Best Practice Validation Master Plan for Equipment, Computer Systems, Networked Systems and Spreadsheet Applications Revision 2.06 July 2002 Publication from www.labcompliance.com Global on-line resource for validation and compliance Copyright by Labcompliance. This document may only be saved and viewed or printed for personal use. User may not transmit or duplicate this document in whole or in part, in any medium. Additional copies can be ordered from www.labcompliance.com. While every effort has been made to ensure the accuracy of information contained in this document, Labcompliance accepts no responsibility for errors or omissions. No liability can be accepted in any way.
40

Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Mar 12, 2018

Download

Documents

dinhdang
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Best Practice

Validation Master Plan

for Equipment, Computer Systems, Networked Systems

and Spreadsheet Applications

Revision 2.06 July 2002

Publication from

www.labcompliance.com Global on-line resource for validation and compliance

Copyright by Labcompliance. This document may only be saved and viewed or printed for personal use. User may not transmit or duplicate this document in whole or in part, in any medium.

Additional copies can be ordered from www.labcompliance.com.

While every effort has been made to ensure the accuracy of information contained in this document, Labcompliance accepts no responsibility for errors or omissions. No liability can be accepted in any way.

Page 2: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 2 of 40

Contents

1. Purpose and scope of this plan 4

2. Introduction 4

3. Responsibilities 5 3.1 Validation team 5 3.2 User representation 5 3.3 Plant safety/maintenance/engineering 5 3.4 Information Services (IS) 6 3.5 Validation (engineering) groups 6 3.6 Quality Assurance (QA) 6 3.7 Responsible person 6 3.8 Consultants 7 3.9 Vendors 7 3.10 All 7

4. Related documents 8

5. Products/processes to be validated and/or qualified 8

6. Validation approach 9

7. Steps for Equipment Qualification 11 7.2. Installation Qualification (IQ) 12 7.3. Operational Qualification (OQ) 15 7.4. Performance qualification (PQ) 16 7.5. Documentation 17

8. Computer system validation 18 8.1 Design qualification 18 8.2 Vendor qualification 19 8.3 Installation qualification 21 8.4 Operational qualification 22 8.5 Performance qualification 22

9. Networks and Networked Systems 23 9.1 Design qualification 23 9.2. Installation Qualification 24 9.3 Operational Qualification 24 9.3 Performance Qualification 25 9.5 Documentation 26

10. Existing (Legacy) Systems 26 10.1 Design qualification 27

Page 3: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 3 of 40

10.2 Installation qualification 27 10.3 Operational qualification 27 10.4 Performance qualification 27

11. Validation of Macros and Spreadsheet Applications 28 11.1 Develop a project validation plan 28 11.2 Define responsible persons 28 11.3 Define user requirements 28 11.4 Specify Functions 29 11.5 Design and implementation 29 11.6 Testing 29 11.7 Ongoing performance checks 30 11.8 User documentation 30 11.9 System security and data integrity 30 11.10 Change and version control 30

12. Change Control 30

13. Instrument Obsolescence and Removal 33

14. Glossary 33

15. Documentation maintenance 33

Appendix A. Checklists and Forms 34 Checklists 34 Forms 34

Form F1001: Change control 35 Form F1002: Change control summary log 36 Form F1004: Initiation and Authorization of Macros & Spreadsheets 37 Form F1006: Validation deliverables and owners 38 Form F1009: Validation team members 39 Form F1010: Preparation and approval of validation project plans (master validation plan) 40

Page 4: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 4 of 40

1. Purpose and scope of this plan Provides a framework and practices for validation and qualification of equipment, computer systems and networked systems for laboratories and manufacturing. It also is applicable to the validation of Macros and Spreadsheet applications. The Validation Master plan should ensure that validations and qualifications are done efficiently and consistently throughout the organization and meet regulatory, quality and business requirements. The plan should ensure that the company's validation procedures are followed. The company validation master plan is the basis of individual project validation plans, sometimes also called master validation plan.

