MUNICIPALIDAD DISTRITAL DE RIO GRANDE M D R G SUB GERENCIA DE SUPERVISION Y LIQUIDACION VALORIZACION MENSUAL Nº 02 NOVIEMBRE DEL 2015 PROCESO : EX0 - PROC - 4 - 2015 - MDRG/CE O B R A: CONTRATISTA : CONSORCIO RANCHERIA SUPERVISOR : ING. MIGUEL ANGEL HERNANDEZ ESPINO RESIDENTE : ING. WILLIAM ROBERTO MEDINA ZEA FECHA : AL 30 DE NOVIEMBRE DEL 2015 “INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
31
Embed
VALORIZACION N° 02 CONSORCIO RANCHERIA - PALPA 2015 II
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
MUNICIPALIDAD DISTRITAL DE RIO GRANDE
M D R G
SUB GERENCIA DE SUPERVISION Y LIQUIDACION
VALORIZACION MENSUAL Nº 02
NOVIEMBRE DEL 2015
PROCESO : EX0 - PROC - 4 - 2015 - MDRG/CE
O B R A :
CONTRATISTA : CONSORCIO RANCHERIA
SUPERVISOR : ING. MIGUEL ANGEL HERNANDEZ ESPINO
RESIDENTE : ING. WILLIAM ROBERTO MEDINA ZEA
FECHA : AL 30 DE NOVIEMBRE DEL 2015
“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
FICHA DE IDENTIFICACION DE LA OBRA
1 Obra :
2 Ubicación : ICA
Region : ICA
Departamento : UCA
Provincia : PALPA
Distrito : RIO GRANDE
Localidad : CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO
Area Geografica : 2
3 Cliente : MUNICIPALIDAD DISTRITAL DE RIO GRANDE
4 Contratista : CONSORCIO RANCHERIA
5 Financiamiento : TRANSFERENCIA DEL GOBIERNO REGIONAL DE ICA
6 Sistema de Contratacion : EXONERACION
7 Modalidad de Contratacion Contractual : EXONERADO
8 Tipo de Proceso : EXO - PROC - 4 - 2015 - MDRG/CE
9 Presupuesto Base : S/. 1,090,409.40 con I.G.V. 924,075.76 sin I.G.V.
10 Contrato Nº :
11 Factor de Relacion (Fr) : 1.00000
12 Monto del Contrato : S/. 1,090,409.40 con I.G.V. 924,075.76 sin I.G.V.
13 Monto para la Elaboracion del Expediente Tecnico : S/. con I.G.V. 0.00 sin I.G.V.
14 Monto para la Ejecucion de la Obra : 1,090,409.40 con I.G.V. 924,075.76 sin I.G.V.
15 Plazo Contractual : 90 dias calendarios
16 Plazo de Ampliacion de plazo Nº 01 : 0 dias calendarios
17 Plazo de Ejecucion de Obra : 90 dias calendarios
18 Costo Directo de la Obra : S/. 803,544.13
19 Gastos Generales : S/. 80,354.41 10.00%
20 Utilidad : S/. 40,177.21 5.00%
21 Monto del Adelanto Directo - Ejecucion de Obra 20% : S/. 454,849.03 con I.G.V. 385,465.28 sin I.G.V.
22 Monto del Adelanto Directo - Expediente Tecnico : S/. 0.00 con I.G.V. 0.00 sin I.G.V.
23 Monto del Adelanto para Materiales : S/. 0.00 con I.G.V. 0.00 sin I.G.V.
Eventos:
24 Fecha del Valor Referencial : May-2015
25 Fecha de Firma de Contrato : 27-September-2015
26 Fecha de Designacion del Supervisor de Obra :
27 Fecha de cambio de Residente de Obra :
28 Fecha de Aprobacion de Expediente Tecnico :
29 Fecha de Entrega de Terreno : 16-October-2015
30 Fecha de Pago de Adelanto Directo :
31 Fecha de Inicio Contractual : 17-October-2015
32 Fecha de Fin Contractual : 14-January-2016
33 Ampliaciones de Plazo :
34 Nueva Fecha de Fin Contractual :
34 Adicionales de obra : Ninguna
“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS
RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE
RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
OBRA :CONTRATISTA : CONSORCIO RANCHERIASUPERVISOR : ING. MIGUEL ANGEL HERNANDEZ ESPINORESIDENTE : ING. WILLIAM ROBERTO MEDINA ZEAFECHA : AL 30 DE NOVIEMBRE DEL 2015
DESCRIPCIONVALORIZACION
ANTERIOR ACTUAL ACUMULADOA: VALORIZACION CONTRACTUAL
001 - RED DE ALCANTARILLADO 714,993.81 280,261.02 192,077.85 472,338.87 66.06% 242,654.94002 - LAGUNA 209,081.95 0.00 0.00 0.00 0.00% 209,081.95
