Top Banner
VIRAJ SAP PS User Guide TABLE OF CONTENTS 1
76
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: User Maual

VIRAJ SAP PS User Guide

TABLE OF CONTENTS

Project Process Name Page No.

Create a Project

Manual Project Cost Planning

Project Budgeting

Release Quarterly Based amount Budgeted value

Release the Budgeted WBS Element for Execution

Create Project Management Work Center

Creation and Change of Network Header and Activities

Project Date Planning and Scheduling

Assignment of Project Team on WBS Element Level

Resource Planning in Internal Activities

Material and Service procurement for project

Project Execution

Project Versions (To set Baseline) and Simulation Versions (To see Future Implications)

Project Material Consumption and Stock transfer from One Project to other Project or Storage Location

Budget supplement to a WBS element

Budget return

Budget Transfer

Project Closure

1

Page 2: User Maual

1 Create a Project

Procedural steps:

Access Project Builder through:

Via ECC Menu Logistics or Accounting > Project System > Project > Project Builder

Via Transaction Code CJ20N

Work List and templates Structure Tree Work AreaStructure Tree

The structure tree displays the project object (project definition, WBS element, Network, activity)

Worklist

You can store user-specifically frequently used project data (project definitions, networks, and WBS elements) in the worklist, so that you can access them quickly later. Furthermore, a list of the last five projects that you have worked on is always displayed in the worklist.

Work Area

In the work area, you see the details view of the object selected in the structure tree. You can also directly access overviews of subordinate objects. Here you can execute all the business transactions for project coordination and execution. You can always move

2

Page 3: User Maual

between the detailed view of the selected object and the overviews of the subordinate objects. There are two ways to create Project in Project Builder as 1).

2).

3

Page 4: User Maual

4

Page 5: User Maual

From this open button we can see created Project list.

5

Select appropriate Investment Profile for document posting.

Page 6: User Maual

Project Objects can be viewed as:

.

Network overview Activity overview Milestone overview PS Text overview Document overview

6

Page 7: User Maual

2 Manual Project Cost Planning

Cost planning for the Project can be done by various methods. We are using Manual Cost Planning (Hierarchical Planning)

Access transaction by:

Via Menus Logistics Project System Financials Planning Cost in WBS Overall Values Change

Via Transaction Code CJ40

7

Page 8: User Maual

.

8

Select the Project by taking drop down here or clicking F4

Select the version, 0 or 1 or 2 as only three versions are available in

Page 9: User Maual

9

Page 10: User Maual

10

Page 11: User Maual

11

Page 12: User Maual

If no error while check cost values then system will allow to save cost planning for version ‘0’

12

Page 13: User Maual

3 Project Budgeting:-

The Project Budgeting will be copying from the Project cost planned with suitable approved version, before scheduling the original project for actual executions. Default cost planning for budgeting is ‘0’.

Access transaction by:

Menu path Logistics Project System Financials Budgeting Original Budget Change

Transaction code CJ30

13

Page 14: User Maual

14

Page 15: User Maual

15

Page 16: User Maual

16

Page 17: User Maual

17

Page 18: User Maual

18

Page 19: User Maual

19

Page 20: User Maual

4 Release Quarterly Based amount Budgeted value:- Access the transaction by:

Via Menus Logistics -> Project system -> Financials -> Budgeting -> Release -> CJ32 – Change

Via Transaction Code CJ32

Once you click CJ32, the selection screen shall appear as follows

20

Page 21: User Maual

21

Page 22: User Maual

22

Page 23: User Maual

The Current Budget and Planned Totals at the right may be used as a reference to decide upon the budgets released amount. You can select the WBS Elements which have budgeted and have the system calculate the budget amounts as a fixed percentage of the Current Budget. In our case, we select all the WBS elements listed above. Then, using the menu path Edit Copy View (Shift + F1), choose 5th option “Current Budget” and giving the percentage as 25.