2. Introduction This is the most important part of a validation plan. It summarizes what the project is all about and what you are trying to accomplish with it and with validation. It summarizes • The purpose of project • Brief description of the system • Validation approach • The name and location of the facility where the equipment or

system is located • Timeline

Page 5: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 5 of 40

3. Responsibilities Identifies all validation responsibilities like system owner, system manager, validation team, QA, operations, plant maintenance/engineering, IT, lab support services, users etc. 3.1 Validation team

• creates, updates, and reviews/ approves individual project validation plans and validation deliverables

• ensures validation compliance with the company validation master plan and project validation plan

• coordinates, implements, verifies elements of the VMP • consults on, evaluates and approves changes • reviews and approves IQ/OQ/PQ procedures and plans • reviews test results and makes recommendations regarding

release • assess risks and develops contingency plan

3.2 User representation • create and maintain equipment inventory • makes a proposal for specifications

(user requirements, functional specifications) • provides resources for all required qualification activities

(IQ, OQ, PQ) • reviews procedures test methods for usability and

practicability • recommends criticality level of failures • monitors on-going system performance and reports problems

3.3 Plant safety/maintenance/engineering • advises on and prepares the facility/laboratory to meet the

equipment's environmental and safety specifications

Page 6: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 6 of 40

3.4 Information Services (IS) • assures that selected system fit into current and future IT

infrastructure • performs installation and maintenance of computer networks • provides tools for data collection and archiving • provides training for users on the use of networks

3.5 Validation (engineering) groups • provides expertise to develop and implement validation

deliverables in efficient and consistent way • provides detailed validation guidance • trains employees on validation requirements and techniques

3.6 Quality Assurance (QA)

• provides quality assurance expertise in the creation of the project validation plan and other validation deliverables

• monitors compliance with regulations and established standards

• approves and administrates SOPs • audits equipment/computer systems • develops test plans for equipment and computer systems

(This can also be done by the development department. In this case QA reviews the plans)

• leads vendor assessment program • trains employees on regulations

3.7 Responsible person • manages the validation project • establishes a project validation team • schedules and facilitates validation team meetings • initiates creation and maintenance of documentation • assures that change(s) are managed and controlled • assures the final approval of the system for use

Page 7: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 7 of 40

• keeps information on all validation activities • informs all parties on changes

3.8 Consultants • Some of the activities can be out-sourced to consultants. For

example, developing specifications based on inputs from users, developing IQ/OQ/PQ procedures, leading vendor assessment programs and preparing validation summary reports

3.9 Vendors • Validates equipment, software and systems during

development following documented procedures • Provides documented evidence that the software has been

validated • Provides documentation on the validation approach taken by

the vendor • Provides a complete list of functional and performance

specifications that can be used to derive a company's specification for the project

• Allows a vendor audit if required by regulatory agencies or the user

• Provides documentation and services for installation qualification

• Provides documentation and services for operational qualification

• Provides training on the technique and operation of the system

• Provides on-going support through phone or on-site

3.10 All • Assure that all people who are involved in the specification,

design, development, validation and use of equipment and

Page 8: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 8 of 40

computer/networked systems are trained and understand regulations.

4. Related documents 1. Corporate and/or local validation policies 2. Standard operating procedures 3. Checklists, e.g., for vendor assessment 4. Templates, e.g., for change control

5. Products/processes to be validated and/or qualified

5.1 Equipment, computers, software, network modules and networked systems that are used in regulated environment. Requirements may come from the US FDA and EPA, EU authorities, Japanese MHW or any other country that may have an impact or the companies business.

5.2 Equipment, computers and networked systems and software that are critical to the operation of a company or department

5.3 New equipment, computers and networked systems

5.4 Existing equipment, computers and networked systems

5.5 Any computerized system that is used to create, modify, maintain, archive, retrieve or transmit data (US FDA 21 CFR Part 11). This includes, for example, analytical instruments, other automated laboratory equipment, computers that are used to acquire, and evaluate data and Laboratory Information Management Systems (LIMS). It also includes systems to create and maintain Standard Operating Procedures (SOP) in electronic format, Calibration Tracking Systems (CTS), and may be e-mail systems. Other examples are Supervisory Control And Data Acquisition (SCADA), Electronic Batch Record Systems (EBRS), Programmable Logic Controllers (PLC), Process Control Systems (PCS), integrated information/business Systems, Enterprise Resource Planning (ERP) Systems, , Digital

Page 9: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 9 of 40

Control Systems (DCS), Systems, Manufacturing Execution Systems (MES) and Laboratory Information Management Systems (LIMS). Ask yourself, if the information on the system is absolutely required for GMP/GMP. If yes, the system should be validated.

5.6 Equipment and computers/networked systems as identified in chapter 5.5 after changes.

6. Validation approach Approach for new systems 6.1 If the equipment/computers are used across more than one

department, form a project validation team representing all affected departments. Expertise of any of the department is needed for doing initial validation 'right' but also for revalidation when the system is changed.

6.2 Develop a validation project plan with time schedule and owners

6.3 Develop user requirement and functional specifications 6.4 Select a supplier (may be internal or external) 6.5 For computer systems, qualify the supplier (for details, see

chapter 7) 6.6 Develop validation procedures (SOPs) and templates that can

be used to qualify or validate the system during installation (IQ), prior to operation (OQ) and during routine use (PQ).

