Top Banner
Charlie Chong/ Fion Zhang API653 Post Exam Summary 1 st April 2016 –Passed.
103

Understanding api icp653 reading 22 post exam summary a

Jul 27, 2016

Download

Documents

Charlie Chong

Understanding api icp653 reading 22 post exam summary a
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

API653 Post Exam Summary1st April 2016 –Passed.

Page 2: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

AST Tanks

Page 3: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

AST Tanks

Page 4: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

AST Tanks

Page 5: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

AST Tanks

Page 6: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Page 7: Understanding api icp653 reading 22 post exam summary a

Fion Zhang at Shanghai1st April 2016

Charlie Chong/ Fion Zhang

Page 8: Understanding api icp653 reading 22 post exam summary a

API 653 Exam Administration -- Publications Effectivity Sheet FOR: November 2015, March 2016 and July 2016 Listed below are the effective editions of the publications required for this exam for the date(s) shown above. API Recommended Practice 571, Damage Mechanisms Affecting Fixed Equipment in the Refining Industry, Second Edition, April 2011

Charlie Chong/ Fion Zhang

Page 9: Understanding api icp653 reading 22 post exam summary a

API 653 Exam Administration -- Publications Effectivity Sheet FOR: November 2015, March 2016 and July 2016 Listed below are the effective editions of the publications required for this exam for the date(s) shown above. API Recommended Practice 571, Damage Mechanisms Affecting Fixed Equipment in the Refining Industry, Second Edition, April 2011

Charlie Chong/ Fion Zhang

Page 10: Understanding api icp653 reading 22 post exam summary a

ATTENTION: Only the following sections / mechanisms from RP 571 are included on the exam:

Section 3, Definitions Par. 4.2.7 Brittle Fracture 4.2.16 Mechanical Fatigue 4.3.2 Atmospheric Corrosion 4.3.3 Corrosion Under insulation (CUI) 4.3.8 Microbiologically Induced Corrosion (MIC) 4.3.9 Soil Corrosion 4.3.10 Caustic Corrosion 4.5.1 Chloride Stress Corrosion Cracking (Cl-SCC) 4.5.3 Caustic Stress Corrosion Cracking (Caustic Embrittlement) 5.1.1.10 Sour Water Corrosion (Acidic) 5.1.1.11 Sulfuric Acid Corrosion

Charlie Chong/ Fion Zhang

Page 11: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

API Recommended Practice 575, Inspection of Atmospheric and Low-Pressure Storage Tanks, Third Edition, April 2014

API Recommended Practice 577 – Welding Inspection and Metallurgy, Second Edition, December 2013

API Standard 650, Welded Tanks for Oil Storage, Twelfth Edition, March 2013 with Addendum 1 (September 2014), Errata 1 (July 2013), andErrata 2 (December 2014).

API Recommended Practice 651, Cathodic Protection of AbovegroundPetroleum Storage Tanks, Fourth Edition, September 2014.

API Recommended Practice 652, Lining of Aboveground Petroleum Storage Tank Bottoms, Fourth Edition, September 2014

API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction, Fifth Edition, November 2014.

Page 12: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

American Society of Mechanical Engineers (ASME), Boiler and Pressure Vessel Code, 2013 Edition

i. ASME Section V, Nondestructive Examination, Articles 1, 2, 6, 7 and 23 (section SE-797 only)

ii. Section IX, Welding and Brazing Qualifications (Welding Only)

See end of this study note for API Official BOK

Page 13: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Page 14: Understanding api icp653 reading 22 post exam summary a

http://independent.academia.edu/CharlieChong1http://www.yumpu.com/zh/browse/user/charliechonghttp://issuu.com/charlieccchong

Charlie Chong/ Fion Zhang

Page 15: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

The Magical Book of Tank Inspection ICP

Page 16: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Page 17: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

闭门练功

Page 18: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Page 19: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

The Prometric Reference Screen: will be similar like this. (no search function)

Page 20: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Damage Mechanisms Affecting FixedEquipment in the Refining IndustryAPI Recommended Practice 571Second Edition, April 2011

Page 21: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

5.1.1.10 Sour Water Corrosion (Acidic)5.1.1.10.3 Critical Factorsa) H2S content, pH, temperature, velocity and oxygen concentration are all

critical factors.b) The H2S concentration in the sour water is dependent on the H2S partial

pressure in the gas phase as well as temperature and pH.c) At a given pressure, the H2S concentration in the sour water decreases as

temperature increases.d) Increasing concentrations of H2S tend to decrease solution pH down to

about 4.5. Streams with a pH below 4.5 indicate the presence of a strong acid which would be the main corrosion concern (see 5.1.1).

