    HUMAN BODY VIBRATION WHILE SITTING POSTURE

    DEPARTMENT OF MECHANICAL ENGINEERING

    THAPAR UNIVERSITY

    Submitted By:

    Tushar AnandME THERMAL

    (801183021)

    Submitted To:

    Dr. S. P NighamDept. of Mechanical Engg.

    1

  • 8/2/2019 TUSHAR NTPC

    2/34

    2

    COMPANY PICTURE

  • 8/2/2019 TUSHAR NTPC

    3/34

    Introduction

    Plant Layout

    Water Source

    Coal Handling Plant

    Boiler & its Accessories

    Turbine

    Condenser & Cooling Tower

    Awards

    References

  • 8/2/2019 TUSHAR NTPC

    4/34

    Company Profile

    NTPC Limited Type : State-owned enterprise

    Public (BSE: 532555)

    Industry : Electricity generation

    Founded : 1975

    Address : Kahalgaon Super Thermal Power Project, P.O.Kahalgaon STP,

    Distt. Bhagalpur-813214 Bihar

    Headquarters : Delhi, India

    Key people : Mr. B.R. Prasoon ,Chairman & Managing Director

    Product : Electricity Beneficiary States : West Bengal , Bihar , Jharkhand, Orissa , Sikkim

    Income 8,837.65 crore (US$ 1.92 billion)(2009-10)

    Employees 25,944 (2009)

    Website www.ntpc.co.in

    4

  • 8/2/2019 TUSHAR NTPC

    5/34

    INTRODUCTION

    NTPC, India's largest power company, was set up in1975 to accelerate power development in India.

    Today, it has emerged as an Integrated Power

    Major, with a significant presence in the entire value

    chain of power generation business.NTPC ranked 317th in the 2009, Forbes Global

    2000 ranking of the Worlds biggest companies.

    With a current generating capacity of 30,644 MW,

    NTPC has embarked on plans to become a 75,000

    MW company by 2017.

    5

  • 8/2/2019 TUSHAR NTPC

    6/34

    PRODUCTION:-

    Total capacity as on 31.03.2010 Generation 2009-2010

  • 8/2/2019 TUSHAR NTPC

    7/34

    7

    FIRE

    BOILERSTEAM

    TURBINE

    GENERATOR

    MAGNET

    PRINCIPLE OF GENERATION OF ELECTRICITY

  • 8/2/2019 TUSHAR NTPC

    8/34

    8

    LAYOUT OF THERMAL POWER STATION

  • 8/2/2019 TUSHAR NTPC

    9/349

    BOILER DRUM

  • 8/2/2019 TUSHAR NTPC

    10/34

    Water TreatmentPlant

    Coal

    HandlingPlant

    Fuel Oil Plant

    Hydrogen

    Plant

    TurbineGene-rator

    Condenser

    Switch

    Yard

    CW

    System

    Compressed

    Air System

    AshHandling

    Plant

    BoiIer

    B.F.P.

    SUPPORTING SYSTEM

    Raw WaterSystem

    CT

  • 8/2/2019 TUSHAR NTPC

    11/34

    GENERAL WORKING OF A THERMALPOWER STATION

    1. Coal Handling Plant2. Boiler3. Turbine

    4. Generator

    11

  • 8/2/2019 TUSHAR NTPC

    12/34

    Coal Handling Plant (CHP)

    CHP is a plant which handles the coal from itsreceipt to transporting it to Boiler and store inBunkers. It also processes the raw coal to make itsuitable for Boiler Opeartion.

    In brief we can say that receipt of coal from coalmines, weighing of coal, crushing it to required sizeand transferring the quanta of coal to various coalmill bunkers.

    12

  • 8/2/2019 TUSHAR NTPC

    13/34

    Major auxiliaries of CHP

    1. Wagon Tipplers2. Vibrating Feeders3. Conveyor Belts

    4. Coal Crushers5. Trippers6. Electromagnetic Separators.7. Dust extraction systems

    8. Gas Extractor.

    13

  • 8/2/2019 TUSHAR NTPC

    14/34

    Definition

    Wagon Tipplers:-These are the giant machines having gear boxes and motorassembly and are used to unload the coal wagons into coalhoppers in very less time (e.g. 20 wagons/hr. or more).Vibrating Feeders:-

    These are electromagnetic vibrating feeders or sometimes inthe form of dragging chains which are provided below thecoal hoppers. This equipment is used for controlled removalof coal from coal hoppers.Conveyor Belts:-

    These are the synthetic rubber belts which move on metallicrollers called idlers and are used for shifting of coal from oneplace to other places.

