ITA ITA / / AITES AITES DFTU 25 års Jubilæumsmøde # ITA ITA / / AITES AITES 1 02.10.2008 Presentation by Jørgen Holst 1 02.10.2008 Velkommen / Welcome Copenhagen 2. October 2008 - 25th Anniversary Dansk Forening for Tunnel - og Undergrundsarbejder 1983 til 2008 Danish Society for Tunnels and Underground Works 1983 to 2008
26

Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

Jul 01, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

1 02.10.2008 Presentation by Jørgen Holst

1 02.10.2008

Velkommen / Welcome Copenhagen 2. October 2008 - 25th Anniversary

Dansk Forening for Tunnel - og Undergrundsarbejder

1983 til 2008

Danish Society for Tunnels and Underground Works

1983 to 2008

Page 2: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

2 02.10.2008 Presentation by Jørgen Holst

2 02.10.2008

DFTU 1983 to 2008

The Danish Tunnel Society was "born" 12th September 1983

The initiative to establish the Society was mostly related to:

– Vejdirektoratet / Danish Road Directorate &

– DSB / Danish State Railways

The objectives:

– Networking among Danish Engineers

– International Tunnel Association (ITA)

– Promote tunnel industri in general

– Knowledge sharing by organising

Excursions to Construction Sites

Meetings and Seminars with presentations of tunnel and underground projects under planning, design and construction

Page 3: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

3 02.10.2008 Presentation by Jørgen Holst

DFTU 1983 to 2008

The Society has been chaired by

– Preben Avnstrøm, DSB/Danish State Railways 1983 - 1987

– Hans Henrik Gotfredsen, Vejdirektoratet/Great Belt Link 1987 - 1993

– Ole Steen Christensen, MT Højgaard 1993 - 1999

– Anders Odgaard, COWI/Metroselskabet 1999 - 2005

– Jørgen Holst, COWI 2005 -

Page 4: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

4 02.10.2008 Presentation by Jørgen Holst

4 02.10.2008

DFTU 1983 - 2008, Tunnelling during 25 years Guldborgsundtunnelen 1984 - 1988

Immersed Tunnel with 2 tubes and 4 lanes

Length ~ 1200 m

Contractor: PIHL and Armton

Designer: Christiani & Nielsen

Page 5: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

5 02.10.2008 Presentation by Jørgen Holst

5 02.10.2008

DFTU 1983 - 2008, Tunnelling during 25 years Great Belt East Tunnel 1988/1998

East Tunnel, length 8.024 m

Two tubes carrying 1 rail in each, 31 Cross-over Tunnels

Deapest point ~ approx. 75 m below normal sea level

4 TBM were in action

Contractor: Monberg & Thorsen (MT Hojgaard)

Page 6: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

6 02.10.2008 Presentation by Jørgen Holst

6 02.10.2008

DFTU 1983 - 2008, Tunnelling during 25 years Great Belt East Tunnel 1988/1998

Page 7: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

7 02.10.2008 Presentation by Jørgen Holst

7 02.10.2008

DFTU 1983 - 2008, Tunnelling during 25 years Sydhavnsgadetunnelen 1993 - 1997

Cut and Cover Tunnel

Length ~ 1600 m

1 tube carrying 2 rails

10 - 15 m below ground level

Contractor: NPL/SIAB

Design: Grontmij l Carl Bro

Page 8: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

8 02.10.2008 Presentation by Jørgen Holst

8 02.10.2008

DFTU 1983 - 2008, Tunnelling during 25 years Tårnbytunnelen 1994 - 1998

Cut and Cover Tunnel, Combined Road and Rail Tunnel

Length ~ 700 m

4 tubes carrying 2 rails and 4 lanes

Includes Tårnby Railway Station

Part of Øresund Link

Design: Grontmij l Carl Bro

Page 9: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

9 02.10.2008 Presentation by Jørgen Holst

9 02.10.2008

DFTU 1983 - 2008, Tunnelling during 25 years Øresundstunnelen 1994 - 2000

Immersed Tunnel, Combined Road and Rail Tunnel + Service Gallery

Length ~ 4.050 m including portals

20 Tunnel Elements

4 tubes carrying 2 rails and 4 lanes

Contractors: Øresund Tunnel Contractors (NCC, PIHL +)

Page 10: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

10 02.10.2008 Presentation by Jørgen Holst

10 02.10.2008

DFTU 1983 - 2008, Tunnelling during 25 years Øresundstunnelen 1994 - 2000

Page 11: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

11 02.10.2008 Presentation by Jørgen Holst

11 02.10.2008

DFTU 1983 - 2008, Tunnelling during 25 years Limfjordstunnelen 1993 - 2001, Main Rehab.

Immersed Road Tunnel, 2 tubes, 3 lanes each

Opened in 1969 - Aalborg

Length ~ 945 m

Post-tensioning of tunnel structure

Renewal of M&E + ITS systems

Repair Costs: 200 mio. DKr. (Priceindex 1997)

Page 12: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

12 02.10.2008 Presentation by Jørgen Holst

12 02.10.2008

DFTU 1983 - 2008, Tunnelling during 25 years Limfjordstunnelen 1993 - 2001, Main Rehab.