TOTAL (A) 924,075.76 280,261.02 192,077.85 472,338.87 451,736.89
AVANCE FISICO DE OBRA 30.33% 20.79% 51.12% 48.88%B: REAJUSTES
001 - RED DE ALCANTARILLADO 0.00 0.00 0.00002 - LAGUNA 0.00 0.00 0.00
TOTAL (B) 0.00 0.00 0.00VALORIZACION BRUTA (VB=A+B) 280,261.02 192,077.85 472,338.87
D: AMORTIZACIONESAMORTIZACION DEL ADELANTO EN EFECTIVO 0.00 0.00 0.00 0.00 0.00AMORTIZACION DEL ADELANTO PARA MATERIALES
E: RETENCIONESFONDO DE GARANTIA (5%*VB) 0.00 0.00 0.00GASTOS DE LICITACION 0.00 0.00 0.00MULTA POR ATRASO DE OBRA 0.00 0.00 0.00
TOTAL (E) 0.00 0.00 0.00
F: MONTO A PAGAR AL CONTRATISTAEN EFECTIVO 280,261.02 192,077.85 472,338.87EN I.G.V. (18%*VN) 50,446.98 34,574.01 85,020.99
TOTAL (F) 330,708.00 226,651.86 557,359.86
TOTAL COMPROMISO A SOLICITAR 226,651.86
% CRONOGR VALORIZ PROGRA ACUML 16.77%
% CRONOGR VALORIZ FISICO ACUMLADO 51.12% CRON VAL
% % PROG ACUML %
ANALISIS COMPARATIVO AL 80% 51.12% 80.00% 40.90% ≤ 51.12%
OBRA: ATRASADA
“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
MONTO CONTRATO (S/IGV)
% AVANCE ACUMULADO
SALDO POR VALORIZAR
M D R G
COEFICIENTE DE REAJUSTE
PROCESO : EX0 - PROC - 4 - 2015 - MDRG/CE
OBRA :
CONTRATISTA : CONSORCIO RANCHERIASUPERVISOR : ING. MIGUEL ANGEL HERNANDEZ ESPINORESIDENTE : ING. WILLIAM ROBERTO MEDINA ZEAFORMULA 01 : RED DE ALCANTARILLADO AREA GEOGRAFICA: 2 ICA
K = 0.351*(Mr/Mo) + 0.340*(CFr/CFo)+ 0.158*(MMDr/MMDo)+0.151*(Ir/Io) PAG. 01
SIMBOLO ELEMENTO REPRESENTATIVO CODIGOOCT'2015 NOV'2015 DIC'2015 ENE'2016 FEB'2012Ir K Ir K Ir K Ir K Ir K
M MANO DE OBRA (INC. LEYES SOC.) 47 0.351 100.00% 523.15 544.59523.15 544.59 0.365 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000
CF CEMENTO PORTLAND TIPO I 21 0.340 99.118% 367.31 367.31FLETE TERRESTRE 32 0.882% 469.08 467.08
MMD DÓLAR MAS INFLAMAQCION USA Y DUCTO DE 31 0.158 2.532% 398.72 398.29MAQUINARIA Y EQUIPO IMPORTADO 49 62.025% 282.51 288.48MADERA NACIONAL PARA ENCOFRADO Y CARP 43 35.443% 603.32 612.75
COEFICIENTE DE REAJUSTE: K = 1.000 K (NOV-15) = 1.019 K (DIC-15) = 0.000 K (ENE-16) = 0.000 K (FEB-12) 0.000 K (MAR-12) 0.000
“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
COEF. INCIDEN
CIA
% INCIDENCI
A
Io IND.BASE SET 2010
M D R G
COEFICIENTE DE REAJUSTE
PROCESO : EX0 - PROC - 4 - 2015 - MDRG/CE
OBRA :
CONTRATISTA : CONSORCIO RANCHERIASUPERVISOR : ING. MIGUEL ANGEL HERNANDEZ ESPINORESIDENTE : ING. WILLIAM ROBERTO MEDINA ZEA
“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
FORMULA 02 : LAGUNA DE AGUAS RESIDUALES AREA GEOGRAFICA: 2 ICA
K = 0.171*(Mr/Mo) + 0.254*(CMr/CMo)+ 0.428*(Mr/Mo)+0.147*(Ir/Io) PAG. 02
SIMBOLO ELEMENTO REPRESENTATIVO CODIGOOCT'2015 NOV'2015 DIC'2015 ENE'2016 FEB'2016Ir K Ir K Ir K Ir K Ir K
M MANO DE OBRA (INC. LEYES SOC.) 47 0.171 100.00% 532.15 544.59532.15 544.59 0.175 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000
CM CEMENTO PORTLAND TIPO I 21 0.254 91.73% 367.31 367.31MADERA NACIONAL PARA ENCOFRADO Y CARP 43 8.27% 603.32 612.75
“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
VALORIZACION DE OBRA No 02
NOVIEMBRE DEL 2015
RESUMEN
OBRA
PROPIETARIO MUNICIPALIDAD DISTRITAL DE RIO GRANDE
CONTRATISTA CONSORCIO RANCHERIA
SUPERVISION ING. MIGUEL ANGEL HERNANDEZ ESPINO
FECHA PRES BASE 15 de mayo de 2015
Presupuesto Base: 1,090,409.40 (con IGV)
Monto del Contrato: 1,090,409.40 (con IGV) 924,075.76 (sin IGV)