PH 4.5OpenBookOpenBook

Page 22: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

4.3.8 Microbiologically Induced Corrosion (MIC)4.3.8.5 Appearance or Morphology of Damagea) MIC corrosion is usually observed as localized pitting under deposits or

tubercles that shield the organisms.b) Damage is often characterized by cup-shaped pits within pits in carbon

steel or subsurface cavities in stainless steel (Figure 4-89 through Figure 4-95).

PittingTubercles

OpenBookOpenBook

Page 23: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Welding Inspection and MetallurgyAPI RECOMMENDED PRACTICE 577FIRST EDITION, OCTOBER 2004

Page 24: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

9.9.1 Ultrasonic Inspection System Calibration……………Calibration system checks should be performed prior toand at the completion of an examination. In addition, a systemcheck is required with any change in the search unit,cabling, and examiner. The temperature of the calibrationstandard should be within 25°F (14°C) of the part to be examined.If the temperature falls out of that range, the referencestandard is brought to within 25°F (14°C), and a calibrationcheck should be performed. For high temperature work, specialhigh temperature transducers and couplants are usuallynecessary. Consideration should be given to the fact that temperaturevariations within the wedge or delay line can causebeam angle changes and/or alter the delay on the time base.

OpenBookOpenBookOpenBookOpenBook

Page 25: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Cathodic Protection of AbovegroundPetroleum Storage TanksAPI RECOMMENDED PRACTICE 651FOURTH EDITION, SEPTEMBER 2014

Page 26: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

4 Corrosion of Aboveground Steel Storage Tanks4.1.4 Physical and chemical properties of the electrolyte also influence the location of cathodic and anodic areas on the metal surface. For example, differing oxygen concentrations between areas on a steel surface may generate differences in potential. Areas with lower oxygen concentrations become anodic and areas with higher oxygen concentrations become cathodic. This phenomenon can cause corrosion of steel tank bottoms on a homogeneous sand pad, and/or when contaminated with clay or other debris or natural soil that does not have a uniform consistency (see Figure 2).

Rock

OpenBook

Page 27: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Linings of Aboveground PetroleumStorage Tank BottomsAPI RECOMMENDED PRACTICE 652FOURTH EDITION, SEPTEMBER 2014

Page 28: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

9.3.4 Lining DiscontinuitiesHoliday testing of thick-film linings shall be carried out with a high-voltage detector in accordance with NACE RP0188. Holiday testing of thin-film liningsshould be performed with a low-voltage (67.5 volts) wet sponge detector.When testing with high voltage detectors, it is important that the voltage beproperly set in accordance with the manufacturers recommended volts per miland that the film thickness properly matches the specified thickness.Otherwise, damage may occur from the testing operation. Also, nothing in thisdocument shall preclude the testing of a thin-film lining using a high voltagedetector, if there are temperature considerations, provided that the voltage beproperly set to correspond with the film thickness.

OpenBook

Page 29: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

9.3.4 Lining DiscontinuitiesHoliday testing of thick-film linings shall be carried out with a high-voltage detector in accordance with NACE RP0188. Holiday testing of thin-film liningsshould be performed with a low-voltage (67.5 volts) wet sponge detector.When testing with high voltage detectors, it is important that the voltage beproperly set in accordance with the manufacturers recommended volts per miland that the film thickness properly matches the specified thickness.Otherwise, damage may occur from the testing operation. Also, nothing in thisdocument shall preclude the testing of a thin-film lining using a high voltagedetector, if there are temperature considerations, provided that the voltage beproperly set to correspond with the film thickness.

OpenBook

Page 30: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

7.5 Surface Profile or Anchor PatternThe abrasive used for blasting should be selected to produce the necessary profile depth, or anchor pattern, for the lining to be applied. The liningmanufacturer’s recommendation for surface profile depth must be achieved inorder to optimize the mechanical adhesion of the lining to the steel tankbottom. The anchor pattern required for linings is typically 1.5 mils to 4.0 mils(38 microns to 102 microns) and generally increases with the thickness of thelining. To achieve adhesion necessary for long-term performance, it isimportant that the anchor pattern is sharp and angular. It may be difficultwhen using recycled media on tank linings to ensure a uniform proper profiledepth, as well as a proper degree of sharpness and angularity. Ownersshould weigh the benefits of recycled media against the risk of not havingadequate surface profile that may be required for internal linings.

Page 31: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

8.3 Temperature and Humidity ControlThe temperature of the steel surface should conform to the lining manufacturer’s recommended application and curing ranges. As a generalrule, the surface temperature must be at least 5 °F (3 °C) above the dew pointtemperature in the tank and the relative humidity should be below 80 % at thesteel surface. If the surface temperatures and/or humidity level expected todeviate from the recommended range, climate control equipment should beemployed to ensure the proper conditions are maintained. It should be notedthat durations of surface preparation, lining application, and cure may becontinuous over a 24-hour period. If so, the required environmental conditionsmust be maintained around the clock. Owner operations may interfere withcontinuous use of environmental control equipment. These operationalconsiderations should be reviewed prior to the execution of the tank liningproject.

