-
Lessons Learned During Startup, Testing and Optimization of MBR
Systems for Enhanced Nutrient Removal Vince Maillard1*, Kristi
Perri1, Jason VerNooy1 1GHD, Bowie, Maryland. * Email:
[email protected]. ABSTRACT Membrane bioreactors (MBRs) are
known for producing high quality effluent from wastewater treatment
facilities in order to meet stringent regulatory requirements
(Fleischer et al., 2005), accommodate growth (Vadiveloo &
Cisterna, 2008), provide opportunities for water reuse (Schmidt et
al., 2011), and achieve other operational goals for various
municipalities, utilities and industries (Cummings & Frenkel,
2008). The process of testing, starting up and optimizing an MBR
process for enhanced nutrient removal at the end of a construction
project is often overlooked. Even a well-designed MBR can fail to
meet expectations if the system is not properly configured during
the startup phase, making this a critical step in any successful
implementation of membrane technology. The startup phase of two
municipal MBR plants were compared to demonstrate the importance of
various strategies for initial process optimization, with a focus
on lessons learned, techniques and performance expectations that
can be applied to future projects. KEYWORDS: MBR, nutrient removal,
startup, testing, optimization. INTRODUCTION Membrane bioreactors
(MBRs), which consist of an activated sludge process and a membrane
filtration system (MFS), offer several benefits which have led to
their widespread application in the treatment of municipal and
industrial wastewater (Cummings & Frenkel, 2008). MBR
technology allows for greater flexibility in both design and
operation, as they are compatible with a broad range of process
configurations, physical layouts, influent characteristics,
operating conditions and control strategies (Pellegrin et al.,
2012). MBRs are also ideal for expansion to accommodate growth or
meet increasingly stringent effluent requirements within a
relatively small footprint (Ferraris et al., 2009). Perhaps one of
the most significant advantages of MBR technology is its ability to
consistently produce high quality effluent, including effluent
total nitrogen (TN) concentrations of 3 mg/L and total phosphorus
(TP) concentrations of 0.3 mg/L, with the possibility of even lower
concentrations following process optimization (Fleischer et al.,
2005). The selection of MBR technology is often based on the
benefits associated with the production of such high quality
effluent, such as more efficient utilization of available discharge
limits, a reduction in the facilitys environmental impact and the
potential to implement water reuse.
mailto:[email protected]
-
However, selection and design are only the first steps towards
capitalizing on these benefits. In order to take full advantage of
the advanced treatment capabilities and maximize the value of the
MBR system, it is also critical for each component to be properly
installed and operated to avoid costly inefficiencies,
underperformance or even process failures (Ellsworth & Riddell,
2007). The successful startup and optimization of any new
biological treatment process can be jeopardized by a wide range of
potential setbacks, including schedule delays, equipment
deficiencies, inadequate feedback or data collection, and lack of
coordination between the parties involved. Standard contract
specifications and other construction phase documents, such as
inspection checklists and report forms, have been established over
time to help manage these general types of issues. Yet these
standard resources are often developed based on conventional
wastewater facilities and may not adequately address the unique
challenges associated with implementing MBR technology,
including:
The large number of interconnected components operating as a
single system; Reliance on complex automatic controls and
interlocks with risk of costly failures; Use of proprietary
terminology, configurations, operational schemes, testing
protocols,
etc., by different system suppliers; and A relatively wide range
of potential operating conditions, control strategies and
performance targets.
As such, an additional degree of planning and execution is
required to bring MBR systems from installation to successful
operation. A project-specific startup plan is essential for meeting
the goals set for each individual installation, which can vary
considerably based on the details of the application and the
reasons for selecting MBR technology. The best approach to startup
and optimization will depend on several factors, including the
features of the proposed MBR system, recommendations of the MFS
supplier, time or budget constraints and owner preferences. In
order to document the impact of different strategies for bringing
an MBR plant online, two municipal MBR wastewater treatment plants
located in Virginia (United States) were studied during startup,
performance testing and initial operation. Results and lessons
learned from both case studies are documented herein. The first
plant (Plant A) is a new 0.95 ML/d (0.25 mgd) facility owned and
operated by a small, seasonal town of about 1,000 permanent
residents on the Eastern Shore of Virginia. Plant A was built on a
greenfield site to replace the Towns existing plant, which
consisted of aging contact stabilization units. The new plant
includes headworks, four-stage Bardenpho reactors, MFS, ultraviolet
(UV) disinfection, and provisions for water reuse. The second plant
(Plant B) is a 2.65 ML/d (0.70 mgd) facility owned and operated by
a town of about 4,000 residents in Northern Virginia. The MFS at
Plant B was added as part of a major upgrade project on the same
site as the existing lagoon treatment plant. The upgrade project
also added new headworks, 2.65 ML (0.7 mgd) of flow equalization,
four-stage Bardenpho reactors, and UV disinfection. Both plants
were designed to meet enhanced nutrient removal (ENR) level
effluent concentrations of 4.0 mg/L TN and 0.3 mg/L TP. A summary
of each plant is shown in Table 1.
