Campus Station, situated as it is just beside the University of
Ottawa, is not surprisingly one of the busiest stops on Ottawa’s
Transitway, a 31-kilometre 4-lane road reserved exclusively for
buses. Buses are notoriously rough on pavements and Campus Station
has to deal with up to 2,400 buses coming and going each day. It is
a load that would test any pavement and after twelve years of
pounding, Campus Station was getting a failing grade. The buses had
worn deep ruts in the asphalt. City engineers resurfaced the
pavement but two years later the ruts were back again. In March
2000, the engineers decided to try another approach – ultra-thin
whitetopping.
Ultra-Thin WhitetoppingUsing concrete over asphalt is not a new
technique. The use of whitetopping, as it is known, has been
recorded as far back as 1918 although it was not until the 1970s
that it became a more popular rehabilitation technique in the US.
Simply spread over the existing asphalt pavements in relatively
thick layers, these conventional whitetoppings performed
surprisingly well and continued in service for up to twenty years
with little or no maintenance.
The idea of whitetopping clearly intrigued engineers who decided
that if a relatively simple technique such as this could work well,
a bit of refinement might make it work better. The first ultra-thin
whitetopping was laid in Kentucky in 1988.
There are two primary differences between conventional
whitetopping and ultra-thin whitetopping. First, joints are spaced
more tightly than normal and second, the concrete overlay is
deliberately bonded to the underlying asphalt to create a composite
pavement. Because the combination of bonding and joint spacing
lowers the stresses in the concrete, engineers can reduce the
thickness of the concrete overlay from the 175mm to 250mm typically
used for conventional whitetopping down to thickness of between
50mm to 100mm – hence the designation ‘ultra-thin’.
UTW is designed for low-speed traffic and areas with a lot of
stop-and-go traffic, such as street intersections, bus stops, or
tollbooths and given its success, agencies are starting to look at
UTW as an alternative to asphalt overlays.
About three hundred UTW projects were completed in the US
between 1988 and 1998.
Laying a UTW SurfaceUTW works because the concrete and asphalt
form a composite pavement. To get the structural integrity needed,
there must be at least 75mm to 100mm of residual asphalt and there
must be a good adhesion between the two layers. For a good bond
between the asphalt and the concrete, the asphalt must be milled to
roughen its surface and then thoroughly cleaned
ULTRA-THIN WHITETOPPING FOR ROAD REHABILITATION Measuring the
depth of the ruts
Cleaning the asphalt base before applying the UTW
Applying and smoothing the UTW
-
MIL
ESTO
NES
• V2
#2
• Jun
e 2
002
6
MILESTO
NES • V2 #
2 • June 2002
7
to open the “pores” of the pavement. It is extremely important
that the surface stays clean and dust free until paving starts.
Concrete mixes for UTW are relatively standard. A typical mix
design includes cement, coarse and fine aggregates, polypropylene
fibres, air entraining agent, and admixtures (water reducers and
plasticizers for a low water-cement ratio). Many UTW projects have
been paved with fast track mixes that have either a higher cement
content or use high early-strength cement (usually 20MPa in
24-hours).
UTW paving is straightforward using conventional slip-form and
fixed-form pavers. Proper curing, however, is critical to avoid
shrinkage cracking and debonding between the asphalt and pavement.
Curing compound should be applied at twice the normal rate.
The final step is to saw cut the joints using lightweight saws
as early as possible to control cracking. Joints are spaced at
about 10 times the thickness of the topping, typically between 0.6
and 1.5 metres. The saw depth should be approximately one-fourth to
one-third of the total depth of the overlay.
Capital ImprovementBy 1997, the condition of the pavement at
Campus Station in Ottawa had deteriorated so badly that it could no
longer be ignored. The constant stopping and starting of the buses
as they entered and left the station had worn deep ruts in the
pavement and in some places, the asphalt pavement had actually been
shoved up over the curb.
The first attempt at rehabilitation called for the pavement to
be milled and the surface replaced with 45mm of stone mastic
asphalt, a premium hot mix known for its strength and durability.
In two years, however, the pavement was as badly rutted as it had
been before. In March 2000, transportation engineers from the City
of Ottawa met with technical staff from the Cement Association of
Canada to discuss the possible use of UTW.
“The depth of the ruts on the asphalt pavement was as
much as 170mm in places, far deeper than the Stone Mastic
Asphalt surface course that had been laid a couple of years
earlier, but there was no rutting of the granular base,” says Rico
Fung, Structural Engineer with the Cement Association of Canada.
“Based on the volume and loads of the buses, we recommended 100mm
of UTW for the southbound lane. On the northbound lane, because of
the curb height and thickness of asphalt, we were restricted to
just 75mm of UTW.”