OpenBook

Page 32: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

7 Surface PreparationGenerally, abrasive blast cleaning to a white metal finish (NACE No. 1/SSPC-SP5) is desired. Abrasive blast cleaning to a near-white metal finish (NACE No. 2/SSPC-SP10) is often specified as the minimum degree of surface cleanliness.

Page 33: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Tank Inspection, Repair, Alteration,and ReconstructionAPI STANDARD 653FIFTH EDITION, NOVEMBER 2014

Page 34: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

1.3 JurisdictionIf any provision of this standard presents a direct or implied conflict with any statutory regulation, the regulation shall govern. However, if the requirements of this standard are more stringent than the requirements of the regulation, then the requirements of this standard shall govern.

1.4 Safe Working PracticesAn assessment shall be made of the potential hazards to which personnel may be exposed when conducting internal tank inspections, making repairs, or dismantling tanks. Procedures shall be developed according to the guidelines given in API 2015 and API 2217A that will include safeguard for personnel health and safety, prevention of accidental fires and explosions, and the prevention of property damage. Conformance to permit procedures is an essential safe work practice for protection of personnel and property.Where welding and hot work are involved, API 2009 states “Except in areas specifically designated as safe for hot work, a hot work permit shall be obtained before starting any work that can involve a source of ignition.”See also API Recommended Practice 2016.

Page 35: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

ClosedBook

3.20major alteration/or major repairAn alteration or repair that includes any of the following:a) installing a shell penetration larger than NPS 12 beneath the design liquid

level;b) installing a bottom penetration within 12 in. of the shell;c) removing and replacing or adding a shell plate beneath the………

4.2.4.3 Operation at Elevated TemperatureAll requirements of API 650, Annex M, shall be considered before changing

the service of a tank to operation at temperatures above 200 °F.

4.2.4.4 Operation at Lower Temperature Than Original DesignIf the operating temperature is changed to a lower temperature than the

original design, the requirements of the current applicable standard for the lower temperature shall be met.

Page 36: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

b) Calculate the critical length, L:L =3.7√(Dt2) , but not more than 40 in.

e) The criteria for continued operation is as follows:i) the value t1 shall be greater than or equal to tmin (see 4.3.3 or 4.3.4),

subject to verification of all other loadings listed in 4.3.3.5;ii) the value t2 shall be greater than or equal to 60 % of tmin; andiii) any corrosion allowance required for service until the time of the next

inspection shall be added to tmin and 60 % of tmin.

4.3.2.2 Widely scattered pits may be ignored provided that:a) no pit depth results in the remaining shell thickness being less than one-

half the minimum acceptable tank shell thickness exclusive of the corrosion allowance; and

b) the sum of their dimensions along any vertical line does not exceed 2 in. in an 8-in. length (see Figure 4.2).

Page 37: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Both Equations

Shell Based

Specific locality

OpenBook

Page 38: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

4.4.3 Tank Bottom Release Prevention Systems (RPSs)API supports the use of a release prevention system (RPS) to maintain the integrity of tank bottoms. The term RPS refers to the suite of API standardsand recommended practices that are designed to maintain tank integrity andthus protect the environment. With respect to tank bottoms, these include:internal inspection of the tank bottom; Leak detection systems and leaktesting of the tank; installing cathodic protection for the underside of the tankbottom; lining the bottom of the tank interior; providing a release preventionbarrier (RPB) under the tank bottom; or some combination of these measures,depending on the operating environment and service of the tank.

Page 39: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

4.4.5 Minimum Thickness for Tank Bottom PlateQuantifying the minimum remaining thickness of tank bottoms based on the results of measurement can be done by the method outlined in 4.4.5.1. Other approaches such as the probabilistic method in 4.4.5.2 may be used.4.4.5.1 An acceptable method for calculating the minimum acceptable bottom thickness for the entire bottom or portions thereof is as follows:

MRT = (Minimum of RTbc or RTip) – Or (StPr + UPr)

Given required MRT, calculate Or

Page 40: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

4.4.6 Minimum Thickness for Annular Plate Ring

OpenBookOpenBook

Page 41: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

4.5 Tank Foundation Evaluation4.5.1 General4.5.1.1 The principal causes of foundation deterioration are settlement,erosion, cracking, and deterioration of concrete initiated by: calcining, attack by underground water, attack by frost, and attack by alkalies and acids. Toensure suitability for service, all tank foundations shall be inspected periodically (see 6.3).4.5.1.2 Some mechanisms of concrete deterioration are briefly described below.a) Calcining (loss of water of hydration) can occur when concrete has been exposed to sufficiently high temperature for a period of time. During intermediate cooling periods, the concrete can absorb moisture, swell, lose its strength, and crack.