-
Table 1. Plant design criteria. Parameter Plant A Plant B
Current Average Flow 0.4 ML/d (0.1 mgd) 1.1 ML/d (0.3 mgd) Design
Average Daily Flow 0.95 ML/d (0.25 mgd) 2.65 ML/d (0.70 mgd) Design
Peak Flow 2.84 ML/d (0.75 mgd) 7.95 ML/d (2.10 mgd)
with flow equalization Peaking Factor for MBR 3:1 3:1 Design
Average Influent Concentrations
BOD TSS
TKN TP
206 mg/L 226 mg/L 39.7 mg/L 6.1 mg/L
290 mg/L 270 mg/L 45 mg/L 6.5 mg/L
Flow Equalization No 2.65 ML (0.7 mil gal) Influent Pumping
Operation Constant Speed Variable Speed Biological HRT 14 hours 24
hours Type of Membranes Hollow Fiber Hollow Fiber No. of Membrane
Trains 2 4
METHODOLOGY The contract specifications for both plants required
an extensive testing sequence as shown in Figure 1. Each step in
the testing sequence had its own milestones or goals which must be
completed before the next step could begin. Many of the steps also
had minimum durations that would be extended in the event that the
performance goals were not met.
-
Figure 1. Specified testing sequence for MBR system startup. The
testing procedures were organized to balance the need to be
thorough and verify the functionality of the installed system with
the need to be concise and minimize unnecessary delays to the
construction schedule. The MFS suppliers own testing procedures
were considerable, so extra coordination was necessary to integrate
these testing activities into the startup plan for each facility.
The MFS suppliers standard testing routine was supplemented by the
engineers specified testing requirements, which were adjusted
during design to account for the unique features of the MBR system.
Initial Planning and Coordination The first step in the startup
process began while the new equipment was still being installed at
each plant. The engineer and contractor worked together to create
template documents that would be used during the various stages of
testing, including inspection checklists, report forms and summary
tables listing the applicable milestones for each step in the
testing sequence. These documents were based on the contract
specifications for the project and provided a consistent means of
tracking progress and communicating results to the project team.
On-site meetings, phone calls and other correspondence were also
utilized to help plan the startup process and keep key parties
informed.
-
During this same time, a comprehensive startup plan was
developed for each facility with input from the owner, engineer,
contractors, suppliers, and all other parties that would be
involved in the startup process. The startup plan was used as a
detailed guide that would supplement the contract specifications
and the contractors construction schedule, providing additional
information and recommendations such as:
Roles and responsibilities for each party during the startup
period; Review of sequencing constraints; Evaluation of the
proposed timing for key events, including activities not
specifically
covered by the contractors schedule (delivery of chemicals,
transfer of activated sludge inoculum, coordination with regulatory
agencies, etc.);
Details of flow transfer and splitting (including closed loop
clean water testing and the introduction of raw wastewater);
Plans for seeding the MBR (source, transfer, handling, target
solids concentration, required volume, etc.);
Milestones or other trigger events to help focus efforts and
determine sequencing; Summary of any available data applicable to
the startup process (including recent flow
rates and influent characteristics); Sampling and monitoring
protocols for each stage of testing and optimization; and Other
applicable input or feedback from parties involved.
The startup plan served as a single, consolidated resource for
collecting relevant information and using it to determine a
practical approach to the startup process, resulting in better
coordination during the critical steps of the startup process.
