UNDP - GEF UNDP - GEF Project: Project: UKR/01/G31/A/1G/99 UKR/01/G31/A/1G/99 Climate Change Mitigation in Ukraine through Energy Efficiency in Municipal District Heating Pilot Project in Rivne
Jan 19, 2016
UNDP - GEFUNDP - GEF Project: UKR/01/G31/A/1G/99Project: UKR/01/G31/A/1G/99
Climate Change
Mitigation in Ukraine
through Energy
Efficiency in Municipal
District Heating
Pilot Project in Rivne
Main ItemsMain Items
• Major Barriers and Lessons learnt
• Best Practices
• Challenge for future
ACCESS TO FINANCE ACCESS TO FINANCE Strategic Priority #2Strategic Priority #2 (UNDP/GEF Business Plan)(UNDP/GEF Business Plan)::Goal:
Creation of the Municipal Energy Service Company
(ESCO)
Demonstration
Project:
Energy Efficiency and
Economical effect Ecological
(Environmental) Effect Social effect
UNDP - GEFUNDP - GEF Project: UKR/01/G31/A/1G/99Project: UKR/01/G31/A/1G/99
MAJOR BARRIERS
• Inappropriate Institutional Approach
• Lack of Community Participation
• Absence of Local Capacity
INSTITUTIONAL INSTITUTIONAL APPROACHAPPROACH
Project Initial Strategy – NEX SCEC (State Committee for Energy Conservation)
Currently NEX – Local (Oblast) Administration
Changes Introduced
INSTITUTIONAL CHANGESINSTITUTIONAL CHANGES
THE FOLLOWING CHANGES HAVE TAKEN PLACE:
• The Project management was moved to the local level;
• Oblast Administration was nominated a national executing agency and the State Committee dismissed from this responsibility.
• As Result the Project Support Office in Kiev was closed and Project Implementation Office in Rivne became to be the only Project office.
COMMUNITY COMMUNITY MOBILIZATIONMOBILIZATION
Lack of appropriate Methodologies in Ukraine
No prior experience and field work in practice
Lessons learnt :
Selecting partners with capacity to understand and work with international assistance
Success when local partners own and manage
UNDP - GEFUNDP - GEF Project: UKR/01/G31/A/1G/99Project: UKR/01/G31/A/1G/99
Best PracticesBest Practices
Mayor’s personal involvement and support
Governor’s office support Sound and fruitful cooperation
between municipality and business (Komunenergia)
Community mobilization and involvement
During During 20042004
Capacity Building of the “ESCO-Rivne”:
ESCO Support Activities, Strategic Business Plan for
ESCO-Rivne Energy Efficiency Plan for
Rivne city launched
Community Mobilization; Experience Dissemination
and Replication country wide;
Preparation to the Stage 2.