6.7 Develop criteria and procedures for revalidation/requalification 6.8 Develop acceptance criteria for OQ and PQ tests. 6.9 Get approval for test procedures and acceptance criteria from

QA and the validation team. 6.10 Install the system and perform IQ 6.11 Perform and document OO tests 6.12 Check if criteria under 6.8 are met

Page 10: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 10 of 40

6.13 If acceptance criteria are not met, check equipment/computerized/networked systems or procedure. Acceptance criteria should not be changed. Repeat steps 6.11 and 6.12. If the problem still exists, report to the supplier.

6.14 Write an OQ summary report. 6.15 Implement procedures for on-going performance qualification

(PQ). 6.16 The validation/qualification documents shall be reviewed and

approved by the validation team, the system owner, e.g., the lab manager for small systems, QA/QC and other departments if, affected, for example, IT departments, for networked computer systems. Changes to the documents should be approved and documented (versioned).

6.17 All validation/qualification documents should be archived in secure locations

Approach for existing systems When the FDA or other representatives or regulatory agencies audit computer systems, they will not ask if the system is new or legacy (legacy means, the system has been in place when a new regulation has been released). They will ask for a validation approach and expect to have similar or the same documents available as for new systems. The following steps demonstrate the approach the company takes to bring legacy systems into the validated status. 6.18 Develop an inventory (master lists) that includes all equipment

and computers currently in use in the laboratory/operation and appropriate business area. The inventory list should be designed such that it can easily be upgraded.

6.19 Categorize the equipment and computers based on impact to regulatory submission and business impact, use yes or no. (yes = requires validation, no = does not require validation)

6.20 Further identify impact on product quality of all equipment as classified in 6.19 with 'yes'. Use categories high (immediate impact on product quality), medium (no immediate impact on product quality), low (no impact on product quality)

Page 11: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 11 of 40

6.21 Develop a time plan to validate the selected systems using classification in 6.20 as criterion. Immediately start to validate all systems classified as "high"

6.22 For further steps, follow 6.1) to 6.17).

7. Steps for Equipment Qualification Equipment qualification should include: 7.1 Design Qualification (DQ) DQ defines the functional and operational specifications of the instrument and details the conscious decisions in the selection of the supplier. DQ should ensure that instruments/computer systems have all the necessary functions and performance criteria that will enable them to be successfully implemented for the intended application and to meet business and regulatory requirements. Inputs for specifications come from anticipated users. Design qualification should include these steps:

• Background information and description of the application problem. If the instrument will be used for several applications, describe a few typical scenarios.

• Selection of the technique and/or type of equipment • Description of the purpose and intended use of the

equipment. If the instrument will be used for several applications, describe a few typical scenarios.

• Description of the intended environment • Description on how the instrument will be used in the

selected environment and within a process. If the instrument will be used for several applications, describe a few typical scenarios.

• Development of user requirement specifications

Page 12: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 12 of 40

• Preliminary selection of the functional and performance specifications (technical, environmental, safety, security access, compatibility with existing and future systems/platforms)

• For larger systems, development of system schematics, network layouts etc

• Preliminary selection of the supplier • Instrument tests (if the technique is new) • Final selection of the equipment • Final selection and qualification of the supplier and

equipment • Discussion and documentation of warranty, familiarization,

training, consulting and other vendor services • Development and documentation of final functional and

operational specifications • Review and approval of user requirement and functional

specifications by users of the system and by the project validation team.

7.2. Installation Qualification (IQ)

Installation qualification establishes that the instrument is received as designed and specified, that it is properly installed and configured in the selected environment, and that this environment is suitable for the operation and use of the instrument. Installation Qualification should include these steps: • Check if the environmental and safety conditions, e.g., power

condition requirements, meet the criteria as specified for the instrument

• Compare equipment, as received, with purchase order (including software, accessories, spare parts)

• Check documentation for completeness (operating manuals, maintenance instructions, standard operating procedures for testing, safety and validation certificates)

Page 13: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 13 of 40

• Check equipment for any damage • Install hardware (computer, equipment, fittings and tubings

for fluid connections, power cables, data flow and instrument control cables)

• Switch on the instruments and ensure that all modules power up and perform an electronic self-test

• Install software on computer following the manufacturer’s recommendation

• Verify correct software installation, e.g., verify that are all files loaded. Utilities to do this should be included in the software itself.

