities as applicable-
- National Fire protection Association (NFPA)
- American Petroleum Institute (API) RP 55
- American Petroleum Institute RP 14 C
- American Petroleum Institute RP 14 G
- American Petroleum Institute RP 2 G
- American Petroleum Institute RP 14 E
- American Petroleum Institute RP 500
- National Electric Code (NEC)
- National Electrical Manufacturer's Association (NEMA)
- UK Department of Energy (DOE)
- Offshore Installations : Guidelines on Design and
Construction.
- Under writers Laboratory Inc, PTB, BASSEEFA or equivalent
Testing
Institution
- Instrument Society of America (ISA)
- Recommended Practices
- Other relevant Codes and good engineering practices followed
in the industry.
-
OFFSHORE
DESIGN
MUMBAI
VOL-II REV. 0
Section - 3
DESIGN CRITERIA
9 Well Platforms Project
Sheet
45 of 45
ANNEXURE-3
LIST OF RTU PARAMETERS
I. WELL PLATFORM - Well head pressure - Flow arm temperature -
SSSV status - SSV status - Main well fluid line pressure - Main
well fluid line temperature - Main gas lift injection line pressure
- Main gas lift injection line temperature - Gas lift injection
pressure (well wise) - Gas lift injection differential pressure
(well wise) - Water injection pressure at well head - Instrument
gas header pressure - Battery charging current - Battery voltage -
Annulus pressure A section - Annulus pressure B section - Annulus
pressure C section II. PROCESS PLATFORM (for monitoring at Control
Room / elsewhere) - Well platform flow line pressure (Incoming) -
Well platform flow line temperature (Incoming) - Gas lift line flow
rate (outgoing) - Gas lift line pressure (outgoing) - Gas lift line
temperature (outgoing) - Water injection line pressure (Outgoing) -
Water injection line flow rate (Outgoing)