Preliminary Equipment Checks As equipment at each facility was
installed, the contractor was responsible for verifying that each
component was properly set and capable of operating. Preliminary
tests were conducted, including point-to-point electrical testing,
infrared testing, and vibration testing, and operator training
began on the new equipment. The preliminary equipment checks also
served as a final opportunity to confirm that the new facilities
were ready to proceed to online testing and operation, which meant
collecting all product information, warranty documents, tools, test
materials and lubrication equipment on site. MFS Clean Water
Testing Separate clean water testing was required for the MFS at
each plant as a prerequisite to clean water testing for the rest of
the new facilities, as multiple components of the MFS must be
operating successfully under automatic control in order to
hydraulically pass flow through the treatment facility. The MFS
supplier for both plants preferred the use of potable water for
clean water testing to protect the membranes, and stressed the
importance of thoroughly cleaning the process tanks before filling
them with water. The MFS supplier also requested that all work in
the area of the MBR tanks be completed before the membrane
filtration equipment was installed for protection of the
membranes.
-
Once the process tanks were cleaned and filled the membrane
filtration equipment was installed and clean water testing began.
For Plant A, the clean water testing loop started in the membrane
tanks, where the potable water was drawn through the membrane
fibers by the permeate pumps. The permeate pumps discharged the
clean water into the backpulse (BP) water storage tank for the MFS,
which overflowed to the downstream UV disinfection structure and
adjacent plant water well. The permanently installed plant water
pumps were then used to pump the clean water back into the membrane
tanks, as shown in Figure 2. A separate loop was established with
the mixed liquor suspended solids (MLSS) recirculation pumps, which
discharged at the distribution box upstream of the biological
reactors and flowed by gravity back into the membrane tanks.
Figure 2. MFS clean water testing loop for Plant A. For Plant B,
the clean water testing loop for the MFS initially consisted of the
MLSS recirculation pumps transferring potable water from the
membrane tanks to the biological reactor tanks, which flowed by
gravity downstream to the membrane tanks. Once the permeate pumps
were placed online, the potable water from the membrane tanks was
drawn through the membrane fibers and discharged into the backpulse
water storage tank, which was able to flow by gravity back to the
raw sewage pump station (RSPS) at the head of the plant. The clean
water loop was then expanded to flow through most of the new
facilities, as shown in Figure 3.
Figure 3. MFS clean water testing loop for Plant B. The contract
specifications for both facilities required a minimum of one week
of successful clean water testing with the MFS prior to plant-wide
clean water testing, which would be extended as necessary if the
system failed to meet the specified performance requirements. The
MFS suppliers own standard clean water testing routine required two
weeks for system configuration and testing, which coincided with
the engineers specified testing period. During the clean water
testing phase the installed equipment ran under automatic control
and was inspected to verify proper function in each available
operational mode. In particular, preliminary clean water testing of
the MBR system was utilized to check the automatic programming
developed for each facility, including data transfer and recording,
alarms, interlocks, alternate control modes and operator interface.
Any discrepancies observed during the clean water testing period
were tracked with project-specific checklists until they could be
suitably resolved.
-
Plant-wide Clean Water Testing After the successful completion
of clean water testing for the MFS, the rest of the new facilities
at each plant went through a similar clean water testing routine.
The control systems for each equipment package (including the MFS)
were integrated with the process control system (PCS) for the
entire plant to allow for the specified remote monitoring and
control functions. Any outstanding issues identified during the
clean water testing phase were recorded and tracked until they were
adequately addressed, at which time the plant was considered ready
for wastewater operation. MBR Seeding and Introduction of
Wastewater The potable water used for clean water testing was
drained out of the process tanks to allow for the addition of
activated sludge inoculum to the MBR system at each plant. The
activated sludge inoculum was obtained from a nearby operating MBR
facility in both cases, as previous studies with ultrafiltration
membrane systems have shown that seeding from an existing facility
can reduce membrane fouling during initial operation and help to
speed up the development of higher MLSS concentrations (Di Bella et
al., 2010). Seeding with activated sludge also helps the MBR system
to achieve the maximum design solids concentrations during the
specified testing period. Plant A initially seeded the new MBR with
activated sludge at about 7,000 mg/L MLSS concentration to obtain a
starting MLSS concentration goal of over 2,000 mg/L, and utilized
additional 120,000 L (32,000 gal) of seed sludge to accelerate
solids accumulation after the introduction of wastewater. The
activated sludge inoculum for Plant A was delivered using septic
hauling trucks, which introduced small amounts of mixed debris into
the sludge. The high solids concentration of the seed sludge caused
it to clog up the fine screens installed upstream of the MFS, so
the seed sludge had to be discharged directly into the biological
reactor tanks and the debris was manually screened out. Plant B
seeded the new MBR with activated sludge at about 3,000 mg/L MLSS
concentration for a starting MLSS concentration goal of about 900
mg/L, and did not utilize additional seed sludge following the
introduction of wastewater. As a result, MLSS concentrations were
significantly higher at Plant A throughout the startup period, as
shown in Figure 4.
