Project NameGovernment Facility
Project LocationCharleston, South Carolina
Project TeamOwner: Federal GovernmentPerformance Contractor: Noresco
GovernmentCentral Plants
Markets
Specializations
Pipe Shop Prefab
Design/Assist
Engineer: McKenney’s, Inc.
Building Information Modeling
Energy Management
McKenney’s provided a turnkey design/build solution to replace an outdated chiller plant in the operating classroom complex of a government training center.
The ChallengeThe specified chillers were much larger than the training center’s existing units, would not fit in the existing central plant’s configuration, and jeopardized the project’s timing and budget. Since training was in session, chilled water service could not be interrupted, and temporarychillers were beyond the budget scope.
The SolutionMcKenney’s implemented the turnkey design solution in phases and used existing central plant equipment during new central plant construction to minimize shutdowns and stay within budget. A redesign of the centralplant was necessary to accommodate the new equipment, and installation took place during four complicated, prolonged shutdowns on weekends.
The content of this document is not intended as an endorsement.
The ResultsAlthough the scope of work dramatically changed, McKenney’s executed and completed this complicated turnkey energy project on time and within budget without interrupting chilled water service. The energy savings now achieved will pay for the project costs.