• Make back-up copy of software. • Configure peripherals, e.g. printers and equipment modules. • Identify and make a list with a description of all hardware,

include drawings where appropriate. • Make a list with a description of all software installed on the

computer. • List equipment manuals and SOPs. • Develop operation and calibration procedures. • Make entries into the equipment logbook. • Prepare an installation report. Enter the equipment in the laboratory's equipment database Items that should be included for each piece of equipment in the database include: • Unique in-house identification number (asset number) • Name of the item of equipment • The manufacturer’s name, address and phone number for

service calls, service contract number, if there is one • Serial number and firmware revision number of equipment • Date received • Date placed in service • Current location • Size, weight

Page 14: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 14 of 40

• Condition when received, for example, new, used, reconditioned

• List with authorized users and responsible person The database should also have entry fields for dates of the last and next operational qualification. For large systems, e.g., computerized protein sequencers, IQ should be performed and documented by the supplier. The user should sign the IQ report. For small equipment, e.g., pH meters, IQ should be performed and documented by the user.

IQ documents must be updated, if there is any change to the system. Changes can include: • move to an other room • update with new hardware, firmware, software • exchange of modules which have individual serial

and/or asset numbers

Page 15: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 15 of 40

7.3. Operational Qualification (OQ)

Operational qualification (OQ) is the process of demonstrating that an instrument will function according to its operational specification in the selected environment. The instrument should be tested against critical performance specifications as specified in the Design Specifications document. Steps for OQ include: • Obtain functional and performance specifications (preferably

use information from DQ). • Identify critical functions that should be tested in the user's

environment. • Link the test cases to the user requirement and functional

specifications as defined in the DQ phase. • Develop SOPs for testing • Test procedures should include what to test, how testing

should be conducted and the expected results with acceptance criteria.

• For modular systems, test the system as a whole, not module by module

• If there are several systems of the same type and function in a laboratory/operation, use the same procedure and preferably the same acceptance criteria for all systems

• Whenever possible use the manufacturer's procedure for testing

• Don't use the manufacturer's performance specification limits if the performance is expected to deteriorate over time. Take performance specification as required by the application.

• Decide for each instrument whether to do OQ tests by your own people, by the vendor or by a 3rd party. Criteria are costs, availability and training of people and available of (traceable) qualification tools.

• Define the frequency of OQ as recommended by the vendor. • Define re-qualification criteria and procedures after

equipment up-dates, moves and repairs.

Page 16: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 16 of 40

7.4. Performance qualification (PQ)

Performance Qualification (PQ) is the process of demonstrating that an instrument consistently performs according to a specification appropriate for its routine use. Important here is the word ‘consistently’. Main activities in the PQ phase are • preventive maintenance • requalification after changes and • on-going tests. The test frequency is much higher than for OQ. Another difference is that PQ should always be performed under method conditions that are similar to routine sample analysis. In practice, for laboratory operation PQ testing can mean system suitability testing, where critical key system performance characteristics are measured and compared with documented, preset limits. For example, a well characterized standard can be injected 5 or 6 times and the standard deviation of amounts are then compared with a predefined value. If the limit of detection and/or quantitation are critical, the lamp’s intensity profile or the baseline noise should be tested. Recommended steps for PQ are: 1. Define test procedures and the performance criteria for the

complete system.

2. Select critical parameters. For a chromatography system this can be • precision of the amounts • precision of retention times • resolution between two peaks • peak width at half height or • peak tailing • limit of detection and limit of quantitation • wavelength accuracy of a UV/Visible wavelength

detector.

3. Define the test intervals, e.g., • every day

Page 17: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 17 of 40

• every time the system is used • before, between and after a series of runs

4. Record any unusual event in the equipment logbook

5. Define corrective actions on what to do if the system does not meet the criteria, in other words if the system operates out of specification.

7.5. Documentation

On completion of equipment qualification, documentation should be available that consists of: • Validation summary report with final approval (disapproval)

statement, the qualified operating ranges, and a list of all deliverables generated during the validation process. The report should also contain a list of follow-up activities if there are some deviations.

• Design qualification documents with purpose of the system, user requirements and functional and performance specifications.

• Installation qualification document (includes description of hardware and software).

• Procedures for OQ testing and acceptance criteria. • OQ test protocols and results with signatures and dates • PQ test procedures, acceptance criteria, test protocols and

representative results • OQ stickers for the equipment with information on test

engineer, date of OQ and date next OQ • Statement by the user on formal acceptance • Updated equipment database with information on validation

status.

Page 18: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 18 of 40

8. Computer system validation

In principle validation of computer systems should follow the same guidelines as outlined in Chapter 7 for equipment qualification. If the computer is connected to equipment and used for instrument control and data evaluation for that equipment without networking to other computers, the computer can be treated as a module of that system and should be qualified as part the system.