-
Figure 4. Startup phase MLSS concentrations. Raw wastewater flow
from the collection system was diverted to each plant after initial
activated sludge addition. Based on the construction schedule for
the respective projects, the introduction of wastewater occurred in
January 2012 for Plant A and in September 2012 for Plant B. The
diversion of raw wastewater to the new MBR systems proceeded in
accordance with the startup plan developed specifically for each
facility. For Plant A, the startup plan recommended that the Towns
existing wastewater plant remain in operation until the new MBR
facility was consistently producing high quality effluent. This
allowed for a gradual increase in flow to the new MBR plant and a
prolonged flow split between the old and new treatment facilities.
The new MBR system at Plant A began receiving 100% of the Towns raw
wastewater flow two months after the initial startup date. The MBR
system at Plant B was constructed as part of an upgrade to the
Towns existing treatment plant, so all of the raw wastewater flow
was immediately diverted from the existing treatment process to the
new MBR facilities. Influent flow rates for each plant are shown in
Figure 5.
-
Figure 5. Startup phase influent flow rates. Final Performance
Testing and Optimization During the performance testing period,
operating conditions and effluent quality were closely monitored at
each facility to assist with process optimization. A combination of
on-site laboratory testing and off-site, third party laboratory
analysis were used to monitor concentrations of nutrients and
suspended solids in the raw influent, mixed liquor and plant
effluent. At both plants, online instrumentation was utilized to
continuously measure influent and effluent flow rates, as well as
dissolved oxygen (DO) and nitrate (NO3) concentrations in the
biological tanks. Instrumentation provided as part of the MFS for
each facility was used to monitor plant feed (raw influent) flows,
permeate (filtered effluent) flows, wastewater temperature,
effluent turbidity and trans-membrane pressure (TMP). Both Plants A
and B were designed to use Micro C-GTM for supplemental carbon and
aluminum sulphate (alum) as a metal coagulant. The startup plans
for both plants called for the chemical feed systems, supplemental
carbon and alum, to be started up sequentially to provide adequate
time to establish dosing rates for the first chemical before
starting addition of the second chemical. Full denitrification was
listed as an initial milestone in the startup plan for Plant A, so
the supplemental carbon feed system was brought online first.
Supplemental carbon addition began 22 days after the introduction
of wastewater at Plant A, followed by alum addition after 38
-
days of wastewater treatment. Plant B started with relatively
high (> 7 mg/L) effluent TP concentrations in the first month of
performance testing, so the alum feed system was started first
after 40 days of wastewater treatment and the supplemental carbon
feed system followed at 54 days of wastewater treatment. RESULTS
AND DISCUSSION Influent Characteristics The raw influent wastewater
characteristics during the startup phase of each plant are listed
in Table 2. The influent characteristics at Plant B remained
relatively consistent throughout the 90-day startup period.
Influent wastewater characteristics at Plant A showed significant
variation as a result of the Towns sewage collection system. Table
2. Startup phase average influent wastewater characteristics.
Parameter Plant A
Average (Min-Max) Plant B
Average (Min-Max) BOD 142 mg/L (64-223 mg/L) 362 mg/L (209-536
mg/L) TSS 91 mg/L (30-256 mg/L) 125 mg/L (32-448 mg/L) TKN 30 mg/L
(14-44 mg/L) 55 mg/L (47-59 mg/L) TP 3.7 mg/L (1.7-5.4 mg/L) 7.4
mg/L (1.7-5.4 mg/L) The collection system for Plant A consists of
two main raw wastewater pump stations: one serving a gravity sewer
system in the Towns historic district and the second connected to a
vacuum sewer system serving primarily new development. The influent
wastewater from the gravity sewer system was relatively dilute due
to generally older construction and higher inflow/infiltration
(I&I) rates in the collection system. In contrast, the vacuum
sewer system has relatively high strength wastewater coming from
the area of new development where there are more low-flow plumbing
fixtures and less I&I. Both pump stations cycled on and off
throughout the day, producing significant variation in the influent
wastewater characteristics. This was particularly noticeable during
the colder months of the year when Plant A began wastewater
treatment (before the seasonal residents arrived in Town). The
cyclic operation of the raw wastewater pumps also produced rapid
fluctuations in the influent flow rate, as shown in Figure 6. This
caused the MFS to frequently transition between production and
standby mode throughout the day.
