Top Banner
Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1
9

Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1.

Dec 24, 2015

Download

Documents

Mabel Morgan
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1.

1

Update on FMS Repair

Stephen TrentalangeSTAR Management Meeting

October 31, 2014

Page 2: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1.

FMS Repair Work Summary• Restacking work nearly completed– Small Cells: 100% complete (476/476)– Large Cells: 95% complete (748/788)– External cabling 100% complete

• Running with DAQ: LED/Jet Patch trigger to diagnose problems with HV and signals

• Cable mapping so far is correct for HV/signals• Large cells: various problems ~24/572 channels• Small cells: HV problem: +6V power supply;

working with the electronics techs to diagnose.

Page 3: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1.

Previous Problems:Updated• 216 Large Cells Left to complete– 34 old FMS Cells (216-34=182)– 90 from PSU by Nov 2 (182-90=92)– 12 bases available (92-12=80 still at PSU)

• Need 5 magnetic shields• Cabling/Stacking 1 week work• Noticed cracking in single small

cell/north side: seems stable

Page 4: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1.

4

Cosmic Rays Observed

Page 5: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1.

5

LED Signal

LED IssuesNo Signal

Yale Bases

Russian Bases

Page 6: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1.

6

Conclusions• Training of 2 extra on site experts in operation/ hardware for

FMS: Sam Heppelman/Grant Webb• Schedule for repair work on bases at PSU is tight, but a stream

of bases is arriving at BNL. Installation is not difficult.• Repair work on individual channels remains before run.• November-January Tasks:

– Repair work on individual channels– Small cell HV (+6V supply)– Spares for HV/LED control machines in hall– Spares for CW low voltage power supplies

• Work on “runaway trigger” problem with Jack/Chris/Eleanor

Page 7: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1.

7

Page 8: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1.

8

Stacking the FMS

The South Side is Fully Stacked

The North Side is 90% Stacked

Need the remaining 150 PMT bases from PSU.

Survey of FMS location completed

Page 9: Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31, 2014 1.

9

The Forward Meson Spectrometer1264 Pb-glass cells

788 large cells 476 small cells