Page 42: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

5.3.5 Step 4—If a tank shell thickness is no greater than 0.5 in., the risk of failure due to brittle fracture is minimal, provided that an evaluation for suitability of service in accordance with Section 4 has been performed. The original nominal thickness for the thickest tank shell plate shall be used for this assessment.5.3.6 Step 5—No known tank failures due to brittle fracture have occurred at shell metal temperatures of 60°F or above. Similar assurance against brittle fracture can be gained by increasing the metal temperature by heating thetank contents.

Page 43: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

6.3.2 External Inspection6.3.2.1 All tanks shall be given a visual external inspection by an authorized inspector. This inspection shall be called the external inspection and must be conducted at least every five years or RCA/4N years (where RCA is thedifference between the measured shell thickness and the minimum required thickness in mils, and N is the shell corrosion rate in mils per year) whichever is less. Tanks may be in operation during this inspection.

6.3.3 Ultrasonic Thickness Inspectionb) When the corrosion rate is known, the maximum interval shall be the smaller of RCA/2N years (where RCA is the difference between the measured shell thickness and the minimum required thickness in mils, and N is the shell corrosion rate in mils per year) or 15 years.

Page 44: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

6.4.2.1 Initial Internal Inspection IntervalThe initial internal inspection intervals for newly constructed tanks and/or refurbished tanks shall be established either per 6.4.2.1.1 or 6.4.2.1.2.6.4.2.1.1 The interval from initial service date until the first internal inspection shall not exceed 10 years unless a tank has one or more of the leak prevention, detection, corrosion mitigation, or containment safeguards listed in Table 6.1. The initial internal inspection date shall be based on incremental credits for the additional safeguards in Table 6.1 which are cumulative.

6.8.1 GeneralInspection records form the basis of a scheduled inspection/maintenance program. (It is recognized that records may not exist for older tanks, and judgments must be based on experience with tanks in similar services.) The owner/ operator shall maintain a complete record file consisting of three types of records, namely: construction records, inspection history, and repair/alteration history.

Page 45: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

7.3.1.2 Each individual plate for which adequate identification does not exist shall be subjected to chemical analysis and mechanical tests as required inASTM A6 and ASTM A370 including Charpy V-notch.

Page 46: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Section 9—Tank Repair and Alteration9.1 General9.1.1 The basis for repairs and alterations shall be an API 650 equivalence.

9.2.1 Minimum Thickness of Replacement Shell PlateThe minimum thickness of the replacement shell plate material shall be calculated in accordance with the as-built standard. The thickness of the replacement shell plate shall not be less than the greatest nominal thickness of any plate in the same course adjoining the replacement plate except where the adjoining plate is a thickened insert plate. Any changes from the original design conditions, such as specific gravity, design pressure, liquid level, andshell height, shall be considered.

9.2.2 Minimum Dimensions of Replacement Shell Plate9.2.2.1 The minimum dimension for a replacement shell plate is 12 in. or 12 times the thickness of the replacement plate, whichever is greater.

Page 47: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

9.3 Shell Repairs Using Lap-welded Patch Plates9.3.1.2 Lapped patch shell repairs shall not be used on any shell course thickness (original construction) that exceeds 1/2 in., nor to replace doorsheets or shell plates.

9.3.1.3 Except as permitted in 9.3.3.2 and 9.3.4.3, the repair plate material shall be the smaller of 1/2 in. or the thickness of the shell plate adjacent to the repairs, but not less than 3/16 in.

9.3.1.7 The maximum vertical and horizontal dimension of the repair plate is 48 in. and 72 in., respectively. The minimum repair plate dimension is 4 in.The repair plate shall be formed to the shell radius.

Page 48: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

9.8 Addition or Replacement of Shell PenetrationsFigure 9.7—Typical Details for Addition of Reinforcing Plate to Existing Shell Penetration

OpenBookOpenBook

Page 49: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

OpenBookOpenBook

Page 50: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Figure 9.10—Details for Installing a New Bottom Through an Existing Tombstone Reinforcing Plate

OpenBookOpenBook

Page 51: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

9.10 Repair of Tank Bottoms9.10.1 Repairing a Portion of Tank Bottoms9.10.1.1 General Repair Requirements

b) A welded-on patch plate smaller than 12 in. in diameter is permitted if: it is equal to or exceeds 6 in. in diameter; it does not overlap a bottom seam; it is not placed fully or partially over an existing patch; and it extends beyond thecorroded bottom area, if any, by at least 2 in.

9.11.2 Supported Cone Roofs9.11.2.1 The minimum thickness of new roof plates shall be 3/16 in. plus any corrosion allowance as specified in the repair specifications. In the event roof live loads in excess of 25 lbf/ft2 are specified (such as insulation, operatingvacuum, high snow loads), the plate thickness shall be based on analysis using the allowable stresses in conformance with API 650, Section 5.10.3 (see 9.11.2.2).

