Update on FCPS Construction/Renovation Projects April 2018
6

Update on FCPS Construction/Renovation Projects€¦ · New Elementary at Athens-Boonesboro Work Completed to Date: Silt fence and BMPs are in place. Construction entrance has been

Jul 23, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Update on FCPS Construction/Renovation Projects€¦ · New Elementary at Athens-Boonesboro Work Completed to Date: Silt fence and BMPs are in place. Construction entrance has been

Update on FCPSConstruction/Renovation Projects

April 2018

Page 2: Update on FCPS Construction/Renovation Projects€¦ · New Elementary at Athens-Boonesboro Work Completed to Date: Silt fence and BMPs are in place. Construction entrance has been

New Elementary at Athens-Boonesboro Architect: EOP Architects

General Contractor: Griggs Enterprises

GC Contract Sum: $17,860,200

Total Project Cost: $23,801,841

Change Orders to Date (0): $0

Scheduled Contract Completion Date: July 2019

% of Contract Completed: 0%

Revised Completion Date per GC: No Change

April 2018

Page 3: Update on FCPS Construction/Renovation Projects€¦ · New Elementary at Athens-Boonesboro Work Completed to Date: Silt fence and BMPs are in place. Construction entrance has been

New Elementary at Athens-BoonesboroSchematic Rendering of Final Façade

April 2018

Page 4: Update on FCPS Construction/Renovation Projects€¦ · New Elementary at Athens-Boonesboro Work Completed to Date: Silt fence and BMPs are in place. Construction entrance has been

New Elementary at Athens-BoonesboroWork Completed to Date: Silt fence and BMPs are in place.

Construction entrance has been completed, as well as 2 additional common lanes for church/soccer field traffic.

Grading at building pad has begun.

Settlement plate installations have begun.

Current Work Effort (April): Site clearing and tree removal.

Continued grading.

Continued settlement pate installations and monitoring.

Utilities coordination for power and water.

April 2018

Page 5: Update on FCPS Construction/Renovation Projects€¦ · New Elementary at Athens-Boonesboro Work Completed to Date: Silt fence and BMPs are in place. Construction entrance has been

New Elementary at Athens-Boonesboro

April 2018

North Entrance

Construction Lane

Common Lane

Common Lane

Page 6: Update on FCPS Construction/Renovation Projects€¦ · New Elementary at Athens-Boonesboro Work Completed to Date: Silt fence and BMPs are in place. Construction entrance has been

New Elementary at Athens-Boonesboro

April 2018

Site Grading