#GridInterop Using the IntelliGrid (sm) Methodology and GWAC Stack in IT Smart Grid Project Management John J. Simmins, Brian Green Electric Power Research Institute Michael Tao Boreas Group Grid-Interop 2011
15

Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

May 06, 2018

Download

Documents

vuongmien
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop

Using the IntelliGrid(sm) Methodology and GWAC Stack in IT Smart Grid Project Management

John J. Simmins, Brian GreenElectric Power Research Institute

Michael TaoBoreas Group

Grid-Interop 2011

Page 2: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 2

Contents

• Introduction

• Framing the problem.

• Enter the GWAC Stack and IntelliGrid(sm)

methodology.

• Some project management terminology.

• Application of the IntelliGrid methodology and GWAC stack to project management.

Grid-Interop 2011

Page 3: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 3

Applications for the IntelliGrid(sm) Methodology

• Requirements Gathering

• Project Planning

• Testing (e.g. System Acceptance Testing)

• Training

• Security Risk Analysis

• Governance

Grid-Interop 2011

Page 4: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 4

The Problem with IT Project Management

Standish Group 2010:Only 32% project succeeded by delivering on time on budget

44% Break one of the constraints

24% Fail entirely

Grid-Interop 2011

Page 5: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 5

Project Management Importance*

• Nearly all respondents said that project management was critical to successful project (47% say “critical” and 43% say “somewhat important”) .

• Less than one half (49%) said they follow a formal project management methodology.

• Around 20% said they have any project management tools.

• Results:

– Less than one third (27%) said they do a very good job of managing projects.

– Only 10% said they do an excellent job.

*Closing the Gap: The Link Between Project Management Excellence and Long-TermSuccess, Economist Intelligence Unit Limited, 2009.

Grid-Interop 2011

Page 6: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 6

The Smart Grid IT Project Management Gap

• Lack of a conceptual model of the Smart Grid IT Project.

• Lack of a methodology for scoping and managing the project.

Grid-Interop 2011

Page 7: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 7

Enter: The GWAC Stack

•Need to envision the entire project to scope it properly.

•If it effects the success of the project, it needs to be planned.

•Need to ensure that the entire scope has been planned.

Grid-Interop 2011

Page 8: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 8

Project Process – Create WBS

•Project scope statement

•Requirements docs.

•Org. process assets

• Decomposition

• WBS

• WBS dictionary

• Scope baseline

• Project doc. updates

• Identifying and analyzing deliverables

• Structuring and organizing the WBS

• Decomposing the upper WBS levels into detailed components

• Verifying the degree of decomposition is adequate

• Business need

• Functional requirements

• Non-functional requirements

• Quality requirements

• Acceptance criteria

• Training requirements

The Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project goal.

Grid-Interop 2011

Page 9: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 9

Project Process – Create WBS

•Project scope statement

•Requirements docs.

•Org. process assets

• Decomposition

• WBS

• WBS dictionary

• Scope baseline

• Project doc. updates

IntelliGridGWACStack

Grid-Interop 2011

Page 10: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 10

GWAC Stack Decomposition to a WBS

Grid-Interop 2011

Page 11: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 11

GWAC Cross Cutting Issues

Grid-Interop 2011

Page 12: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 12

Applying the Cross Cutting Issues to the Plan

Grid-Interop 2011

Page 13: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 13

Post Workshop Analysis

Grid-Interop 2011

Page 14: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 14

In Conclusion:

1. Description of Project Management– Failure to plan is planning to fail.– Bad project management is the single biggest cause of

failed projects.2. GWAC Stack

– GWAC Stack is a model for defining project scope.– GWAC Stack is clearly seen and addressed in the

project plan.

3. Apply the Methodology to Smart Grid IT Projects

– Applying the IntelliGrid methodology can completely scope the project.

– It isn’t magic. Grid-Interop 2011

Page 15: Using the IntelliGrid(sm) Methodology and GWAC Stack …€¦ · Using the IntelliGrid(sm) Methodology and GWAC Stack in ... The Work Breakdown Structure ... • WBS • WBS dictionary

#GridInterop Phoenix, AZ, Dec 5-8, 2011 15

For More Information

John SimminsEPRI

[email protected]

A Utility Application Implementation Strategy Using the EPRI IntelliGrid Methodology And the GridWise* Architecture Council Stack as a Model, 1024590

*GridWise is a registered trade mark of the GridWise Architecture Council

Grid-Interop 2011