01 RED DE ALCANTARILLADO 714,993.81 280,261.02 192,077.85 0.00 0.00 472,338.87
02 LAGUNA 209,081.95 0.00 0.00 0.00 0.00 0.00
SUB TOTAL 924,075.76 280,261.02 192,077.85 0.00 0.00 472,338.87
100.00% 30.33% 20.79% 0.00% 0.00% 51.12%
“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO
GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
VALORIZACION DE OBRA No 02
NOVIEMBRE DEL 2015
RESUMEN
Valorización Saldo por
% Valorizar
66.06% 242,654.94
0.00% 209,081.95
451,736.89
48.88%
INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO
GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
VALORIZACION DE OBRA Nº 02(Periodo : NOVIEMBRE 2015)
Obra :“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
Ubicación : DISTRITO DE RIO GRANDE - PALPA - ICA
Tipo de Proceso : EX0 - PROC - 4 - 2015 - MDRG/CE
Contratista : CONSORCIO RANCHERIA
Plazo de Ejecucion : 90 DIAS CALENDARIOS Valor Referencial (S/.) : 1,090,409.40 con IGV
Supervisor : ING. MIGUEL ANGEL HERNANDEZ ESPINO Costos al : May-2015
Residente : ING. WILLIAM ROBERTO MEDINA ZEA Monto del Contrato (S/.) : 1,090,409.40 con IGV
Factor de Relacion : 1.0000
Formula : 001 RED DE ALCANTARILLADO
ITEM DESCRIPCION DE PARTIDAPRESUPUESTO
AVANCESSALDO
ANTERIOR ACTUAL ACUMULADO
UNIDAD METRADO PARCIAL Metrado Monto % Metrado Monto % Metrado Monto % Metrado Monto %
01.00 OBRAS PROVISIONALES01.01 CASETA PARA OFICINA Y ALMACEN GLB 1.00 3,279.6000 3,279.60 1.00 3,279.60 100.00% 0.00 0.00 0.00% 1.00 3,279.60 100.00% 0.00 0.00 0.00%01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS, MAQUINARIAS Y HERRAMIENTAS GLB 1.00 2,779.6800 2,779.68 0.33 917.29 33.00% 0.33 917.29 33.00% 0.66 1,834.59 66.00% 0.34 945.09 34.00%01.03 TRANQUERA DE MADERA MOVIL PARA DESVIACION VEHICULAR Y/O PEATONAL UND 8.00 126.4700 1,011.76 4.00 505.88 50.00% 4.00 505.88 50.00% 8.00 1,011.76 100.00% 0.00 0.00 0.00%01.04 SEÑALIZACION EN OBRA (CINTA DE SEGURIDAD) M 3,360.27 0.8600 2,889.83 1,680.14 1,444.92 50.00% 840.07 722.46 25.00% 2,520.20 2,167.37 75.00% 840.07 722.46 25.00%01.05 PUENTE DE MADERA PARA PASE PEATONAL UND 8.00 144.3700 1,154.96 2.00 288.74 25.00% 6.00 866.22 75.00% 8.00 1,154.96 100.00% 0.00 0.00 0.00%01.06 SERVICIOS HIGIENICOS PORTATILES MES 4.00 450.0000 1,800.00 1.00 450.00 25.00% 3.00 1,350.00 75.00% 4.00 1,800.00 100.00% 0.00 0.00 0.00%02.00 TRABAJOS PRELIMINARES 0.00 0.00 0.00 0.00 0.00 0.00 0.0002.01 TRAZO, NIVELES Y REPLANTEO EN REDES DE ALCANTARILLADO M 3,360.27 0.6000 2,016.16 2,688.22 1,612.93 80.00% 672.05 403.23 20.00% 3,360.27 2,016.16 100.00% 0.00 0.00 0.00%03.00 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 0.00 0.00 0.00 0.0003.01 EXCAVACION CON EQUIPO T.N. P/TUBERIA ALCANTARILLADO H<=1.00 m. M 23.25 5.1800 120.43 0.00 0.00 0.00% 23.00 119.14 98.92% 23.00 119.14 98.92% 0.25 1.30 1.08%03.02 EXCAVACION CON EQUIPO T.N. P/TUBERIA ALCANTARILLADO 1.00<H<=1.50 m. M 2,003.38 5.6000 11,218.93 814.00 4,558.40 40.63% 985.00 5,516.00 49.17% 1,799.00 10,074.40 89.80% 204.38 1,144.53 10.20%03.03 EXCAVACION CON EQUIPO T.N. P/TUBERIA ALCANTARILLADO 1.50<H<=2.00 m. M 210.68 8.5500 1,801.31 99.70 852.44 47.32% 44.40 379.62 21.07% 144.10 1,232.06 68.40% 66.58 569.26 31.60%03.04 EXCAVACION CON EQUIPO T.N. P/TUBERIA ALCANTARILLADO 2.00<H<=2.50 m. M 195.93 10.7700 2,110.17 80.31 864.94 40.99% 80.00 861.60 40.83% 160.31 1,726.54 81.82% 35.62 383.63 18.18%03.05 EXCAVACION CON EQUIPO T.N. P/TUBERIA