-
Figure 6. Screen shot of the influent flow chart for Plant A
showing significant fluctuations over a two hour period during
routine plant operation. Flows are displayed in units of million
gallons per day (mgd) and range between 0 and 1 mgd. Nitrogen
Removal Full nitrification occurred rapidly at both MBR facilities
(within 7 days for Plant A and 14 days for Plant B), and as
expected the time required to achieve nitrification did not appear
to be significantly impacted by the volume of activated sludge
inoculum utilized (Di Bella et al., 2010). As shown in Figure 7,
Plant A was able to achieve partial denitrification until the
addition of supplemental carbon. Full denitrification was achieved
shortly after startup of the supplemental carbon feed system. Plant
B was able to achieve nearly complete denitrification without the
addition of supplemental carbon addition; however, as shown in
Figure 7, the startup of the supplemental carbon feed system
provided stable and complete denitrification.
-
Phosphorus Removal Plant A demonstrated significant phosphorus
removal due to biological treatment after startup of the
supplemental carbon system, as shown in Figure 7. Alum addition was
required to maintain effluent TP concentrations below 0.3 mg/L as
the plant flows and influent loads increased. Effluent TP
concentrations at Plant B decreased below the target concentration
of 0.3 mg/L after the addition of alum on day 40 of the performance
testing period.
Figure 7. Startup Phase Effluent Total Nitrogen (TN) and Total
Phosphorus (TP) Concentrations. Chemical Addition At Plant A, the
supplemental carbon system started up on day 24 of the performance
testing period, and the effluent TN concentrations quickly
decreased from approximately 25 mg/L on day 22 to less than 3 mg/L
by day 29. Supplemental carbon (Micro CGTM) was initially dosed in
manual control while the automatic control programming for the
plant was finalized. While under manual control, the supplemental
carbon was over-dosed at approximately 142 mg/L to ensure
consistent denitrification, resulting in an average effluent TN
concentration of 1.2 mg/L. After the automatic controls became
available the dosing rate was flow-paced using the influent flow
signal, allowing the feed rate to be adjusted to achieve the
desired effluent quality. After a temporary increase in effluent TN
concentration following the implementation of the automatic control
programming, the effluent TN concentration was again maintained
below 2 mg/L for the
-
remainder of the performance testing period with typical
supplemental carbon dosing rates of approximately 130 mg/L. At
Plant A, the initial alum dose was approximately 20 mg/L and was
increased to 40 mg/L by the end of the performance testing period.
During startup, Plant A tested for effluent TP using a 0.2 mg/L
detection limit; however, more recent laboratory testing with a
detection limit of 0.02 mg/L has shown that the MBR system is able
to consistently produce at or below 0.02 mg/L with an alum dosing
rate of approximately 30 mg/L. This effluent TP concentration is
approaching the current limit of technology (deBarbadillo et al.,
2010; Bott, 2009). The alum feed system for Plant B was started on
day 40 and resulted in a significant decrease in the effluent TP
concentration from 7.7 mg/L on day 27 to 0.2 mg/L on day 48. Plant
B continued to maintain alum feed rates for the remainder of the
startup period to achieve an effluent TP concentration of 0.3 mg/L
or less. Laboratory results for Plant B indicated TN concentrations
as low as 4.3 mg/L without supplemental carbon addition, likely as
a result of the favorable influent BOD/TKN ratio of about 6.6:1
(Fleischer et al., 2002). However, the supplemental carbon feed
system for Plant B was started in automatic control on day 54 of
the performance testing period to achieve the target effluent TN
concentration of less than 4 mg/L. MFS Performance Both plants
maintained average effluent turbidity levels below 0.1 NTU
throughout the startup period, as shown in Table 3. The average
pressure differential across the membranes (i.e. trans-membrane
pressure, or TMP) was minimal for Plant A and well below the
maximum allowable TMP of 55 kPa for Plant B. Permeability data was
also monitored for both plants as a relative indicator of membrane
fouling and system efficiency, with higher permeability values
generally representing decreased fouling and increased efficiency.