23

Page 24: User Maual

24

Page 25: User Maual

25

Page 26: User Maual

26

Page 27: User Maual

After released the Budget, Rlease Budgeted WBS element, so background system will be created AUC ( Asset Under Construction) or CWIP Asset with WBS data for monthly settlment form WBS to AUC and at the time of Capatilzation settlment from AUC to Fix Asset settlement

27

Page 28: User Maual

5 Release the Budgeted WBS Element for Execution:-

28

Page 29: User Maual

6 Create Project Management Work Center:-

Menu Path Logistics Project Systems Basic Data Master Data Work Centers master Record Create

Transaction Code CNR1

Note: After entering in all required data fields, press the tab page ‘Capacities’, following screen will appear

29

Page 30: User Maual

Enter Capacity category 002 (person) and formula for calculating the capacity requirementPress Enter, following screen will appear.Enter factory calendar VL, capacity planner group-A, base unit of measure DAY, working times and no. of individual capacities in the work centre. After this press enter system calculates the available capacity and operating time based on the input data. Enter percentage overload, and check the indicators shown in the screen above. This is to ensure that the availability check of this work centre will happen during scheduling.

30

Page 31: User Maual

Note: After entering in all required data fields, press the green arrow , to go back to Capacity overview page, than press the ‘Scheduling’ tab page, following screen will appear

Enter capacity category

Note: After entering in all required data fields, press the tab page ‘Costing’, following screen will appear

31

Page 32: User Maual

Enter respective cost center, activity type and formula again. Now you can link your Project Organization structure (Project Department Hierarchy Defined in HR) can link to this work center for Resource Planning.

32

Page 33: User Maual

33

Page 34: User Maual

You have now created a New Work Center. Note: You must now save your work by clicking on the “Save”, which will then give you the message, “Work Center “xxxxx” in Plant “xxxx” was created.” You have now finished the task.

7 Creation and Change of Network Header and Activities:-

Access the transaction using:

Via Menus Logistics Project System Project Special Maintenance Functions Networks Create

Via Transaction Code CJ20N/ CN21

34

Page 35: User Maual

A network consists of the following:

Activities Activity elements Relationships

In the network header you can enter the following data, which are used as default values for the entire network:

Assignments to other object like WBS element Basic start (in case of Forward scheduling) or finish date (in case of backward

scheduling) as well as indicator for Auto scheduling Release and scheduled dates Assignments of organizational data, such as profit center

The process of creating Network manually is explained here.

35

Page 36: User Maual

36

Page 37: User Maual

37

Page 38: User Maual

8 Project Date Planning and Scheduling:-

8.1 Project Planning Board / Date Planning

1. Durations are maintained in each activity.2. Relationships are maintained among activities

8.1.1 Overview of Project Planning Board

Access the transaction using:

Menu path Logistics Project System Project Project Planning Board Change

Transaction code CJ2B

OR

2. From Project Builder by clicking Project planning board – button as shown below, on the application bar.

On the following Change Project Planning Board screen enter the necessary data:Before entering the project planning board, expand the project structure so that the activities are visible. These are then shown in the Project planning board as well. Users can go to planning board

38

Page 39: User Maual

Goto Settings Options. The following selection options will appear for scheduling

8.1.2 Other functions of Project planning boardAll activities in the network are scheduled. Dates are copied to WBS.

Critical activities are shown in red colour. The chain of critical activities is called as critical path.

There are various activities can be perform through planning board. Icons on the planning board are as follows:

a. b. c. d. e. f. g. h. i. j. k. l. m. n. o. p. q. r. s. t. u. v. w. x. y. z.

a. Select allb. Deselect allc. Move up

39

Page 40: User Maual

d. Move downe. Createf. Copyg. Cuth. Pastei. Undoj. Connect activities selectedk. Relationships listl. Deletem. Detailsn. Confirm activityo. Schedulep. Calculate planned costsq. System/user statusr. Network headers. Component overviewt. Capacity overviewu. Maintenance ordersv. Costs overvieww. Milestone trend analysisx. Successor/predecessory. Showz. hide

1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11.12.13.14.15.16.17.18. 19. 20.

1. Open / close left window2. Open / close bottom window3. Filters4. Group5. Sort6. Highlighting7. Position8. Connect9. Scheduling comparison10. Zoom11. Adjust diagram area12. Adjust time axis13. Planning board assistant14. Time axis assistant15. Set of dates16. Options17. Field selection18. Legend19. Logs20. User settings.