ALCANTARILLADO 2.50<H<=3.00 m. M 15.51 12.2200 189.53 0.00 0.00 0.00% 15.51 189.53 100.00% 15.51 189.53 100.00% 0.00 0.00 0.00%03.06 EXCAVACION CON EQUIPO T.N. P/TUBERIA ALCANTARILLADO 3.00<H<=3.50 m. M 172.52 14.9400 2,577.45 34.50 515.49 20.00% 82.30 1,229.56 47.70% 116.80 1,745.05 67.70% 55.72 832.40 32.30%03.07 EXCAVACION MANUAL DE ZANJA PARA TENDIDO DE TUBERIA a= 0.80 m. HASTA 3.70 m. APROX. M 657.40 116.5100 76,593.67 347.25 40,458.10 52.82% 0.00 0.00 0.00% 347.25 40,458.10 52.82% 310.15 36,135.58 47.18%03.08 EXCAVACION MANUAL PARA BUZON EN TERRENO GRAVOSO H<=1.00 m. M3 4.42 31.1100 137.51 0.00 0.00 0.00% 4.42 137.51 100.00% 4.42 137.51 100.00% 0.000000 0.00 0.00%03.09 EXCAVACION MANUAL PARA BUZON EN TERRENO GRAVOSO 1.00<H<=1.50 m. M3 125.26 35.5600 4,454.25 125.26 4,454.25 100.00% 0.00 0.00 0.00% 125.26 4,454.25 100.00% 0.00 0.00 0.00%03.10 EXCAVACION MANUAL PARA BUZON EN TERRENO GRAVOSO 1.50<H<=2.00 m. M3 28.75 41.4800 1,192.55 28.75 1,192.55 100.00% 0.00 0.00 0.00% 28.75 1,192.55 100.00% 0.00 0.00 0.00%03.11 EXCAVACION MANUAL PARA BUZON EN TERRENO GRAVOSO 2.00<H<=2.50 m. M3 14.48 49.7800 720.81 14.48 720.81 100.00% 0.00 0.00 0.00% 14.48 720.81 100.00% 0.00 0.00 0.00%03.12 EXCAVACION MANUAL PARA BUZON EN TERRENO GRAVOSO 2.50<H<=3.00 m. M3 5.83 62.2100 362.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.83 362.68 100.00%03.13 EXCAVACION MANUAL PARA BUZON EN TERRENO GRAVOSO 3.00<H<=3.50 m. M3 55.69 82.9501 4,619.49 0.00 0.00 0.00% 33.20 2,753.94 59.62% 33.20 2,753.94 59.62% 22.49 1,865.55 40.38%03.14 EXCAVACION MANUAL PARA BUZON EN TERRENO GRAVOSO 3.50<H<=4.00 m. M3 7.84 124.4300 975.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.84 975.53 100.00%03.15 ENTIBADO DE ZANJAS DESDE 2.00m A 3.70m DE PROF M 383.96 44.8600 17,224.45 153.58 6,889.78 40.00% 135.60 6,083.02 35.32% 289.18 12,972.79 75.32% 94.78 4,251.65 24.68%03.16 REFINE Y NIVELACION DE ZANJA PARA TUBERIA M 3,278.67 3.7900 12,426.16 983.60 3,727.85 30.00% 1,880.00 7,125.20 57.34% 2,863.60 10,853.05 87.34% 415.07 1,573.11 12.66%03.17 CAMA DE APOYO E=0.10cm, M 3,278.67 5.3300 17,475.31 2,295.07 12,232.72 70.00% 452.60 2,412.36 13.80% 2,747.67 14,645.08 83.80% 531.00 2,830.24 16.20%03.18 RELLENO COMPACTADO CON MATERIAL PROPIO; H<1.00m M 23.25 9.4300 219.25 0.00 0.00 0.00% 23.25 219.25 100.00% 23.25 219.25 100.00% 0.00 0.00 0.00%03.19 RELLENO COMPACTADO ZANJAS P/TUBERIA ALCANTARILLADO 1.00<H<= 1.50 m. M 2,003.38 10.1000 20,234.14 801.35 8,093.66 40.00% 0.00 0.00 0.00% 801.35 8,093.66 40.00% 1,202.03 12,140.48 60.00%03.20 RELLENO COMPACTADO ZANJAS P/TUBERIA ALCANTARILLADO 1.50<H<=2.00 m. M 210.68 11.5900 2,441.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 210.68 2,441.78 100.00%03.21 RELLENO COMPACTADO ZANJAS P/TUBERIA ALCANTARILLADO 2.00>H<=2.50 m. M 195.93 16.5500 3,242.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 195.93 3,242.64 100.00%03.22 RELLENO COMPACTADO ZANJAS P/TUBERIA ALCANTARILLADO 2.50<H<=3.00 m. M 15.51 16.6900 258.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.51 258.86 100.00%03.23 RELLENO COMPACTADO ZANJAS P/TUBERIA ALCANTARILLADO 3.00<H<=3.50 m. M 172.52 22.7800 3,930.