The permeability of the membranes, reported in units of litres per
square meter of membrane surface area per day per kPA of TMP
(Lm2d/kPa), was approximately 40% higher for Plant A during the
90-day performance testing period. The lower average permeability
value for Plant B may have been a result of the limited volume of
activated sludge inoculum used to seed the MBR system, as the
biomass in the MBR system typically forms a protective layer around
the surface of the membranes that can enhance filtering and reduce
certain types of fouling (Di Bella et al., 2010). Table 3. Startup
Phase MFS Performance Data.
Parameter Plant A
Average (Min-Max) Plant B
Average (Min-Max) Wastewater Temperature (oC) 15.5 (9.6 20.5)
12.4 (7.3 19.8)
Turbidity (NTU) 0.06 (0.04 0.80) 0.06 (0.00 0.76) Trans-Membrane
Pressure (kPa) 0.4 (-3.5 9.8) -2.0 (-7.2 2.1)
Permeability (Lm2d/kPa) 256 (5 296) 182 (6 295) System
performance was also maintained during extreme conditions,
including periods of low/sporadic flow caused by cyclic operation
of the raw wastewater pumps upstream for Plant A and high flow
events such as Hurricane Sandy at Plant B.
-
CONCLUSIONS There are many different ways to start up an MBR,
and each will yield different results, as evidenced herein. The
milestones, durations, and sequencing associated with each phase of
testing and optimization were especially important for the selected
case studies. In the case of Plant A, the Town expressed interest
in maximizing nutrient removal through the new MBR facility to take
advantage of available nutrient credits. In response to this
objective, a significant volume of activated sludge inoculum was
utilized for seeding to quickly increase the MLSS concentration in
the biological tanks and achieve the desired performance. The
chemical feed systems were also started up earlier to enhance
nutrient removal during the preliminary stages of plant operation.
As a result, Plant A achieved ENR-level effluent concentrations of
4.0 mg/L TN and 0.3 mg/L TP approximately 2-3 weeks earlier in the
startup process when compared to Plant B, likely as a result of the
increased seeding volume and earlier chemical feed (Manninaa &
Di Bella, 2012). The larger volume of sludge inoculum also appears
to have reduced fouling of the membranes at Plant A during the
first 90 days of operation. By maintaining conservative dosing
rates for supplemental carbon and alum Plant A has consistently
achieved effluent concentrations below 2.0 mg/L TN and 0.05 mg/L TP
following the completion of performance testing on the new MBR
facilities. Plant B took a different approach to startup of the new
MBR facilities, choosing instead to develop MLSS concentrations
gradually instead of relying on large volumes of activated sludge
inoculum. This ultimately reduced the cost of the startup process,
but delayed subsequent milestones related to chemical addition and
solids processing that were dependent on reaching target solids
concentrations in the MBR system. Plant B demonstrated the ability
to meet ENR-level effluent concentrations within the 90-day
performance testing period even with limited seeding. Plant B has
averaged effluent concentrations of approximately 2.6 mg/L TN and
0.2 mg/L TP since the completion of startup testing. The two case
studies demonstrated the importance of developing a
project-specific startup plan early in construction, which could
then be utilized as a valuable resource for coordinating between
multiple parties, guiding on-site personnel, identifying and
preparing for possible setbacks, and addressing variations in
startup conditions. The detailed, step-by-step organization of the
startup plan helped to identify what additional information was
required to prepare for the startup process, and also provided a
central location to document the information once it was collected.
Following the logical, sequential order of the startup plan raised
key questions, such as:
Do the characteristics of the raw influent wastewater match
previously collected data and design criteria?
How much influent flow is expected at the time of plant startup?
How much seed sludge is required? How will it be delivered into the
MBR system? How long will it take before wastewater reaches each
process tank? When is operator
action required? What initial set points should be used for
process control? What information is required to track performance
during initial operation?
-
When should chemical addition and sludge wasting begin? What are
the operational goals for the plant owner?
