UTA Airport TRAX LineNorth Temple Viaduct &

Construction Phasing

Page 2: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing.

North Temple Viaduct Detours

North Temple viaduct closure and construction begins April 18. Construction will take 18 months

Alternative A• Westbound detour – 300 West to 600 North to 900 West

Alternative B• Eastbound detour – 900 West to 400 South to 300 West

Page 3: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing.

UTA Bus Routes

UTA bus routes that travel North Temple will be rerouted beginning April 4. For specific route information visit www.rideuta.com

Page 4: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing.

When Is the Airport Line Being Built?

Page 5: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing.

North Temple Construction - Phases

Phase 1Phase 2

Phase 3Phase 4

Phase 5

Page 6: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing.

North Temple Phasing – Spring 2010

North Temple Phasing – Spring/Summer 2010

Page 7: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing.

North Temple Phasing – Summer/Fall 2010

North Temple Phasing – Spring 2011

Page 8: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing.

North Temple Phasing – Summer 2011

Page 9: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing.

Downtown Phasing – Spring 2012 – Fall 2012

Page 10: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing.

Communications and Marketing

• Weekly construction updates• Regular one-on-one visits to corridor properties• Comprehensive marketing plan

• Milestone events • Direct mail• Radio• Billboards• Print

• Looking for others ways to communicate construction information

Page 11: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing.

Airport Construction & Viaduct Open House

Thursday, March 185 p.m. to 7 p.m.

UTA FrontLines Headquarters669 West 200 South

Page 12: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing.

Thank youMatt Sibul, UTA Airport TRAX Project Manager: 801-236-4731