Managed by UT-Battelle for the Department of Energy Vector Control Algorithm for Efficient Fan-out RF Power Distribution Yoon W. Kang SNS/ORNL Fifth CW and High Average Power RF Workshop March 25-28, 2008
Managed by UT-Battellefor the Department of Energy
Vector Control Algorithm for Efficient Fan-out RF Power
Distribution
Yoon W. Kang
SNS/ORNL
Fifth CW and High Average Power RF Workshop
March 25-28, 2008
2 Managed by UT-Battellefor the Department of Energy Presentation_name
Motivation
Fan-out RF distribution with one higher power amplifier feeding multiple cavities may save construction/installation cost significantly especially in high power SRF linear accelerator projects
If a fixed power splitter is used with Vector Modulators in the fan-out system, power overhead is required for proper amplitude control
– Each cavity load needs one vector modulator that consists of two phase shifters and two hybrids
– The vector modulator dissipates the power difference between the input and the output
It is desirable to maximize the RF power to beam efficiency for further savings in operation
– Almost no power overhead is required - deliver only the beam power to the cavities with right RF voltages
An algorithm for fan-out RF distribution and control as a whole system is presented
3 Managed by UT-Battellefor the Department of Energy Presentation_name
Use of Vector Modulator
This gives the output amplitude and phase of the vector modulator in terms of the phase shift of each of the two phase shifters.
For a fixed input power, unused power PL is lost output
RF Control
Vector Modulator
input
2
2cos
21
21
out
in
out
A
A
P L
4 Managed by UT-Battellefor the Department of Energy Presentation_name
Comparison of RF Power Distribution Systems One klystron/one
cavity
Fan-out one klystron with Vector Modulators – power overhead requirement
Fan-out one klystron with no overhead power
PS
PS
Cavities
Amplifiers
RF Signals &Controls
VectorModulators+ Controls
Cavities
Amplifier
PS
RF Control
Cavities
Amplifier
5 Managed by UT-Battellefor the Department of Energy Presentation_name
Fan-out RF Distribution
1. Distributing RF power to N-loads through a transmission line network – a parallel connection
2. If the spacing Si = M(/2), Ls, Zs, and Bs can supply the specified voltages to the load – a series connection
3. A variation to the above case
6 Managed by UT-Battellefor the Department of Energy Presentation_name
Fan-out System Control using Transmission-line Sections and Reactive Loads
A set of specified voltages [Vi] can be supplied to the load cavities by adjusting the transmission-line impedances, lengths, and reactive loadings
This can be seen as a narrow-band multi-port impedance matching network
– Di = physical spacing between cavities
– di = length of transmission section between cavities
– Vi = voltage delivered to the cavity input
– Zi = transmission-line characteristic impedance
– Xi = reactive load
7 Managed by UT-Battellefor the Department of Energy Presentation_name
Network Parameters
A two-port network is used as a building block of a multi-port network synthesis
Various configurations are realizable: series fed, parallel fed, mixed, etc.– Network with parallel connections can be synthesized and analyzed by
using short-circuit admittance matrices [Z]– Network with series connections can be synthesized and analyzed by
using open-circuit impedance matrices [Y] Short-circuit admittance parameters [Y] are useful for network consists of
elements in parallel connections Using [Y], the voltages and currents of a two port network are related as
where
2
1
2
1
V
V
yy
yy
I
I
of
ri
)0(1
111
2
V
i V
Iyy
)0(2
112
1
V
r V
Iyy
)0(1
221
2
V
f V
Iyy
)0(2
222
1
V
o V
Iyy
8 Managed by UT-Battellefor the Department of Energy Presentation_name
System Equation (I)
PSS VYI
LTPS YYYY
PN
PPPtP VVVVV 1321
Consider an array of N-cavity loads connected to a transmission-line network. Let [VP] be the port voltage vector of a set of specific cavity excitations for an optimum operation.
where the short-circuit terminal admittance matrix of the whole system
[YP] = port admittance matrix for the cavities,
[YT] = short circuit admittance matrix of the transmission line network,
and [YL] = load admittance matrix.