For the selected case studies, the answers to these questions
were not emphasized in the contract specifications or construction
schedule but proved to have a significant influence on the startup
process. In the case of Plant A, the actual influent concentrations
and raw wastewater flows at the time of plant startup were
considerably different from the values estimated during the
preliminary design phase of the project due to changes in growth
projections and seasonal variations in the local population. The
owners of each plant also had different preferences regarding the
use of activated sludge inoculum and the treatment objectives for
the plant, which resulted in different approaches to the startup of
each plant. Documenting these critical factors in the startup plan
helped to minimize miscommunication, delays and unexpected results.
In particular, details of the MBR seeding plan, from the source and
delivery method of the activated sludge inoculum to the amount
used, can have a major impact on plant startup in terms of process
performance, scheduling, and potential risks to installed
equipment. Depending on the source of the seed sludge and the
method of delivery, screening of the activated sludge inoculum
should be considered for protection of the MBR equipment. Utilizing
larger volumes of activated sludge inoculum can increase project
costs and possibly create logistical issues, but can also improve
treatment and accelerate the plant startup process based on the
results of the selected case studies. The condition of the sludge
(age, MLSS concentration, solids retention time of the seed plant,
etc.) should be checked for each batch to avoid process upsets
during initial operation. In order to function as an effective tool
for on-site personnel and other decision makers, the startup plan
should establish intermediate milestones or goals for each phase of
testing, startup and optimization. The minimum performance
requirements and durations for the various stages of testing should
be included in the contract specifications for the project, but the
startup plan should account for possible delays due to unfinished
work or equipment failures. Once wastewater is introduced to the
facility the milestones may be linked to certain events or
conditions, such as adding seed sludge until a target MLSS
concentration is reached, waiting to start chemical addition until
full nitrification is observed, adjusting chemical feed systems
after receiving a certain number of consistent laboratory results
or observing a specific change in effluent quality, or beginning to
waste sludge when the MLSS concentration in the MBR process reaches
a certain level. These goals and milestones helped to communicate
objectives, assess priorities, track progress and focus efforts
during startup. Extensive clean water testing is recommended for
future MBR installations. Thorough clean water testing procedures
can take multiple weeks to complete, but can potentially eliminate
costly delays or shutdowns during wastewater operation.
Point-by-point testing of the automatic controls for the MBR
process during clean water testing was especially valuable for the
selected case studies, and also served as a helpful training
exercise for plant operators. Issues related to the automatic
system controls at Plant A, including missing steps in the membrane
cleaning sequence and failure to automatically re-start the system
after a power outage, were successfully identified and corrected
before they resulted in critical failures by utilizing
project-specific checklists during clean water testing. Other
automatic control issues, such as missing logic for
-
the operation of RAS pumps under bypass conditions at Plant A
and excessive opening and closing of flow control gates at Plant B,
were not identified until after the introduction of wastewater,
which resulted in programming changes late in construction as well
as additional costs for repairing equipment. The clean water
testing protocols should cover the entire range of specified
operational modes, alarm conditions and control features, with a
focus on any project-specific modifications to the suppliers
standard design. Extensive laboratory testing and data collection
is important for accurately monitoring performance of the new MBR
for a successful startup. Frequent testing can add cost and
increase labor, but the benefits include faster response to changes
in the MBR process, reduced risk of making key decisions based on
inaccurate or marginal data, and a better understanding of the
system response to various operating conditions. Plant A collected
multiple samples for laboratory testing each week of the startup
period, and utilized the additional data to fine-tune chemical
dosing rates and plant performance early in the startup phase.
Plant B opted for less frequent testing, and achieved ENR level
treatment later in the startup period. On-site testing is
recommended for obtaining test results as soon as possible, with
packaged reagent test kits offering a relatively low cost option
for checking plant performance on a regular basis. Another
important consideration for the successful startup of a membrane
filtration system is how to best integrate and train the plant
operators to run the new process and associated facilities.