For networked computer systems with more complex functionality additional tasks should be performed for the individual qualification steps (see also next chapter).

8.1 Design qualification

DQ should include a background information and a description of the current computer system platform, future plans and how the new system fits into this environment. It should describe which role the system plays in the workflow of an overall process. This includes interfaces to equipment but also to a corporate IT system. Once the workflow and data flow known, there should be a definition

• of raw data and meta data,

• how integrity of the data is ensured

• for how long these data must be archived and

• how they can be retrieved.

DQ should also describe whether the system will be configured or otherwise customized in the user's environment. If the system is purchased from a vendor and customized by the user, it should clearly describe who is providing what.

When documenting communication between equipment and the computer, the user requirement and functional specifications should clearly state if it is a one-way or two-way communication.

Page 19: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 19 of 40

8.2 Vendor qualification For computer systems there should be documented evidence that software and system has been validated during and at the end of development. The vendor should also provide assistance for DQ, IQ and OQ and on-going support during routine use. The user must have confidence in the supplier's quality, validation and support processes that should be documented in a formal vendor assessment document. There are different possibilities to assess a vendor. They are listed in table 8.1.

Table 8.1 Possibilities to assess a vendor

# Assessment Comment 1 Through references

outside your company Useful if there is no experience with thevendor within your company. Criteria are • acceptance of the vendor in the

market place • image of the vendor as software

supplier • quality reputation of the product

2 Through own experience with the vendor

Experience may come from the product under consideration or from other products. Criteria are • Quality of the products (failure rate)• Responsiveness in case of errors

(phone call, on-site visit, bug fix) 3 Through own experience

with the product Very much the same as in 2, but more accurate because most likely the software has been developed and is supported by the same people as the new purchase

4 Checklist - Mail audit Use checklists available within your company, through public organizations, e.g., PDA and from private authors, e.g., in this book

5 Follow up through video Can be used to proof that documents

Page 20: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 20 of 40

or teleconference referred to in the mail audit exist, are readily available and have required content and quality

6 Assessment through 3rd party audits

Give an independent assessment of the quality system and/or product development

7 Vendor audit through user to assess the quality system

Gives a good picture on the vendors quality system

8 Vendor audits through user for individual projects

Gives a good picture on how the qualityof the individual product

The required assessment level depends on the complexity of the system and should be defined by the project team and documented in the individual project validation plan.

The vendor should be qualified based on business aspects (size, market focus, financial strengths, attitude to people qualification, future perspective) and technical aspects (specification, design, development, testing and support).

Key elements of a vendor assessment are:

• The vendor must provide documented evidence that the software has been validated during development. This can include a validation certificate and a description on the vendor's development and validation procedure. The vendor should also agree to provide access to additional information like test plans, test results or source code at the vendor's location.

• The vendor should have procedures and/or systems in place for: security, maintenance, user feedback, change control, backup and disaster recovery system to ensure safe ongoing support of the system.

• All people in software development should be adequately trained on software engineering practices but should also have a basic understanding on regulatory requirements, e.g., GLP and GMP.

• Customer support people should be available on the phone and for on-site visits, if need arises.

Page 21: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 21 of 40

• Depending on the criticality and complexity of computer system, the assessment can be based on historical experience with the vendor, checking the documentation as provided by the vendor, developing and evaluation of additional questions/answers and finally through a vendor audit.

• A vendor assessment or qualification report should be developed which includes a statement on 'vendor qualification status'.

Depending on the complexity and information existing on a vendor a direct audit can be necessary. The validation team should decide on this for each individual project. Criteria for a vendor audit are: • Commercial off the shelf system or be-spoke • Complexity of the system • Number of systems purchased from the vendor • Availability of development validation from the vendor • Stand alone or networked system • Influence of the system on other systems • Maturity of system • Experience with the system • Reputation of the system in the market place • Experience with the vendor • A vendor's documented evidence of audits from other

companies within the same industry? • Own audit experience with the vendor • Business impact of the system

8.3 Installation qualification • IQ should include a test to verify that the software has been

copied accurately and completely to the computer's hard disk. Preferably the vendor should provide such verification programs as part of the application software.

• For complex computer systems, a schematic diagram should be developed to illustrate the individual hardware connections and the data flow.

Page 22: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 22 of 40

• Verify correct use of cables as specified by the vendor, for example type and length.

• Computers should be entered in the equipment inventory database. Information should include - Computer hardware with information on the processor,

hard disk space, memory and the monitor - Software with product and revision number

8.4 Operational qualification

Most important for OQ testing of computer systems is the right selection of tests. It is obvious, that not all functions can be tested. Selection of tests should be based on risk assessment and must be approved by the validation team.