The relation between the terminal currents [IS] and the terminal voltages [VP] is
[1]
9 Managed by UT-Battellefor the Department of Energy Presentation_name
System Equation (II)
Nin
in
in
in
p
Y
Y
Y
Y
Y
,
3,
2,
1,
000
000
000
000
The port admittance matrix only with the loads with no couplings between the cavities
If a cavity is mismatched, the port admittance matrix at the input of a cavity is found as:
cL
co
co
cL
oin djYdY
djYdYYY
sincos
sincos
)(1
)(1
z
zZZ oL
where Yo and dc are the characteristic impedance and the length of the transmission line connects the cavity to the network, respectively, YL is the cavity load impedance, and is the phase constant. The load is related to the reflection coefficient
11
332222
22221111
1111
cot000
0)cotcot(csc0
0csc)cotcot(csc
00csccot
NN
T
djY
dYdYjdjY
djYdYdYjdjY
djYdjY
Y
The transmission line admittance matrix
10 Managed by UT-Battellefor the Department of Energy Presentation_name
System Equation (III)The reactive load admittance matrix
N
L
jB
jB
jB
Y
00
00
00
2
1
1 SS YZ
The input impedance is found by selecting the element Zii in impedance matrix [Zs]
If the n-th terminal is used for feeding, only In =1 in the current matrix
01000 tSI
mTmm
Pm
Tmm
Pm
Tmm
Pm
Tmm
Pm
Tm
Pm
inmnm
S BjVdVYdVYdVYdVYjVyI )}csc()cot()cot()csc({ 111111
From the m-th element of the current vector is found as
(for m=1, 2, ..N) where n is the feed port index.
The above equations can be solved for a specified load voltages [VP] if any one out of the three parameters is given: transmission-line characteristic admittances, transmission-line lengths, and reactive loads. If a standard transmission line impedance YS is used, the lengths dm (dm-1), and reactive loads Bm can be found. YS
m-1 (YSm ) and, dm-1 (dm) are given so that the dm (dm-1), and reactive loads Bm are
found.
LTPS YYYY
11 Managed by UT-Battellefor the Department of Energy Presentation_name
Generalized RF Distribution
The lengths of the transmission line sections and the reactive loads are related to the phase shifts as
The transmission-line lengths and reactive loads can be realized by using high power phase shifters
nTn d )(cot 1
onLn YB
C1 C2 Ci-1
2
V1 V2 Vi-1 Vi
i-1
Z1 Z2 Zi-1 Zi
IS
Ci+1
Vi+1 Zi+1
CN-1 CN
VN-1 VNZN-1
-2i
r,1 r,2 r,i-1 r,N
r,i
r,i+1 r,N-1
z
m
m
o
o eV
V
ZzZ
ZzZz 2
)(
)()(
where voltage reflection coefficient (z)
If the loads are mismatched loads, the voltage standing wave in the transmission line section between the cavity and the input port is
)}(1{)()( zezVzV zjo
The voltage vector can be defined for no power (Vi = 0), forward power, or standing wave with the reflection coefficient (z)
12 Managed by UT-Battellefor the Department of Energy Presentation_name
Input Matching
The total power delivered to the loads is the sum of real power at the loads and must be identical to the output power of the klystron
C1 C2 C3
2
V1 V2 V3VN
i
Z1 Z2 Z3ZN
IS
CN-1
VN-1 ZN-1
-1
r,Nr,1 r,2 r,3 r,N-1
Pf
Pf
Pi
N
i
Pi
PPP YVYVVYVP2
1
2*
The feed terminal voltage is found from the above expression for a desired input impedance.
