UNCLASSIFIED Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark D. Smith, PE, CEM, CEA Energy Manager, Redstone Arsenal Federal Utility Partnership Working Group - Fall 2010
15

Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

Aug 04, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

Utility Energy Savings

Contract Project Redstone Arsenal, Alabama

Presented by

Doug Dixon, Pacific Northwest National Laboratory

For Mark D. Smith, PE, CEM, CEA

Energy Manager, Redstone Arsenal

Federal Utility Partnership Working Group - Fall 2010

Page 2: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

Page 3: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

0

50

100

150

200

250

Klbs

FY09 Total Hourly Steam

FY09 Total

Threshold

$22.76 / MMBTU

(Minimum take-or-pay base rate)

(Consumer Price Index)

Average FY09

Natural Gas Price

$5.52 / MMBTU

$16.91 / MMBTU

(High capacity rate)

(Petroleum Price Index)

Hours

Page 4: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

Resolution

• Manage the steam load to the minimum take-or-

pay thresholds under the existing contract.

Prune the distribution system by eliminating

long runs with low density and high thermal

losses.

Ensure summer steam loads are utilized.

• Cooling – Absorption chillers

• Domestic hot water

Page 5: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

Method

• UESC with TVA

Decommissioned four miles of existing steam service and

installed a natural gas distribution system.

Audited 44 buildings for feasible energy conservation

measures.

Lighting

Controls / Energy Management System

HVAC upgrades

Insulation

Page 6: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

Method

Project

Cost

Energy

Savings

Simple Pay

Back

Meter

Group A

$9,823,367 $1,411,825 7 yrs

Monthly payment amount - $111,975 – 120 months

Monthly savings - ~$117,652

Page 7: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

Method

• Key Components

Commissioning Agent

Project documentation and design adherence

Quality Assurance and Engineering

Monitor maintenance and energy savings as part of

the performance assurance plan

Measurement and Verification

One year

Preventative Maintenance

Three years

Page 8: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

Commissioning Agent

• Independent Third Party

• Involved through entire project implementation

process

– Design

– Construction

– Acceptance

– Warranty

• Provided final commissioning documentation

• Funded through UESC project (About 1.5% of total

project cost)

8 OF 10

Page 9: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

Commissioning Scope

Design Phase Commissioning

Basis of Design evaluation

Construction Document evaluation

Construction Phase Commissioning

Submittal and Shop Drawing Review

Start-up procedure Submittals

Site Observations

Pre-Functional Tests

Project Issues Log

9 OF 10

Page 10: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

Commissioning Scope (cont.)

Acceptance Phase Commissioning

Functional Performance testing

O&M Manual

Training and Orientation

Final Commissioning Report

Warranty Period Commissioning

10 OF 10

Page 11: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

Commissioning Benefits

Eyes in the field to protect government interests

Project issues log that required resolution prior to

systems acceptance testing

Acceptance testing to insure proper operation of all

systems

Final documentation of all tasks, findings, and actual

building systems performance

11 OF 10

Page 12: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

0

50

100

150

200

250

Klbs

FY09 Total Hourly Steam

FY09 Total

Threshold

3046 HDD

Hours

Page 13: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

0

50

100

150

200

250

Klb

sFY10 Total Hourly Steam

FY 10 Total

Threshold

3338 HDD

Hours

Page 14: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

Direction

• Award second UESC task order for Steam

Decentralization meter group B

Include commissioning agent

• Audit government owned boiler plants / distribution

system and associated buildings

• Conduct Audits for reimbursable customers

• Re-commission Major Existing Facilities

Page 15: Utility Energy Savings Contract Project · Utility Energy Savings Contract Project Redstone Arsenal, Alabama Presented by Doug Dixon, Pacific Northwest National Laboratory For Mark

UNCLASSIFIED

Questions?