OpenBookOpenBook

Page 52: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Table 9.1—Hot Tap Connection Sizes and Shell Plate Thicknesses

OpenBookOpenBook

Page 53: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

10.4 Reconstruction10.4.2.3 No welding of any kind shall be performed when the surfaces of the parts to be welded are wet from rain, snow, or ice; when rain or snow is falling on such surfaces; or during periods of high winds unless the welder and the work are properly shielded. No welding of any kind shall be performed when the temperature of the base metal is less than 0 °F. When the temperature of the base metal is between 0 °F and 32 °F or the thickness is in excess of 1 in., the base metal within 3 in. of the place where welding is to be started shall be heated to a temperature warm to the hand (approximately 140 °F) before welding. (See 10.4.4.3 for preheat requirements for shell plates over 1 1/2-in. thick.)

Page 54: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Table 10.1—Maximum Thicknesses on New Welds

OpenBookOpenBook

Page 55: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

10.4.4 Shells10.4.4.1 Plates to be joined by butt welding shall be matched accurately and retained in position during welding. Misalignment in completed vertical joints over 5/8-in. thick shall not exceed 10 % of the plate thickness, with amaximum of 1/8 in. Misalignment in joints 5/8-in. thick or less shall not exceed 1/16 in. Vertical joints shall be completed before the lower horizontal weld is made.

10.4.4.2 In completed horizontal butt joints, the upper plate shall not project beyond the face of the lower plate at any point by more than 20 % of the thickness of the upper plate, with a maximum projection of 1/8 in., except that a projection of 1/16 in. is acceptable for upper plates less than 5/16-in. thick.

10.4.4.3 For horizontal and vertical joints in tank shell courses constructed of material over 1 1/2-in. thick (based on the thickness of the thicker plate at the joint), multi-pass weld procedures are required, with no pass more than 3/4-in. thick permitted. A minimum preheat of 200 °F is required of these welds.Open

BookOpenBook

Page 56: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

10.5 Dimensional Tolerances

OpenBookOpenBook

Page 57: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

10.5.4 PeakingWith a horizontal sweep board 36-in. long, peaking shall not exceed 1/2 in.The sweep board shall be made to the true outside radius of the tank.

10.5.5 BandingWith a vertical sweep board 36-in. long, banding shall not exceed 1 in.

Page 58: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

10.5.6 Foundations10.5.6.2 Where foundations true to a horizontal plane are specified,

tolerances shall be as follows:a) where concrete ringwalls are provided under the shell, the top of the

ringwall shall be level within ±1/8 inches in any 30 ft of the circumference and within ±1/4 inches in the total circumference measured from the average elevation;

b) where concrete ringwalls are not provided, the foundation under the shell shall be level within ±1/8 in. in any 10 ft of circumference and within ±1/2 in. in the total circumference measured from the average elevation.

OpenBookOpenBook

Page 59: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Section 11—WeldingWelding with inert gas safety and danger from inert gas asphyxiation

Section 12—Examination and Testing12.1.6 Shell-to-bottom Weld12.1.6.1 New welding on the shell-to-bottom joint shall be examined for its entire length by using a right-angle vacuum box and a solution film, or by applying light diesel oil. Additionally, the first weld pass shall be examined by applying light diesel oil to the side opposite the first weld pass made. The oil shall be allowed to stand at least 4 hours (preferably overnight) and then the weld examined for wicking action. The oil shall be removed before the weld is completed.

Page 60: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

12.2 Radiographs12.2.1 Number and Location of RadiographsThe number and location of radiographs of the full penetration shell plate to

shell plate welds shall be in accordance with API 650, Section 8.1.2 and the following additional requirements:

12.2.1.1 For vertical joints:a) new replacement shell plates to new shell plates, no additional

radiographs required, other than those required by API 650, Section 8.1.2.2 and Figure 8-1 for new construction;

b) new replacement shell plates to existing shell plates, one additional radiograph shall be taken in each joint;

c) repaired joints in existing shell plates shall have one additional radiograph taken in each joint.

OpenBookOpenBook

Page 61: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

12.2.1.3 For intersections of vertical and horizontal joints:a) new replacement shell plates to new shell plates, no additional

radiographs required, other than those required by API 650, Section 8.1.2 and Figure 8-1 for new construction;

b) new replacement shell plates to existing shell plates, each intersection shall be radiographed;

c) all repaired intersections in existing shell plates shall be radiographed.

12.2.3 Marking and Identification of Radiographs12.2.3.1 Each film shall show an identification of the welder(s) making the weld. A weld map showing location of welds, weld number, radiograph number, welder identification, and grading of each weld is an acceptable alternative to this requirement.