The pavement rehabilitation was scheduled to start on a Friday
night and finish on Monday morning during which time the station
would be closed and buses re-routed. A high early-strength concrete
with a compressive strength of 20MPa within 24-hours was specified
so that the station could be reopened as quickly as possible.
On June 9, 2000, the contractor started milling the asphalt
pavement and had finished the job within about two hours. What the
contractor was not prepared for, however, was the high degree of
cleanliness needed to ensure a bond between the asphalt pavement
and the concrete overlay. Eventually, a high-pressure power-washer
truck was brought in to complete the job.
By Saturday morning, the contractor was ready to start pouring
the concrete for the two 55 metre long, 3 metre wide bus lanes. A
stiff broom finish was applied, shallow grooves 18mm apart were cut
across the pavement to provide skid resistance and the surface was
sealed with two coats of white-pigmented curing compound.
Joint spacing is critical to ensure that stresses in the UTW are
relieved and that the concrete does not crack. For this project,
the joints were spaced at 10 times the depth of the UTW (0.75
metres for the northbound lane and 1 metre for the southbound
lane). Cuts were made using the “Soff-Cut” system. With Soff-Cut,
used primarily to minimize random cracking in concrete, control
joints can be cut within one to two hours after the finishing
process and are not as deep as traditional methods.
ULTRA-THIN WHITETOPPING FOR ROAD REHABILITATION
Three days from start to completion and the buses are rolling
once again!
continued on page 18
-
MIL
ESTO
NES
• V2
#2
• Jun
e 2
002
18
MILESTO
NES • V2 #
2 • June 2002
19
ULTRA-THIN WHITETOPPING FOR ROAD REHABILITATION continued from
page 6
By Monday morning, despite a number of heavy rain showers that
had delayed construction, the station was reopened for traffic.
The UTW at Campus Station has now seen almost two years of heavy
use. Steve Goodman (Pavement Engineer in the Infrastructure
Services Branch of the City of Ottawa) recently joined the city and
one of his first tasks was to inspect the station.
“This was my first exposure to UTW and I was quite impressed,”
he says. “When you have up to 600 buses an hour rushing up to a
station, applying the brakes and then taking off again, that is a
punishing load for any pavement.
“The southbound lane is holding up very well although the
northbound lane is showing some distress. That can probably be
explained by the difference in the pavement thickness. The
southbound lanes have 100mm of UTW applied over 100mm of asphalt.
The northbound lanes, restricted by curb height, have 75mm of UTW
over 75mm of asphalt. I am told that the design engineers were
hesitant to go with the thinner pavement but we wanted to give it a
try.”
There was also, Goodman noted, some cracking at the transition
between the asphalt pavement of the Transitway and the UTW at the
station due to the restrictions on edge thickening. Edge
thickening, normally done with UTW, had to be curtailed to maintain
a minimum thickness of 75mm of asphalt. All things considered,
however, the distress is relatively minor, Goodman says.
“Considering that at the busiest stations the asphalt pavement
was rutting within two years, the UTW pavement looks very clean.
And there’s no rutting. If the costs are in-line, it seems a good
solution.”
F o r f u r t h e r i n f o r m a t i o n o n t h e s e i s s u
e s c h e c k o u t t h e O G R A w e b s i t e a t w w w. o g r a
. o r g
Here are just some of the current “hot
topics” that are on OGRA’s agenda:
Electrical SafetyAs a result of deregulation, municipalities
must manage the risk to public safety associated with electrical
installations for street lighting and traffic signals. Since the
Electrical Safety Authority (ESA) is now the sole authority for
permitting and inspecting new installations and maintenance,
municipalities need to be familiar with ESA’s requirements and the
fiscal impact that these requirements will have in 2003. OGRA will
be asking the Ministry of Environment and Energy to consider more
cost-effective ways to deliver these services. For more
information, visit the ESA website at www.esainspection.net.
Smart GrowthThe Central Ontario Smart Growth Panel’s Subpanel on
Gridlock will be submitting preliminary recommendations to the
Minister of Municipal Affairs and Housing by the end of June. For
more information, visit the MMAH website at www.mah.gov.on.ca.
Infrastructure FundingMTO held a series of consultation
workshops to identify Smart Growth transportation issues in January
and February. Once OGRA has received the summary report of the
workshops, it will request a meeting with the new Minister of
Transportation, Hon. Norm Sterling, to discuss OGRA’s position on
municipal infrastructure funding.
Performance Measurement DataThe Ontario Municipal Roads 2001
Questionnaire gathers condition information about municipal roads
and cost to deliver service data that is used by Ontario Municipal
CAO’s Benchmarking Initiative and is compatible with MMAH’s MPMP
program. The questionnaire is now in circulation to all
municipalities and is available on the OGRA website at
www.ogra.org.
ON YOUR BEHALF