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 172.52 3,930.01 100.00%03.24 RELLENO COMPACTADO ZANJAS MANUAL P/TUBERIA ALCANTARILLAD0 M 657.40 25.8100 16,967.49 262.96 6,787.00 40.00% 113.50 2,929.44 17.26% 376.46 9,716.43 57.26% 280.94 7,251.06 42.74%03.25 ELIMINACION DE MATERIAL EXCEDENTE M3 430.73 15.5400 6,693.54 0.00 0.00 0.00% 235.70 3,662.78 54.72% 235.70 3,662.78 54.72% 195.03 3,030.77 45.28%04.00 SUMINISTRO E INSTALACION DE TUBERIAS 0.00 0.00 0.00 0.00 0.00 0.00 0.0004.01 SUMINISTRO E INSTALACION DE TUBERIA PARA ALCANTARILLADO PVC-UF ISO-4435, S-20 D=200mm M 3,278.67 42.7200 140,064.78 983.60 42,019.43 30.00% 1,242.00 53,058.24 37.88% 2,225.60 95,077.67 67.88% 1,053.07 44,987.11 32.12%04.02 DADOS DE CONCRETO TUBERIA BUZON UND 136.00 85.2200 11,589.92 0.00 0.00 0.00% 78.00 6,647.16 57.35% 78.00 6,647.16 57.35% 58.00 4,942.76 42.65%05.00 PRUEBA HIDRAULICA 0.00 0.00 0.00 0.00 0.00 0.0005.01 DOBLE PRUEBA HIDRAULICA Y ESCORRENTIA P/TUBERIA A ZANJA TAPADA D=200mm M 3,278.67 3.6500 11,967.15 655.73 2,393.43 20.00% 1,108.00 4,044.20 33.79% 1,763.73 6,437.63 53.79% 1,514.94 5,529.52 46.21%06.00 BUZONES 0.00 0.00 0.00 0.00 0.00 0.0006.01 BUZON DE CONCRETO D=1.20m, H=1.00m, e=0.20m UND 2.00 1,133.5000 2,267.00 1.00 1,133.50 50.00% 0.00 0.00 0.00% 1.00 1,133.50 50.00% 1.00 1,133.50 50.00%06.02 BUZON DE CONCRETO D=1.20m, 1.00<H<=1.50 m. UND 44.00 1,313.4900 57,793.56 35.20 46,234.85 80.00% 6.40 8,406.34 14.55% 41.60 54,641.18 94.55% 2.40 3,152.38 5.45%06.03 BUZON DE CONCRETO D=1.20m, 1.50<H<=2.00 m. UND 7.00 1,474.8900 10,324.23 5.00 7,374.45 71.43% 1.00 1,474.89 14.29% 6.00 8,849.34 85.71% 1.00 1,474.89 14.29%06.04 BUZON DE CONCRETO D=1.20m, 2.00<H<=2.50 m. UND 3.00 1,885.0000 5,655.00 2.00 3,770.00 66.67% 0.00 0.00 0.00% 2.00 3,770.00 66.67% 1.00 1,885.00 33.33%06.05 BUZON DE CONCRETO D=1.20m, 2.50<H<=3.00 m. UND 1.00 2,397.3900 2,397.39 1.00 2,397.39 100.00% 0.00 0.00 0.00% 1.00 2,397.39 100.00% 0.00 0.00 0.00%06.05 BUZON DE CONCRETO D=1.20m, 3.00<H<=3.50 m. UND 8.00 2,887.9800 23,103.84 4.00 11,551.92 50.00% 2.00 5,775.96 25.00% 6.00 17,327.88 75.00% 2.00 5,775.96 25.00%06.05 BUZON DE CONCRETO D=1.20m, 3.50<H<=4.00 m. UND 1.00 3,727.8000 3,727.80 0.00 0.00 0.00% 1.00 3,727.80 100.00% 1.00 3,727.80 100.00% 0.00 0.00 0.00%07.00 CONEXIONES DOMICILIARIAS DE ALCANTARILLADO 0.00 0.00 0.00 0.00 0.00 0.00
PRECIO UNITARIO
VALORIZACION DE OBRA Nº 02(Periodo : NOVIEMBRE 2015)
Obra :“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
Ubicación : DISTRITO DE RIO GRANDE - PALPA - ICA
Tipo de Proceso : EX0 - PROC - 4 - 2015 - MDRG/CE
Contratista : CONSORCIO RANCHERIA
Plazo de Ejecucion : 90 DIAS CALENDARIOS Valor Referencial (S/.) : 1,090,409.40 con IGV
Supervisor : ING. MIGUEL ANGEL HERNANDEZ ESPINO Costos al : May-2015
Residente : ING. WILLIAM ROBERTO MEDINA ZEA Monto del Contrato (S/.) : 1,090,409.40 con IGV
Factor de Relacion : 1.0000
Formula : 001 RED DE ALCANTARILLADO
ITEM DESCRIPCION DE PARTIDAPRESUPUESTO
AVANCESSALDO
ANTERIOR ACTUAL ACUMULADO
UNIDAD METRADO PARCIAL Metrado Monto % Metrado Monto % Metrado Monto % Metrado Monto %PRECIO UNITARIO
07.01 EXCAVACION DE ZANJA P/CONEX. DOMICILIARIAS Hprom= 1.00 HASTA 3.00m M 1,550.20 6.7300 10,432.85 0.00 0.00 0.00% 723.00 4,865.79 46.64% 723.00 4,865.79 46.64% 827.20 5,567.06 53.36%07.02 REFINE Y NIVELACION DE ZANJA TN P/TUB 6”-8” HASTA 3.00 m DE PROFUNDIDAD M 1,550.20 3.1100 4,821.12 0.00 0.00 0.00% 723.00 2,248.53 46.64% 723.00 2,248.53 46.64% 827.20 2,572.59 53.36%07.03 CAMA DE APOYO E=10CM PARA TUBO HASTA 10” CON MATERIAL SELECTO COMPACTADO M 1,550.20 3.8100 5,906.26 0.00 0.00 0.00% 652.00 2,484.12 