8.1.3 WBS Scheduling

4. On the following Project change screen click on the select all icon.

5. Edit Function Schedule. Or click on the Schedule icon . System uses the networks start and finish date (in turn project start and finish dates since dates are copied from Project Definition) as the basis for calculating and displaying the earliest and latest dates for the activities.

40

Page 41: User Maual

6. Choose Edit Select WBS Elements.

8.1.4 Copying Schedule dates and extrapolating to WBS elements

7. Choose Edit Reconcile dates Copy scheduled dates. The system copies the maximum dates (earliest start and latest finish) determined in scheduling for each activity and displays them as date bars in the WBS elements.

8. To copy dates from lower WBS Elements to superior WBS Elements,Edit Deselect AllEdit Reconcile Dates Extrapolate Dates.

41

Page 42: User Maual

Save your settings.

9 Assignment of Project Team on WBS Element Level

Select WBS Element, Edit->WBS Element-> Project team for WBS Element

42

Page 43: User Maual

Select WBS and Create assignment (F7)

43

Page 44: User Maual

44

Page 45: User Maual

10 Resource Planning in Internal Activities:-

Transaction:-Cj20n

As shown in below screen shot the required amount of work system will calculate automatically from duration Activity type is maintained under cost center which contains the per unit rate of the work. In below example work planned is 10 Days for activity Excavation for 5400 plant. Activity type will be taken from cost center.

45

Page 46: User Maual

Here we can distribute 10 Days work in different resources.

11 Material and Service procurement for project

Once the structure exists for the project, you can start to plan/add components to activities. Cost planning and scheduling takes place simultaneously.

46

Page 47: User Maual

To add component for an activity:

Select an activity

There are different views under the activity:

Adding material for an activity

There are two ways to add components to activities:1) By dragging and dropping from the template area

Drag and drop the “Material component” – object from template area to an activity. The screen will look as illustrated in the picture above. Give material definition, item category ‘L’ (stock ), and qty.

2) By selecting the Component overview – button, you can start to add components.

47

Page 48: User Maual

After the selection the screen looks as follows:

In this table you can add components to activities. Required fields are “Material”, “Requirement qty” and “Item category”.

1) Adding items which is manufactured by same BU: Always select “L Stock item” in the item category – field.

48

Page 49: User Maual

The alternatives when the item category marked as “L - Stock item” for material

[Reserve for network: Use this indicator to specify that a reservation is created for materials kept in stock (stock items).]

[Reserve. WBS element: You use this indicator to create a reservation for the non-stock item for the network and post the material in the project stock after goods receipt.]

Preq+Res – WBS elem.: Use this indicator to specify that the purchase requisition for the non-stock item and stock items, will be converted into a standard purchase order for the project.

[Prelim. Preq-WBS el: Specifies that a purchase requisition is created for the material and this purchase requisition is then converted into a preliminary order for the WBS element. No MRP-relevant reservation is created. After goods receipt for the purchase order, a receipt is posted to the project stock.]

[3rd party req. WBS el: Specifies that a purchase requisition should be created for the material and then converted to a third-party order for the WBS element. When the delivery address is separate from the plant address]

Procurement Parameter Tab:-

49

Page 50: User Maual

The data in Procurement parameter tab defaulted from material masters setting based on item category selected while creating component.

“From release” means that the activity is released when the WBS element above is released

“Immediately” means that the activity is immediately when the component is attached to activity

Long Text Tab

12 Project Execution:-

12.1 Activity Confirmation

5.1.1 Manual Confirmation of activity

Via MenusLogistics Project System Projects Project Builder

Via Transaction Code CJ20N

Enter Actual date for milestone: Actual date can be entered, either Confirming the activities so that the milestone will pick the actual date from activities OR , enter actual date manually in milestone actual date field.

Open the project through Project Builder transaction (CJ20N) > Select the network > click on activity overview > select the activities which are required to be confirmed > click on confirm icon.

50

Page 51: User Maual

51

1. Select the Network

2. clcik on activity overview

3. Select the activity

4. Confirm the activity

Page 52: User Maual

4. If processing % is less than 100% then don’t select the final confirmation and completed check box. Only enter Processing %.

5. After save system will save PCNF: Partially confirmed this activity. 6. At the time of Full confirmation select final confirmation and completed check boxs. Enter actual date finish date and go back.

