RECRATIONAL BUSH HUT OVER POND

Page 2: umer bush design

INTRO

Page 3: umer bush design

To Propose A Bush Hut At A Suitable Site Which Can Be

Utilized For Out Door Briefing / Bruch / Recreational

Activity

AIM

Page 4: umer bush design

Suitable Designs for Bust Hut Planning Parameters

• Location • Layout of the Footbridge• Height of Deck• Material Req• Manpower Req

Time Frame Cost Effect Fishing Rod Prices

SEQ

Page 5: umer bush design

Suitable Hut Designs

Page 6: umer bush design

PLANNING PARAMETERS

Page 7: umer bush design

LOCATIONMiddle of Fish Pond Adv :• View of Fish Pond • Easy to Catch Fish • Loc Middle of Dabori

Camp

Disadv :• Far from Offices and

Accn• Time taking on walk• Less attractive natural

view

FISH POND

Page 8: umer bush design

LOCATIONOver Nullah Stream (Dabori Enterence)Adv :• Loc at Walking

Distance• Can Make Visiter Visit • Natural View• Pleasant Smell of Mint

Plants

Disadv :• Near to Entrance• Visible from

Outside Camp

Dabori Entrance

Page 9: umer bush design

LAYOUT OF THE FOOTBRIDGE

STEP 1

STEP 2

Page 10: umer bush design

HEIGHT OF DECK

Height of

Deck

Height of Deck = Approx 4 Ft

Bush Hut SpecHeight = 6.5 FtWidth = 6x6 Ft

Capacity = 6-8 Indls

Page 11: umer bush design

MATERIAL REQ

Item Avail CostWater Resist able Wood (Kiel)

Avail 1800 -/Rs

Nail & Glue Not Avail 2000 -/Rs

Bushes for Roof Avail -----

Lasani Sheet Not Avail 4600 -/Rs

Brown Paint Not Avail 900 -/ Rs

Page 12: umer bush design

MANPOWER REQ

Indl Avail CostEngr Effort(For Foot Bridge)

Avail ------------

1 x civil Carpenter Hire(If Req)

2000 -/Rs

Page 13: umer bush design

TIME FRAMEEstimated Time Frame is 2 x Weeks In Case Built over Water Stream

It will be Reduced to 5 Days If Built at Bank of Nullah

Page 14: umer bush design

COST EFFECT

Estimated Cost = 4700 -/RsWithout Lassani Sheet

Estimated Cost = 9300 -/Rs

Page 15: umer bush design

FISHING ROD

Page 16: umer bush design