Page 13: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

13 02.10.2008 Presentation by Jørgen Holst

13 02.10.2008

DFTU 1983 - 2008, Tunnelling during 25 years Copenhagen Metro 1993 - 2007

Ørestadsselskabet / Metroselskabet I/S

Phase I opened October 2002

Phase II a + II b / May and October 2003

Phase III opened in September 2007 (Kastrup)

TBM & NATM Methods

21 km in total, 10 km underground metro including 9 undergroundstations

Page 14: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

14 02.10.2008 Presentation by Jørgen Holst

14 02.10.2008

DFTU 1983 - 2008, Tunnelling during 25 years District Heating Tunnel 2005 - 2009

Client: Københavns Energi

Contractor: MT Højgaard (DK) + Hochtief Construction (D)

Consultants: COWI

Contract form: Partnering

Length ~ 3,9 km, D = 5.1 m, EPB shield TBM

Level ~ 35 to 40 m in Copenhagen Limestone

Tunnel break - through in April 2007

Page 15: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

15 02.10.2008 Presentation by Jørgen Holst

15 02.10.2008

DFTU 1983 - 2008, Tunnelling during 25 years Other Underground Works completed

New Opera House "Operaen", Copenhagen Harbour Front

New Royal Theater "Nye Skuespilhus", Copenhagen Harbour Front

Automated Underground Parking facilities, Copenhagen City Center

"Forsinkelsesbassin" på Sct. Annæ Plads (MT Højgaard)

CTR tunneling (naturgas project in 1980's)

NCC tunneling, Faroe Islands

And many many more projects

Page 16: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

16 02.10.2008 Presentation by Jørgen Holst

16 02.10.2008

DFTU 1983 - 2008, Tunnelling for the Future Potential Tunnel Projects

Nordhavnsforbindelsen (EIA on-going)

Copenhagen Municipality as developer

Cut & Cover Solution (Rambøll) Bored Tunnel Solution (Rambøll)

Page 17: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

17 02.10.2008 Presentation by Jørgen Holst

17 02.10.2008

DFTU 1983 - 2008, Tunnelling for the Future Potential Tunnel Projects

Roskilde Fjord Crossing (EIA on-going) Vejdirektoratet / Road Directorate

Short Immersed Tunnel Solution (Vejdirektoratet)

Page 18: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

18 02.10.2008 Presentation by Jørgen Holst

18 02.10.2008

DFTU 1983 - 2008, Tunnelling for the Future Potential Tunnel Projects

Silkeborg, Kombilinien decided 2008, Vejdirektoratet / Road Directorate

350 m Cut & Cover Solution (Vejdirektoratet)

Page 19: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

19 02.10.2008 Presentation by Jørgen Holst

19 02.10.2008

DFTU 1983 - 2008, Tunnelling for the Future Potential Tunnel Projects

Marselis Boulevard Tunnel, Aarhus Municipality (EIA on-going)

2.100 m Cut & Cover Road Tunnel Solution (Grontmij l Carl Bro) Uni-directional tunnel, 2 x 2 lanes, EU supported infrastructure project

Page 20: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

20 02.10.2008 Presentation by Jørgen Holst

20 02.10.2008

DFTU 1983 - 2008, Tunnelling for the Future Potential Tunnel Projects

Copenhagen Harbour Tunnel - 20, 30, 40 billion DKr? Project

Cross section, 12 km Immersed Tunnel Solution (Københavnertunnelen Aps) Many solutions have been considered along Copenhagen Harbour

Page 21: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

21 02.10.2008 Presentation by Jørgen Holst

21 02.10.2008

DFTU 1983 - 2008, Tunnelling for the Future Potential Tunnel Projects

New Limfjord Tunnel ? Status unknown at the moment

New Immersed Tunnel Parallel Solution (Vejdirektoratet/Road Directorate)

Page 22: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

22 02.10.2008 Presentation by Jørgen Holst

22 02.10.2008

DFTU 1983 - 2008, Tunnelling for the Future Potential Tunnel Projects

Copenhagen Metro Cityring - Phase 4 (Phase V, VI ……)

New 15,5 km TBM Tunnel Solution including 17 new underground MetroStations 2007 - 2018 (Metroselskabet)

Page 23: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

23 02.10.2008 Presentation by Jørgen Holst

23 02.10.2008

DFTU 1983 - 2008, Tunnelling for the Future Potential Tunnel Projects

Fehmarnbelt Fixed Link (DK/D Agreement signed 3. September 2008), 2008 - 2018

Immersed Tunnel Solution ? or Bridge Solution ?

Page 24: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

24 02.10.2008 Presentation by Jørgen Holst

24 02.10.2008

DFTU 1983 - 2008, Tunnelling for the Future Potential Tunnel Projects

Fehmarnbelt Fixed Link 2008 - 2018

Immersed Tunnel Solution ? or Bridge Solution ?

Page 25: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

25 02.10.2008 Presentation by Jørgen Holst

25 02.10.2008

DFTU 1983 - 2008, Tunnelling for the Future Other Potential Tunnel & Underground Projects

Helsingør - Helsingborg (Rail/Road Tunnel)

Tunnel on the Faroe Islands (12 km Road Tunnel, Sandø - Strømø)

New East Randers Fjord Crossing (Road Tunnel, EIA on-going)

Copenhagen City (H.C. Andersens Boulevard) (Road Tunnel)

Automated Underground Parking Facilities in City Centers expected to continue many years ahead

And many many more projects are foreseen to be realised going underground due to environmental aspects (noise and pollution)

Page 26: Velkommen / Welcome Copenhagen 2. October 2008 - 25th ...dftu.dk/25aar/velkomst.pdf · ITA/AITES # DFTU 25 års Jubilæumsmøde ITA/AITES 5 02.10.2008 Presentation by Jørgen Holst

ITAITA//AITESAITES

DFTU 25 års Jubilæumsmøde #

ITAITA//AITESAITES

26 02.10.2008 Presentation by Jørgen Holst

26 02.10.2008

DFTU 1983 - 2008, Tunnelling for the Future Other Potential Tunnel & Underground Projects

Once Again - Welcome to all of You

and do enjoy

the next presentations

and a social very good evening