52

Page 53: User Maual

13 Project Versions (To set Baseline) and Simulation Versions (To see Future Implications):-

13.1 Project Version Creation: Once our Project Date Planning will be frozen out and scheduled the Project then system calculates start and finish dates for all WBS and activities. If you want set this will baseline for my future reference then create Version through ‘T’ code CN72 (Create Project Version).

Menu path Logistics -> Project System -> Project -> Project Version -> Create

Transaction CN72

53

Page 54: User Maual

13.2 Project Creation In Simulation mode: We can Transfer our active Project into Simulation Project for Future date implications.

Menu path Logistics -> Project System -> Project -> Simulation -> Transfer Project

Transaction CJV4

54

Page 55: User Maual

55

Page 56: User Maual

14 Project Material Consumption and Stock transfer from One Project to other Project or Storage Location:

14.1 Project Material Consumption:-

The Purchase Department will convert your Project Material Purchase requisition into Purchase Order. Then that material received in Project Stock for consumption.

Menu path Logistics Logistics Execution Outbound Process Goods Issue for Other Transactions Enter Goods Issue (Mvt type is 281)

Transaction MB1A

Before Procurement, the stock of material is as

After Procurement, the stock of material is as

56

Page 57: User Maual

Consumption of Materail against Network Activity:-

57

Page 58: User Maual

After consumption Project stock is as

58

Page 59: User Maual

14.2 Project stock transfer from one project to other Project:-

As per project requirement we can transfer project material from one to another project. Here the receiver WBS and sender WBS must have same system status and sufficient budget must be available for stock transfer.

Menu path Logistics Logistics Execution Internal Whse Processes Posting Change Via Inventory Management Enter Posting Change (Movement type is 415)

Transaction MB1B

59

Page 60: User Maual

60

Page 61: User Maual

61

Page 62: User Maual

14.3 Project stock transfer from Project stock to storage Location:-

At the time of Project closer all project stock should consumed or transferred to another project or we can transfer this project stock into storage location stock.

Menu path Logistics Logistics Execution Internal Whse Processes Posting Change Via Inventory Management Enter Posting Change (Movement Type :411)

Transaction MB1B

62

Page 63: User Maual

63

Page 64: User Maual

15 Budget supplement to a WBS element

Menu path Logistics Project System Financials Budgeting Supplements Supplement to ProjectTransaction CJ36

You will get the following screen

Input the receiver year and the text describing the reason of supplement

Press Enter

You will get a screen like the one shown below

64

Page 65: User Maual

Enter the Receiver WBS Element and Amount being supplemented to the WBS element as shown above. Save the transaction by clicking on the Save Button. After that release the same amount in CJ32 (Release Budget), then only system will allow using it.

65

Page 66: User Maual

16 Budget return

Menu path Logistics Project System FinancialsBudgeting Return from Project Transaction CJ35

Following screen appears,

66

Page 67: User Maual

67

Page 68: User Maual

17 Budget Transfer

Menu path Logistics --> Project system-->Financials --> Budgeting --> Transfer

Transaction code CJ34

Input sender/receiver years, the text and Press Enter

68

Page 69: User Maual

69

Page 70: User Maual

Enter the Sender WBS Element, Receiving WBS Element and Amount being transferred between the WBS elements as shown above. Save the transaction by clicking on the Save Button.

Budget Line Item Report

Menu path Logistics --> Project system--> Information system --> Financials --> Line Items --> Budget

Transaction code CJI8

The initial screen follows as below,

70

Page 71: User Maual

Budget Type – KBUD – Original BudgetBudget Type – KBNO – SupplementBudget Type – KBRO – ReturnBudget Type – KBUS – Transfer

You can view the changes made in the report S_Alr_87013560Enter the Project Definition and execute

71

Page 72: User Maual

The report shall be displayed as follows

18 Project Closure:-

Prerequisites for project closures are as1. All Budget amount should be either consumed against WBS or transfer to another project

or returned to controlling area.2. All expenditures must be settled to AUC or Fix asset or Cost center.3. All Project stock against that WBS should be nil

72

Page 73: User Maual

4. All activities or child components belong to this WBS must be zero.

Access Project Builder through:

Via ECC Menu Logistics or Accounting > Project System > Project > Project Builder

Via Transaction Code CJ20N

73