Note: weld ID on actual workpiece- 3feet

12.2.3.2 Radiographs and radiograph records of all repaired welds shall be marked with the letter “R.”

OpenBookOpenBook

Page 62: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

12.3 Hydrostatic Testing12.3.1 When Hydrostatic Testing is RequiredA full hydrostatic test, held for 24 hours, shall be performed on the following.a) A reconstructed tank. (no exemption)

12.3.2.2 Review/Approval/Authorization RequirementsItems a) and b) below must be satisfied.a) The repair has been reviewed and approved by an engineer experienced

in storage tank design in accordance with API 650. The engineer must concur in writing with taking the hydrostatic testing exemption.

b) The tank owner/operator has authorized the exemption in writing.

Page 63: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

12.3.2.3.3 Existing tank materials in the repair area shall meet at least one of the following requirements.

a) API 650 requirements (Seventh Edition or later).b) Fall within the “safe for use” area on Figure 5.2.c) Stress in the repair area shall not exceed 7000 lbf/in.2. This limiting stress

shall be calculated as follows:

Given t, calculate H

OpenBookOpenBook

Page 64: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

12.5 Settlement Survey During Hydrostatic Testing

The minimum number of elevation points shall be as indicated by the following equation:N = D/10whereD is the tank diameter, in feet (ft).AndN is the minimum required number of settlement measurement points, but no less than eight. All values of N shall be rounded to the next higher even whole number. The maximum spacing between settlement measurement points shall be 32 ft.

Page 65: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Section 13—Marking and Recordkeeping13.1 Nameplates13.1.1.2 The new nameplate shall be attached to the tank shell adjacent to the existing nameplate, if any. An existing nameplate shall be left attached to the tank. Nameplates shall be attached as specified in API 650, Section10.1 and Figure 10-1.

Page 66: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Annex B(normative)Evaluation of Tank Bottom SettlementFigure B.2—Measurements of Bottom Settlement (Internal) Tank Out-of-service

OpenBookOpenBook

Page 67: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

B.3.3 Internal Bottom Settlements or BulgesMeasure the bulge or depression. The permissible bulge or depression is given by the following equation (see Note).BB = 0.37RwhereBB is maximum height of bulge or depth of local depression, in inches;R is radius of inscribed circle in bulged area or local depression, in feet.

OpenBookOpenBook

Page 68: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Figure B.11—Maximum Allowable Edge Settlement for Areas with Bottom Lap Welds Approximately Parallel to the Shell

OpenBookOpenBook

Page 69: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

D.5 RecertificationD.5.2 Actively engaged as an authorized inspector shall be defined as one of

the following provisions:a) a minimum of 20 % of the time spent performing inspection activities, or

supervision of inspection activities, or engineering support of inspection activities as described in API 653 over the most recent three-year certification period;

b) performance of inspection activities or supervision of inspection activities or engineering support of inspection activities on 75 aboveground storage tanks as described in API 653 over the most recent three-year certification period

NOTE Inspection activities common to other API inspection documents (NDE, record keeping, review of welding documents, etc.) may be considered here.

Page 70: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Annex F(normative)NDE Requirements SummaryDefinitions:MT = Magnetic ParticlePen Oil = Penetrating Oil TestingPT = Liquid Penetrant ExaminationRT = Radiographic ExaminationUT = Ultrasonic ExaminationVB = Vacuum Box TestingVE = Visual Examination

Page 71: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Acceptance Standards:Air Test: NonePen Oil: NoneMTPT: ASME Section VIII, Appendix 8 (paragraphs 8-3, 8-4, 8-5)RT: ASME Section VIII (paragraph UW-51(b))Tracer Gas: NoneUE: API Std. 650, Section 8.3.2.5VB: NoneVE: API Std 650, Section 8.5.1

Page 72: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Examiner Qualifications:Air Test: NonePen Oil: NoneMTPT: API Std 650, Section 8.2.3RT: ASNT SNT-TC-1A Level II or III. Level I personnel may be used under the supervision of Level II or Level III personnel with a written procedure in accordance with ASME Section V,Article 2.Tracer Gas: NoneUE: ASNT SNT-TC-1A Level II or III. Level I personnel may be used under the supervision of Level II or Level III personnel with a written procedure in accordance with ASME Section V,Article 2.VB: API Std 650, Section 8.6.4VE: API Std 650, Section 8.5.1

Page 73: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Annex G(informative)Qualification of Tank Bottom Examination Procedures and PersonnelG.5 Qualification TestingG.5.1 Qualification Test PlatesG.5.1.1 The qualification test will be performed on a sample tank bottom with designed flaws. The sample tank bottom should be a minimum of 70 ft2 toprovide space for the designed flaws. The plate material used to fabricate sample plates may be either new steel or used steel. It should be noted that the results obtained during qualification tests might not be indicative of the results of examinations performed on other plates of differing quality or permeability. When used steel is utilized for qualification purposes, the qualification test acceptance standards recommended in G.5.2 may not be appropriate. The owner/operator should establish its own acceptance standards in such cases.