Membrane filtration technology can represent a significant
operational change from the treatment processes it replaces in
various ways, including increased automation, different performance
indicators and process variables to monitor and control, and
unfamiliar equipment and terminology. This was especially true for
the operators at Plant A, as limited staffing required them to work
full-time at the existing treatment plant until almost all of the
influent wastewater flow was diverted to the new membrane
filtration plant. This resulted in a rapid transition from an aging
contact stabilization plant with minimal automation and no nutrient
removal to a state-of-the-art facility equipped with a high level
of automation and ENR level nutrient removal. Special
considerations were made to gradually familiarize the operators
from Plant A with the new membrane filtration system both before
and after startup, including on site meetings with the engineer and
MFS supplier and review of the plant-specific computerized
operation and maintenance manual (COMM) for the MFS. This was in
sharp contrast to the operators at Plant B, who were on-site while
the new membrane filtration system was constructed, tested, and
started up, allowing for much more exposure to the new technology
and more familiarity with system operation before they had to take
the reins. In both cases, communication with the MFS suppliers
support staff after the completion of plant startup helped continue
the process of system optimization and operator training. These and
other valuable lessons from the case studies can be applied to the
startup phase of future projects. ACKNOWLEDGEMENTS The authors of
this paper would like to thank Bob Panek, Dave Fauber and Patrick
Christman (Town of Cape Charles); Dave Tyrrell (Town of
Berryville); the staff of the Cape Charles and Berryville WWTPs;
Shawn Addison and Jeny Chacko (GE Power and Water); Greg Jablonski
and Sebastian Smoot (GHD).
-
REFERENCES Bott, C; Parker, D.; Neethling, J.B.; Pramanik, A.;
Murphy, S. (2009) WEF/WERF Cooperative
Study of BNR Plants Approaching the Limit of Technology: II.
Statistical Evaluation of Process Reliability.WEF Proceedings,
Nutrient Removal 2009.
Cummings, G. and Frenkel, V. (2008) Membranes for industrial
water reuse - they're not just for municipal applications anymore.
Water Environment Federation, 77-91.
deBarbadillo, C.; Shellswell, G.; Cyr, W.; Edwards, B.; Waite,
R.; Sabherwal, B.; Mullan, J.; Mitchell, R. (2010) Development of
Full-scale Sizing Criteria from Tertiary Pilot Testing Results to
Achieve Ultra-low Phosphorus Limits at Innisfil, Ontario. WEF
Proceedings, WEFTEC 2010.
Di Bella, G.; Durante, F.; Torregrossa, M.; Viviani, G. (2010)
Start-up with or without inoculum? Analysis of an SMBR pilot plant.
Desalination 260, 79-90.
Ellsworth, S. and Riddell, K. (2007) Startup operation and
maintenance of the Delphos MBR WWTP. WEF Proceedings, WEFTEC
2007.
Ferraris, M.; Innella, C.; Spagni, A. (2009) Start-up of a
pilot-scale membrane bioreactor to treat municipal wastewater.
Desalination 237(1-3), 190-200.
Fleischer, E.J.; Broderick, T.A.; Daigger, G.T.; Fonseca, A.D.;
Holbrook, R.D. (2002) Membrane bioreactor pilot facility achieves
level-of-technology effluent limits. WEF Proceedings, WEFTEC
2002.
Fleischer, E. J.; Broderick, T.A.; Daigger, G.T.; Fonseca, A.D.;
Holbrook, R.D.; Murthy, S.N. (2005) Evaluation of membrane
bioreactor process capabilities to meet stringent effluent nutrient
discharge requirements. Water Environment Research 77(2),
162-178.
Manninaa, G. and Di Bella, G. (2012) Comparing two start-up
strategies for MBRs: experimental study and mathematical modelling.
Biochemical Engineering Journal 68, 91-103.
Pellegrin, M.; Greiner; A.D.; Aguinaldo, J.; Diamond, J.; Gluck,
S; Burbano, M.S.; Arabi, S.; Wert, J.; McCandless, R; Padhye, L.P.;
Shoaf, R. (2012) Membrane processes. Water Environment Research
84(10), 1114-1216mi.
Schmidt, H.; Glenny, Y.; Hirani, Z.; Casado, L.; Arrebola, V.;
Ferguson, J. (2011) Miami-Dade's reuse pilot program - investigates
the limits of technologies to meet ultra-low levels of nutrients
and micropollutants. Water Environment Federation, 6301-6313.
Vadiveloo, E. and Cisterna, R. (2008) Wastewater reuse: South
Florida's answer to a sustainable 21st century. Water Environment
Federation, 726-739.
CONCLUSIONSACKNOWLEDGEMENTS