• OQ should also include specific tests to meet requirements of 21 CFR 11, e.g., limited system access, electronic audit trail, generation of exact copies, prevention of overwriting raw data when reprocessing data.

• If multiple analytical instruments are connected to single computers, proper function and correct data transmission should be verified under the highest anticipated data transfer rate (worst case testing).

• If the computer system is expected to perform multiple tasks simultaneously, proper function should be verified under highest anticipated workload.

Tests cases and acceptance criteria should be traceable to specifications. Test data sets and procedures should be designed such that they can be easily re-used for later requalification.

8.5 Performance qualification

Performance qualification should include

• regular virus checks

• regular data backup and removal of unnecessary files to avoid hard disk overflow. As a rule of thumb, the hard disk should not be loaded more than 80%

• procedures and regular check for authorized user access

Page 23: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 23 of 40

• procedure and regular problem reporting system back to the system developer

9. Networks and Networked Systems

In principal networked systems and applications running on networks are computer systems and as such should follow practices for computer system validation. Everything what is important about computer validation can be applied to networks as well. A network component should be treated like a piece of equipment, which is installed and qualified. As next typical network functions such as limited access and network transactions should be qualified. As the final step the complete network application should be tested and test results compared with specifications.

Compared to standalone computer systems, networks and networked systems require some special considerations for all qualification phases:

9.1 Design qualification

When a network is specified, the following questions should be answered: • How much traffic will it carry, especially under highest load

or under so called worst case conditions? • What is the maximum distance between individual network

components? • How many users are using the network concurrently? • What is the risk and impact of a server failure? • What are the backup and archiving cycles? • What availability is expected from the network? • What is the environment in which it will be operating? • What are the protocols: GPIB-IEEE vs. TCP/IP?

Page 24: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 24 of 40

• For networked systems: Description of the scope of the system: what is it, what is it not (important to define the validation box). This is important to draw the boundaries to other systems.

9.2. Installation Qualification

Network specific IQ activities include:

• Configure and document all network settings (e.g., routers

settings). • Include network cables and other hardware components, e.g.,

hubs, and software into the equipment data base. • Check if physical security specifications are met (e.g.,

lockable hardware to prevent unauthorized access to the server's RAID system).

• Develop high level and detailed system drawings, physical diagrams such as floor plans with component locations and cabling, and logical diagrams like TCP/IP schemes and how components interrelate with each other.

9.3 Operational Qualification

Network specific tests should include • Starting and shutting down networked systems (including

documenting messages indicating whether the network was successfully started/shutdowned)

• Switching of and on network components (e.g., hubs, routers, switches) and to note the impact of the action on the network capability to operate.

• Security tests, for example logging on with correct and incorrect password.

• Checking correct password administration, for example, when the password policy says that a password should have a minimum length of six characters, try to specify one with four characters.

Page 25: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 25 of 40

• Checking session unlock and user specific automated time-outs, if there are any.

• Checking access to task and file permissions. For example, if an operator has permission to review data, try to modify them and see if the system behaves as expected.

• Checking correct backup and restoration of data. • Checking how the system behaves and recovers from system

failures. Trigger a failure through disconnecting and reconnecting network components.

• Checking correct audit trail of network transactions. • Checking correct data transfer under normal AND under

high traffic. • Checking individual software modules and systems for virus

infection

9.3 Performance Qualification • Develop and implement procedures for back-up and

retrieval. The frequency should be based on risk assessment and be defined by the validation team.

• Validate back-up and retrieval procedures. • Develop and implement a contingency plan for failures of

network components to avoid loss of data. • Review of network diagrams. • Verify individual software modules and systems for virus

infection.

Page 26: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 26 of 40

9.5 Documentation

Network specific documentation should include • Network drawings. • Updated glossary with network terminology • Updated equipment data base with network hardware,

firmware and software • Procedures to control network security in general • Procedures for generation, distribution and use of passwords • Procedures for back-up and contingency planning • Network configuration management

10. Existing (Legacy) Systems Existing equipment and computer systems should be qualified and/or validated. The same principles apply as for new systems. As explained in the preamble of FDA's 21 CFR Part 11 does not grandfather legacy systems and FDA expects that firms using legacy systems will begin taking steps to achieve full compliance. Firms should have a reasonable timetable for promptly modifying any system not in compliance (including legacy systems) to make them Part 11 compliant, and should be able to demonstrate progress in implementing their timetable. FDA expects that 21CFR Part11 requirements for procedural controls will already be in place. FDA recognizes that technology based controls may take longer to install in older systems

The main difference to new systems is that typically no information on the development process is available. Instead, there is lots of knowledge from past experience. This experience should be used to proof correct function and performance. Develop an equipment master plan that lists all equipment and computer systems together with a judgment for validation need. Develop an implementation plan with a time schedule for the validation of all systems. Validation should follow the same steps as for new systems.