Page 74: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Welded Tanks for Oil Storage API Standard 650 Twelfth Edition, March 2013 Addendum 1, September 2014 Errata 1, July 2013 Errata 2, December 2014

Page 75: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

SECTION 1—SCOPE 1.1 General 1.1.1 This standard establishes minimum requirements for material, design, fabrication, erection, and inspection for vertical, cylindrical, aboveground, closed- and open-top, welded storage tanks in various sizes and capacities for internal pressures approximating atmospheric pressure (internal pressures not exceeding the weight of the roof plates), but a higher internal pressure is permitted when additional requirements are met (see 1.1.13). This standard applies only to tanks whose entire bottom is uniformly supported and to tanks in non-refrigerated service that have a maximum design temperature of 93 °C (200 °F) or less (see 1.1.20).

Page 76: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

1.1.3 This standard has requirements given in two alternate systems of units. The Manufacturer shall comply with either:

1) all of the requirements given in this standard in SI units; or

2) all of the requirements given in this standard in US Customary units.

The selection of which set of requirements (SI or US Customary) to apply shall be a matter of mutual agreement between the Manufacturer and Purchaser and indicated on the Data Sheet, Page 1.

1.1.20 Annex M provides requirements for tanks with a maximum design temperature exceeding 93 °C (200 °F) but not exceeding 260 °C (500 °F).

Page 77: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

1.3 Responsibilities 1.3.1 The Manufacturer is responsible for complying with all provisions of this standard. Inspection by the Purchaser’s inspector does not negate the Manufacturer’s obligation to provide quality control and inspection necessary to ensure such compliance. The Manufacturer shall also communicate specified requirements to relevant subcontractors or suppliers working at the request of the Manufacturer.

Page 78: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Page 79: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Figure 4.1b—Minimum Permissible Design Metal Temperature for Materials Used in Tank Shells without Impact Testing (USC)

Page 80: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Figure 4.2—Isothermal Lines of Lowest One-Day Mean Temperatures (°F)

Page 81: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Figure 4.1b—Minimum Permissible Design Metal Temperature for Materials Used in Tank Shells without Impact Testing (USC)

Page 82: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

LA

Page 83: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

4.8 Welding Electrodes 4.8.1 For the welding of materials with a minimum tensile strength less than 550 MPa (80 ksi), the manual arc- welding electrodes shall conform to the E60 and E70 classification series (suitable for the electric current characteristics, the position of welding, and other conditions of intended use) in AWS A5.1 and shall conform to 7.2.1.10 as applicable.

4.8.2 For the welding of materials with a minimum tensile strength of 550 MPa to 585 MPa (80 ksi to 85 ksi), the manual arc-welding electrodes shall conform to the E80XX-CX classification series in AWS A5.5.

Page 84: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

SECTION 5—DESIGN5.1.1.2 double-welded butt joint A joint between two abutting parts lying in approximately the same plane that is welded from both sides.

5.2 Design Considerations 5.2.1 Loads Loads are defined as follows. a) Dead Load (DL): The weight of the tank or tank component, including any corrosion allowance unless otherwise noted. b)

Design External Pressure (Pe): Shall not be less than 0.25 kPa (1 in. of water) except that the Design External Pressure (Pe) shall be considered as 0 kPa (0 in. of water) for tanks with circulation vents meeting Annex H requirements. Refer to Annex V for design external pressure greater than 0.25 kPa (1 in. of water). Requirements for design external pressure exceeding this value and design requirements to resist flotation and external fluid pressure shall be a matter of agreement between the Purchaser and the Manufacturer (see Annex V). Tanks that meet the requirements of this standard may be subjected to a partial vacuum of 0.25 kPa (1 in. of water), without the need to provide any additional supporting calculations. c) Design Internal Pressure (Pi): Shall not exceed 18 kPa (2.5 lbf/in.2).

Page 85: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

5.4.5 If specified on the Data Sheet, Line 12, a foundation drip ring shall be provided to prevent ingress of water between the tank bottom and foundation. Unless the Purchaser specifies otherwise, the ring shall meet the following requirements (see Figure 5.5). 1) Material shall be carbon steel, 3 mm (1/8 in.) minimum thickness. 2) All radial joints between sections of the drip rings, as well as between the drip ring and the annular plate or bottom, shall be continuously seal-welded.3) The drip ring shall extend at least 75 mm (3 in.) beyond the outer periphery of the foundation ringwall and then turn down (up to 90°) at its outer diameter.

Page 86: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Page 87: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Table 5.2b—Permissible Plate Materials and Allowable Stresses (USC)

Page 88: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Page 89: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Table 5.6b—Dimensions for Shell Nozzles (USC)

Page 90: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

5.10.2.6 Frangible Roof: A roof is considered frangible (see 5.8.5 for emergency venting requirement) if the roof- to-shell joint will fail prior to the shell-to-bottom joint in the event of excessive internal pressure. When a Purchaser specifies a tank with a frangible roof, the tank design shall comply with a, b, c, or d, of the following:

a) For tanks 15 m (50 ft) in diameter or greater, the tank shall meet all of the following.