42.06% 652.00 2,484.12 42.06% 898.20 3,422.14 57.94%07.04 RELLENO COMPACTADO DE ZANJAS @ 0.30m EN CONEX. DOMIC. C/MAT. PROPIO M 1,550.20 15.9800 24,772.20 0.00 0.00 0.00% 652.00 10,418.96 42.06% 652.00 10,418.96 42.06% 898.20 14,353.24 57.94%07.05 CONEXIONES DOMICILIARIAS SIMPLE DE DESAGUE INCLUYE CAJA Y TAPA CA HASTA L=7.00m 160mm UND 133.00 547.4100 72,805.53 46.55 25,481.94 35.00% 38.00 20,801.58 28.57% 84.55 46,283.52 63.57% 48.45 26,522.01 36.43%07.06 DOBLE PRUEBA HIDRAULICA DE DESAGUE TUBERIA HASTA 160 mm M 1,550.20 2.8700 4,449.07 0.00 0.00 0.00% 522.00 1,498.14 33.67% 522.00 1,498.14 33.67% 1,028.20 2,950.93 66.33%07.07 ELIMINACION DE MATERIAL EXCEDENTE M3 34.24 15.5400 532.09 0.00 0.00 0.00% 12.00 186.48 35.05% 12.00 186.48 35.05% 22.24 345.61 64.95%08.00 COSTOS AMBIENTALES 0.00 0.00 0.00 0.00 0.00 0.0008.01 RIEGO DE MATERIAL EXTRAIDO DE EXCAVACION P/EVITAR POLVO GB 1.00 4,204.0200 4,204.02 0.25 1,051.01 25.00% 0.50 2,102.01 50.00% 0.75 3,153.02 75.00% 0.25 1,051.01 25.00%09.00 FLETE TERRESTRE 0.00 0.00 0.00 0.00 0.0009.01 FLETE DE MATERIALES, PALPA A OBRA EST 1.00 1,800.0000 1,800.00 0.25 450.00 25.00% 0.50 900.00 50.00% 0.75 1,350.00 75.00% 0.25 450.00 25.00%
COSTO TOTAL 843,692.71 330,708.00 226,651.86 557,359.86 286,332.85
VALORIZACION DE OBRA Nº 02(Periodo : NOVIEMBRE 2015)
Obra : “INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
Ubicación : DISTRITO DE RIO GRANDE - PALPA - ICA
Tipo de Proceso : EX0 - PROC - 4 - 2015 - MDRG/CE
Contratista : CONSORCIO RANCHERIA
Plazo de Ejecucion : 90 DIAS CALENDARIOS Valor Referencial (S/.) : 1,090,409.40 con IGV
Supervisor : ING. MIGUEL ANGEL HERNANDEZ ESPINO Costos al : May-2015
Residente : ING. WILLIAM ROBERTO MEDINA ZEA Monto del Contrato (S/.) : 1,090,409.40 con IGV
Factor de Relacion : 1.0000
Formula : 002 LAGUNA
ITEM DESCRIPCION DE PARTIDAPRESUPUESTO
AVANCESSALDO
ANTERIOR ACTUAL ACUMULADO
UNIDAD METRADO PARCIAL Metrado Monto % Metrado Monto % Metrado Monto % Metrado Monto %
01.00 TRABAJOS PRELIMINARES01.01 TRAZO Y REPLANTEO M2 2511.800 0.550 1,381.4900 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2,511.800 1,381.49 100.00%01.02 TALA Y RETIRO DE MALEZA M2 2511.800 0.490 1,230.7820 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2,511.80 1,230.78 100.00%02.00 MOVIMIENTO DE TIERRAS 0.0000 0.0002.01 CORTE DE TERRENO NORMAL CON MAQUINARIAS M3 4623.880 5.600 25,893.7280 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4,623.88 25,893.73 100.00%02.02 EXCAVACION CON EQUIPO T.N. P/TUBERIA ALCANTARILLADO H=1.20M M 118.910 5.600 665.8960 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 118.91 665.90 100.00%02.03 CONFORMACION DE SUELO BASE PARA PISO Y TALUDES DE LAGUNA M3 199.140 21.120 4,205.8368 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 199.14 4,205.84 100.00%02.04 RELLENO COMPACTADO CON MATERIAL PROPIO M3 118.910 7.680 913.2288 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 118.91 913.23 100.00%02.05 AFIRMADO DE 4” PARA CORONA M2 754.480 7.210 5,439.8008 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 754.48 5,439.80 100.00%02.06 ELIMINACION DE MATERIAL EXCEDENTE M3 4349.290 15.540 67,587.9666 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4,349.29 67,587.97 100.00%03.00 DISPOSITIVO DE LLEGADA 0.0000 0.0003.01 BUZONES DE LLEGADA 0.0000 0.00