The voltage vectors are reconstructed to include the input that has an impedance specified. This constraints the input to be matched to the generator output
PNPf
PPPtP VVVVVV 321
C1 C2 C3
2
V1 V2 V3
i
Z1 Z2 Z3
IS
CN-1
VN-1 ZN-1
r,1 r,2 r,3 r,N-1
The voltage distribution is done, but the input of the network is not impedance matched to the source impedance
The input of the network can be impedance matched to a source with a specific source impedance by adding one more port
13 Managed by UT-Battellefor the Department of Energy Presentation_name
Simplified Fan-out System
PS
PhaseShifters
Cavities
KlystronRF Control
FP
DC
FP
DC
DC
Driverto PhaseShifters
Using proposed fan-out approach requires matching LLRF control system that must be developed
14 Managed by UT-Battellefor the Department of Energy Presentation_name
Procedure Summay and Consideration
Directional coupler at each cavity input measures cavity coupling (and load impedance)
A set of voltage vectors is defined for the required cavity RF voltages (amplitudes and phases)
The system equation is solved for the transmission line phase delays and the reactive loads at the ports
Phase shifters are tuned to the computed values The resultant voltages are read back and adjusted with FF and FB The above steps can be repeated
For a system with N- load cavities, followings are need to deliver the required voltages at the cavity coupler inputs with completely matched klystron amplifier output– N phase shifters between the terminals (transmission-line sections)– N+1 phase shifters at all terminals (reactive loads)
Fast high power phase shifters are needed Amplifier output control
15 Managed by UT-Battellefor the Department of Energy Presentation_name
Example12 cavities @ f = 805 MHz,cavities are critically coupled
Cavity Distance (m) Voltage (V) Zo () di (m) jBi ()
1 1.50 1.0000 0 50.0000 1.8742 - 0.0056i
2 1.50 1.0500 10 50.0000 1.8690 - 0.0026i
3 1.50 1.1000 20 50.0000 1.8673 + 0.0020i
4 1.50 1.1500 30 50.0000 1.8664 + 0.0056i
5 1.50 1.2000 40 50.0000 1.8659 + 0.0088i
6 1.50 1.2500 50 50.0000 1.8330 + 0.0715i
7 (3.9083 0 ) 50.0000 - 0.0544i
8 1.50 1.2500 50 50.0000 1.8330 + 0.0715i
9 1.50 1.2000 40 50.0000 1.8659 + 0.0088i
10 1.50 1.1500 30 50.0000 1.8664 + 0.0056i
11 1.50 1.1000 20 50.0000 1.8673 + 0.0020i
12 1.50 1.0500 10 50.0000 1.8690 - 0.0026i
13 1.50 1.0000 0 50.0000 1.8742 - 0.0056i
V1 V2
Vf
Vi
d1 d2
VN-1 VN
Zo
jB1 jB2 jBN+1
C1C1 CN
dN+1
16 Managed by UT-Battellefor the Department of Energy Presentation_name
Example - 4 Cavities
C2 C3 C4
VM1 VM2 VM3 VM4
1:1Splitter
2:1Splitter
2:1Splitter
C1
Amp
Using vector modulators
– Each VM employs two phase shifters and two hybrid power splitters
Using proposed fan-out approach
– Nine phase shifters are needed
– No circulator is needed
C1 C2 C3
d d2
jB1 jB2 jB3
V1 V2 V3 d
C4
jB4
V4 d
jBf
Zo AmpVf
17 Managed by UT-Battellefor the Department of Energy Presentation_name
Example – 4 Cavities4 cavities @ f = 402.5 MHz
cavities are critically coupled
Cavity Distance (m) Voltage (V) Zo () di (m) jBi ()
1 1.00 0.8000 0 50.00 1.5375 - 0.0070i
2 1.00 0.9000 20 50.00 1.5161 - 0.0017i
3 1.00 1.0000 40 50.00 1.5090 + 0.0065i
4 1.00 1.1000 60 50.00 1.4289 + 0.0175i
5 (50.00 input)
- 0.0233i
C1 C2 C3
d d2
jB1 jB2 jB3
V1 V2 V3 d
C4
jB4
V4 d
jBf
Zo AmpVf
18 Managed by UT-Battellefor the Department of Energy Presentation_name
Conclusion The proposed fan-out power distribution system can eliminate power
overhead to achieve efficient operation The fan-out system can be controlled as a whole to deliver the exactly
required amplitudes and phases of RF voltages at the cavities only with phase shifters
– Any cavities missing or need to be disabled in the system can be set to have 0 voltage vector
Phase delays and reactive loads at the cavity ports of the transmission line network are found by solving a network equation for a case using a standard transmission-line impedance
This system can also be seen as an adjustable narrow-band N-port power splitter or impedance matching network
The phase delays and reactive loadings can be realized by using high power fast phase shifters
– System bandwidth will still be dependent on the response of High power fast phase shifters are necessary
For practical waveguides, slight modification of the system admittance matrices will have to be made