US Army Corps of Engineers BUILDING STRONG ® Walla Walla District SAME 21 June 2011 David A. Caldwell, Lieutenant Colonel Commander and District Engineer
US Army Corps of Engineers
BUILDING STRONG®
Walla Walla District
SAME21 June 2011
David A. Caldwell, Lieutenant ColonelCommander and District Engineer
BUILDING STRONG®
Agenda
Overview
Budget
Project Focus Areas
A-E and Planning Services Contract Status
2011 Industry Day Events
BUILDING STRONG®
Walla Walla District Overview
Civil Works District► Support to the Nation
(OCO, NPT, & EM)► Environmental Stewardship► Hydropower ► Navigation► Flood Damage Reduction► Recreation
Workforce: 823 Employees► 3 Military Officers► 187 Women► 56 Minorities► 150 Engineers► 113 Registered Professionals ► 270 Wage Grade Employees
Boundaries include portions of WA, OR, ID, WY, NV, UT
Bus
ine
ss L
ines
BUILDING STRONG®
Walla Walla DistrictWalla Walla District
Covers 107,000 sq mi Includes parts of six
States Civil Works Boundary
focused on the Snake River Basin
Regulatory Boundary is Idaho borders
Mill Creek Dam (Bennington Lake)
Mill Creek Dam (Bennington Lake)McNary Lock & DamMcNary Lock & DamIce Harbor Lock & DamIce Harbor Lock & Dam
Lower Monumental Lock & Dam
Lower Monumental Lock & Dam
Little Goose Lock & Dam
Little Goose Lock & Dam
Lower GraniteLock & Dam
Lower GraniteLock & Dam
Dworshak DamDworshak DamLucky Peak DamLucky Peak Dam
BUILDING STRONG®
District Infrastructure Over $2.5 Billion of infrastructure assets
including:► Hydropower Facilities► Navigation Facilities ► Flood Risk Reduction Reservoirs and Levee
System► Recreation Sites► Environmental mitigation
BUILDING STRONG®
Columbia RiverFish Mitigation
$40.7 Million
Operations& Maintenance$23.7 Million
Fish Ladders
Fish Screens
Transportation Program
Spill
Fish Collection
Removable Spillway Weir
Fish Hatcheries
Fish Counting
$64.4 Million in FY11
Fish Program
BUILDING STRONG®
0
25
50
75
100
125
150
175
200
225
250
FY
02
FY
03
FY
04
FY
05
FY
06
FY
07
FY
08
FY
09
FY
10
FY
11
FY
12
$ M
illi
on
s
ARRA ProgramReim/ContributeGICAPCG - ProjsBPA L. CapO&M BPAO&M AppFCCE/Reg Total
NWW Program OverviewFY2002 – FY 2011
BUILDING STRONG®
Walla Walla DistrictFY 12 Anticipated Budget
$0.7
$1.8 $20.7
$6.1
$43.4
$28.3
$38.0
$44.3
$10.0
$0.0
$0.3
CG Projects
CAP
GI
FCCE
RegulatoryO&M Approp
BPA Joint
BPA Large Cap
Work for Others
BPA Hydro
O&M Joint
$193.6 million Program 57% from BPA
BUILDING STRONG®
Project Focus Areas
Environmental Restoration Projects
Dam Safety Program Upcoming O&M Projects Upcoming CRFM Projects
and Studies Upcoming BPA Large
Capital Improvements
BUILDING STRONG®
Environmental RestorationProjects & Studies
Walla Walla River GI Feas Study, WA & OR Boise River GI Feasibility Study, ID Big Wood River GI, vicinity of Haley, ID Fort Hall GI, Pocatello, ID Weiser River GI, Weiser, ID Twin Falls Wetland Development (Sec 206) Bennington, WW, WA (Sec 1135) Boise River at Eagle Island, ID (Sec 1135) Portnuef River, Pocatello, ID (Sec 1135) Lower Snake River Fish & Wildlife Comp Plan Little Wood River, Gooding, ID
BUILDING STRONG®
Dam Safety ProgramDevelop, Prepare, and Implement Interim Risk Reduction Measures (IRRMs)
Construction ► Levee Vegetation Removal at Mill Creek and
McNary► Decommission Sluice Gate in Intake Tower
at Lucky Peak Studies► Revise Emergency Action Plan at Mill Creek► Certify Diversion Dike at Mill Creek► Upgrade Water Seepage Monitoring System
at Mill Creek► Update the Probable Maximum Flood and
Generate Water Surface Profile► Perform Potential Failure Mode Analysis
BUILDING STRONG®
Construction► Continue ongoing activities at Lower Monumental to repair Navigation
Lock wall ► Rock replacement at Jackson Hole Levees► Dam Safety DSAC Interim Risk Reduction Measures at Mill Creek and
Lucky Peak
Upcoming O&M Projects
BUILDING STRONG®
Construction► Juvenile Bypass Outfall Relocations at
McNary► Juvenile Bypass Outfall Relocations at
Lower Monumental► Prepare designs for new adult ladder
entrance at McNary and Ice Harbor that incorporates lamprey passage.