1) The slope of the roof at the top angle attachment does not exceed 2:12.2) The roof support members shall not be attached to the roof plate.

Page 91: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Page 92: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

7.3.7 Testing of the Roof 7.3.7.1 Upon completion, the roof of a tank designed to be gas-tight (except for roofs designed under 7.3.7.2, F.4.4, and E.7.5) shall be tested by one of the following methods.

a) Applying internal air pressure not exceeding the weight of the roof plates and applying to the weld joints a bubble solution or other material suitable for the detection of leaks.

b) Vacuum testing the weld joints in accordance with 8.6 to detect any leaks.

7.3.7.2 Upon completion, the roof of a tank not designed to be gas-tight, such as a tank with peripheral circulation vents or a tank with free or open vents, shall receive only visual examination of its weld joints, unless otherwise specified by the Purchaser.

Page 93: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

7.5.3 Roundness Radii measured at 0.3 m (1 ft) above the bottom corner weld shall not exceed the following tolerances:

Page 94: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

8.1.5 Radiographic Standards Welds examined by radiography shall be judged as acceptable or unacceptable by the standards of Paragraph UW-51(b) in Section VIII of the ASME Code.

8.1.6 Determination of Limits of Defective Welding When a section of weld is shown by a radiograph to be unacceptable under the provisions of 8.1.5 or the limits of the deficient welding are not defined by the radiograph, two spots adjacent to the section shall be examined by radiography; however, if the original radiograph shows at least 75 mm (3 in.) of acceptable weld between the defect and any one edge of the film, an additional radiograph need not be taken of the weld on that side of the defect. If the weld at either of the adjacent sections fails to comply with the requirements of 8.1.5, additional spots shall be examined until the limits of unacceptable welding are determined, or the erector may replace all of the welding performed by the welder or welding operator on that joint. If the welding is replaced, the inspector shall have the option of requiring that one radiograph be taken at any selected location on any other joint on which the same welder or welding operator has welded. If any of these additional spots fail to comply with the requirements of 8.1.5, the limits of unacceptable welding shall be determined as specified for the initial section.

Page 95: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

8.1.3.4 The finished surface of the weld reinforcement at the location of the radiograph shall either be flush with the plate or have a reasonably uniform crown not to exceed the following values:

Page 96: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

8.5 Visual Examinationd) The reinforcement of the welds on all butt joints on each side of the plate shall not exceed the following thicknesses:

Page 97: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

8.6 Vacuum Testing8.6.3 A partial vacuum of 21 kPa (3 lbf/in.2, 6 in. Hg) to 35 kPa (5 lbf/in.2, 10 in Hg) gauge shall be used for the test. If specified by the Purchaser, a second partial vacuum test of 56 kPa (8 lbf/in.2, 16 in. Hg) to 70 kPa (10 lbf/in.2, 20 in. Hg) shall be performed for the detection of very small leaks.

Page 98: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

SECTION 9—WELDING PROCEDURE AND WELDER QUALIFICATIONSQualification of Welding Procedures 9.2.1 General Requirements 9.2.1.1 The erection Manufacturer and the fabrication Manufacturer if other than the erection Manufacturer, shall prepare welding procedure specifications and shall perform tests documented by procedure qualification records to support the specifications, as required by Section IX of the ASME Code and any additional provisions of this standard. If the Manufacturer is part of an organization that has, to the Purchaser’s satisfaction, established effective operational control of the qualification of welding procedures and of welder performance for two or more companies of different names, then separate welding procedure qualifications are not required, provided all other requirements of 9.2, 9.3, and Section IX of the ASME Code are met. Welding procedures for ladder and platform assemblies, handrails, stairways, and other miscellaneous assemblies, but not their attachments to the tank, shall comply with either AWS D1.1, AWS D1.6, or Section IX of the ASME Code, including the use of standard WPSs.

Page 99: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

9.4 Identification of Welded Joints The welder or welding operator’s identification mark shall be hand- or machine-stamped adjacent to and at intervals not exceeding 1 m (3 ft) along the completed welds. In lieu of stamping, a record may be kept that identifies the welder or welding operator employed for each welded joint; these records shall be accessible to the inspector. Roof plate welds and flange-to-nozzle-neck welds do not require welder identification.

Page 100: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Page 101: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

■ ωσμ∙Ωπ∆∇ º≠δ≤>ηθφФρ|β≠Ɛ∠ ʋ λ α ρτ√ ≠≥ѵФε ≠≥ѵФdsssa→

Page 102: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang

Good Luck!

Page 103: Understanding api icp653 reading 22 post exam summary a

Charlie Chong/ Fion Zhang