Page 27: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 27 of 40

10.1 Design qualification

• Describe the use of the systems.

• Describe required functions and performance.

No vendor qualification or evidence of development validation is required.

10.2 Installation qualification Document system hardware and software and enter equipment data into the laboratory's database.

10.3 Operational qualification

• Evaluate which tests have been done in the past and check if they are sufficient to proof operational qualification

• If not, develop test procedures and acceptance criteria. • Execute and document test and compare test results with

acceptance criteria. • Declare the system as validated.

10.4 Performance qualification

Follow steps as described in chapter 7 and 8.

Page 28: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 28 of 40

11. Validation of Macros and Spreadsheet Applications Macro programs and spreadsheet calculations are considered to be software and should be validated to demonstrate suitability for their intended use. The extent of validation depends on the impact of the Macro on product quality and on the complexity of the Macro. Any step can be passed over as long as there is sufficient explanation that the skipped step has no relevance for the program. The validation steps should include:

11.1 Develop a project validation plan Defines the scope of the project, responsibilities, validation approach and timeline and it includes checkpoints.

11.2 Define responsible persons Identify persons responsible for specifications, design, development, tests, and approvals.

11.3 Define user requirements Describe the task, how the task is done currently and how the new program will do it more efficiently. Describe user requirements (what the user wants to do with the system), system requirements (computer hardware, operating system), regulatory (GLP/GMP/GCP, 21 CFR Part 11) requirements and security requirements. Describe the user's current environment: hardware environment, software environment, IT environment. Specify minimum hardware and software requirements that will be used. Describe the required skill level of the end users. Describe how extensively and how long the software is intended to be used (anticipated number of users, life time, frequency of use) and whether any changes are anticipated during the life of the program.

Page 29: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 29 of 40

11.4 Specify Functions Describe the program in terms of the functions it will perform, written in such a way that it is understood by both the software developer and the user. Review the functional description against the requirement specifications

11.5 Design and implementation Document formulae or algorithms used within the program. Write the code. Define file structure, e.g., whether to use one Excel workbook with multiple sheets, several single-sheet workbooks or just a template. Define formulas to perform calculations. When using Excel, define whether to use Excel functions or VBA procedures. Determine the most appropriate user interface: dialog boxes, list boxes, menus, toolbars, short cut keys. Define the level of security to restrict access to the whole or particular elements of the program. Define how to handle errors, e.g., how the application detects and deals with errors. Annotate the code using documentation standards of your organization, if available Document the program such that it can be understood by other people whose education and experience are similar to the programmer.

11.6 Testing Develop a test plan to test the Macro and Spreadsheet application for all functions the user will use. Develop a matrix that links functions to be tested to requirement specifications. Develop test cases and test data sets with known inputs and outputs. Describe the test environment and the execution of tests. Test protocols must clearly state the Macro title, revision number, and file name. Tests should describe the test environment and the execution of tests. Develop test cases and data test sets that can be used for current and future testing that simulate as much as possible the real-life environment (life testing). Include test cases with normal data across the operating range, boundary testing and unusual cases (wrong inputs). Include procedures to verify calculations. Test procedure and results should be documented, reviewed and approved by the programmer’s, and for complex macros by quality assurance departments.

Page 30: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 30 of 40

11.7 Ongoing performance checks Specify type and frequency of checks as well as expected results and acceptance criteria. Develop test data sets and procedures for ongoing performance checks.

11.8 User documentation Describe the program’s functionality and formulae used for calculations and how to install, operate and test the program.

11.9 System security and data integrity Describe which features are implemented to meet security requirements, for example, back-up procedures and limited authorized system access to the program and data. Describe how integrity of Macro and Spreadsheet program and data generated by the program is ensured, for example how can you ensure that only authorized Macros are used and Macros are not changed, either incidentally or accidentally, outside the change control environment.

11.10 Change and version control Develop a procedure to authorize, test, document and approve any changes to the software before implementation.

12. Change Control Equipment, computers and networked systems are frequently changed during the life of the systems. It is of utmost importance to keep systems in the validation status. • Any change to equipment and computerized/networked systems

that may affect the system’s validation status should follow documented procedures and should be formally approved. The procedure should include instructions for requesting, approving, documenting and implementing changes. They should also describe the method of evaluation to determine the degree of revalidation or requalification necessary to maintain the

Page 31: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 31 of 40

validated state of the system. The procedure should also identify the persons responsible for determining the necessity for change control and for authorizing the change.