Studies► Configuration and Operation Plans for
Fish► Performance Verification Testing► Lamprey Passage Studies► Avian Predation Studies
Upcoming CRFM Projects and Studies
BUILDING STRONG®
Large Capital Improvements► McNary Fishway Crane 9 and 10
Replacement► McNary Potable Water System Upgrade► McNary Heat Pumps and Controls
Replacement► Ice Harbor DC System and Low Voltage
Switchgear Upgrades► Little Goose Intake Gantry Crane
Replacement► Dworshak National Fish Hatchery Boiler
Controls Replacement
BUILDING STRONG®
TYPE FIRM SIZE TIME STATUS
Multi-Discipline Design Services
McMillen, LLC$1M/yr,
$5M total
Base with
4 OptionsBase Year
Cost Engineering (large)Project Time & Cost
$90M totalBase with
4 Options
Option
Year 1
Cost Engineering (small business)
MOCA Systems
$2 M/yr,
$10M total
Base with
4 Options
Option
Year 1
Survey (primary Hydro)David Evans & Associates
$2M/yr,
$10M total
Base with
4 OptionsBase Year
Survey (primary Hydro) Terrasond$2M/yr,
$10M total
Base with
4 OptionsBase Year
Existing NWW A-E Contracts (IDIQ)
For information contact Bob Williams – 509-527-7539
BUILDING STRONG®
TYPE FIRM SIZE TIME STATUS
Multi-Discipline Design Services
Jacobs$2M/yr,
$10M total
Base with
4 OptionsBase Year
Multi-Discipline Design Services
McMillan$1M/yr,
$5M total
Base with
4 OptionsBase Year
Multi-Discipline Design Services
Harbor$1M/yr,
$5M total
Base with
4 OptionsBase Year
Survey (primary land) Rogers Surveying$1 M/yr,
$3M total
Base with
2 OptionsFinal Year
Multi-Discipline Planning Services
HDR Engineering, Inc
$1M/yr,
$3M total
Base with
2 OptionsFinal Year
Tetra-Tech EC, Inc$1M/yr,
$3M total
Base with
2 OptionsFinal Year
Existing NWW A-E Contracts (IDIQ)
For information contact Bob Williams – 509-527-7539
BUILDING STRONG®
Anticipated Future NWWA-E Contracts
TYPE AMOUNT TIMEFRAME
Multidiscipline Design Services
3 firms (large)IDIQ
$2 M/year, $10M total, Base w/ 4 options
Firms selected for negotiation, expect award mid July
Cost Engineering A-E IDIQ$1 M/yr, $240M total, Base w/4 options
Anticipated award by September 2011
Land Survey IDIQ$1 M/yr, $5M total, Base w/4 options Anticipated award by
September 2011
For information contact Bob Williams – 509-527-7539
BUILDING STRONG®
Anticipated Future NWWIDIQ Contracts
TYPE AMOUNT TIMEFRAME
Planning and Environmental Services
2 firms (large) MATOC (Regional)
IDIQ$2 M/year, $10M total, Base w/4 options
Synopsis - April
Advertise - June
Evaluate - July
Award - August
Planning and Environmental Services
2 firm (small business) MATOC (Regional)
IDIQ$1 M/yr, $5M total, Base w/4 options
Synopsis - April
Advertise - June
Evaluate - July
Award - August
Cultural Resource Services
2 firm (small business) MATOC (Regional)
IDIQ$500K/yr, $2.5M total, Base w/4 options
Synopsis - April
Advertise - June
Evaluate - July
Award - August
For information contact Rebecca Kalamasz – 509-527-7277
BUILDING STRONG®
Anticipated Future NWWIDIQ Contracts
TYPE AMOUNT TIMEFRAME
Asbestos and Lead Paint Removal
IDIQ$1 M/year, $5M total, Base w/4 options
Award - July
For information contact Ruthann Haider– 509-527-7201
BUILDING STRONG®
Outreach events recently held for local industry► Walla Walla, WA was held on 28 April 2011► Boise, ID was held on 12 May 2011
Purpose► Provided industry with the tools needed to do business with USACE► Provided industry an opportunity to showcase capabilities to USACE► Allowed an opportunity for dialogue
Future outreach events being planned for FY12► Introducing an advanced version as well
2011 Industry Day Events
For information contact Scott Beckstrand– 509-527-7434
BUILDING STRONG®
POC Info
Small Business Deputy – Scott BeckstrandPhone: 509-527-7434Email: [email protected]
Walla Walla District: http://www.nww.usace.army.mil Walla Walla District Solicitations: https://www.fbo.gov Keyword/Solicitation #: W912EF Twitter: http://twitter.com/wwcontracting
Facebook:
http://www.facebook.com/pages/WallaWallaUSACE-Contracting/148523221852286?sk=app_2309869772
BUILDING STRONG®
US Army Corps of EngineersWalla Walla District
Serving our Community, our Nation, the World