03.01.01 BUZON DE CONCRETO D=1.20m, H=0.70 m. e=0.20m, (BUZONETA) UND 3.000 943.780 2,831.3400 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 2,831.34 100.00%03.01.02 DADO DE CONCRETO TUBERIA BUZON UND 7.000 83.240 582.6800 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.00 582.68 100.00%
04.02 BUZON DE SALIDA 0.0000 0.0004.02.01 BUZON DE CONCRETO D=1.20m, H=2.10 m, e=0.20m. UND 2.000 1830.320 3,660.6400 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 3,660.64 100.00%04.02.02 BUZON DE CONCRETO D=1.20m, H=1.30 m, e=0.20m. UND 1.000 995.430 995.4300 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 995.43 100.00%04.02.03 DADO DE CONCRETO TUBERIA BUZON UND 7.000 83.240 582.6800 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.00 582.68 100.00%
04.03 SUMINISTRO E INSTALACION DE TUBERIAS 0.0000 0.0004.03.01 SUMINISTRO E INSTALACION DE TUBERIA PARA ALCANTARILLADO PVC-UF ISO-4435,S-25 D=200m M 61.300 42.720 2,618.7360 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 61.30 2,618.74 100.00%
04.04 OTROS 0.0000 0.0004.04.01 COMPUERTA DE FIERRO DE DISPOSITIVO DE SALIDA DE 0.50 x 1.60 M UND 1.000 1079.850 1,079.8500 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,079.85 100.00%04.04.02 COMPUERTA DE FIERRO DE DISPOSITIVO DE SALIDA DE 0.50 X 0.80 m. UND 1.000 639.920 639.9200 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 639.92 100.00%04.04.03 DOBLE PRUEBA HIDRAULICA Y ESCORRENTIA P/TUBERIA A ZANJA TAPADA D=160mm M 118.910 5.070 602.8737 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 118.91 602.87 100.00%04.04.04 CAJA DE SALIDA DE TUBERIA HACIA CANAL SEGÚN DISEÑO UND 1.000 270.380 270.3800 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 270.38 100.00%
VALORIZACION DE OBRA Nº 02(Periodo : NOVIEMBRE 2015)
Obra : “INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
Ubicación : DISTRITO DE RIO GRANDE - PALPA - ICA
Tipo de Proceso : EX0 - PROC - 4 - 2015 - MDRG/CE
Contratista : CONSORCIO RANCHERIA
Plazo de Ejecucion : 90 DIAS CALENDARIOS Valor Referencial (S/.) : 1,090,409.40 con IGV
Supervisor : ING. MIGUEL ANGEL HERNANDEZ ESPINO Costos al : May-2015
Residente : ING. WILLIAM ROBERTO MEDINA ZEA Monto del Contrato (S/.) : 1,090,409.40 con IGV
Factor de Relacion : 1.0000
Formula : 002 LAGUNA
ITEM DESCRIPCION DE PARTIDAPRESUPUESTO
AVANCESSALDO
ANTERIOR ACTUAL ACUMULADO
UNIDAD METRADO PARCIAL Metrado Monto % Metrado Monto % Metrado Monto % Metrado Monto %PRECIO UNITARIO
06.01.01 EXCAVACION MANUAL EN TERRENO NORMAL M3 8.400 31.110 261.3240 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.40 261.32 100.00%06.02 OBRAS DE CONCRETO SIMPLE 0.0000 0.00
“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
VALORIZACION DE OBRA Nº 01 - CURVA "S"(Periodo : NOVIEMBRE 2015)
Obra : “INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
Ubicación : DISTRITO DE RIO GRANDE - PALPA - ICA
Tipo de Proceso : EX0 - PROC - 4 - 2015 - MDRG/CE
Contratista : CONSORCIO RANCHERIA
Plazo de Ejecucion : 90 DIAS CALENDARIOS Valor Referencial (S/.) : 1,090,409.40 con IGV
Supervisor : ING. MIGUEL ANGEL HERNANDEZ ESPINO Costos al : May-2015
Residente : ING. WILLIAM ROBERTO MEDINA ZEA Monto del Contrato (S/.) : 1,090,409.40 con IGV
MONTO DEL CONTRATO S/. 1,090,409.40 (con IGV) S/. 924,075.76 (sin IGV)
PORCENTAJE DE ADELANTO 0.00%
ValorizaciónAmortización
Saldo por
Nº Mes Monto sin IGV Amortizar
01 (OCTUBRE DE 2015) 0.00 0.00 0.00
02 (NOVIEMBRE DE 2015) 0.00 0.00 0.00