• If changes are made within a complex computerized/networked

system, the project validation team consisting of users of equipment, support personnel and computer validation experts should evaluate the need, type and extend of re-qualifications on a case by case basis. The user of the system should get advice from the computer validation experts on which impact the change may have on her/his system and which type tests should be done.

• If a vendor changes the software the new release should be

shipped to the user’s site with a validation certificate to demonstrate that the update has been developed and validated at the vendor’s site to appropriate standards. The vendor should also inform users if the new software may have an impact on Marco programs the user has written.

• The vendor should provide a list with functions that have been changed, added or deleted and with information on which impact the changes have on the validation status.

• At the user’s site the system with the new software revision

should undergo formal installation qualification (IQ) as for a new system.

• The validation team should evaluate the need for OQ testing. Where possible, the test cases test data used for the re-qualification should be designed so that the results can be compared with those obtained using earlier versions.

• Before the system continues with routine analysis, a performance

qualification (PQ) should be carried out. All details of the change should be formally documented with information on:

- clear identification of software or hardware to be

changed - reference number of change for clear process

identification

Page 32: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 32 of 40

- nature of the change - the reason for the change - date when the change was requested - removed software errors - new functions together with their features and benefits - impact analysis the change may have on the

performance of connected modules and systems - the impact the change may have on user contributed

Macro programs - the type of revalidation or re-qualification tests based

on the impact analysis - acceptance criteria and - test results - revision history with old and new version numbers - date when the update was installed - list of people who have been informed

Page 33: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 33 of 40

13. Instrument Obsolescence and Removal When instruments are retired, a plan should be in place to ensure that the application can run on the new system and data generated on the old system work on the new instrument. Steps include • Transfer the application, e.g., analytical methods, raw data,

analytical results and databases to the instrument. • Check if the new system generates the same results from raw

data as the old system.

14. Glossary For an extensive glossary on qualification and validation see: www.labcompliance.com/glossary The glossary also includes terminology for network hardware and software.

15. Documentation maintenance • Lists all documents • Describes where documentation and software is archived. • Describes criteria and examples for time the documentation must

be archived: examples include validation master plans, project validation plans, validation deliverables, user manuals

• Defines owners of documents

Page 34: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 34 of 40

Appendix A. Checklists and Forms Checklists

Forms

F1001 Change control form F1002 Change control summary log F1004 Initiation and authorization of Macros and Spreadsheets F1006 Validation deliverables and owners F1009 Validation team members F1010 Preparation and approval of the validation master plan

Page 35: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 35 of 40

Form F1001: Change control

Change Control Form

Form ID

Date:

System ID:

Location:

Description of change (should include reason for change)

Expected impact on validation

Authorization to change

Name: Signature Date

Change implemented on Date:

Comments (implementation, testing)

e.g., document any observation and new version or revision number, types of tests that have been performed

Completed by Name: Signature Date

Approved by Name: Signature Date

Page 36: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 36 of 40

Form F1002: Change control summary log

System ID Name: CDS ChemStation Plus Number: C4663B

Date Type of Change Change control form ID

04/75/01 ChemStation software upgrade from version A.08.01 to A.08.01

H1674

Page 37: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 37 of 40

Form F1004: Initiation and Authorization of Macros & Spreadsheets

Form ID

System Location:

Initiator:

Description of problem, how it is solved now and how the new software can improve efficiency

Expected duration of use and frequency of use: e.g., 6 months, 5 times a day

Approval of supervisor:

Supervisor function:

Name Signature Date

Comments:

Approval/rejection by QA:

Approval yes/no

Reason for approval/rejection

Name Signature Date

Comments/Recommendations:

Page 38: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 38 of 40

Form F1006: Validation deliverables and owners

Deliverable Prepared by Reviewed by

Approved by

Reference document

Validation plan

Validation team Operation manager

QA system Owner

VP 679

IQ Protocol

Vendor Validation team

QA manager

V456

Page 39: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 39 of 40

Form F1009: Validation team members Department Name Tel E-mail QA

Consultant

IT

Lab

Validation group

Vendor

Page 40: Validation Master Plan - SDLC BUSINESS SOLUTION – … de calculo... ·  · 2013-03-10Validation Master Plan Page 4 of 40 1. Purpose and scope of this plan Provides a framework

Validation Master Plan

www.labcompliance.com Page 40 of 40

Form F1010: Preparation and approval of validation project plans (master validation plan) Preparation Representing department

Name

Signature Date

User

QA

IT

Validation group

System owner Business Management

Review and approval Representing department

Name Title

Signature Date

System Owner/ Management

QA Compliance