    14

  • 8/2/2019 TUSHAR NTPC

    15/34

    Conveyor Belts

  • 8/2/2019 TUSHAR NTPC

    16/34

    Coal Crushers:-We receive the coal in the form of odd shaped lumps. Theselumps are to be crushed to required size. These lumps arecrushed by coal crushers.

    Trippers:-These are the motorized or manually operated machines andare used for feeding the coal to different coal bunkers as pertheir requirement .Electromagnetic Separators:-

    Electromagnets are used for removing of Iron and magneticimpurities from the coal.Dust Extraction System:-This system is provided in CHP for suppression of coal dust incoal handling plant.

    16

  • 8/2/2019 TUSHAR NTPC

    17/34

    Gas Extractors:-Gas extractors are provided at the bunker level toremove all types of poisonous and non poisonousgases from the working area.

    17

  • 8/2/2019 TUSHAR NTPC

    18/34

    Boiler

    Boiler is a device for generation of steam for powergeneration. In thermal power stations water tubeboilers are used. Boiler is suspended from the topon four columns and kept free from the bottom side

    for free expansion on downward direction.

    18

  • 8/2/2019 TUSHAR NTPC

    19/34

    Fan section

    Boiler drum

    Reheater

    Superheater

    Furnace

    Economizer

    Air Pre Heater

    Boiler

  • 8/2/2019 TUSHAR NTPC

    20/34

  • 8/2/2019 TUSHAR NTPC

    21/34

    21

  • 8/2/2019 TUSHAR NTPC

    22/34

    E.S.P.THEORY:-

    The full form of ESP is electro static preceptor .An ESP can be defineed as a device that utilized electrict forces to separate suspandedparticle from flue gasesESP is highly efficient device for extraction of suspended particle andfly ash fromThe industrial flue gases .

    WORKING PRINCIPLE :-ESP can handle large volume of gases from which solid particles areto be removed .

    ADVANTAGES OF ESP :-

    High ash collection efficiency. Low resistance path for gas flow.

  • 8/2/2019 TUSHAR NTPC

    23/34

    TurbineThe steam turbine generator being rotatingequipment generally has a heavy, large diametershaft. The shaft therefore requires not only

    supports but also has to be kept in position whilerunning.

    23

  • 8/2/2019 TUSHAR NTPC

    24/34

  • 8/2/2019 TUSHAR NTPC

    25/34

    COOLING TOWER

    Cool the warm water discharged fromthe

    condenser and feed the cooled water

    back to the condenser.

    Reduced the cooling water demandIn the plant.

  • 8/2/2019 TUSHAR NTPC

    26/34

  • 8/2/2019 TUSHAR NTPC

    27/34

    CT Bottom area

  • 8/2/2019 TUSHAR NTPC

    28/34

    Tower Top Deck

  • 8/2/2019 TUSHAR NTPC

    29/34

    CT Fan Gear Box

  • 8/2/2019 TUSHAR NTPC

    30/34

    Cooling Tower Fan

  • 8/2/2019 TUSHAR NTPC

    31/34

    CONCLUSION

    Summer training plays a vital & effective role in astudents life no matter whatever respective field he

    is working upon & want to expertise his\her skills intheir field.

    It is for the student to see & adjust on working culture& environment to a sufficient period of time & tocheck the students adaptability & flexibility.

    It gives the practical idea & picture of what we all

    have only theoretically gained.Last not the least it provide student a platform to to

    shape their knowledge into practical work.

    31

  • 8/2/2019 TUSHAR NTPC

    32/34

    Reference

    www.energy.com

    NTPC, Kahalgoan.

    Power Plant Engineering by P.K. Nag

    Power Plant Engineering by Dr. R.Yadav

  • 8/2/2019 TUSHAR NTPC

    33/34

  • 8/2/2019 TUSHAR NTPC

    34/34