03 (DICIEMBRE DE 2015) 0.00 0.00 0.00
04 (ENERO DE 2016) 0.00 0.00 0.00
05 (FEBRERO DE 2016) 0.00 0.00 0.00
TOTAL ACUMULADO 0.00
“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
VALORIZACION DE OBRA No 02METRADOS - OCTUBRE DEL 2015
03.02.05 REJILLA METALICA 2” x ¼” UND 1 - 1.00 0.00%
03.02.06 REJILLA METALICA 3/4” x ¼” UND 1 - 1.00 0.00%
03.03 LOSA DE CAIDA - 0.00
03.03.01 SOLADO E = 10 CM M2 17.29 - 17.29 0.00%
03.03.02 CONCRETO EN LOSA DE CAIDAF'C= 175 KG/CM2 M3 3.46 - 3.46 0.00%
03.03.03 ENCOFRADO Y DESENCOFRADO LOSA DE CAIDA M2 7.20 7.20
03.03.04 ACERO ESTRUCTURAL f'y =4200Kg/cm2. KG 176.24 - 176.24 0.00%
03.03.05 REVESTIMIENTO DE LOSA DE CAIDA CON ADITIVO E=1CM M2 18.73 - 18.73 0.00%
03.04 OTROS - 0.00
03.04.01 SUMINISTRO E INSTALACION DE TUBERIA PARA ALCANTARILLADO PVC-UF ISO-4435 M 57.61 57.61
03.04.02 COMPUERTA DE DISPOSITIVO DE ENTRADA DE 0.30x0.22m UND 1.00 - 1.00 0.00%
04.00 DISPOSITIVO DE SALIDA - 0.00
04.01 DISPOSITIVO DE SALIDAD DE LAGUNA - 0.00
04.01.01 SOLADO E= 10CM M2 9.82 - 9.82 0.00%
04.01.02 CONCRETO EN LOSA DE CAIDA F'C= 175 KG/CM2 M3 11.23 - 11.23 0.00%
04.01.03 ENCOFRADO Y DESENCOFRADO NORMAL M2 75.82 - 75.82 0.00%
“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
SALDO DE OBRA
VALORIZACION DE OBRA No 02METRADOS - OCTUBRE DEL 2015
SUPERVISION ING. MIGUEL ANGEL HERNANDEZ ESPINO FECHA : 31-Oct-15
FECHA PRES.BAS 5/15/2015 P. REFERENCIAL C/I.G.V. :
P. CONTRATO C/I.G.V. :
FACTOR DE RELACION : 1.00000 Nº
DESCRIPCION DE PARTIDA PRESUPUESTO
% EJECUTADO PART. UND METRADO OCTUBRE NOVIEMBRE DICIEMBRE ENERO TOTAL
“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
06.03.01 CERCO PERIMETRICO DE SEGURIDAD M 209.64 - 209.64 0.00%
06.03.02 PUERTA DE INGRESO UND 1.00 - 1.00 0.00%
INFORME VAL- N°0002-2015/CR
A : ING. MIGUEL ANGEL HERNANDEZ ESPINOSupervisor de Obra
DE : ING. WILLIAM ROBERTO MEDINA ZEARESIDENTE DE OBRA
ASUNTO : VALORIZACION MENSUAL N° 02Correpondiente al mes de OCTUBRE 2015
REFERENCIA : EXO - PROC - 4 - 2015 - MDRG/CEO b r a :
Contratista: CONSORCIO RANCHERIA
FECHA : Rio Grande, 04 de Diciembre del 2015
Me dirijo a Ud. para remitirle adjunto al presente, el expediente de la Valorización Mensual N° 02 de la Obra de la referencia, correspondiente a los trabajos ejecutados al 30 de Noviembre del 2015 por la Empresa Contratista:
CONSORCIO RANCHERIALos cálculos fueron elaborados por la Supervision y se tienen como resultado lo siguiente:
A. VALORIZACION CONTRACTUAL (V)RED DE ALCANTARILLADO 192,077.85LAGUNA 0.00
SUB-TOTAL S/. 192,077.85
AVANCE PROGRAMADO ACUMULADO 61.99%AVANCE REAL ACUMULADO 51.12% ATRASADA
MONTO DE LA VALORIZACION BRUTA (VB=V+S) S/. 192,077.85
C. AMORTIZACION (A)Amortización del Adelanto Directo 0.00Amortización del Adelanto de Materiales 0.00Total Amortización 0.00
MONTO DE LA VALORIZACION NETA (VN=VB-A) S/. 192,077.85
“INSTALACION DE LA RED DE ALCANTARILLADO Y DISPOSICION FINAL DE AGUAS RESIDUALES EN EL CENTRO POBLADO DE RANCHERIA Y PAUCARRASTRO, DISTRITO DE RIO GRANDE, PROVINCIA DE PALPA, DEPARTAMENTO DE ICA"
D. RETENCIONES (R)
Multa por atraso de obra -
E. MONTO A PAGAR AL CONTRATISTAEn Efectivo 192,077.85En I.G.V. (18%VN) 34,574.01MONTO TOTAL DE LA VALORIZACION CON I.G.V. 226,651.86
F. TOTAL COMPROMISO A SOLICITAR S/. 226,651.86
_ Se adjunta copia de SCRT, SUNAT, CONAFOVICER, SENCICO._ El monto acumulado real supera el 80% del acumulado programado, por lo que